Determination 799391
Escape of water damage claim settlement - insurer sought to apportion loss to 70% based on earth movement exclusion
Summary
The complainant claimed escape of water damage to their home after blocked stormwater pipes; the insurer accepted the claim but sought to pay only 70% of repairs due to earth movement exclusions. AFCA found the escape of liquid was the dominant cause, ordered cash settlement of $67,119.64 and $1,000 non-financial loss.
The escape of liquid was the proximate (dominant) cause of the damage and the insurer had not established pre-existing movement to justify apportionment under the earth movement exclusion.
Issues
- Claim amount dispute primary · upheld
“The insurer is to pay the complainant $67,119.64 in settlement of the complainant's claim for the internal and external damage and the resin injection”
- Claim denial secondary · not upheld
“I do not accept the damage can be apportioned as indicated by GP in the absence of evidence from the insurer to indicate there was pre-existing movement”
- Inadequate claim investigation secondary · upheld
“GP's report of 29 January 2021 was clear... The insurer's assessor considered GP believed only one area slightly exceeds the floor deflection tolerances. This is inaccurate.”
- Delay secondary · upheld
“the insurer's offer based on the quote from AI... has led to further delays and confusion in the finalisation of the claim”
Subjects and remedies
home or building damagenatural disasterpay claimpay non financial loss
Text of the determination
Determination
Case number 799391
Financial firm AAI Limited
Determination | Case number: 799391 Page 1 of 6
Case number: 799391 3 June 2022
1 Determination overview
1.1 Complaint
The complainant holds a Home & Contents Insurance policy with the financial firm (insurer)
and in March 2020 lodged a claim for damage due to the escape of water from blocked
stormwater pipes.
The insurer accepted the claim but maintains it is liable only to 70% of the cost of repairs as
other factors that fall within the policy exclusions were contributing to the movement of the
house. The complainant disagrees and maintains the proximate cause of the damage to the
home was the escape of liquid and that the insurer should pay for the repair of the home.
The complainant is represented by a consumer advocate. Any reference to the complainant in
this determination includes reference to submissions by the consumer advocate.
1.2 Issues and key findings
Is the insurer required to cover the damage claimed in full?
Yes. The engineering reports provided establish that most likely the proximate cause of the
damage was the escape of liquid from the damaged stormwater drains and blocked sewer.
How is the claim to be settled?
It is fair that the insurer pays the cost to relevel the property using resin injection as quoted by
MM in the sum of $46,997.50. In addition, the insurer should cash settle the internal and
external repairs for $36,183.14 for to the property (total $83,180.68). The insurer can deduct
$16,061.00 already paid leaving an outstanding payment of $67,119.64.
Is the complainant entitled to compensation for non-financial loss?
Yes. The insurer’s handling of the claim has caused the complainant an unusual degree of
inconvenience and in the circumstances, I consider it fair that the insurer pays the
complainant $1,000 compensation by way of non-financial loss.
Why is the outcome fair?
The outcome is fair as it considers all the information provided, the terms of the policy and
reasonably reflects the cost of repairs as provided by the various quotes.
1.3 Determination
This determination is substantially in favour of the complainant.
Within 21 days of the complainant’s acceptance of this determination, the insurer is to pay the
complainant $67,119.64 in settlement of the complainant’s claim for the internal and external
damage and the resin injection as quoted by the ground engineer MM.
In addition, the insurer is to pay the complainant $1,000 compensation for non-financial loss
pursuant to AFCA Rule 3.3.
Determination | Case number: 799391 Page 2 of 6
2 Reasons for determination
2.1 Is the insurer liable to meet the cost of repairs?
Yes. The engineering reports provided establish that most likely the proximate cause of the
damage was the escape of liquid from the damaged stormwater drains and blocked sewer.
Complainant has established the claim falls within the terms of the policy
It is established insurance law that a complainant bears the initial onus to prove on the
balance of probabilities (that is more likely than not) that the loss or damage claimed falls
within the terms of cover under the policy. This is commonly called a prima facie claim.
The complainant’s Home & Contents Insurance policy provides cover for a series of insured
events listed under the Product Disclosure Statement (PDS) including the escape of liquid
(EOL) subject to several conditions and exclusions.
The complainant lodged a claim on or about 25 March 2020 after noticing cracking and
movement damage to the property that had been developing over a period of 12 months.
The complainant provided the insurer with a plumbing report from SPD dated 4 March 2020
which confirmed the presence of water leaks from the stormwater drains and blocked sewer.
