Claim declined for cracking and movement damage to home allegedly caused by earth movement versus a 2017 mains water leak
Text of the determination
Determination
Case number 790942
Financial firm RAA Insurance Limited
Determination | Case number: 790942 Page 1 of 24
Case number: 790942 27 June 2022
1 Determination overview
1.1 Complaint
The complainant holds a home and contents insurance policy with the financial firm (insurer).
He lodged a claim in December 2020 for cracking and movement damage to his home.
The insurer identified a misaligned shower drainpipe but said this did not contribute to the
damage. It said the damage is a result of general ground movement which is excluded under
the policy. It declined the claim.
During the complaint process with AFCA, the complainant recalled an earlier leak from a
mains water pipe in October 2017. The insurer‟s engin eer recommended a soil suction test to
determine whether this leak had caused the claimed damage. The insurer agreed to pay the
complainant‟s preferred engi neer for this testing. The complainant did not arrange this test.
The complainant says there is sufficient evidence to show his home has suffered significant,
widespread damage because of leaks. He says the insurer and its agents have engaged in a
deliberate campaign to obfuscate the truth and decline the claim. He seeks for the insurer to
repair all damages, reimburse his costs, and pay compensation.
1.2 Issues and key findings
Is the insurer liable for some of the claimed damage?
Yes. The available information establishes on the balance of probabilities:
the complainant has established a valid claim for some of the claimed damage
while damage was caused by earth movement, the proximate cause of the earth
movement was the 2017 leak
a soil suction test is not required to determine causation but to determine when it is
appropriate to commence repairs.
How is the claim to be settled?
The parties are to take the actions and settle the claim and complaint as set out in section 2.2
of this determination.
Is the complainant entitled to compensation?
Yes. The available information establishes it is fair the insurer reimburses the complainant for
the cost of expert reports from his engineer and plumber.
The available information establishes the complainant is entitled to some compensation
because the insurer adequately managed the claim save for the delay in maki ng a claims
decision after receipt of IN‟s report .
Why is the outcome fair?
The available information establishes on the balance of probabilities damage was caused to
certain areas of the property by the 2017 leak., Whilst the insurer is not entitled to decline the
claim, the available information does not establish the extent of damage claimed by the
Determination | Case number: 790942 Page 2 of 24
complainant. In those circumstances it is fair the claim is settled based on IN‟s preliminary
scope of works which is to be updated as set out i n section 2.2 of this determination.
The complainant has not lodged a claim for damage caused by newly identified leaks. It
would not be fair for AFCA to consider this damage without the insurer having the opportunity
to assess its liability via its usual claims process.
It is fair the insurer pays $2,500 compensation for failing to assess the claim upon receipt of
IN‟s report.
It is fair the insurer reimburses the complainant for the cost of IN‟s and AL‟s reports (if not
reimbursed already) because the reports assisted in the assessment of the policy response to
the claim and will assist with the future repairs.
1.3 Determination
This determination is substantially in favour of the complainant.
Should the compliant accept this determination then within seven days of notification of
acceptance, the parties are to take the actions and settle the claim and complaint as set out
in section 2.2 of this determination.
Should the complainant accept this determination then also within seven days of notification
of acceptance, the insurer is to pay to the complainant:
$2,500 non-financial loss compensation
$2,250 for past temporary accommodation
$1,563.10 for his plumber‟s report (if not reimbursed already)
$ 2,750 for his engineer‟s report.
If the complainant has paid for the reports, and subject to proof of the date of payment for the
reports, the insurer is also to pay interest pursuant to section 57 of the Insurance Contracts
Act 1984 (the Act) from the date of payment of the reports until settlement.
Determination | Case number: 790942 Page 3 of 24
2 Reasons for determination
2.1 Is the insurer liable for the claimed damage?
Complainant has the onus to establish a valid claim
The complainant must establish on the balance of probabilities he has suffered a loss caused
by an event to which the policy responds. This is known as a prima facie or valid claim.
Once so established, the onus shifts to the insurer to prove on the balance of probabilities
that an exclusion applies if it seeks to deny or limit its liability for the loss.
The complainant ‟s policy provides cov er for certain events listed in the policy, including loss
or damage because of bursting, leaking, discharging or overflowing water from various items
including pipes and drains.
Relevant to the dispute, the policy excludes damage caused by earth movement such as
subsidence, shrinkage and any other type of earth movement.
Extracts from relevant policy terms are set out in supporting section 3.2 of this determination.
Complainant lodged a claim for cracking damage to front of the home
The complainant contacted the insurer in December 2020 claiming cracking damage to the
front corner of the house from an unknown cause. The damage was said to have been
occurring over the previous 18 months. The claim was lodged for this damage.
A report prepared by assessor (A) in December 2020, describes cracking to the front corner
of the house, a garage wall, and the concrete driveway near the garage entrance, as well as
balcony floor tiles which had cracked in various locations.
The claim has since evolved into a claim for damages across the entire home which the
complainant says has suffered significant structural damage and may require a rebuild.
The most recent information includes a report from the complainant‟s engineer (IN) dated 18
January 2022 and a report from his plumber (AL) dated 7 February 2022. AL identified
numerous leaks which did not form part of the initial claim.
This determination is confined to the claim for resultant damage caused by leak in 2017.
Both parties obtained expert opinion. Extracts from the opinions are set out in supporting
section 3.3 of this determination.
This determination adopts IN’s terminology to identify the claimed damage
For the purpose of this determination, the panel adopts IN‟s terminology to identify th e
claimed damage as follows:
1. In May/June 2017, IN notes there was a pressurised mains water leak next to the
mandarin tree at the front of the building. The leak was repaired in 2017. This is noted
Event 1 in IN‟s report.
2. The downstairs shower drain was found to be dislodged by a plumber in November
2020. This is noted as Event 2 in IN‟s report. (IN says the leak has not been repaired
and says the downstairs shower has not been used since December 2020).
Determination | Case number: 790942 Page 4 of 24
3. The upstairs shower alcove is leaking; however, this has not been confirmed by a
plumber. For the purpose of IN‟s report, this unconfirmed leak is referred to as Event 3 .
As recommended by IN in February 2022 the complainant arranged for AL to undertake water
leak investigations, testing, and CCTV inspections.
AL noted no pipe repairs were performed at that stage. AL confirmed cracking movement and
water damage was evident in various places.
Several leaks (including past leaks) were identified but, most relevantly to the claim made and
IN‟s observations, in the downstairs bathroom the PVC floor trap had completely separated
from the floor trap riser pipe and had subsided, leaving a large gap where water during the
shower/bath floods into the underfloor area. An inspection of the drainage stack at path level
from the upstairs bathroom reveals the pipe bend has been cracked in the past and has been
silicone sealed.
