Home / Suncorp Group / Determination 788262

Determination 788262

Insurer cash settled fire damage claim for an amount insufficient to repair the damage

FirmSuncorp Group
Decided2022-05-27
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$38,198
Non-financial loss$2,000
Amount claimed$35,045
SourceAFCA PDF

Summary

A fire damaged the complainant's property and the insurer cash settled the claim after the parties could not agree on a scope of works. AFCA found the cash settlement insufficient and ordered a further $38,198.09 plus interest and $2,000 non-financial loss compensation.

Where an insurer elects to cash settle, it must act fairly and ensure the settlement is sufficient to repair the claimed damage, including contingencies.

Issues

Subjects and remedies

business interruptionhome or building damagenatural disasterpay claimpay interestpay non financial loss

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination Case number 788262 Financial firm AAI Limited Determination | Case number: 788262 Page 1 of 21 Case number: 788262 26 May 2022 1 Determination overview 1.1 Complaint The insureds are the complainant and his brother. The complainant has represented his brother in this complaint. For the sake of brevity and convenience, references to the complainant include references to both insureds. The complainant has a listed events building and contents policy with the financial firm (the insurer). On 30 September 2018 the complainant lodged a claim with the insurer after a fire caused damage to his property. After assessing the reported damage, the insurer calculated its liability for the damage at $92,896.97. This assessment did not include an allowance for contingency as the insurer was willing to undertake the repairs. T he complainant disputed the insurer‟s assessment and provided his own quote to repair the damage at $129, 007.71. The insurer arranged for further assessment of the complainant‟s quote and reaffirmed its liability assessment. Due to a breakdown of the relationship between the insurer and the complainant, the insurer elected to cash settle the complainant for $92,896.97. Following escalation of the complaint to AFCA, the insurer increased this offer and paid the complainant an additional 10% ($9,289.70) for contingencies due to the transfer of risk. This means a total amount of $102,186.67 has been paid to the complainant. The complainant remains dissatisfied with the amount offered and the insurer‟s claims management. He requires the insurer to increase its offer based on his builder‟s quotations. He also seeks compensation. 1.2 Issues and key findings Is the insur er’s offer fair in the circumstances? No. In addition to the amounts already paid, the insurer is to pay to the complainant $38,198.09 plus interest. Is the complainant entitled to compensation? Yes. There was an unusual degree of physical inconvenience and time taken to resolve the complaint which would have interfered with the complainant‟s expectation of enjoyment or peace of mind. Why is the outcome fair? While the policy provides the insurer may cash settle the claim, when doing so it must act fairly and ensure the cash settlement is sufficient to repair the claimed damage. The available information establishes the cash settlement offer was insufficient to repair the claimed damage. In these circumstances it is fair the insurer pays the complainant a further $38,198.09 plus interest. Determination | Case number: 788262 Page 2 of 21 1.3 Determination The determination is substantially in the complainant‟s favour. Should the complainant accept this determination then within seven days of notification of acceptance the insurer is to pay to the complainant:  $2,000 non-financial loss compensation  $38,198.09 in addition to the amounts already paid for the cost of repairs. The insurer is also to pay to the complainant interest pursuant to section 57 of the Insurance Contracts Act 1984 (the Act) on $38,198.09 from 13 October 2020 (the date of its offer) until settlement. Otherwise, the insurer is not required to take any further action in relation to the claim or the complaint. Determination | Case number: 788262 Page 3 of 21 2 Reasons for determination 2.1 Is the insurer’s offer fair in the circumstances? Parties’ submissions and material considered There is no dispute the complainant‟s property sustained damage in a fire in 2018. The complainant raised concerns regarding the insurer‟s assessme nt of its liability and whether it has adequately identified the required repairs during its assessments of the damage to the property. The insurer cash settled the complainant in the total amount of $102,186.67, for the damage its assessor (SB) and builder (PB) identified as being fire related damage. The complainant requires the insurer to accept his quote for repairs from his builder (NH). NH‟s first quote in January 2021 was for $129,007.71. NH provided a second quote in June 2021 for $130,628.35. In recent correspondence NH says materials and labour costs have increased. He told the complainant to expect a revised quotation for the same works for about $145,000 - $155,000. The complainant says NH‟s quote is a more accurate reflection of the cost to re pair the damage caused by the fire. The complainant says:  the insurer has not acted fairly as he expected the repairs to be completed by the insurer‟s builder (PB) before the end of 2019 rather than cash settled (thereby losing the lifetime guarantee on workmanship)  there were many concerning variations in the two versions of the scopes of works provided by PB and the insurer‟s initial expert (S)  S are experts in fire damage, scoping and rectification and their SOW is preferred.  