Home / Suncorp Group / Determination 792331
Determination 792331
Electrical fire claim settlement offer and scope of rewiring works
Summary
The complainant's home was damaged by an electrical fire and he sought $180,000 plus temporary accommodation and non-financial loss. AFCA found the insurer's offer mostly fair, ordered settlement of $47,333.13 including a 35% contingency with interest, and ordered temporary accommodation based on a 35% contingency on the works timeframe, but refused non-financial loss.
The insurer's scope of works for rewiring is fair under AS/NZS 3018 and consistent with pre-existing wiring, but a substantive contingency is warranted for the risk of further asbestos removal.
Issues
- Claim amount dispute primary · upheld
“Panel does not accept KBA's quote is fair and reasonable; insurer to pay $47,333.13 in full and final settlement including a 35% contingency.”
- Inadequate claim investigation secondary · not upheld
“Panel is not persuaded all the asbestos walls need to be replaced; S's evidence is persuasive that surface mounted cabling is acceptable.”
- Delay secondary · not upheld
“The panel is not satisfied there is sufficient information to show the insurer mismanaged the claim; claim managed appropriately.”
Subjects and remedies
health or medicalhome or building damagepay compensationpay interestreassess claim
Text of the determination
Determination
Case number 792331
Financial firm AAI Limited
Determination | Case number: 792331 Page 2 of 10
Case number: 792331 3 May 2022
1 Determination overview
1.1 Complaint
The complainant holds home and contents insurance with the financial firm (insurer). He
lodged a claim on 14 November 2020 for damage caused by an electrical fire.
The insurer assessed the claim and offered the complainant $42,207.63 to resolve the claim.
The complainant is dissatisfied with the offer and seeks $180,000, temporary accommodation
costs and non-financial loss.
1.2 Issues and key findings
Is the insurer’s offer fair and reasonable?
Mostly. The panel accepts the insurer’s scope of works and quote fairly reflects its obligations
under the policy. However, it should include a substantive contingency to address the real risk
that further asbestos removal could be required during the works.
Is the complainant entitled to non-financial loss?
No. The complainant has not established the insurer caused unusual delays or mismanaged
the claim.
1.3 Determination
This determination is partly in favour of the complainant.
The insurer is to settle the complainant’s claim in the manner set out in section 2.1 .
Determination | Case number: 792331 Page 3 of 10
2 Reasons for determination
2.1 Is the insurer’s offer fair and reasonable?
Policy covers fire damage
There is no dispute an event covered by the policy occurred or that the insurer is liable to
repair the damage.
The substantive issue is whether the insurer’s proposed scope of works for the r ewiring is fair.
Review of expert evidence
Both parties obtained expert evidence to support their position. The insurer relied upon
reports from RCC and S. The complainant obtained a report from electrician SVE and is
relying on KBA’s quote. KBA is a cont ractor engaged by the insurer.
The details of the reports are set out in section 3 of this determination.
Following several assessment and quotations, all experts agreed the property requires
complete re-wiring. However, the experts conflict on whether the removal of all asbestos
sheeting is required.
The complainant seeks for the insurer to cash settle him for $180,841.23. This is based on
KBA’s quote that includes removal and replacement of all the asbestos sheeting. This method
is consistent with that proposed by SVE.
The insurer has based its cash settlement offer on RCC’s revised quote totalling $35,061.58.
SVE’s report indicates the wiring does not meet today’s standards and cannot be clipped
along the wall as it currently is. It also says it is near impossible to complete the re-wiring
without disturbing the asbestos in the walls.
The insurer disagrees. It provided a report from expert S who says as per ‘ AS/NZS 3018 –
Electrical Installations – Domestic ’, surface mounting of cabling is acceptable when
mechanically protected (i.e. inside a conduit). RCC’s quote allows for the use of conduits to
protect the wiring and for it to be nailed into the wooden beams (to ensure the sheeting is not
disturbed).