2017 leak not identified as cause of the claimed damage when claim first made
When the claim was first made and before the complainant identified the 2017 leak, the
insurer engaged a plumber (LH) to identify any leaking pipes which may have contributed to
damage. LH supplied a report in January 2021 and recommended the complainant repair the
shower and laundry sewer branch drains and renovate the shower alcove area.
When LH provided his report, the claim only consisted of what IN identified as Event 2.
LH noted:
the shower drain had completely separated from the earthenware main sewer drainage
pipe
minor root intrusion and leaks from a laundry branch pipe
major leaking from the shower branch pipe and minor leaking from the laundry branch pipe
leaking from the shower alcove was due to lack of waterproof membrane and puddle
flange, and imperfect grout and silicone seals
otherwise in the bathroom, toilet, laundry, and kitchen LH said no faults or leaks were
located
downpipes discharged to the ground rather than a storm water system
several areas of fault, root intrusion and areas of leakage were in the sewer pipe work
adjacent to the laundry and shower
no faults and/or areas of leakage were located to the mains water.
The insurer sought comment from an engineer (GP) as to cause of cracking damage, and any
relation to the leaks. GP inspected and photographed the property in December 2020.
GP reviewed cracking to the carport at the front of the home and in the carport; to the shower
area of the downstairs bathroom and the laundry and to the rear walls.
At this time, no review was made with knowledge of the 2017 leak event.
GP undertook a floor level survey which identified settlement towards the rear of the home
which he said was likely because of the drying effects of trees and shrubs near the home. He
thought the damage in the carport was too far from the leaks in the bathroom.
GP said the leaks were unrelated to the claimed damage and should be repaired as soon as
possible. He identified the claimed damage was because of other causes such as long-term
differential movement of the foundations of the home or wear and tear or run-off water or
brick growth.
Determination | Case number: 790942 Page 5 of 24
The complainant supplied a report from engineer (TM). TM reviewed the report from LH and
inspected the property in February 2021. TM found no evidence of building movement yet
noted when the leak is repaired there is likely to be a reduction in soil moisture content
resulting in subsidence. TM says this may cause cracking damage, possibly in two or three
years.
Based on this material the insurer declined the claim because it was not satisfied the cracking
damage was caused by an insured event but by earth movement which is excluded from
cover.
The insurer acknowledged there was a leak in the PVC waste pipe from the shower. It said
there was no evidence the leak caused damage. It said the policy does not respond to repairs
to fix a broken pipe only the resultant damage.
2017 leak later identified as a possible cause of the claimed damage
During the complaint process with AFCA (in or about June 2021) the complainant recalled a
leak from a mains water pipe in October 2017 pipe which he had repaired, and which he then
said may be the cause of the claimed damage. He also said the upstairs shower drain had
commenced leaking and the bathroom floor tiles had commenced cracking at about same
time as the cracking to the front wall.
He supplied evidence of the 2017 leak, and the insurer agreed to look at this leak as part of
the current complaint. After discussion, it engaged another engineer (IP).
IP inspected and photographed the property on 4 and 5 August 2021 and carried out a level
survey. IP also reviewed various photographs taken before and after purchase.
IP notes the complainant owned the property from early 2017. The complainant told him he
began noticing damage at the time he made the claim in late 2020. During his inspections the
complainant showed him many examples of damage to the building, concrete pavement
around the building and the rear retaining wall.
The complainant told him the upstairs shower alcove had been leaking which he tried to
resolve by installing a fiberglass shower tray (Event 3). He says as it continued to leak this
caused moisture damage to the downstairs laundry and toilet ceilings.
At the time of IP‟s report, the source of the leak in the upstairs shower was not known and IP
said its cause should be investigated and the leak repaired. IP said the upstairs leak was not
contributing to footing movement.
IP researched the nature of the soil and concluded it was probably moderately to highly
reactive clay soil. IP said the actual foundation soil conditions at the site can be determined
by carrying out site sampling and undertaking soil identification and classification.
IP carried out a level survey which showed heave in the southeast corner (the apparent
location of the 2017 leak).
Having reviewed material from the water company IP accepted a water supply leak occurred
at the property in June – September 2017 but the water bills provided no evidence as to the
leak location.
IP accepted water would have leaked from the shower waste each time the shower was used.
He said the downstairs shower should not be used until the waste pipe is repaired.
Determination | Case number: 790942 Page 6 of 24
Insurer’s expert IP identified many issues which contributed to damage
The comprehensive report from IP is summarised in section 3 of this determination. In short,
IP‟s opinion is that there were many issues which contributed to the damage to the building.
IP said:
a leak from a mains water pipe occurred somewhere at the property in 2017
the leak may have caused heave and cracking at the southeast corner
the leak may have caused the shower drain to separate from the mains drain
the cause of cracking at the southeast corner may be differential footing movement due to
environmental influences
the evidence of previous movement is clear and cracking across the wider building is a
result of differential footing movement and unrelated to leaks
cracking to the external brickwork is brick growth
any damage to the retaining walls is wear and tear over time
damage to the upper entrance balcony tiles existed prior to purchase (therefore prior to the
2017 leak) although it is possible heave in the southeast corner could have worsened th is
damage
damage to the roof is unrelated to differential footing movement
leaks probably did not damage the perimeter paving.
On the available information IP was unable to conceive of a mechanism by which the
differential footing movement (regardless of its cause) could have caused the leak in the
upstairs shower.
IP said the available information did not conclusively establish whether the claimed damage
resulted from the leak, or differential footing movement. To determine the cause, IP
recommended total soil suction testing to determine the current moisture state of the soil and
monitoring the building over time to see if there are changes in seasonal and environmental
conditions.
If leak related heaving movement had occurred, IP concluded the resultant damage would
include:
cracking to the south-eastern garage walls
cracking of the south-eastern garage wall/floor joint
possible exacerbation of pre-existing cracking in the upper dwelling entrance balcony floor
tiles and
possibly the separation of the ground floor shower waste pipe.
Complainant’s expert report from IN considered
Upon receipt of IP‟s report, the insurer said the expert reports did not establish the differential
movement of the building was caused by leaks and IP‟s report was equivocal.
As IP said much of the damage to the building was unrelated to leaks the insurer made ex-
gratia offer of $7,500 which was rejected by the complainant. A more recent offer has also
been rejected by the complainant.
The complainant said the reports were misleading and false. The complainant also said it is
probable the footings are significantly compromised and that his entire home may be
damaged by movement.
The insurer was not willing to pay for a further engineer‟ s report about causation but offered
to pay the cost of soil suction testing and analysis direct to and to be carried out by the
complainant‟s preferred engineer, IN.
Determination | Case number: 790942 Page 7 of 24
The complainant agreed and supplied a quote in October 2021 from IN ($1,500 plus GST) for
a geotechnical investigation and soil suction testing.
