Text of the determination
Determination
Case number 789073
Financial firm RAA Insurance Limited
Determination | Case number: 789073 Page 1 of 10
Case number: 789073 16 August 2022
1 Determination overview
1.1 Complaint
The complainants hold home and contents insurance with the financial firm (the insurer).
They are represented by their son, ER. On 20 May 2015, the complainants lodged a claim for
cracking dam age to their hom e caused by a leaking pipe under their property.
The insurer accepted the claim and repairs were completed in October 2017. However, in
August 2018, the complainants reported further cracking and movement damage which they
attribute d to the insurer’s inadequate repairs .
The insurer agreed that the repairs partially caused the additional damage. However, it said
that the damage was also due to long term ground movement related to the highly reactive
soil and the drying effect of tree roots. The policy does not cover damage from that cause.
The insurer offered a cash settlement of 50% of what it said were the reasonable repair costs.
The complainants say the inadequate repairs are the sole cause of the further damage. They
want the insurer to rectify all of it and to be reimbursed the cost of their expert reports.
1.2 Issues and key findings
Is the insurer required to cover more than 50% of the damage?
No. The insu rer’s offer to cover 50% of the damage is reasonable. The complainants have not
established the insurer is liable for the other 50%.
Are further investigations required to enable settlement of the claim?
Yes. The insurer is entitled to cash settle but the scope of works (SOW) and quotes it relies
on are over 18 months old. The insurer is to ask BE (its builder who provided SOWs/quotes
for both the building and the roof repairs) to provide a current SOW and fully costed quote for
the building and roof repairs. The insurer is to pay the complainants 50% of the new quote
plus a 15% contingencies uplift. BE is also to be asked to estimate how long (if at all) the
property will be unfit to be lived in due to the works. The insurer is to cash settle 50% of the
reasonable temporary accommodation (TA) costs for that period, in line with the policy.
Is the insurer to reimburse the complainants’ professional costs?
Yes. The claim has involved complex issues and it was reasonable for the complainants to
obtain reports from IE, engineers. The insurer is to reimburse to the complainants so much of
the $3,820.30 IE charged that is proven to have been paid .
Is the insurer required to pay non-financial loss compensation?
Yes. The insurer has contributed to the delay experienced and its continuing reliance on
increasingly aged quotes in making cash settlement offers was not reasonable. These
matters have caused the complainants considerable stress. The insurer is to pay them $3,000
in non-financial loss compensation.
Determination | Case number: 789073 Page 2 of 10
Why is the outcome fair?
50% of the damage is not covered, so it would not be fair to require the insurer to cash settle
for more than 50% of current repair quotes plus a contingencies uplift, plus 50% of the
reasonable TA costs (if any). Given the claim’s complexity and how it has been handled, it is
fair that insurer pays the proven cost of IE ’s reports plus $3,000 in non -financial loss
compensation.
1.3 Determination
This determination is partially in favour of the complainants.
Upon receiving written confirmation that the complainants accept this determination (the
notice), the insurer is to take the following steps:
within seven days of receiving the notice, request BE to provide an updated fully costed
SOW/quote for the building and roof repairs. The SOW is to include an estimate of the
period in which the home will be unliveable due to the work
w ithin 14 days of receiving BE’s updat ed SOW/quote, pay the complainants:
> 50% of the quoted amount
> 15% of that 50% as a contingencies uplift
> 50% of the reasonable TA costs for the complainants over the unliveable period (if any),
in line with the policy
within 14 days of receiving proof of payment, reimburse the complainants the $3,820.30
paid to IE (or so much of that amount that is proven to have been paid)
within 14 days of receiving the notice, pay the complainants $3,000 in non-financial loss
compensation.
Determination | Case number: 789073 Page 3 of 10
2 Reasons for determination
2.1 Is the insurer required to cover more than 50% of the
damage?
No. The insu rer’s offer to cover 50% of the damage is reasonable. The complainants have not
established that the insurer is liable for the other 50%.
