Home / QBE / Determination 796414

Determination 796414

Claim decline for inground pool damage relying on exclusion for faulty or poor workmanship

FirmQBE
Decided2021-10-19
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The complainants claimed under their home building policy for damage to their inground pool, attributing it to a November 2019 storm or a leaking stormwater pipe. AFCA found the damage was most likely caused by inadequate installation, which is excluded, and determined in favour of the insurer.

Under the insured-events policy the complainants must establish a valid claim; they failed to do so, and the expert evidence establishes the proximate cause was faulty installation, an excluded cause.

Issues

Subjects and remedies

home or building damagenatural disasterno remedy

Related

All QBE determinations · Find similar determinations

Text of the determination

Determination Case number 796414 Financial firm QBE Insurance (Australia) Limited Determination | Case number: 796414 Page 1 of 8 Case number: 796414 19 October 2021 1 Determination overview 1.1 Complaint The complainants hold a home building and contents policy with the financial firm (the insurer). In November 2019, they lodged a claim for damage to their inground swimming pool saying it was damaged in a recent storm and/or by a leaking stormwater pipe. Relying on expert opinion, the insurer declined the claim saying the damage was caused by the incorrect installation of a pool. The insurer says as these circumstances are excluded from cover it is entitled to decline the claim. The complainants disagree with the insurer’ s decision to decline the claim. They require the insurer to indemnify them and replace the pool. The case analyst provided the parties with a preliminary assessment on the issues in dispute. The preliminary assessment was in favour of the insurer. The insurer accepted the preliminary assessment, but it was not accepted by the complainant s . In the circumstances, the complaint s ha ve been referred to me for determination . 1.2 Issues and key findings Is the insurer entitled to decline the claim? Yes. The available material does not establish on the balance of probabilities the claimed damage was caused by the storm or by the leaking stormwater pipe. Rather, the available material establishes on the balance of probabilities the claimed damage was caused by inadequate installation of the pool by the complainants. As this cause of damage is excluded from cover, the insurer is entitled to decline the claim. Why is the outcome fair? The insurer is entitled to rely on the available expert material and its policy terms. In circumstances where the expert material establishes on the balance of probabilities the claimed damage was not caused by an insured event but was caused by inadequate installation of the pool (which cause is excluded from cover under the policy) it would not be fair to compel the insurer to pay the claim. 1.3 Determination This determination is in favour of the insurer. The insurer is not required to take any further action in relation to the claim or the complaint. Determination | Case number: 796414 Page 2 of 8 2 Reasons for determination I have decided this complaint based on what is fair in all the circumstances, having regard to legal principles, applicable industry codes or guidance, good industry practice and previous relevant determinations of AFCA or predecessor schemes (which are not binding). I have considered all the material submitted by the parties, both before and after the preliminary assessment. I am satisfied that the documentation I have relied on has been provided to both parties. The parties have raised numerous issues in their submissions to AFCA. However, commentary in this determination is restricted to those issues considered relevant to the outcome. After the preliminary assessment was rejected, the complainants made a further submission and provided photographs. Where relevant, these will be referred to in the determination. 2.1 Is the insurer entitled to decline the claim? Submissions and material considered When making the claim the complainants told the insurer they had drained the pool and the pool was leaking. At the same time, they were in correspondence with the pool supplier seeking a remedy under the warranty. The insurer’s adjuster recommended the complainants continue with the warranty claim. The pool supplier inspected the pool in January 2020 and provide an email saying, “the problems were quickly evident that can be related to the installation”. The supplier says the pool was not installed in accordance with their instructions. The supplier lists several issues with the pool installation which are summarised in supporting section 3 of this determination. Relevant extracts from other expert reports are also set out in supporting section 3 of this determination. The complainants sent the supplier’s email and photographs to the insurer and in a lengthy email rebutted the supplier’s contentions. They renewed their claim against the insurer saying the supplier would not cover the pool under the warranty even though it was sold as a DIY kit. The complainants say they had the pool for three years and everything was fine until November 2019 when there was a large rain storm. They also contend issues with the pool may be because of a faulty rainwater pipe from the house roof. The insurer arranged for the pool to be inspected by an engineer in March 2020. The engineer reviewed the correspondence from the pool supplier. The engineer noted the complainants’ concerns both in relation to the cause of damage being the storm event or the faulty rainwater pipe. The engineer concluded: The installation of the in-ground fibreglass pool is contrary to the requirements of the relevant Australian Standard A51839 and is considered to be a building defect. Had the pool been installed in compliance with A51839, the damage would not be expected to Determination | Case number: 796414 Page 3 of 8 have occurred. The engineer noted the damage to the pool including that the base of the pool had popped upwards. The engineer discounted any rainfall event being the cause of damage because material from the Bureau of Meteorology website showed there was no significant rainfall in the relevant period. The engineer also described relevant Australian Standards in relation to backfill material and lateral bracing. He said: Had the backfill been cement stabilised and a full perimeter concrete