The complainant subsequently supplied a causation and scope of works report from IN dated
18 January 2022. The report did not contain the agreed soil suction testing.
The complainant said before a soil suction test is performed more leak detection tests are
required.
The complainant provided two photographs of the rear fence describing them as a “soil
suction test”.
The complainant also said IN told him the soil suction testing could be performed (once
floorboards were removed) but this was not necessary because there was heave evidence
throughout the home.
The panel notes IN was not instructed to carry out the agreed soil suction testing. It is not
clear from the report if IN had a copy of the report from plumber LH.
The IN report is comprehensive and summarised in section 3 of this determination.
IN reviewed the other engineers‟ reports, conducted level survey tests, and inspected and
photographed the property on 27 October 2021. The photographs are usefully and
comprehensively annotated.
IN reported the complainant showers upstairs but this is taxing because of his medical
condition.
IN said the complainant was considering relocation to another property which he owns.
The panel notes IN‟s level survey results were very similar to IP‟s survey results. IN noted the
reduction in building movement since IP tested which IN thought was consistent with climatic
conditions.
IN said there was evidence of heave at the southeast corner in the vicinity closest to the
water leak in 2017. There was also localised heave at the location of the ground level shower.
IN reports it has many soil bore log investigations obtained through geotechnical
investigations across the nation. IN referred to numerous investigations conducted around the
subject site. Relying on this information IN said the soils near the site have been classified
mainly as highly reactive sites or extremely reactive sites. IN concluded:
Hence, the subject site is most likely founded on highly to extremely reactive clay
soil.
And that:
…. the subject building is founded on a highly to extremely reactive clay site with
deep-seated moisture changes which will experience high to extreme ground
movement from moisture changes.
Based on his observations and the level survey results IN said there was heave near the
leaks at the southeast corner of the building and outside the ground floor shower. At these
locations IN recorded elevated levels and noted cracks consistent with heave.
Determination | Case number: 790942 Page 8 of 24
IN considered that:
the claimed damage at the southeast corner is a result of the mains leak
it is plausible the leaking shower branch pipe was induced by the mains leak: a
comprehensive plumbing investigation is required to determine this and whether there are
further subsurface leaks
the building does not require structural underpinning
cracking inside and outside is aesthetic and not of structural significance except for one
crack adjacent to the front single garage
trees near the building on the northern wall have resulted in differential footing movement
surface cracks to concrete are typical of concrete shrinkage cracks
vertical cracking on each of the four corners is consistent with brick growth
the 2017 leak contributed to the concrete perimeter paving, cracking to the balcony and
driveway
much cracking damage pre-existed the property purchase and the 2017 leak or is caused
by wear and tear
the leaking shower caused cracking of floor and wall tiles in the ground floor bathroom and
minor wall cracking internal and external to ground floor bathroom
at most the leaking shower would have contributed to the cracking damage to the floor in
the upper-level bathroom and event 3 caused moisture damage to plasterboard ceiling of
ground floor toilet and bathroom and moisture damage to the suspended concrete slab
event 3 was caused by wear and tear and the lack of a membrane and at most the upward
movement from events 1 and 2 contributed to impairing the watertightness of the upstairs
shower
repairs to event related damage would be at least six months away (from his inspection) so
the moisture levels in the reactive clay soil can return to normal
soil suction testing can determine whether soil moisture levels are normal
further movement damage can be expected as soil moisture content returns to normal.
IN provided opinion on the cause of damage. He said the 2017 leak caused upward
movement of the house which will dissipate and reach a point of normalisation at which point
the moisture levels in the soil will be normal.
2017 leak caused damage; soil testing required to determine if repairs can
commence
IN said the leak damaged the building, but its effects were not yet completed. IN said more
time is needed for soil moisture levels to normalise.
Therefore, IN said it is premature to scope damages although he provided a preliminary
scope which is attached to his report.
The insurer indicated it obtained quotes. A quote was provided at the request of AFCA
recently. The insurer also made an offer to settle the claim which offer was rejected by the
complainant.
IN recommended level surveys, be performed in six months‟ time (from his inspection) to
gauge building movement and suitability for repairs to commence.
Comparing the level surveys undertaken by IP suggests the soil moisture levels are
decreasing.
As for soil testing, IN noted it had been commissioned but not performed. He said soil testing
would provide:
Determination | Case number: 790942 Page 9 of 24
the site-specific soil classification and characteristic surface level movement value, specific
to this site
the specific soil profile and soil layer characteristics, which can be used to draw expected
soil response to increases or decreases in soil moisture.
And total soil suction moisture testing can be performed:
to gauge whether the moisture levels in the soil are normal or abnormal
the testing determines the soils „affinity‟ to water and could be used to determine at which
point in time repairs should be made to the building.
Prior to any soil testing IN said a comprehensive plumbing investigation was to be
undertaken. This was done by AL as discussed earlier in this determination.
IN also recommended the prompt repair of the leaking ground floor shower branch pipe.
IN concluded in relation to the soil testing as follows:
Soil testing (total soil suction testing) at specific and targeted locations of the site,
to demonstrate that soil moisture levels are normal or abnormal, which will then
be used, in conjunction with repeat floor and brick course level surveys, when the
repairs to Event-related damage can be undertaken.
Complainant has established a valid claim
The panel notes IP said the available information did not conclusively establish whether the
claimed damage resulted from the leak, or differential footing movement and that he required
soil testing to determine the cause.
The panel notes many of the findings made by IN and IP are similar. However, IN was able to
determine the cause of damage. The panel find IN‟s report comprehensive and persuasive.
His opinion is supported by his inspection, photographs, and tests.
The panel is not satisfied a soil test is required to determine the cause of damage. The panel
accepts the available information establishes the soil is probably highly reactive. The panel
accepts the available information establishes the soil test is required to determine when
repairs should commence.
Based on the available information the panel is satisfied the complainant has established on
the balance of probabilities the damage as set out in IN‟s report and preliminary scope of
works was caused by the 2017 leak.
Having considered the plumb ers‟ reports, and IN‟s opinion, the panel is satisfied it is probable
movement from the 2017 leak caused the movement in the downstairs bathroom which
caused the leak from the downstairs bathroom.
And in turn the panel accepts IN‟s opinion that some of th e damage in the upstairs bathroom
contributed to impairing the water tightness of the upstairs shower enclosure which in turn
caused the damage described by IN in his report.
In short, the panel accepts the complainant has established a valid claim that the damage as
set out in IN‟s report and preliminary scope of works was caused by the 2017 leak.
Determination | Case number: 790942 Page 10 of 24
Available evidence does not establish leaks caused widespread damage
The complainant says the building has suffered widespread and significant damage. This
includes cracked ridge capping, cracking damage to a bathroom, blockages to internal pipes,
uneven flooring and walls which have visibly deviated from plane. He says the leaks have
affected foundations across the entire home which is now unsafe.