if his concerns regarding the pool were sufficiently addressed and PB adequately addressed the required works in accordance with S‟s scope of works (SOW) he would be satisfied for PB to commence repairs  before proceeding he required another quotation from an insurer‟s approved panel builder (he suggested (A) who had already completed a site visit)  he proposed an independent building surveyor be engaged to prepare a second scope of works  he arranged for several local builders to inspect the fire damage to provide a quotation to complete the rep airs in accordance with S‟s SOW. The insurer says:  S was only meant to provide a SOW for the structural damage (the foundation in a corner of the property)  S did not do as requested and provided information which is incorrect  as part of determining the SOW it requires its builder‟s involvement  SB and the building coordinator (BC) deemed S‟s SOW excessive so it cannot arrange repairs on a SOW it does not agree with  S‟s SOW is a guide only  A‟s quote was incomplete until the SOW was agreed by the insurer Determination | Case number: 788262 Page 4 of 21  the complainant could arrange an independent person to provide a scope of works or his own repair quote, but it required a meeting on site with the complainant, the assessor, the building coordinator, and a builder to verify S‟s SOW before any builder was appointed. The requisite site visits took place on 5 August 2019 and 9 September 2019. At the second inspection the assessor arranged for PB to attend to develop the SOW and quote. PB brought the pool specialist (SP) as well. The complainant said:  the pool specialist (SP) required a second visit to finalise his opinion  the integrity and function of the fibreglass pool has been severely compromised as it was emptied of water by the insurer and left idle  he required further information about PB who he says is not genuine and independent (he says the Facebook page provided by the insurer promoted a company operating in UK)  he also required another panel builder such as (A) to prepare a quotation. The insurer said:  the pool is not fire damaged, but a second visit will be required by SP when the chipboard flooring to the pool room is removed  PB did not then have an active website, but it provided a Facebook page  A quotation from A was not required as it has agreed and approved the SOW based on its assessor an d building coordinator‟s review. Relying on policy terms and the circumstances of the claim, the insurer says it was entitled to provide cash settlement instead of repairs because the parties were unable to agree on the SOW. PB was willing to undertake repairs but could not do so unless the SOW was agreed. The complainant says PB, and the insurer engaged in misleading and deceptive conduct and so he cannot accept the policy terms relied on by the insurer because of this conduct. In May 2020 the insurer suggested S return to confirm the SOW. The complainant was unwilling to deviate from the original SOW. In June 2020 the insurer reviewed the claim indicating it would include the part of S‟s SOW which refers to the spa pool. The insurer wanted a further site meeting, so it could complete an updated SOW for the repairs. The insurer proposed an on-site meeting with its internal assessor, its building coordinator, an engineer, a fibreglass pool specialist and PB on 9 July 2020. It said PB would be authorised to proceed with repairs once it had determined the SOW. The complainant did not want repairs carried out by PB. He was willing to meet with the internal assessor and building coordinator. The insurer said its intention was to meet on site with all relevant trades was to determine a complete and accurate scope of works to include the lifting and reinstatement of the spa. Otherwise, it would require PB to complete a desktop quotation for the repairs. The site meeting did not go ahead. The insurer arranged for its building coordinator to review the additional SOW and quote for the lifting and reinstatement of the spa. In July 2020 the insurer offered two options for repairs which included authorising PB to complete repairs as per PB‟s SOW or cash settling based on PB‟s quoted amount of $87,376.34. The complainant asked the insurer to reconsider and agree to a builder other than PB. Determination | Case number: 788262 Page 5 of 21 The complainant reviewed the SOW for replacement of the pool and asked the work required be reconsidered relying on two specialists who had recently visited his property. He said a cost estimate in the range of $70,000-$80,000 was provided. The items the complainant required the insurer to include were set out by the complainant to include: 1) laying of a concrete slab 2) building of a retaining wall around the pool 3) installation of a sump pit 4) removal of the floor frame (including stumps, floor joists, bearers) at least 500mm around the pool and between the window and the pool 5) removal of the timber frame below and above the window including at least 500mm on either side of the existing window to provide access to a crane and preparation work 6) an allowance for the replacement of the pool heater 7) an allowance for the reinstatement of the rear garden and lawn area due to the movement of the digging equipment, materials, crane , movement tracks and the spa itself 8) the north wall window is a timber framed window and not aluminium as stated on the SOW. As for the second SOW for the other repairs, he said:  there