bond beam been installed, slump ing would not have expected to occur and the deviations of the southern side wall in particular to the subject pool would likely have been less significant. Cement stabilised backfill and a concrete bond beam to provide lateral restraint to the tops of the perimeter walls would also have most likely prevented the cracking to the side walls at the steps of the pool to occur. The engineer described Australian Standards requirements regarding drainage and the installation of a standpipe and said adequate drainage had not been provided. Because of these issues, he said the pool installation does not comply with the Australian Standard which “resulted in a configuration susceptible to damage due to pressure imbalances.” Having considered the engineer’s opinion, the insurer declined the claim saying the claimed damage was caused because the pool was not installed to the relevant Australian Standards and water was removed from the pool using an incorrect technique . About a year later, the complainants brought the complaint to AFCA supported by further submissions and photographs. In addition, the complainants say the pool shell was too thin to have been able to withstand the water pressure from the water under the shell. Because of rainfall in March 2021, they reiterated their contention the damage to the pool was caused by the broken rainwater pipe redirecting all the rain behind the pool shell. They asked if the insurer could carry out further testing. The insurer’s engineer did not conduct a further inspection or undertake any further tests but reviewed the emails from the pool supplier and the material in relation to the March 2021 rain event and the stormwater pipe breakage and repairs. The engineer reiterated his opinion. He said had the pool been installed to the relevant Australian Standard then irrespective of the March 2021 event or the reported failed inground stormwater plumbing pipe the damage to the pool would not have occurred. He also said the pool shell thickness was not a significant factor given the shortcomings of the pool installation. Because of this further opinion, the insurer continues to contend the complainants have not established a valid claim and the available material establishes the damage was caused by faulty installation which is excluded under the policy. On this basis, the insurer continued to decline the claim. Determination | Case number: 796414 Page 4 of 8 Complainants must establish damage caused by storm or leaking pipe The complainants must establish on the balance of probabilities that they have suffered a loss caused by an event to which the policy responds. This is known as a prima facie or valid claim. The policy is an insured events policy. The complainants are covered if damage is caused by one of the insured events that are listed in the policy. In view of the complainants ’ submissions, the relevant insured events are damage because of storm, rain water, flood or wind or damage caused by water escaping from a fixed pipe. The cover is subject to exclusions. The insurer is not liable to pay for any damage or liability arising directly or indirectly by a defect in an item, structural defects, faulty or poor workmanship or design. If a valid claim is established, the onus shifts to the insurer to prove on the balance of probabilities that this exclusion applies if it seeks to deny or limit its liability for the loss. Damage not caused by November 2019 storm The complainants provided submissions and photographs before and after the preliminary view. The complainants have not provided any expert independent opinion. They say this is because the cost of the engineer would outweigh the cost of repairing the pool. They criticise the engineer’s reports because they say he did not test or consider information regarding the leaking rainwater drain pipe. After the preliminary view the complainants also said the pool does have a bond beam and is tied into the concrete surrounding the pool by rio bar through hangers in the pool wall, as per the installation instructions supplied by the pool supplier. They say as the engineer cannot see this he has ruled there is none which they say is “ sloppy investigation ” . I have care fully considered all the available material, the complainants’ lengthy submissions and their photographs. I do not find the complainants’ material sufficiently compelling to rebut the opinions of both the pool supplier and the engineer. In view of the material from the Bureau of Meteorology, as insignificant rainfall fell during the period of the claimed storm event, I accept the complainants have not established on the balance of probabilities the proximate (or the dominant or operative) cause of the damage was a storm event in November 2019. Available material does not establish damage caused by leaking pipe As for the contention the engineer did not test or consider information regarding the leaking rainwater drain pipe, I am satisfied he was aware of the contention and considered it and yet continued to conclude the damage to the pool was because of incorrect installation. The pool supplier lists the issues with the pool installation. The insurer’s engineer considered that material and explained in his reports why it is relevant. As for comment regarding the bond beam, the pool supplier explained the wide concrete area forms part of the bond beam which is not separate. In his email dated 20 January 2020, he explains the installation problem which is the concrete area goes under the lip of the pool, is not adhered to the pool with reinforcing or any form and there is a gap between the lip of the pool and the concrete which has allowed water to flow under the pool. Determination | Case number: 796414 Page 5 of 8 The engineer notes concrete bond beams are recommended by Australian Standards and describes the concrete surround ground slab. In the context of his report I do not accept the engineers investigation is “sloppy” or that this observation derogates from the tenor of all reports which is that the proximate cause of the damage is the poor installation. The complainants have the onus of proof and, on the available material, I do not accept the complainants have established the leaking rainwater drainpipe was the proximate (or the dominant or operative) cause of the claimed damage. Damage caused by inadequate installation of the pool Having considered the available material, I do not accept the complainants have established a valid claim. I do not accept the available material establishes the claimed damage was caused by a storm event in November 2019 or by the leaking rainwater drain pipe. Rather, I accept the available material establishes on the balance of probabilities the proximate cause of the damage was the inadequate installation of the pool by the complainants. The policy says the insurer will not pay for any damage which is directly or indirectly caused by a defect or faulty or poor workmanship. In these circumstances, as the available material establishes the proximate cause of damage is excluded from cover, the insurer is entitled to decline the claim. 