The insurer accepted the original claim and undertook repairs
The complainants hold a home and contents policy issued by the insurer. Subject to its terms
and conditions, the policy provides cover for loss or damage caused by an insured event
listed in the product disclosure statement (PDS). One of those insured events is ‘Bursting,
leaking, discharging or o verflowing of water or liquid’.
On 20 May 2015, the complainants lodged a claim with the insurer. They said their house had
developed cracking damage due to a leaking pipe. The insurer’s investigations confirmed that
a sewer pipe on the southern side of the property was leaking. The insurer’s appointed
builder, AT, attended to repairs. The repairs included replacement of a section of the pipe,
which required excavation and subsequent refilling of a trench close to the house.
Due to cracks reappearing, the insurer appointed GP, engineer. GP inspected the property on
23 October 2015 and noted that the pipe replacement had been completed and the trench
refilled but the disrupted paving was yet to be replaced. GP provided a report dated 6
November 2015, which stated:
the soil in the area was likely to be highly to extremely reactive clay, which may experience
high to extreme ground movement from moisture changes
a moisture increase above equilibrium levels leads soil volume to increase (heave) and a
decrease below equilibrium levels leads to decreased soil volume (shrinkage)
the property had a long history of cracking, involving settling from the drying effect of trees
to the south. However, the leaking pipe would have also caused some localised heave
the leaks likely assisted in balancing moisture conditions and prevented further settling.
Once the leaks stopped, some initial rapid movement was to be expected from tree drying
effects. This has been exacerbated by the paving removal and recent high temperatures
it is possible the trenching work caused some minor footing undermining which would
affect the southern side of the house
GP recommended the paving be replaced and a drying out and monitoring period. At the
end of the period, any distress to the south side of the house could be attributed to the
leak/trenching work.
GP ‘ categorically states that once repairs have been made any further distress or
reoccurrence of the repaired cracking shall NOT be attributed to the water event and rather to
environmental conditions.’
Following the drying out/monitoring period, further repair work was performed pursuant to
GP’s SOW dated 26 October 2016. O n 4 October 2017, the insurer concluded the claim had
been finalised.
The parties disagree on the cause of the additional damage
On 27 August 2018, the complainants notified the insurer that their house had sustained
further cracking and movement damage. They say that all of that damage is due to AT’s
inadequate repair work.
Determination | Case number: 789073 Page 4 of 10
The insurer disagrees. It accepts that AT’s repairs have been a contributing factor but says
the damage is also due to long term ground movement related to the highly reactive soil and
tree drying effects. The policy does not cover damage from that cause.
The insurer has offered to cover 50% of the reasonable costs to repair the additional damage.
It says that represents the outer limit of its liability.
Both parties rely on expert reports
The parties have exchanged multiple expert reports, dating back to July 2015. As the parties
are familiar with them, it is not necessary to comment on each report in this determination.
The panel has, however, carefully reviewed all of the expert evidence provided.
The complainants’ main expert is IE, engineers. IE’s report dated 12 December 2019, say s:
the property was built on reactive clay and has a long term history of cracking
the cracking damage since the repairs were completed in late 2016 is primarily due to
drying shrinkage following rectification of the leak
undermining from the trench excavation may have induced some subsidence and
cracking, but this is not the dominant cause of movement
repair of the damage to t he house’s southern portion was undertaken far too early in the
recovery phase after the pipe replacement and before the house had stabilised
further movement meant it was inevitable the repairs would fail and that there would be
further cracking damage
there i s evidence of continuing movement, meaning ‘ the home cannot be considered to
have fully recovered from the influence of the former leaking pipes ’.
On 28 September 2021, IE resurveyed the property and said the results demonstrated
significant ongoing settlement beneath the middle of the home’s southern elevation, centred
on the bathroom. The northern side of the house had not moved much at all. IE said:
In my opinion, this indicates that the area formerly affected by long-term sewer
leakage is still continuing to settle down, even five years after the sewer was
replaced! This isn’t unprecedented – I’ve monitored homes in the past that have
taken several years to fully recover from long-term leakage issues or
environmental changes.