Having carefully considered the opinions of IN and IP, the panel does not accept these
submissions about the extent of damage.
The panel has considered the complainant‟s plumber‟s report (AL). AL identified new issues
including several leaks some of which are described as severe or large. The leaks were not
identified by any party previously, including the complainant. It is unclear when the leaks
developed. The available information does not establish these leaks have caused or
contributed to damage, nor is the panel provided with confirmation there is a new claim for
damage caused by these leaks.
Subject to the cause of these leaks being identified, the complainant is entitled to lodge a
claim for damage caused by newly identified leaks, and the insurer is to assess liability via its
usual claims process. In the event a dispute arises in relation to a claim for these newly
identified leaks, the complainant is entitled to bring a further complaint to AFCA.
This determination is confined to the claim for damage caused by the 2017 leak.
The panel does not accept the available information establishes the house requires
underpinning. The panel accepts the only damage caused by events 1,2 and 3 (as defined by
IN) is set out in IN‟s report.
On present information, the panel accepts some of the damage claimed by the complainant to
other areas of the house is caused by other causes which are either not insured events or are
excluded from cover.
Insurer has not established proximate cause of damage is earth movement
As for t he damage set out in IN‟s report and attributed to events 1,2 and 3, the panel does not
accept on the balance of probabilities the insurer has established this damage was caused by
earth movement. The panel notes IP was unsure about the cause of damage and
recommended soil suction testing to determine the current moisture state of the soil.
The panel is not persuaded IP required this test to help him determine the cause of damage.
The panel is satisfied IN has more persuasively described the reasons for a soil suction test
which are not to determine causation but to determine when it is appropriate to commence
repairs.
While there is earth movement which has caused damage, the panel is satisfied on the
balance of probabilities the proximate cause (or the dominant or effective cause) of the earth
movement is the leak in 2017.
Insurer not entitled to decline the claim
In the circumstances, based on the available information and for the reasons stated, the
insurer is not entitled to decline the complainant‟s claim for damage caused by the leak in
2017 and the subsequent damage to the southeast corner of the house, and the downstairs
and upstairs bathrooms. In this regard, the panel notes (as set out earlier in this
determination) IP‟s conclusion about the res ultant damage was similar.
Determination | Case number: 790942 Page 11 of 24
2.2 How is the claim and complaint to be settled?
IN to review AL’s report and provide opinion about the cause of the newly
identified leaks
Should the complainant accept this determination, if not done so already, the parties are to
immediately refer AL‟s report to IN. IN is to provide his opinion (at the insurer‟s expense)
about the cause of the leaks identified in AL‟s report and whether the leaks were caused by
the 2017 leak and subsequent movement in the downstairs bathroom.
If the leaks identified by AL are caused by the 2017 leak and the subsequent movement in
the downstairs bathroom, then the insurer is to assess liability via its usual claims process.
If the leaks identified in AL‟s report are unrelated to the 2017 leak and the subsequent leak in
the downstairs bathroom, the complainant should immediately repair the leaks (save for the
repair of the misaligned shower drainpipe in the downstairs bathroom). The cost of repairs of
leaks is not covered by the policy. The panel accepts the complainant is not required to repair
the misaligned shower drainpipe because it is resultant damage from the 2017 leak . In this
scenario, the insurer is not required to take any action until the complainant confirms these
other leaks are repaired. Seven days after confirmation these leaks are repaired the insurer is
to take the steps set out in the next section.
As set out earlier in this determination, depending on the cause of the newly identified leaks,
the complainant is entitled to lodge a claim for damage caused by newly identified leaks, and
the insurer is to assess liability via its usual claims process. In the event a dispute arises in
relation to a claim for these newly identified leaks, the complainant is entitled to bring a further
complaint to AFCA
Settlement mechanism provided
Should the complainant accept this determination then within seven days of notification of
acceptance the insurer is to undertake the following actions:
1. re-engage IN (at its expense) to advise whether repairs can be undertaken now
2. provide IN with AL‟s plumbing report
3. as set out in the proceeding section, ask IN to provide an opinion (at its expense) about
the cause of the leaks identified by AL
4. pay IN to carry out further level surveys and a soil suction test to determine if the
property is ready for repair
5. arrange for IN to finalise the preliminary scope of works set out in his report (including
the cost to repair the misaligned shower drainpipe in the downstairs bathroom) and
(depending on his opinion about the cause of the leaks identified by AL) other damage
caused by the leaks identified by AL
6. ask IN to specifically comment on the time it will take to undertake repairs
7. obtain a quotation for the cost of repairs based on IN‟s final scope of works
In the event IN says the property is not ready for repair, the insurer should follow IN‟s
recommendations in relation to repeat floor and brick course level surveys and any other tests
or investigations to confirm when repairs can be carried out.
Determination | Case number: 790942 Page 12 of 24
As set out in the proceeding section, if the leaks identified in AL‟s report are unrelated to the
2017 leak and subsequent leak in the downstairs bathroom, the complainant should
immediately repair the leaks (save for the repair of the misaligned shower drainpipe in the
downstairs bathroom). The cost of repairs of leaks is not covered by the policy. The panel
accepts the complainant is not required to repair the misaligned shower d rainpipe because it
is resultant damage from the 2017 leak . In this scenario, the insurer is not required to take
any action until the complainant confirms these other leaks are repaired. Seven days after
confirmation these leaks are repaired the insurer i s to take the next relevant steps set out in
the mechanism of settlement above.
The policy provides if the insurer accepts the claim, it can choose whether it will repair the
damage or pay the complainant what it would cost it to repair the damaged parts of the home.
The insurer is to decide whether it will carry out repairs or cash settle the complainant. If the
insurer cash settles the complainant, the insurer should ensure the cash settlement is fair and
includes a fair uplift to cover contingencies and variations which may occur once repairs
commence.
If the complainant wishes to obtain a quotation pursuant to IN‟s final scope of works, then he
is entitled to do so within 14 days of receipt of IN‟s final scope of works and the insurer‟s
quotation.
The parties are encouraged to work together to finalise the claim and the cost of repairs. If the
parties are unable to agree, the parties can return to AFCA for a decision about the cost of
repairs.
If the insurer cash settles the claim, it is to pay interest pursuant to section 57 of the Act on
the cash settlement from 18 February 2022 (one month after IN‟s report by which time it
should have made a claims decision) until settlement.
Available evidence establishes insurer is liable for some loss of rent
The complainant claims loss of rent. The complainant advised IN from August 2017 until
November 2020 the upstairs area was rented to 5 occupants while the downstairs area was
occupied by the complainant, his carer (Geoff), and another couple. He says because of the
leak in the downstairs shower and a bad sewerage smell the property was uninhabitable and
the tenant vacated. He claims $400 per week loss of rent.