2.2 Why is the outcome fair? Insurer entitled to rely on expert opinion and policy terms The insurer is entitled to rely on the available expert material and its policy terms. In circumstances where the expert material establishes on the balance of probabilities the claimed damage was not caused by an insured event but was caused by inadequate installation of the pool (which cause is excluded from cover under the policy) it would not be fair to compel the insurer to pay the claim. Determination | Case number: 796414 Page 6 of 8 3 Supporting information 3.1 Process AFCA’s approach to this complaint It is an accepted principle of general insurance law that the insured bears the onus to establish on the balance of probabilities that they have suffered a loss caused by an event to which the policy responds. This is known as a prima facie or valid claim. Once so established, the onus shifts to the insurer to prove on the balance of probabilities that an exclusion applies if it seeks to deny or limit its liability for the loss. How we assess complaints AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider available documents, the recollections of the parties, and all relevant circumstances. We give more weight to documents created at the time the events occurred. If there is no relevant documentation, we will decide what is most likely to have occurred based on the information provided to us. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. Case law and proximate cause Case law establishes: · The proximate cause of the loss is the dominant or effective or operative cause of the loss whether or not that be the last in time or the sole cause. · If there are several causes operating contemporaneously, each must be examined for the qualities of reality, predominance and efficiency as the active, efficient cause that sets a relevant chain of events in action. If one cause would have caused the harm in any case, and the other would not have done so in the absence of the first, the first is the proximate cause. · A common-sense approach is taken to determine proximate cause. 3.2 Relevant policy terms The relevant policy extracts are referred to in the correspondence between the parties and in the insurer’s Notice of Response. Both the policy document and the Notice have been exchanged with the complainants. Building and Contents Cover Exclusions We will not pay for any loss or damage which is caused directly or indirectly by: a defect in an item, structural defects, faulty or poor Determination | Case number: 796414 Page 7 of 8 workmanship or design" 3.3 Extracts from material relied on by the parties Date Action Site inspection report (RB) 2 December 2019  Loss adjuster and RB inspect ed pool and fibreglass pool shell with complainant s 2 December 2019.  Complainant s said noticed water level dropping and drained the pool down past the first step and found the fibreglass cracked which they repaired. It was Ok for 3 weeks then the wat er leve l dropped again. They again drained half of the pool and found another crack.  Manufacture r of pool has still not inspected .  Recommended complainant s continue with warranty claim. Adjuster (S) 27 November 2019  S i nspected and photographed the pool 2 December 2019 which ha d cracking to the fibreglass base .  Complainant s to provide report from pool supplier as possible claim under warranty .  Confirmed pool base has three separate small cracks. Pool supplier email 20 January 2020  Inspected pool 9 Jan uary 202 0.  P roblems are related to the installation as the pool was not installed in accordance with our instructions including:  P ool was backfilled with crusher dust with no cement added; no separate bond beam which goes under the lip of the pool and i s not adhere d to the pool with reinforcing leaving a gap between the lip and the concrete which allows water to flow under the pool ; pool emptied with no bracing; deviations in the walls leading to cracking; no standpipe as required by our instructions and t he engineer’s instructions; pool was set too low.  To rectify the problem, remove the pool, repair the fibreglass and reinstall the pool with one of our qualified builders. Engineer’s report 30 March 2000  Inspected and photographed pool on 5 March 2020 with complainant s and adjustor.  Reviewed email correspondenc e from pool supplier.  Proxi mate cause of the damage to the pool is incorrect installation.  Popped base and report ed crack to the base of the pool is a direct result of emptying the pool without adequate internal bracing.  Installation of the pool is contrary to the requirements Determination | Case number: 796414 Page 8 of 8 of the relevant Australian S tandard and is a building defect.  Had the pool been installed in compliance with Australian S tandards the damage would not have occurred.  No significant rain fell during the period of claimed storm event and was not a contributing factor to the pool damage. Engineer’s report 10 May 2021  Reviewed email correspondenc e between the pool supplier and the complainant s and photographs of the repo rted stormwater pipe breakage and repairs including a photograph of the backyard inundated with water following rain in March 2021.  Reiterated h ad the pool been installed to all requirements of Australian Standard then the damage would not have occur red i rrespective of rainfall events since the pool installation or the reported failed in ground stormwater plumbing pipe.  D o not consider the thickness of the pool shell a significant factor giving the shortcomings of the pool installation described in the re port. 3.4 Other relevant material considered and relied on  Parties’ submissions /emails and all attachments to all submissions/emails.  Expert reports.  Photographs.  Correspondence with the pool supplier.  Correspondence between the parties.