The insurer primarily relies on reports from engineers GP and FE.
GP has provided a total of seven reports, including the report dated 6 November 2015
outlined above. GP’s comments include :
the complainants confirmed the property had a history of cracking spanning decades, but
that cracking was minor compared to what had been experienced from 2015 onwards
the additional damage involves reopening of the same cracks that had been present prior
to the repairs. This shows the cracks could not have been caused by the trenching work
by reference to plumbing tests in 2015, the leaks were very minor, so contrary to what IE
says, the effect of the leaks on the house had stabilised by the time repairs occurred
if IE was correct that the repairs were done too early, you would expect the cracks to
reduce over time as the soil dried out, not worsen (as has happened)
the surveys undertaken by GP and IE showed continuing settlement in the south west
corner, consistent with GP’s prediction that trees would continue to influence the home .
Determination | Case number: 789073 Page 5 of 10
In a report dated 6 June 2020, FE said the cause of the initial damage was a combination of
excessive soil wetting from the pipe leak and the desiccating effect of trees in conjunction
with inadequate footings incapable of resisting both seasonal and abnormal soil movement.
The cause of the additional damage was lack of proper detailing of the remedial works,
resulting in wall and ceiling construction unable to accommodate continuing soil movement.
FE found no evidence that the additional damage was caused or contributed to by AT’s
repairs. Rather, the damage was contributed to by repairs not carried out but that should have
been. FE noted that GP had provided a SOW requiring provision of retrospective control
joints in accordance with a specification it failed to include. AT did not ask for the specification
and did not install the control joints.
In response, GP has said it is not aware of the reason for the control joints not being provided
by AT, but this can be done retrospectively if required.
FE provided a second report dated 7 September 2020, along with an SOW for recommended
repairs. FE included the following caveats in the report:
2.3. It must be noted, that even if our final recommendations are carried out that
future movements may occur due to the reactive nature of the soil and the
inadequate footing system, and which are not attributable to the water leak.
2.4. I recommend that the owners should seek further advice for any
recommendation relating to future site management which is their responsibility.
2.5. Complete stabilisation of the soil moisture content cannot be achieved
without very high capital cost. The purpose of our recommendations would be to
attempt to limit movement to a more acceptable level in the future.
The insurer is not required to cover more than 50% of the damage
There is no dispute between the engineering experts that:
the property is built on reactive soil
the soil has been (and will continue to be) influenced by the drying effect of trees
there is a long term history of cracking
the cracking reappeared after the repairs and has continued to worsen (expand).
In the circumstances, the panel is satisfied that not all of the damage is due to the water leak
and/or inadequate repairs. It is apparent that the cracking is a longstanding problem.
Further, on balance, the panel prefers GP’s view that if it was the case that the repair work
was undertaken before the effect of the water leak had ceased, one would expect the cracks
to shrink as soil moisture content decreased. Instead, the cracks have widened considerably.
The panel also notes that there is no proof that the trenching work undermined foundations,
leading to major movement. The highpoint of the expert evidence on that point is IE ’s view
that undermining from the trench excavation may have induced some subsidence and
cracking, but this is not the dominant cause of movement.
Nevertheless, it does appear that the repairs were not properly undertaken. The panel
particularly notes GP does not reject or otherwise substantively comment on the concerns FE
raises in its report dated 6 June 2020.
Determination | Case number: 789073 Page 6 of 10
The available information does not enable a precise apportionment of responsibility for the
further damage. However, on balance, the panel considers that the issues with the repair
work have not made a significant contribution.
In the circumstances, the panel considers the insurer’s offer to cover 50% of the additional
repair costs to be fair and reasonable.
2.2 Are further investigations required?
Yes. The insurer is entitled to cash settle but the scope of works (SOW) and quotes it relies
on are over 18 months old. The insurer is to ask BE (its builder who provided SOWs/quotes
for both the building and the roof repairs) to provide a current SOW and fully costed quote for
the building and roof repairs. The insurer is to pay the complainants 50% of the new quote
plus a 15% contingencies uplift. BE is also to be asked to estimate how long (if at all) the
property will be unfit to be lived in due to the works. The insurer is cash settle 50% of the
reasonable temporary accommodation (TA) costs for that period, in line with the policy.