The insurer appointed ABG to assess the damage and ABG engaged a second plumber BB
to carry out relevant leak detection plumbing investigation. AI concluded that there was a
strong possibility that the damage had been caused by water leaking out of the stormwater
system as it came across several areas of concern.
The insurer does not dispute that the property has suffered damage because of EOL. The
insurer seeks to rely upon exclusions within the policy relating to earth movement to apportion
its liability for the claimed damage and settle the claim based on 70% of the assessed repair
quote.
Escape of liquid the proximate cause of the damage
As the insurer seeks to rely upon the exclusions within the policy, the insurer needs to
establish on the balance of probabilities that a proximate cause of the damage to the property
was due to one of the excluded factors under the terms of the policy.
The proximate cause of damage is the dominant or effective cause of damage. This is a
question of fact in each case and the proximate cause is not necessarily the first or last or
sole cause of the loss.
The insurer’s engineer GP reported in September 2020 that the site was likely to have highly
reactive soil classification notoriously reactive to changes in moisture with heave and
subsidence. It considered there may have been a slight contribution to movement of the
foundation with trees and poor surface drainage contributing to the foundation movement. GP
considered however that the leaking pipes were the dominant cause of the foundation
movement resulting in the differential movement of the house and to the internal and external
damage.
The complainant provided an engineering report from SP. SP reported in June 2020 that
while minor cracks had appeared a year ago, they had progressed to serious structural
movement in the past three to four months. SP disagreed with GP’s apportionment of the
Determination | Case number: 799391 Page 3 of 6
cause of damage and considered that the water leakage was the sole contributor to the
cracking and damage to the house.
A Geotech report provided by STM on 10 September 2020 confirms that the site classification
was highly reactive with very high ground movement from moisture changes. I accept that this
is an accurate description of the site. Clearly the site has been impacted by the moisture
changes resulting from the leaking pipes. The pipes may have been leaking for 12 months or
more.
I accept that GP and SP agree the dominant or effective cause of the internal and external
damage to the home is due to the EOL. No evidence has been provided to indicate damage
had been occurring to the property because of seasonal changes or variations in swell/sink
cycle. There is no indication of prior repairs to the property to suggest any significant
movement.
I do not accept the damage can be apportioned as indicated by GP in the absence of
evidence from the insurer to indicate there was pre-existing movement or damage to the
property. In the circumstances, I am satisfied that the insurer is liable for the internal and
external damage sustained to the complainant’s home.
2.2 How is the claim to be settled?
It is fair that the insurer cash settles the claim for the resin injection and relevelling as quoted
by for and cash settle the internal and external repairs $36,183.14 (total $83,180.68). The
insurer can deduct $16,061.00 already paid leaving an outstanding payment of $67,119.64.
Insurer should settle based on the scope of works from GP and SP
The insurer has offered the complainant $16,061.66 based on 70% of its builder AI’s scope of
works plus a 10% uplift. The total scope of works is for $22,945.23. The quote provided by AIis
said to be based on the scope of works from GP.
There is no dispute that the complainant completed all relevant maintenance works
recommended by the insurer’s engineer GP. In a report dated 29 January 2021, GP confirmed
that the complainant had completed the recommended maintenance. Nearby trees were from
the property and new pavement slabs installed consistent with the National Construction Code
(NCC). The report indicated that there was some additional internal damage identified but
largely the movement of the property had not significantly changed since its previous report in
May 2020.
I do not accept the quote from AI complies with the SOW from GP. The report from GP notes
the floor deflection levels exceed tolerances and that resin injection underpinning was to be
implemented particularly in the southeast corner of the foundation slab. GP recommended
that, after allowing a 12-month stabilisation period from the completion of the maintenance
works (20 January 2021), structural augmentation works could commence.
No allowance for resin injection underpinning has been included in the assessment from AI.
GP also recommended:
adjustment of the front door to facilitate easy operation after structural augmentation works
cut and refix architrave to the front entrance
adjust laminate flooring near floor entrance
replacement of bricks above the front entrance and repointing
patching and painting of the southern window moulding
patching and painting of the interior windows, hallways, bedrooms.
Determination | Case number: 799391 Page 4 of 6
The complainants engineer SP also recommended slab jacking and grouting work be
performed.
As indicated, the AI scope of works did not allow for the relevelling of the house or adjusting of
the laminate flooring. I note the insurer’s assessor in her report in August 2021 commented
that the building did not require slab or grouting work as recommended by SR. The assessor
also considered GP believed only one area slightly exceeds the floor deflection tolerances.
This is inaccurate. GP’s report of 29 January 2021 was clear. It considered the floor deflection
levels exceeded tolerances over the front of the dwelling and resin injection underpinning was
to be implemented upon completion of the stabilisation period.