The insurer refers to an earlier determination by AFCA (the earlier complaint) in which the
complainant claimed loss of rent because tenants left the insured property (and another
insured property) due to the COVID-19 pandemic.
The insurer says even if the complainant establishes there was an insured event arising from
the water leak, the subject of the current claim and this complaint, the complainant has not
established a valid claim for loss of rent in this claim and complaint.
It notes no rental agreement or other supporting documents have been provided.
In response the complainant says when the tenants left, he renovated upstairs with a view to
renting upstairs to one single tenant. He claims rental loss due to the pandemic was limited to
August 2020 (upstairs) and May 2020 (downstairs). But for the building damage, he says he
could rent the property on Air BNB or as a normal rental.
In recent emails the complainant also says two tenants (Dan and Geoff) vacated due to the
smell from the shower drain downstairs not the pandemic. From the available information the
panel can find no reference to rent paid by a tenant called Geoff.
Determination | Case number: 790942 Page 13 of 24
From the earlier complaint, the panel accepts a tenant called Dan rented downstairs in 2020.
The complainant says the claim for loss of rent should be paid because the policy provides
this additional benefit.
The panel agrees the policy provides the additional benefit of loss of rent, but the benefit is
subject to policy terms including if the home becomes unfit to live in, and it was being let at
the time of loss.
Having reviewed the available information including material on the earlier complaint the
panel accepts:
the complainant used to rent this property
the complainant used to live downstairs and rented upstairs.
someone called Dan rented downstairs but left when the complainant was in hospital in
late April 2020. He was paying rent at $410 per fortnight
the insurer has the necessary documentation from the earlier complaint to establish the
complainant was renting downstairs in 2020 to Dan for $410 per fortnight
the downstairs shower has not been used since December 2020 (see IN‟s report)
due to personal health concerns the complainant probably would not have secured new
tenants immediately once the old tenants left in 2020
the 2017 leak probably damaged the waste pipe in the downstairs shower causing it to
leak so the complainant can establish the downstairs bathroom is not used due to an
insured event.
Having considered the available information, the panel is satisfied downstairs is unfit to live in
if the shower cannot be used. IN indicates the downstairs shower has not been used since
December 2020. The panel considers this is not unreasonable because the shower would
leak every time it is used.
The available material does not support the complainant‟s contention that the whole property
is uninhabitable. The panel is not satisfied the complainant has established the upstairs floor
is unfit to live in.
The panel does not accept the tenants left and stop paying rent because of the damage
caused by the leaking pipe or the smell in the downstairs bathroom. This is because this was
not mentioned in the other complaint and the panel prefers contemporaneous evidence. The
panel accepts the tenants stopped paying rent and left the premises due to the pandemic.
The available information does not establish the property was let when this claim was made
in late 2020. Information from the earlier complaint shows various tenants were at the
property until about August 2020. Their leases were for different periods, and they vacated on
different dates. No other supporting documentation has been provided save for that in the
earlier complaint.
The panel considers it would be unfair to decline the claim for loss of rent on the basis the
property was not let at the time of the loss. This is because the panel accepts once the
complainant‟s personal h ealth concerns were over then he would have resumed renting
downstairs.
From material on the earlier complaint the panel accepts due to personal health concerns the
complainant probably would not have secured new tenants in 2020 when th ose tenants left.
The panel considers the complainant probably would have resumed renting downstairs once
it was safe to do so after the complainant received two vaccinations against Covid 19 (the
safe date).
Determination | Case number: 790942 Page 14 of 24
In all the circumstances, subject to the policy terms, the panel considers it is fair the insurer
pays the complainant for loss of rent for the ground floor at the rate of at least $440 per
fortnight from the safe date until the ground floor is fit to live in.
The insurer is to pay interest pursuant to section 57 of the Act on the loss rent settlement
from 18 February 2022 (one month after IN‟s report by which time it should have made a
claims decision) until payment.
Should the complainant accept this determination within seven days of acceptance, the
complainant is to provide the insurer with the date he received the two vaccinations against
Covid19 and documentation establishing Geoff rented downstairs.
The panel acknowledges rental costs have probably increased since 2020. The parties are to
work together to establish a fair current rate and then the insurer is to assess liability for loss
of rent of the ground floor via its usual claims process and pursuant to the policy terms.
The parties are encouraged to work together to finalise the claim for loss of rent of the ground
floor. If the parties are unable to agree, the parties can return to AFCA for a decision about
loss of rent of the ground floor.
Insurer to pay complainant $2,250 for past temporary accommodation
The complainant said he was having difficulty showering as one shower was disconnected
and the other shower leaked. The insurer was not prepared to pay for temporary
accommodation based on the then available information but was willing to pay for the soil
suction tests recommended by IP.
In November 2021 the insurer reconsidered the temporary accommodation request. It offered
to pay temporary accommodation costs at the rate of $450 per week for five weeks.
The complainant said $450 per week was insufficient to find suitable accommodation. He
supplied some quotations for his accommodation and pet accommodation.
In February 2022 the complainant said he was paying $1,260 per week for accommodation.
The insurer said the complainant had not provided copies of any invoices or proof of payment
to support this claimed expense. The insurer asked for supporting documents. It said it was
not prepared to consider the claim for reimbursement unless the requested information was
provided.
IN met with the complainant on site on 27 October 2021. He noted the leak in the downstairs
shower drain was still not repaired. IN understood the complainant showered in the upstairs
bathroom but given his medical condition this was taxing. At the time of inspection IN noted
the complainant was considering relocation to another property which he owns.
In the absence of proof of payment to support the claimed expense, the panel is not satisfied
on the available information the insurer is liable to pay more than its current offer for
temporary accommodation.
Should the complainant accept this determination then within seven days of notification of
acceptance the complainant is to provide to the insurer supporting documents for past
temporary accommodation. The insurer is to promptly consider the claim for reimbursement
when and if further supporting documentation are provided by the complainant.
Should the complainant accept this determination then within seven days of notification of
acceptance, the insurer is to honour its offer and pay the complainant $2,250.
Determination | Case number: 790942 Page 15 of 24
Insurer to address if temporary accommodation payable while repairs are
undertaken
The panel notes the policy provides cover for temporary accommodation if it agrees the home
is unfit to live in because of damage caused by an insured event. Subject to some limits the
policy covers an insured for the cost of temporary accommodation for the complainant during
the time it takes to repair the home.
Should the complainant accept this determination the insurer is also to consider whether
temporary accommodation is payable while repairs are undertaken.
The parties are encouraged to work together to finalise the claim for temporary
accommodation. If the parties are unable to agree, the parties can return to AFCA for a
decision about the past and future temporary accommodation.