The insurer obtained further information from S rega rding the application of the ‘ AS/NZS 3018
– Electrical Installations – Domestic ’. This included a copy of the relevant excerpt which
states surface mounted cabling is acceptable if it is provided with adequate mechanical
protection to prevent damage.
Compl ainant’s position is not persuasive
The panel is not persuaded all the asbestos walls need to be replaced.
S’s evidence is persuasive in showing surface mounted cabling is acceptable. They have
quoted relevant standards. RCC agreed with this. Whilst KBA has provided a quote for
replacing all the asbestos walls, they have not commented on why the insurer’s proposed
method could not be done.
SVE says it will be nearly impossible not to disturb the walls. This is not persuasive given S
notes:
most of the wiring and conduits are fixed to timber battens or timber weatherboard
Determination | Case number: 792331 Page 4 of 10
similar methods could be employed for the new wiring.
The insurer’s position is also consistent with the pre -existing nature of the wiring. The photos
include several examples of the wiring being external to the walls. The insurer’s proposed
method is consistent with reinstating the wiring to its pre-existing condition.
Therefore, the panel does not accept KBA’s quote is fair and reasonable.
Insurer should allow a substantive contingency
The panel is concerned that RCC’s allowance for asbestos removal is low. Only ten square
metres has been allowed for its removal and replacement at a cost of $1,300 (exclusive of
builder’s margin and GST) for the sleepout area.
There seems to be a legitimate risk that further removal of asbestos would be required whilst
the repairs are undertaken. This is because it is not clear that:
all the wiring in the other rooms could all be secured on timber battens or weatherboard, or
no other asbestos sheeting would be disturbed during the re-wiring process
Therefore, the panel accepts a substantive contingency should be added to account for this
risk. In this regard, the panel considers 35% is fair. Whilst this is higher than the amount
AFCA would normally allow, the panel notes the following factors specific to these
circumstances:
the additional cost of removing and replacing asbestos can result in a significant increase
as evident by the substantial differences between RCC and KBA’s quote
the insurer’s own initial estimates were substantially undervalued ($19,148.10 compared to
the current quote of $35,061.58) which shows the final cost is not easy to estimate
there is a real risk further works would be required if any asbestos becomes disturbed, or
is likely to be disturbed, during the works.
Therefore, the insurer should pay the following in full and final settlement of the claim:
$47,333.13, minus any amounts it has already paid and any outstanding applicable policy
deductions (e.g. excess)
interest on the above outstanding amount pursuant to section 57 of the Insurance
Contracts Act 1984 (the Act). Interest is payable from thirty days after RCC issued its
quote until payment is made.
Insurer is to settle temporary accommodation in this way
There is no dispute the complainant is entitled to temporary accommodation whilst the repairs
are being done.
The insurer is to obtain an estimate from RCC as to how long it would take for the works to be
completed. Once this is done, the insurer should add a 35% contingency on the timeframe
and then provide temporary accommodation benefits for the overall period of time pursuant to
the policy.
2.2 Is the complainant entitled to non-financial loss?
Compensation is awarded conservatively
Under the AFCA Rules, we may award compensation (capped at $5,400) for non-financial
loss where a complainant has suffered an unusual degree or extent of physical
Determination | Case number: 792331 Page 5 of 10
inconvenience, time taken to resolve the situation or interference with their expectation of
enjoyment or peace of mind.
We take a conservative approach to compensation for non-financial loss. It is not awarded
when a person suffers the normal degree of inconvenience when a problem occurs.
Insurer managed claim reasonably well
The complainant seeks compensation for stress and inconvenience (non-financial loss) due
to the way the insurer handled their claims.
The complainant says the insurer breached its duty of good faith by failing to finalise the claim
in a timely manner. He says the delays resulted in his family living without appropriate heating
throughout winter due to the number of functioning power points in the property.