was a shortfall of $1,907.06 for timber wall cladding to the east and north walls  there was a shortfall of $1,855.34 for the removal disposal and replacement of cement wall lining. In August 2020, the insurer‟s building coordinator responded to the scope of works queries saying the items were either not required, may constitute a variation or have been agreed on site. The insurer said it had been agreed on site to an additional sum of $1,855.34 for the timber wall cladding and cement wall lining which was to be added to the cash settlement. The complainant said it did not agree and that the total shortfall amount for this item was $6,751.60. He articulated other concerns he had regarding the proposed repairs and scopes of work. The scopes of works were reviewed by the assessor and building coordinator and the insurer responded to the complainant‟s concerns. The insurer said its liability for the spa replacement was $44,720.51 and for building repairs was $45,976.46. It said a builder‟s margin of 13% has been allowed. It allowed a contingency of $2,200 for the reinstatement of the garden and lawn. In October 2020 the insurer paid the complainant a cash settlement of $92,896.97. The complainant rejected the offer. He indicated he was almost in agreement with the SOWs except for the area of timber wall cladding. He also said he did not want a cash settlement. The insurer continued to assert the timber wall cladding was included in the settlement figure. And the insurer continued to assert its decision to cash settle the claim was fair because of the lack of agreement on the SOW, lack of agreement on a builder, and inability to meet to finalise matters in July 2020. The complainant challenged the insurer‟s assertions and obtained his own repair quote (NH) (which included the supply and installation of a new spa) in the amount of $127,941.52. He said he would cash settle the claim if the shortfall of $35,044.56 was paid. Determination | Case number: 788262 Page 6 of 21 The complainant said NH‟s quote was based on the same SOW used by PB except for some items which used measurements proposed by S in its SOW. The insurer arranged for NH‟s quote to be reviewed by its assessor. The assessor said he could not validate the costs as the breakdown was not enough. The insurer asked the complainant to provide a breakdown to the line items as per the scope of works so it could review and determine if a further settlement was warranted. The complainant said he did not believe he should be in the position to give directions to an independent builder on how they should quote their works. In its final decision the insurer said the assessor reviewed PB‟s scope of works and quote and found it to be the correct and fair amount to repair the fire damage. It points out this includes the replacement of the indoor spa despite its pool specialist (SP) confirming this was not damaged. It says the spa was accepted to try to resolve the concerns about the scope of works for the fire damage. The insurer reiterated S‟s SOW was not accurate, excessive, and redundant. Therefore, repairs were not to proceed based on its SOW. It says the SOW provided by PB included all required repairs. AFCA queried the insurer about a contingency. As a result, the insurer paid a 10% contingency to the complainant ($9,289.70) on 2 June 2021. The insurer says it will not be taking any price increases in the last 12 months into consideration as the claim was settled in October 2020 and the complainant did not arrange for the repairs to be done. It says it allowed for price increases, with the contingency that was provided as part of the cash settlement. AFCA asked the complainant to provide a copy of an itemised quote, which includes costings from NH. The complainant said he requested this information from several builders but received no reply. He says he is not able to instruct builders how to quote their work. He provided lengthy submissions attempting to compare the costs provided by NH and PB. Fair the insurer cash settled the claim I have carefully considered all the submissions of the parties including attachments. Some of the material is summarised in supporting section 3.3 of this determination. The complainant bears the onus to establish on the balance of probabilities that he has suffered a loss caused by an event to which the policy responds. This is known as a prima facie or valid claim. It is not in dispute the property was damaged by fire. The dispute is about the extent of damage caused by the fire. The complainant must establish all his claimed costs were caused by the fire. The complainant says he did not want the claim cash settled unless the cash settlement was adequate to repair all the damage. The complainant does not dispute receiving the policy terms. In the circumstances the insurer is entitled to rely on the policy terms. The relevant policy terms are set out in supporting section 3.2 of the determination. The policy terms are clear and unambiguous. I accept the insurer can decide if it will repair the damage to the building or pay the complainant what it would cost the insurer to repair the damage to the building. In making this decision, I also accept the insurer must act fairly. While I acknowledge the complainant wanted the insurer to undertake repairs, I am satisfied the relationship between the parties was such that a cash settlement was fair in the circumstances. This is because despite several meetings and proposals and significant Determination | Case number: 788262 Page 7 of 21 correspondence the parties were unable to agree