2.3 Is the complainant entitled to compensation?
Insurer to pay $2,750 for IN’s report
AFCA can require an insurer to reimburse a complainant‟s costs (capped at $5,400) incurred
in making a complaint, including expert report fees. These costs will be awarded if they were
fair and reasonable and helped resolve the complaint.
The insurer engaged plumber LH to ascertain whether leaks may have contributed to the
damage. LH identified a leak and reported this to the insurer. The insurer then engaged
engineer GP to comment on whether the leak caused or contributed to the claimed damage.
These reports were prepared before the complainant advised the insurer of the 2017 leak
incident.
Relevant findings are set out in supporting section 3 of this determination and earlier in this
determination.
The complainant distrusted LH‟s findings and elected to obtain another plumbing report from
AL. While AL identified leaks from fixtures and fittings which were not noted in the LH report,
it reached similar conclusions regarding the disconnected shower pipe.
On its own, the AL report has not assisted in resolving the complaint. Nonetheless in view of
IN‟s recommendation the complainant engaged AL, the panel is satisfied it is fair the insurer
reimburses the complainant for the cost of AL‟s report ($1,563.10).
The panel understands from recent correspondence the cost of this plumbing report has been
reimbursed to the complainant.
Regarding IN‟s report, the insurer agreed to pay the cost of soil suction testing. The
complainant did not arrange this testing but instructed IN to prepare a structural report and
scope.
As set out earlier in this determination the panel considers:
IN‟s report persuasively establishes the 2017 leak damaged the home
Soil suction testing was not required to determine causation.
In these circumstances the panel is satisfied it is fair the insurer reimburses the complainant
for the cost of IN‟ s report.
IN provided an email in October 2021 indicating a forensic investigation and remediation
report would cost $2,500 plus GST.
Determination | Case number: 790942 Page 16 of 24
Should the complainant accept this determination then within seven days of notification of
acceptance the insurer is to reimburse the complainant as follows:
$1,563.10 for AL‟s report (if not done so already)
$2,750 for IN‟s report
If the complainant has paid for these reports, and subject to proof of the date of payment for
the reports, the insurer is also to pay interest pursuant to section 57 of the Act from the date
of payment of the reports until settlement.
The insurer is not liable to reimburse the complainant for the cost of TM‟s report. This is
because the report was prepared before the complainant provided the salient information
about the 2017 leak.
AFCA may award non-financial loss compensation in some circumstances
AFCA will award compensation (capped at $5,400) if there has been an unusual degree or
extent of physical inconvenience, time taken to resolve a complaint or interference with the
complainant‟s expectation of enjoyment or peace of mind.
AFCA takes a conservative approach to awarding compensation. We do not award
compensation because the complainant has suffered some inconvenience and anxiety. AFCA
expects complainants to be moderately robust and to bear the normal degree of
inconvenience experienced when a problem occurs and to take reasonable steps to manage
the situation.
AFCA cannot award punitive, exemplary, or aggravated damages.
Available information does not establish a breach of privacy
The complainant complains his privacy was breached by GP when sharing information with
others. He provided some screenshots in support of his contention.
The complainant says GP spoke highly of ID when they met. He accuses GP of deliberately
covering up significant issues, so his cartel can move to acquire a valuable property.
The insurer raised the issue with GP who denies the disclosure of confidential information.
GP says he does not know ID and has never met him.
In late February 2022 the insurer‟s privacy officer asked for further details. The panel does
not have any further information from the parties in relation to the insurer‟s privacy officer‟s
inquiries and provision of requested information.
Based o n the available information the panel does not accept the complainant‟s privacy was
breached by GP.
Insurer adequately managed the claim until receipt of IN’s report
The complainant made many submissions outlining his concern with the insurer‟s
management of the claim. He distrusted the insurer‟s experts, describing the reports as
flawed and seeking to hide relevant information. He considers the insurer‟s approach was
deliberately difficult and abusive.
The complainant says the insurer should pay compensation for the claims experience.
The panel has reviewed each submission and the available material carefully. The panel does
not agree the insurer or its contractors/experts deliberately manipulated or falsified
information. The panel does not agree the LH report of 11 January 2021 is misleading in
Determination | Case number: 790942 Page 17 of 24
describing the disconnected shower pipe as an external pipe from an internal wet area; this
description is accurate. While the exact location of the disconnection could be more clearly
marked, the impact on the report and its conclusions is immaterial.
The panel is unconvinced by the complainant‟s allegations that the insurer‟s engineer GP is
sinister or has otherwise acted improperly. The panel considers the available information
does not support this c onclusion. The panel considers GP‟s report contains no information
which has been contradicted by any other expert and was prepared before the complainant
advised of the October 2017 leak.
The panel is unconvinced that the insurer has deliberately sought to refuse the claim or has
otherwise acted improperly. The panel considers the insurer has sought to assist where it
could. Rather than direct the complainant to lodge a new claim after he recalled the October
2017 leak it agreed to investigate the new leak and then agreed to allow use the
complainant‟s preferred engineer rather than its own expert for soil suction testing.
Fair the insurer pays the complainant $2,500 compensation
The panel accepts the claim significantly interfered with the complainant‟s expectation of
enjoyment and peace of mind. Given the complainant‟s physical condition, the panel accepts
the claim caused physical inconvenience.
AFCA may only award compensation caused by some error or failure of the insurer. The
panel considers the insurer generally adequately managed the claim save for the delay in
making a claims decision after receipt of IN‟s report.
The panel notes the extensive discussion about the requirement of soil suction testing.
However, as set out earlier in this determination, the panel considers:
the testing was not required to make a claims decision
the claims decision could have been made in February 2022 (one month after IN‟s report).
Taking all matters into account, the panel is satisfied an award of compensation is warranted
for this delay. The panel is satisfied an award of $2,500 is fair in the circumstances.
2.4 Why is the outcome fair?
As the available information establishes on the balance of probabilities damage was caused
to certain areas of the property by the 2017 leak, the insurer is not entitled to decline the
claim. The available information does not establish the extent of damage claimed by the
complainant. In those circumstances it is fair the claim is settled based on IN‟s preliminary
scope of works.
The complainant has not lodged a claim for damage caused by newly identified leaks. It
would not be fair for AFCA to consider this damage without the insurer having the opportunity
to assess its liability via its usual claims process.
The insurer has managed the claim adequately and has not breached the complainant‟s
privacy but should pay $2,500 compensation for failing to assess the claim upon receipt of
IN‟s report.
It is fair the insurer reimburses the complainant for the cost of IN‟s and AL‟s reports (if not
done so already) because the reports assisted in the assessment of the policy response to
the claim and will assist with the future repairs.