The complainant lodged the claim on 14 November 2020. The claim notes show the insurer
offered the complainant the option for temporary accommodation on 17 November 2020 and
2 December 2020. These were rejected.
The claim was assessed, and multiple scopes of work were drawn. The complaint was lodged
with AFCA on 25 March 2021.
Having reviewed this information, the panel is not satisfied there is sufficient information to
show the insurer mismanaged the claim. Given the type of damage and that fact the claim
occurred prior to Christmas, the panel is satisfied the insurer managed the claim
appropriately.
The panel notes the circumstances of the claim itself were unfortunate and limited. However,
temporary accommodation was offered to the complainant and it was rejected. The
complainant does not appear to have returned to the insurer to request it at a later stage.
Given this, the panel is not satisfied the complainant established the insurer mismanaged the
claim such that an award of non-financial loss is warranted.
Determination | Case number: 792331 Page 6 of 10
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
A panel determined this matter
Due to the nature of this complaint, we referred it to a panel for determination. The panel
includes:
an ombudsman
a member with significant experience in consumer and small business advocacy
a member with extensive experience in the insurance industry.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
Determination | Case number: 792331 Page 7 of 10
3.2 Relevant policy terms
What you are covered for – Insured events
You can choose to take out insurance for your home or your contents at the insured address, or
both. The cover you have chosen will be shown on your certificate.
If you have a home insurance policy, we cover your home fo r loss or damage at the insured
address caused by an insured event during the period of insuranc e.
If you have a contents insurance policy, we cover your contents for loss or damage at the
insured address caused by an insured event during the period of ins urance.
There are some things we do not cover and these are shown in the ‘We do not cover’ section of
the following tables on pages 28 to 41 and in the ‘General exclusions’ on pages 76 to 83.
Fire
We cover
Loss or damage caused by fire (burning with flames), including bushfire.
We do not cover
Loss or damage arising from:
• heat, ash, soot and smoke when your home or contents have not caught on fire unless it is
caused by a burning building within 10 met res of the insured address;
• arcing, scorching or cigarette burns, unless and only to the extent that a fire spreads from the
initial burn spot;
• pollution or vapour from a home heater or a cooking appliance unless a fire spreads from the
initial source.
Temporary accommodation when you have home cover
We cover
When an ins ured event damages your home to the extent you cannot live there, and we agree,
we will pay for your reas onable temporary accommodation costs for the time it will take to repair
or rebuild your home to a liveable condition. We will also pay for temporary accommodation for
your domestic pets in a commercial boarding establishment for the same period that we pay for
your temporary accommodation.
The most we will pay it:
• up to 4 weeks in short term accommodation agreed to by us (e. g. standard rates for a hotel,
motel or serviced apartment), then if necessary;
• up to another 48 weeks in residential accommodation of a similar standard to your home.
Lifetime guarantee on home repairs
Determination | Case number: 792331 Page 8 of 10
When we repair or rebuild your home, we guarante e the quality of materials and workmanship of
that work for the lifetime of the home if we:
• authorise;
• arrange; and
• pay the builder or repairer directly for this work.
3.3 Relevant expert evidence
Record Key points
Complainant’s expert ( SVE )
Report
20 - 11 - 20
Electrical fault cased a fire to start in the right room of the house.
This has damaged 2 circuits which will need replacing. Also, the
wiring does not meet today’s standards and cannot be clipped
along the wall like it has been.
To prevent any further fire an insulation resistance test was done
on all circuits. Majority of the circuits failed. Only 2 lights and 2
PowerPoints passed the test and are operating correctly.
Bringing the home up to standard will require full re - wire but will
be near impossible without disturbing the asbestos in the walls.
Majority of exterior and interior walls are made from asbestos and
I also believe the insulation may be asbestos too. This will require
the removal of all asbestos to rewire the home to AS3000
Standards.
Financial firm’s expert ( RCC )
Report
20 - 11 - 20
Switchboard is in OK condition for its age, however does not have
RCDs (safety switches), it is asbestos, and the service mains are
not compliant (they are not mechanically or electrically protected).