on a way forward, on the scope of works and on the choice of builder. The insurer provided an actionable quote and acknowledged some variations may occur once repairs commenced. PB was ready and able to carry out the repairs. I accept the insurer was entitled to reject S‟s SOW if it was excessive and outside the scope of its engagement. I also accept the insurer was entitled to rely on PB‟s scope once PB had inspected the damage with the insurer‟s assessor and building coordinator. On the available material I accept PB was qualified to carry out the work. I do not accept the available information establishes PB or the insurer engaged in misleading or deceptive conduct. The quotations provided by PB indicate his business is in Eltham. The quotes have a telephone number and an ICN and ABN number on the bottom of the quotes. I acknowledge the Facebook material provided by the insurer was not helpful, but I consider the information on the quotes was sufficient to establish PB‟s bona fides. Cash settlement is insufficient Once a decision is made to cash settle the claim, the insurer must ensure the cash settlement is sufficient to enable the complainant to complete repairs and consider any contingencies and variations which may occur once repairs commence. Both parties have made lengthy submissions about the sufficiency of the cash settlement. The complainant has provided a lengthy submission and analysis of the insurer‟s offer. The complainant seeks:  $2,556.60 being an increase on the allowance for external timber cladding and installation  $5,027+18% margin +10% GST being an increase on building permit fees  $3,500 plus GST being an increase on the allowance for landscaping ($2,200)  $9,897 plus GST being an allowance for the replacement of pool equipment  $2,500 plus GST being an allowance for the replacement of the pool windows. Fair the insurer pays $2,556.60 for replacement of external cladding It is not in dispute the fire damaged the property for which the insurer has agreed to cash settle the complainant. The insurer‟s reports and quotes are persuasive and generally provide sufficient and persuasive information and more detail for consideration than NH‟s quotes. Nonetheless I am also persuaded by the complainant‟s submissions. I have considered the submissions by the parties in relation to the external timber cladding and installation. While I accept S‟s SOW was not the final arbiter on this point, I accept S has the expertise to comment on this aspect. I also accept the photographs provided by the complainant in his submissions, support his contentions. The parties disagree on what was agreed at a site meeting. I am not persuaded the explanation provided by the insurer is sufficiently persuasive. In all the circumstances, on the available information I am satisfied it is fair that an increase of $2,556.60 including GST should be made for the replacement of external cladding. Determination | Case number: 788262 Page 8 of 21 Fair the insurer pays $4,200 for building permit fees The complainant seeks $5,027+18% margin +10% GST being an increase on building permit fees. The insurer allowed $2,500 for preliminaries. The complainant says this is inadequate after he made inquiries at the local council. The insurer provided no comprehensive reply. The insurer‟s assessor says if the floor is damaged during insta llation this will be added and fixed by the builder and an engineer is not required. The assessor continued to maintain no engineering was required to repair the damage. While I note S made a provisional allowance of $2,500 I am not satisfied this establishes engineering work is fact required. Based on the available material I am not satisfied on the balance of probabilities a full allowance for engineering costs is required although it can be considered in the uplift I will provide in this determination. Nonetheless I am satisfied the complainant has established the amount allowed for by the insurer for this item is inadequate. The complainant has provided submissions which support his position that allowances made by PB for building permits is inadequate to fulfil local municipal charges and requirements. In those circumstances I am satisfied it is fair the insurer makes a further allowance on the net amount payable of $4,200 for this item which includes a builder‟s margin of 13% and 10% GST. Fair the insurer pays $4,102 for landscaping NH allowed $5,500 to make good the rear garden and lawn affected by pool installation and building works. The complainant provided photographs of the garden area. The complainant seeks $3,500 plus GST being an increase on the allowance for landscaping ($2,200). The insurer says due to the lack of breakdowns it is unable to justify the cost difference. I have considered the quotation provided by NH. On this issue I consider it is sufficiently detailed and explains the quantity of material and labour required. In those circumstances I am satisfied it is fair the insurer makes a further allowance on the net amount payable of $4,102 for this item which includes a builder‟s margin of 13% and 10% GST. Fair the insurer pays $10,124.23 for pool equipment Relying on NH‟s report, the complainant requires the insurer to increase its offer by $9,897 plus GST being an allowance for the replacement of pool equipment. He submits several key pool equipment items had to be replaced because they were no longer in operational order and could not be repaired except for the filter. The complainant provided photographs of the pool equipment located at the external west wall of the pool