Determination | Case number: 790942 Page 18 of 24
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
It is an accepted principle of general insurance law that the insured bears the onus to
establish on the balance of probabilities that they have suffered a loss caused by an event to
which the policy responds. This is known as a prima facie or valid claim. Once so established,
the onus shifts to the insurer to prove on the balance of probabilities that an exclusion applies
if it seeks to deny or limit its liability for the loss.
Caselaw and proximate cause
Case law establishes:
The proximate cause of the loss is the dominant or effective or operative cause of the loss
whether or not that be the last in time or the sole cause.
If there are several causes operating contemporaneously, each must be examined for the
qualities of reality, predominance and efficiency as the active, efficient cause that sets a
relevant chain of events in action. If one cause would have caused the harm in any case,
and the other would not have done so in the absence of the first, the first is the proximate
cause.
A common-sense approach is taken to determine proximate cause
A panel determined this matter
Due to the nature of this complaint, we referred it to a panel for determination. The panel
includes:
an ombudsman
a member with significant experience in consumer and small business advocacy
a member with extensive experience in the insurance industry
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
Determination | Case number: 790942 Page 19 of 24
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
AFCA’s role
AFCA is a complaint resolution service offered as a free alternative to the courts. We are not
a regulator of the financial services industry. We can consider individual complaints regarding
loss or damage caused by an insurer‟s actions.
The purpose of AFCA is not to punish or impose a fine on an insurer. We do not have the
power to review a general practice unless the practice breaches a specific duty or obligation,
or it is not consistent with industry practice. Organisations such as the Australian Securities
and Investments Commission (ASIC) and the Australian Competition and Consumer
Commission (ACCC) have a role in consumer protection and the regulation of the financial
services industry.
3.2 Relevant sections of policy wording
The relevant policy extracts are referred to in the correspondence between the parties and in
the insurer‟s Notice of Response. Both the policy document and the Notice have been
exchanged with the complainant.
Additional benefits
Loss of rent
If Home is shown on your Certificate of Insurance, and:
• the home becomes unfit to live in as a result of loss or damage covered by an
insured event or an optional cover and we have agreed to pay for the loss or
damage, and
• it was being let at the time of loss then we will cover you for the loss of rent during
the shorter of:
• the period that it remains unfit to live in, or
• 12 months.
This benefit is calculated on the rentable value of the home immediately prior to the loss or
damage.
We pay this benefit in addition to the sum insured for the home.
The maximum we will cover you for Loss of rent is 10% of the home sum insured for
any one event.
Insured events
If Home and/or Contents is shown on your Certificate of Insurance we will cover you for:
Determination | Case number: 790942 Page 20 of 24
…
7. Bursting, leaking, discharging or overflowing of water or liquid
Loss or damage as a result of bursting, leaking, discharging or overflowing water or
liquid from:
a water main or fire hydrant at or near the home
dishwashers or washing machines at the home
drainage and sewerage systems at the home
fixed baths, sinks, basins and toilets at the home
pipes or plumbing apparatus fixed to pipes
rainwater or hot water tanks, septic or fish tanks at the home
roof gutters and their down-pipes at the home
swimming pools or spas at the home
waterbeds at the home.
But we will not cover you for loss or damage:
caused by a leak that you knew about or should have reasonably known about
and did not fix before the loss or damage occurred
caused by underground (hydrostatic) water (for example, swimming pool
movement)
caused by leaking shower floors, bases or cubicle wall (for example,
deteriorated grouting and/or cracked tiles)
to a tank, pipe, part, container or waterbed that caused the damage
to leaking shower floors, bases or cubicle walls
of gas or liquid that escaped.
General exclusions
Earth movement
We will not cover you for loss, damage or liability caused by or arising out of erosion,
vibration, subsidence, landslip, landslide, mudslide, collapse, shrinkage or any other
earth movement.
But we will cover you for:
explosion – insured event 2
earthquake or tsunami – insured event 5
bursting, leaking, discharging or overflowing of water or liquid – insured event 7
flood – insured event 12.
Determination | Case number: 790942 Page 21 of 24
3.3 Summary of relevant reports
Record Key points
Complainant’s plumber (ST)
Undated
arrived on site and inspected shower drain, removed grate and
inspected drain. Found draining completely dislodged. CCTV
inspected and confirmed this. Shower floor is required to be
rem oved to repair pipework
Insurer’s engineer (GP)
Report
12 - 01 - 2021
inspected and photographed property 10 December 20 .
complainant told him he had owned the home for about four years
and noticed cr acking around the home rec ently
photographed cracking to the carport wall at the front (east) of the
home and in the carport
shower area to the bathroom at the southwest corner of the home
showed little evidenc e of damage, and laundry at the west side of
the home shows little evidence of damage .
no damage to external wall of bathroom and laundry
vertical hairline cracking to bricks at southwest corner of the home
and northern wall of the ba throom
retaining wall at rear and stepped cracking noted northwest corner
of the home which is remote from the area of wat er leaks
several trees and large shrubs found around the home and in the
garden at the rear
home sits atop highly to extremely react ive soil which may
experience high to extreme movement due to moisture
water leaks, long periods of wet or dry weather, negative falls
toward the structure, and tree roots can impact soil moisture
content; an imbalanc e in soil moisture cont ent can res ult i n heave
or shrink age, in turn causing differential movement and cracking
floor level survey identified overall settlement toward the rear of
the home, likely due to the soil drying effect of trees and large
shrubs in close proximity to the home
no anomalies in levels were found to the area of the leaks
externally to the bathroom and laundry at the southwest corner
cracking damage to the southeast corner of the home is far
removed from wet areas, and would not be influenced by water
from a leak 7 to 8 meters away
damage to the northwest and southeast corners of the home is not
related to the water leaks and rather to a long term, differential
movement of the foundations of the home
rear wall damage consistent with long - term wear and tear
leading e dge of balcony damage related to run off wat er – not due
to a one - off event
step cracking to the northeast corner of the home is 15 meters
from the leak and unrelated
vertical hairline cracking to the southwest is due to brick growth.
leaks are unrelated to the claimed damage but should be repaired
as soon as possible
Complainant’s engineer (TM)
Report
19 - 02 - 2021
reviewed ins urer‟s plumber‟s report and inspected and
photographed property 12 February 21.
few signs of building movement were noted within the
southwestern portion of the home (near to the major leak from the
shower branch pipe)
agrees presence of reactive clay soils
repairs to the leak are likely to result in a reduction in soil moisture
content to the soils under this southwestern part of the home over
Determination | Case number: 790942 Page 22 of 24
Record Key points
time resulting in settlement of the home within the southwestern
part following plumbing repairs
the effects of settlement, such as cracking damage, may take 2 or
3 years to materialise.
Insurer’s engineer (GP)
Report
19 - 03 - 2021
reviewed co mplainant‟s emails and engineer‟s report
brick swell not caused by rainwater run - off but is inherent problem
with fired clay bricks
water run - off from the hous e needs to be ameliorated
damage to leading edge of balcony likely due to rainwater run - off
ove rtime
no damage to the home which can be relat ed to the water leak
from the shower base and complainant‟s engineer agrees.
