Home / Youi / Determination 791067

Determination 791067

Hail damage roof claim cash settlement variation cost dispute

FirmYoui
Decided2021-09-28
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$6,107
Non-financial loss—
Amount claimed$10,305
SourceAFCA PDF

Summary

The complainant's roof hail claim was cash settled, and her repairer MB sought a higher variation cost for additional work to meet QBCC standards. AFCA decided the insurer should pay $6,107.32 plus a 15% allowance, rejecting the full claimed variation amount.

The policy allows the insurer to pay the fair and reasonable cost of repairs as determined by it, and the variation required insurer approval that was not sought before the work was completed.

Issues

Subjects and remedies

home or building damagenatural disasterthird party authoritypay claim

Related

All Youi determinations · Find similar determinations

Text of the determination

Determination Case number 791067 Financial firm Youi Pty Ltd Determination | Case number: 791067 Page 1 of 5 Case number: 791067 24 September 2021 1 Determination overview 1.1 Complaint The complainant holds a building insurance policy with the financial firm (insurer). On 9 October 2020 the complainant lodged a claim for hail damage to her roof. The insurer cash settled the claim ba sed on the quote provided by the complainant’s preferred repairer (MB). Following the completion of repairs, MB submitted a variation cost to the insurer for approval. MB says it cost an additional $11,125.36 to complete the repairs to standard. The insurer accepted a variation was required but says MB’s costs exceed a fair and reasonable amount. The insurer offered $6,107.32. MB invoiced the complainant for $10,304.97 and says it will settle for this amount. When the insurer would not agree to this, MB lodged this AFCA complaint on behalf of the complainant. MB is the complainant’s listed representative. 1.2 Issues and key findings Is it fair for the insurer to increase its settlement offer? It is fair in all the circumstances that the insurer increases its settlement offer of $6,107.32 by an additional 15%. This is because:  the policy says the insurer will only pay the fair and reasonable cost of repair work  the insurer raised several valid concerns regarding the reasonableness of MB’s claimed costs which MB has not sufficiently addressed  the insurer was not provided the opportunity to assess the variation work required and MB did not seek approval to proceed with the work as required under its own quote  the available information shows the insurer’s quote for the variation will allow the repairs to be adequately completed to the required standard  it is fair in all the circumstances to increase the insurer’s quote by 15% to allow for the transfer of risk to the complainant and the loss of the lifetime guarantee. 1.3 Determination This determination is substantially in favour of the insurer. Upon the complainant’s acceptance of this determination, the insurer is to pay the complainant $6,107.32 (if it has not already done so) and an additional allowance of 15% on this amount. Determination | Case number: 791067 Page 2 of 5 2 Reasons for determination 2.1 Is it fair for the insurer to increase its settlement offer? It is fair in all the circumstances that the insurer increases its settlement offer of $6,107.32 by an additional 15%. This is because:  the policy says the insurer will only pay the fair and reasonable cost of repair work  the insurer raised several valid concerns regarding the reasonableness of MB’s claimed costs which MB has not sufficiently addressed  the insurer was not provided the opportunity to assess the variation work required and MB did not seek approval to proceed with the work as required under its own quote  the available information shows the insurer’s quote for the variation will allow the repairs to be adequately completed to the required standard  it is fair in all the circumstances to increas e the insurer’s quote by 15% to allow for the transfer of risk to the complainant and the loss of the lifetime guarantee. AFCA can only consider the complainant’s con cerns Under our Rules, AFCA cannot consider any complaint MB has with the insurer in its capacity as a repairer. This is because the insurer did not provide a financial service to MB. My review is therefore limited to whether the insurer has an obligation to increase the complainant’s cash settlement beyond $6,107.32 as already offered. MB says a variation was required to ensure the repairs were to standard MB says the variation was submitted because further tie downs were required to complete the repairs in accordance with Queensland Building and Construction Commission (QBCC) standards. MB says the insurer was appropriately notified a variation might be required because its original quote, which the insurer agreed to settle on, stipulates that: This estimate does not include and additional collar ties, struts, or rafters. Should these be required for certification and to comply with QBCC standards a variation will be submitted for your approval. If any extra tie downs are needed from direction of the certifier other than noted in the scope of works a variation will be submitted to the insurance for approval. Insurer says it was not informed of the variation before MB completed repairs When the insurer cash settled the complainant for MB’s repairs, the complainant signed an agreement that released the insurer from any further liability for the claimed damage. However, the insurer accepts additional work was required to bring the repairs to code and it agreed to cover what it considers to be the reasonable cost for the variation. The insurer does not agree that MB’s variation cost is fair and reasonable. It says MB did not inform it of the need for additional repairs until the work was completed. It was not given the opportunity to assess the variation required, and to confirm a reasonable repair cost. The insurer provided a quote from its builder (AB) for $6,107.32 and offered to pay the complainant this amount. AB confirmed this is the amount it can supply the materials and complete the work for. Determination | Case number: 791067 Page 3 of 5 The policy says the insurer will pay the reasonable cost of repairs The complainant’s policy outlines that, if the complainant wishes to use her own repairer she can. However, the insurer may not authorise repairs and it will only pay the fair and reasonable cost for repair work as determined by the insurer. It says: You may choose another repairer, however we may not authorise repairs. If we do not authorise repairs we will pay you the fair and reasonable cost