I consider it fair the insurer pays the cost of the resin injection and pays for the internal and
external damage as assessed by the engineers.
Insurer is to cash settle the claim
In March 2021 the complainant provided a quote from MM of approximately $11,000 to
complete the resin injection. This quote was based on an inspection of the property in
November 2020. The current quote provided on 16 February 2022 is $46,997.50. I sought
clarification of this given the significant increase.
I note the current quote follows a second inspection of the property on 8 February 2022, MM
has advised that following receipt of the engineer’s report and the inspection, the d amage
was considered worse. The insurer has not provided a response to the quote that was
exchanged on 17 February 2022.
In the circumstances, I consider it fair that the quote be relied upon and that the insurer cash
settle the complainant for the cost of the resin injection and relevelling of the property in the
sum of $46,997.50. As the quote is a current quote, interest is not payable.
I also consider that in addition to the cost of the resin injection and relevelling it is fair that the
insurer cash settles the claim for the remaining internal and external damage. However, I do
not consider the quote provided by the complainant’s builder MHI fairly reflects the extent of
the internal and external damage.
I do not believe that following the resin injection, it will be necessary for the complainant to
replace the doors, fly wire screens or windows of the home nor do I believe it will be
necessary for the complainant to replace the entire laminate flooring.
I accept that the amount quoted for the walls and ceilings of $13,500 is fair and reasonable. To
this should be included an allowance of $500 to allow for a flooring contractor to adjust the
laminate flooring near the front entrance as identified in the report from GP.
The complainant’s quote from MHI of $28,050 to replace the concrete driveway and damaged
post does not appear reasonable. The report from GP confirms that the complainant had
already completed the new apron pavement slab and repaired the damage to the concrete
pathways caused by the EOL.
I consider the assessment contained from AI more fairly reflects the likely cost to repair the
external pavement area including concreting, brick laying, demolition and caulking. The AI
quote for this work comes to $17,463.60 including relevant builder’s allo wances, site
supervision and GST.
This brings the total cost of the internal and external repairs to $31,463.60. Given the age of
the quotes and transfer of risk it is fair to allow a 15% ($4,719.54) uplift for contingencies.
This brings the total cash settlement for the remaining internal and external repairs to
Determination | Case number: 799391 Page 5 of 6
$36,183.14.
The complainant has already been paid $16,061 in settlement of the claim on 10 May 2021.
The insurer is entitled to deduct this from the total settlement payable of $83,180.64 making
an outstanding cash settlement payable to the complainant of $67,119.64.
2.3 Is the complainant entitled to compensation for non-
financial loss?
Yes. The insurer’s handling of the claim has caused the complainant an unusual degree of
inconvenience and in the circumstances, I consider it fair that the insurer pays the
complainant $1,000 compensation by way of non-financial loss.
AFCA can award compensation for non-financial loss
AFCA can award compensation of up to $5,400 for non-financial loss where a complainant
suffers an unusual degree of physical inconvenience or time taken to resolve the situation.
AFCA takes a conservative approach to the award of compensation and expects the
complainant to be moderately robust in dealing with the usual inconvenience associated with
any insurance claim.
Complainant suffered an unusual degree of inconvenience
While the insurer accepted the complainant’s claim, the insurer’s decision to seek to apportion
the loss even though there was little evidence of prior damage to the complainant’s property,
has caused considerable inconvenience to the complainant.
Further, the insurer’s offer based on the quote from AI without considering the scope of works
provided by its own engineer GP, in particular, the need for the resin injection to level the
foundations has led to further delays and confusion in the finalisation of the claim.
While I accept an insurer is entitled to form its view based on the information available, I
consider, considering the engineering reports exchanged that the insurer should have
addressed the issues with respect to the relevelling of the property when making its
settlement offers to the complainant.
In my view, it is fair in the circumstances to award the complainant $1,000 compensation for
non-financial loss.
2.4 Why is the outcome fair?
The outcome is fair as it considers all the information provided, the terms of the policy and
reasonably reflects the cost of repairs as provided by the various quotes.
Given the fact that the insurer and it failed to assess the cost of the resin injection despite
being aware of the need for the resin injection to level the property from February 2021, it is
fair to rely on the quote provided by the complainant.
Determination | Case number: 799391 Page 6 of 6
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances,
havingregard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and
eachparty has had the opportunity to address any issues raised. We have reviewed and
considered all the information the parties have provided.
While the parties have raised several issues in their submissions, we have restricted
this determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or
torequire third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are
norelevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a
claimcannot be established.