In our opinion without any works taking place the switchboard and
sub - circuit wiring was compliant at time of install and as such is
compliant wit hout additions or alterations. The Consumers mains
are not protected but the event of this claim h as not affected the
mains.
In closing, we confirm the damages to the sub - circuit wiring is a
result of the fire and the switchboard and consumers mains will
need to be upgraded to allow the repair work to be carried out, but
the remainder of the sub - circui ts can just be tested at time of
switchboard replacement. If cabling tests OK according the AS
3019, they are fine to be rec onnected.
Financial firm’s expert
( asse ssor )
Report
17 - 12 - 2020
Assessor has reviewed RC’s report following their site attendance
o n 20 November 2020. RCC confirmed there was electrical wiring
to have caught fire which has caused damage to the wiring, wall
and ceiling linings as well as carpet. RCC requested an Electrician
specialist to attend and inspect the property for scope.
RCC Electrician has advised the switchboard and mains will need
Determination | Case number: 792331 Page 9 of 10
Record Key points
to be upgraded to allow repairs work to the remainder of the work
to be carried out but the remainder of the sub circuits came just be
tested at the time of the switchboard replacement. RCC co nfirm if
the cabling tests OK, according to AS 3019 they are fine to be
reconnected.
The customer has provided their own electrical report. This report
advis ed the wiring is not to today’s standards and can now be
clipped along the wall like it has been.
They advised most of the circuits failed insulation resistance
testing and only 2 lights and 2 power points were operating
correctly.
They have noted to bring the home up to standard they will require
a full re - wire but will be near impossible without di sturbing
asbestos.
Financial firm’s expert ( KBA )
Report
23 - 12 - 2020
Your a dvice would be to upgrade the switchboard and bring it up
to current Australian Wiring Rules Standards 3000:2018. Rewire
the VIR circuits and rewire/provide mechanical protection to the
non - conformant cabling. However, testing of the wall and ceiling
linings for asbestos would be required. Which could ultimately
mean as bestos removal before any works can proceed.
Upon inspection of the property, and the information provided to
us by our electrician. The damage has been caused by an
electrical short. The existing wiring is not compliant to today's
standards, including the installation locations of the wiring. The
property has several metal conduits on the external face of the
wall and ceiling linings that house the old wiring. To carry out
repairs, these wires will need to be remove, replaced and
relocated into the wall and ceiling cavities. The existing wall and
ceiling linings contain asbestos. All the associated wall and ceiling
lini ngs will need to be replaced during and prior to the electrical
repairs commencing. Upgrade the switchboard and bring it up to
current Australian Wiring Rules Standards 3000:2018. Rewire the
VIR circuits and rewire/ provide mechanical protection to the non -
conformant cabling. However testing of the wall and ceiling linings
for asbestos would be required. Which could ultimately mean
asbestos removal before any works can proceed.
Financial firm’s expert ( S )
Report
23 - 12 - 2020
The repairs required to reinstate the residence aft er the fire
include the replacement of the damaged wiring (2 circuits) and
switchboard including re - running the consumer mains and the
replacement and or repainting of the wall and ceiling linings in the
s leepout.
The RCC tender amount for the reinstatement of the residence
due to the fire damage is $19,148.10 and should be considered.
Any electrical circuits not damaged by the fire, which when tested
are not serviceable, should be the responsibility of the insured to
replace/repair up to current standards.
Determination | Case number: 792331 Page 10 of 10
Record Key points
A review of AS/NZS 3018 – Electrical Installations – Domestic has
indicated that surface mounting of cabling is acceptable when
mechanic ally protected, ie inside a conduit.
With regards to the need t o remove all the asbestos, as shown in
the electrical report, the majority of the wiring and conduits
currently installed are fixed to timber battens or on timber
weat herboards and can be replaced without disturbing the
asbestos sheeting below.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.