of repairs as determined by us, considering a number of factors, including comparison quotes from an alternate repairer we choose and our Quality Guarantee will not apply. Therefore, while the complainant can choose to use MB as a repairer, this does not mean MB’s costs will be automatically accepted. The insurer is entitled to review MB’s c osts and to compare them against comparable quotes to ensure they are fair and reasonable. Insurer raises several concerns with MB’s quote for the additional work MB initially invoiced the complainant $11,125.36 for the additional work. However, MB contracted the work out to a roofer who invoiced MB for $9,790. The insurer says the contractor’s initial invoice includes a supply of carpenters, which would be classified as labour, and it also lists ‘Supply & Install’ next to each part required. The insurer says it appears the invoice includes labour twice. MB has since amended the complainant’s invoice to $10,304.97. However, this also lists ‘Supply & Install’ in addition to labour, and the supply of four carpenters for installation. MB has not sufficiently explained the apparent duplication of labour costs in its invoice. Upon the provision of an itemised invoice from MB’s contracted roofer , the insurer also noted upgraded materials were used. The invoice suggests the upgrade was due to supply issues. However, the insurer says this has not been established and it provided a list of three suppliers with the required material. The insurer says the upgraded materials are more than twice the cost of the required material and unreasonable in the circumstances. MB has not satisfactorily responded to the insurer’s reasonable concerns about the costs in its , and its contractor’s, invoice. MB just says the claimed costs are what it actually cost to do the work. This is not sufficient to establish the claimed costs are covered under the policy. Fair for the insurer to settle the complainant $6,107.32 plus a 15% allowance I have reviewed AB’s itemised quote for the variation work. It is consist ent with the recommendations from the building certifier and engineer. I appreciate MB says this is a liability quote and does not reflect the true cost incurred. However, given the insurer was not notified of the need for the work before it was completed, the insurer was unable to complete a quote based on a site assessment. This was from no fault of the insurer’s. The insurer has, however, provided a quote based on the engineer’s and building certifier’s recommendation for the additional work. It also reflects MB’s scope of works less the additional labour and upgraded materials. AB confirmed it can organise trades to the complainant’s location and can guarantee the work for the quoted amount. I accept this is sufficient to establish what it would reasonably cost the insurer to complete the work itself. Determination | Case number: 791067 Page 4 of 5 I note AB included a 19% mark-up in its quote. The quote does not, however, itemise its builder’s margin, insurance and site supervision costs. I therefore consider the 19% mark -up is to account for these costs. I must also consider that a cash settlement transfers the risk to the complainant to organise the repairs herself. It removes the availability of the life time guarantee which is provided on the insurer’s authorised repairs. This was not factored in the insurer’s initial cash settlement. The risk of additional unforeseen contingencies was also transferred to the complainant when her claim was cash settled. Considering all this, I accept it fair in all the circumstances for the insurer to pay the complainant $6,107.32, plus an allowance of 15%, to finalise the additional work required to bring the roof repairs to code. MB’s additional submissions do not assist the complainant MB has provided several submissions on behalf of the complainant. I have carefully reviewed these submissions; however, they do not assist the complainant. MB says its initial quote informed the insurer variations were required. This quote was addressed to the complainant, not the insurer. Even if it was addressed to the insurer, I do not agree it informs the insurer additional unquoted costs would proceed without approval. The quote says, should additional costs be required, ‘a variation will be submitted for your approval’. It also says, ‘ If any extra tie downs are needed […] a variation will be submitted to the insurance for approval ’. This shows the variation was subject to approval by the recipient of the quote and the insurer. It does not give MB permission to proceed without approval. MB says it could not wait for approval because the roof was already off and, it would have inconvenienced the complainant. I do not agree this gives MB a right to proceed with variation work without seeking approval, a requirement outlined in its own quote. The complainant has a temporary accommodation benefit available under the policy. She therefore would have been entitled to temporary accommodation if required while approval was sought. MB says the insurer previously offered $8,500 in resolution of the complaint and this establishes AB’s quote is not reasonable or actionable. I do not agree. The insurer made a commercial offer of $8,500 in full and final settlement of the comp lainant’s concerns. This was an early attempt to resolve the complaint. The insurer is at commercial liberty to make such an offer on a good will basis and it is not an admission of liability. This offer was withdrawn by the insurer when MB rejected it. It is not clear if MB communicated the insurer’s offer of $8,500 to the complainant. An email exchange between MB and the insurer, dated 23 February 2021, shows MB refused the offer because its own estimator advised against it, not the complainant. However, as the insurer withdrew this offer, and because the information shows AB’s quote plus a 15% increase is adequate, I am not in a position to reinstate the insurer’s offer for th e complainant. It would not be fair to require the insurer to cover all the claimed costs It is not clear if MB sought the complainant’s approval to proceed with the variation work. However, neither the complainant nor MB notified the insurer that additional work was required before it was completed, despite expecting the insurer to cover these costs. I do not accept this was fair in the circumstances. I do not accept it is fair for the insurer to pay the complainant for all of MB ’s costs when the available information shows MB invoiced for expenses that are not fair and reasonable. Determination | Case number: 791067 Page 5 of 5 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.