The insurer is entitled to cash settle
The complainants want the insurer to attend to repairs rather than pay a cash settlement.
However, the PDS gives the insurer the option to pay (cash settle) an insured the cost of
covered repairs rather than attend to the repair work.
Nevertheless, the insurer must act reasonably in choosing whether to exercise that option
and in determining the cash settlement amount.
Given the determination that the insurer is only liable for 50% of the required repairs, the
panel is satisfied that it is fair and reasonable for the insurer to proceed by way of a cash
settlement.
Cash settlement should be based on an actionable quote and include an uplift
When an insurer cash settles a claim, it transfers to the insured the risk that the cost of
repairs may unexpectedly increase and/or that additional works not quoted are required. The
insured also loses the insurer’s warranty that would apply to repairs arranged by the insurer.
In the circumstances, there is a reasonable expectation that when cash settling a claim an
insurer will base its offer on a recent quote that is actionable for a retail customer. Further, it
should increase (uplift) the quoted figure by applying a fair percentage, to allow for the
transfer of risk, conti ngencies and loss of access to the insurer’s repair warranty.
Based on FE’s SOW dated 7 September 2020, the insurer obtained the following builders’
combined SOWs/quotes:
HP dated 7 January 2021 for building repairs - $64,831.25
M&S dated 4 December 2020 for building and roof repairs - $64,721.66
BE dated 4 January 2021 for roof repairs - $15,213.00
BE dated 23 October 2020 for building repairs - $74,265.40.
On 5 February 2021, the insurer offered to pay the complainants a cash settlement
representing 50% of HP’s building repair quote and 50% of BE’s roofing repair quote. It has
consistently maintained since then that the offer represents the outer limit of its liability to the
complainants.
Determination | Case number: 789073 Page 7 of 10
The quotes from HP, M&S and BE are all now more than 18 months old so will not reflect
current pricing, particularly given the rapid increase in the cost of building materials and
labour over the last year or so. This means none of the quotes are actionable.
BE has quoted for both the building and the roof repairs, while HP has only quoted on the
building repairs. The pane l does not consider it reasonable for the insurer to combine HP’s
building quote with BE’s roofing quote to obtain a combined figure lower than the total of the
two BE quotes. This is particularly so given that if the insurer was attending to repairs it would
likely use a single builder.
Accordingly, the insurer is to obtain from BE an updated SOW and fully costed quote for the
building and roof repairs, using current prices. The insurer is to pay the complainants 50% of
the quoted amount plus a further 15% of the 50% figure to allow for contingencies, transfer of
risk and loss of warranty.
The panel acknowledges that the complainants have provided a quote dated 19 August 2021
from their builder, CB, totalling $151,055.02. However, the PDS does not require the insurer
to use an insured’s preferred builder or adopt their quote. Further, CB’s quote is now 12
months old. The panel is satisfied that once BE updates its earlier quotes, the new quote will
reflect the current reasonable cost of repairs.
TA costs may be payable
As set out on page 17 of the PDS, the policy includes as an automatic additional benefit cover
for TA costs.
If the insurer agrees that the home is unfit for the insured to live in as a result of covered
damage, it will cover the insured for TA costs during the time it takes to repair the home or for
the period it remains unfit to live in (for a maximum period of 12 months). The TA cost
payable will be based on the rentable value of the home immediately prior to the damage and
the maximum sum payable is 10% of the sum insured.
The quotes provided previously by BE outline extensive work that may have rendered the
complainants’ home unfit to be lived in for a period. Accordingly, when the insurer asks BE to
provide an updated SOW/quote it is to specify that the SOW is to include an estimate of the
period (if any) in which the home will be unfit to be lived in due to the work.