Complainant should repair wat er leak
reiterated that as no damage present the lost water has not
caused a heave in the area of the leak
home suffering from long - term settlement towards the rear likely
due to the drying actions of trees but not related to the wat er leak .
Insurer’s engineer (IP)
Report
2 - 09 - 2021
inspected and photographed home 4 and 5 August 21 and carried
out perimeter level survey
reviewed and compared photographs provided by complainant
complainant says house was “in original condition” with no
damage when he purchased in or about 2017 and he began
noticing damage around the home in late 2020/early 2021
outlined examples of the observations that were recorded and
photographed at the time of the site attendances
evidence clearly shows the building has a history of differential
footing movemen t, although this is inconstant with the
complainant‟s recollection
foundation soil is moderately to highly reactive clay which can
expand significantly when moisture content increases, causing
upward heave, and downward settlement when drying
a water supply leak of approximately 210,000 litres likely occurred
at the property in the period June – September 2017
accepts water would‟ve leak ed from the shower waste each time
the shower was used with the waste pipe in its current condition
Nearmap photogra ph identifies the location of the historic water
supply leak near the garage and driveway
floor level survey identified the building was higher at the south -
eastern corner, and lowered toward the north and eastern
elevations
various issues which have cont ributed to the damage.
some damage consistent with differential footing movement whic h
relates to the soil that makes up the foundation
upward movement towards southeast corner (where 2017 water
supply pipe leak occurred) and possible this leak contribute d to
this movement which may have caused cracking to the
surrounding area
heave may have res ulted in misalignment of the ground floor
shower alcove waste pipe which leaked but could not identify any
damage caus ed by the shower leak
heave at the southeast corner relat es to the 2017 leak, or there is
settlement away from the south - eastern corner as a result of
decreasing soil moisture content from seasonal and environmental
conditions
settlement cause consistent with absence of recovery movement
Determination | Case number: 790942 Page 23 of 24
Record Key points
to the crack ing in the southeast garage
available evidence does not support either conclusion;
recommend further investigation including a total soil suction
testing which will allow a more definite opinion
only way the leaks could have caus ed damage to the perimet e r
paving would be by causing the home‟s footing to move upward
almost in its entirety (essentially causing the footing to move up
relative to the pavement). This could cause the type of gap
between the external walls and the pavement. However, for such
a w idespread movement to have occurred, expect to observe far
more damage to the superstructure because such a movement
would not occur at a constant rate around the building. Therefore,
we do not believe this has occurred.
unable to conceive of a mec hanism by which the leaks (all leaks
that were identified) could have caused damage to the perimeter
concrete pavements or retaining walls. This damage, along with
much of the other cracking to the home‟s external brickwork, is
related to other matters
in relatio n to other cracking damage, a mechanism by which leaks
could cause cracking damage across the entire building cannot be
conceived, and the likely cause is differential footing movement
damage to balcony tiles likely existed before purchase
damage may also be a result of a brick growth, corrosion of a
steel beam supporting the balcony, normal wear and tear and the
retaining wall is nearing end of life
much of the damage is unrelated to leaking pipework.
Complainant’s engineer (IN)
Report
18 - 01 - 2022
inspected tested and photographed site 27 October 21 after
reviewing ot her expert reports
floor level survey showed evidence of heave at the southeast
corner of the building in the vicinity of the 2017 leak; evidence of
localised heave at the location of t he shower pipe leak; settlement
along the north part of the house closest to trees
survey results consistent with IP‟s survey results
building movement reduced since IP tested inferring moisture
levels in foundation soils have reduced consistent with clim atic
conditions
building is founded on highly to extremely reactive clay soils –
building will experience high to extreme ground movement from
moisture changes and IN says at leak locations (1 and 2) elevat ed
building levels were recorded and cracks were s een
in the event soil became wetted, heave and cracking damage
would be expected in the vicinity of a leak
it is possible the 2017 leak led to the shower pipe disconnect, yet
a plumbing investigation would be required to confirm
building is structurally s ound, and cracking damage is aesthetic in
nature (except for the crack next to the garage) and building does
not require underpinning
internal observations failed to identify any signs of significant
structural distress showing the structural performanc e of the
building is satisfactory
row of trees to the north are too close to the building and evidence
these trees have resulted in differential footing movement, and
cracking
surface cracks of concrete pavement are typical of concrete
shrinkage cracks and not of structural concern
fine vertical cracking on the four corners of the building are
Determination | Case number: 790942 Page 24 of 24
Record Key points
consistent with brick growth due to abs ence of an articulation joint
a reduction in heave since the IP report suggests soil moisture
content is reducing, soil suction testing can confirm this
building not fully recovered and need to wait for the soil moisture
levels to normalise
soil testing commissioned but not performed - would help
regarding site specific soil classification and characteristics of
surface le vel movement
to gauge where the moisture levels in the soil are normal total soil
suction moisture testing can be performed which determines the
source affinity to water and could be used to determine at which
point in time repairs should be made
imperat ive that prior to testing a comprehensive plumbing
investigation is undertak en
2017 leak has caused cracking at the sout heast of the building,
contribut ed to concrete perimeter and pre - existing driveway
cracking, and contributed to cracking of the suspende d concrete
slab
moisture damage to the concrete slab and delamination of floor
and edging tiles is wear and tear
shower drain leak has caused cracking of floor and wall tiles in the
bathroom, and minor wall cracking
upstairs shower leaks are a result of w ear and tear, and have
caused moisture damage to plasterboard ceilings and the
suspended conc rete slab
recommended engagement of a plumber, prompt repair of the
leaking ground floor shower branch pipe, soil testing (total soil
suction testing) at specific and targeted loc ations of the site, to
demonstrate that soil moisture levels are normal or abnormal,
which will then be used, in conjunction with repeat floor and brick
course level surveys, when the repairs to event - related damage
can be undertaken
recom mended repair to event related damage which should be at
least six months away so the moisture levels in the reactive clay
foundation soils can ret urned to normal
recommended a brick course level and internal floor level survey
to be performed in six mont hs‟ time to gauge building movement
and suitability for remedial works to commence
prepared scope of works but also noted further damage will occur
as foundation soils dry and soil moisture levels return
works can only be performed after all abnormal soi l moisture
conditions have been removed and aft er repair of plumbing leaks
and then a minimum six - month drying period after plumbing
repairs .
3.4 Other relevant material considered and relied on
Parties‟ submissions /emails and all attachments to all submissions/emails.
Loss adjuster reports.
Expert reports.
Photographs and invoices.
Correspondence between the parties.
Determination | Case number: 790942 Page 1 of 1