The insurer is then to pay the complainants 50% of the reasonable TA costs for the
complainants over the unliveable period (if any), in line with the policy terms. To assist in that
regard, the panel notes that the date of the relevant damage was the completion of the initial
repairs in October 2017. That is the date at which the rentable value of the home is to be
assessed. The maximum amount payable is 10% of the building sum insured in place at that
time.
2.3 Is the insurer required to reimburse professional costs?
Yes. The claim has involved complex issues and it was reasonable for the complainants to
obtain reports from IE, engineers. The insurer is to reimburse to the complainants so much of
the $3,820.30 IE charged that is proven to have been paid .
Determination | Case number: 789073 Page 8 of 10
AFCA may require insurer to contribute to complainant’s professional costs
The AFCA rules enable AFCA to require an insurer to contribute to the professional costs
incurred by the complainant. These costs are, however, usually capped at a total of $5,000,
unless special circumstances apply.
When considering whether to require an insurer to make a costs contribution, AFCA takes
into account the complexity of the complaint and whether the particular complainant needed
to incur costs to understand or establish their claim.
The insurer is to reimburse the complainants the costs charged by IE
It is clear that this matter has involved complex engineering concepts, technical reports and
progressive dam age to the complainants’ home over time. As noted in section 2.1, there have
been a number of factors that have contributed to that damage.
Noting none of the complainants are specialist engineers, the panel accepts that they needed
to incur costs in obtaining reports from IE to enable them to properly understand their case
and to respond to the insurer’s position.
In the circumstances, the panel is satisfied that it is fair and reasonable for the insurer to
reimburse to the complainants so much of the $3,820.30 IE charged that is proven to have
been paid .
2.4 Is insurer required to pay non-financial loss compensation?
Yes. The insurer has contributed to the delay experienced and its continuing reliance on
increasingly aged quotes in making cash settlement offers was not reasonable. These
matters have caused the complainants considerable stress. The insurer is to pay them $3,000
in non-financial loss compensation.
AFCA may award non-financial loss compensation in certain circumstances
Under paragraph D.3 of the AFCA Rules, we may award compensation for non-financial loss
(capped at $5,400) where the insurer’s actions have caused an unusual amount of:
physical inconvenience
time taken to resolve the situation
interference with the complainant’s expectation of enjoyment or peace of mind.
Where a complainant has contributed to their loss arising from the insurer’s conduct, their
level of compensation may be reduced accordingly.
Insurer has unreasonably caused stress and inconvenience
The complainants have complained of delays in communication, delays in provision of expert
reports and inappropriate conduct and commentary from the insurer’s experts when visiting
the property.
The issues the subject of the claim have been on foot for seven years. Even accepting that
some of the delay was outside the insurer’s control, that is too long, particularly taking into
account the fact that the complainants are elderly and have continued to live in their
det eriorating home. Further, by reference to the insurer’s cl aim notes, were occasions where
communications should have been more prompt.
Determination | Case number: 789073 Page 9 of 10
The panel also considers that the insurer’s continuing cash settlement offer based on
increasingly old quotes and without consideration of a contingencies uplift or potential TA
costs entitlement has not been reasonable.
The panel is unable to make a finding the insurer’s experts acted inappropriately on the
available information.
The panel accepts that these matters have caused the complainants considerable stress and
inconvenience. In all the circumstances, it is reasonable that the insurer pays them $3,000 in
non-financial loss compensation.
2.5 Why is the outcome fair?
50% of the damage is not covered, so it would not be fair to require the insurer to cash settle
for more than 50% of current repair quotes plus a contingencies uplift, plus 50% of the
reasonable TA costs (if any). Given the claim’s complexity and how it has been handled, it is
fair that insurer pays the proven c ost of IE’s reports plus $3,000 in non -financial loss
compensation.
Determination | Case number: 789073 Page 10 of 10
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
A panel determined this matter
Due to the nature of this complaint, we referred it to a panel for determination. The panel
includes:
an ombudsman
a member with significant experience in consumer and small business advocacy
a member with extensive experience in the insurance industry.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.