room. The NH Report says: The existing pool equipment includes two pumps, filter, saltwater chlorinator and air blower. And all the items listed below must be replaced since they are no longer in operational order and cannot be repaired except for the filter. The items were: Determination | Case number: 788262 Page 9 of 21 1 x Insrg Vi25 Salt Chlorinator with pH and Chlorine control 1 x Insrg Gi natural gas outdoor heater 1 x Dual air switch with timer 1 x Insrg Si 300 Pool & Spa Pump On 9 September 2019 the insurer arranged for a pool renovation specialist (SP) to inspect the pool equipment to see if there was fire damage. SP reported it did not identify any resultant damage to the shell of the pool or its interior. The complainant says SP only performed a visual inspection inside the pool room and did not inspect or test the pool equipment. I accept SP did not specifically comment on the pool equipment. In his October 2020 report, the assessor said the pool equipment was included in reconnecting the spa. He said the specialist said there was no damage to current equipment. The assessor also said if there are damages this will be an unforeseen cost pending what equipment needs to be replaced. In correspondence between the insurer and complainant in October 2020, the insurer acknowledges the concerns raised by the complainant regarding replacement of the pool equipment. While the fire did not directly cause damage to the pool heater, pump, blower, filters, and chlorination system the equipment had remained idle for about two years and the complainant says this may have been detrimental to the operation of some or all the equipment. The complainant asked the insurer whether it would confirm PB had included a contingency to cover any costs relating to the recommissioning or repairing of equipment. The insurer replied saying PB had included the cost of reconnection of this equipment, and if there is damage, this is unforeseen cost pending what/if equipment subsequently requires replacement. In a later report in February 2021 the assessor said the pipes/equipment would be checked once removed. I note PB‟s quotation in relation to repairing the spa includes the supply and installation of a new sump pit and pump and re-commissioning of the existing spa plumbing and motor. The costs of these items are not specifically itemised, but I am satisfied some allowance has been made for replacement of some pool equipment by PB. I am also satisfied the insurer has acknowledged pipes and equipment will be checked once removed and replaced if damaged. To prepare the quote, I am satisfied NH must have examined the pool equipment. He unequivocally says the listed equipment is no longer operational and cannot be repaired. I accept he has the expertise to comment. I am satisfied PB has made some allowance for replacement of the pump. In the circumstances I am satisfied it is fair the amount claimed for pool equipment ($9,897) is reduced by $1,752 making a net total payable of $8,145. In those circumstances I am satisfied it is fair the insurer makes a further allowance on the net amount payable of $1 0,124.23 for the pool equipment which includes a builder‟s margin of 13% and 10% GST. Determination | Case number: 788262 Page 10 of 21 Fair the insurer pays $3,107.50 to replace pool room window The complainant requires the insurer to cover the replacement of the pool room window on the north side wall. He claims $2,500 plus GST for the replacement of the pool room window as per NH‟s quote to supply and install the window. The complainant provided a photograph of the window and said he was unaware it did not comply with current building regulations. He says the window will have to be removed to provide access to the installation of the new pool. He criticises the insurer for failing to provide him with the report it relied on. In the report relied on and dated 27 November 2018 S states: it is unlikely that the glazing in the timber framed windows in the indoor spa room comply with current building regulations. The glazing is not damaged as a result of the fire, therefore there is not an allowance to upgrade the glazing. However, it is recommended that the glazing is assessed and replaced where necessary to comply with current building regulations. In its October 2020 report and correspondence with the complainant the assessor said the north wall window does not need to be replaced. But in correspondence in August 2020 (after consultation with the building coordinator) the insurer said the removal of the timber frame below and above the window to provide access to a crane can constitute a variation and will need to be re-costed by PB. From the available material I am unable to locate any re-costing on this item by PB. I note the policy provides repair costs do not include upgrading the damaged parts of the building to comply with the current home building regulations and laws. I also note the glazing was not damaged because of the fire. The insurer has agreed to pay to install the spa. And in its August 2020 correspondence it agreed this item constituted a variation. Based on the available information I accept the windows to the pool room will have to be removed to install the pool. The windows will then need to be replaced. In those circumstances I am satisfied it is fair the insurer makes a further allowance of $3,107.50 for the pool windows which includes a builder‟s margin of 13% and 10% GST. Fair the insurer pays a further $38,198.09 plus interest to the complainant Taking all matters into account I am satisfied the insurer is entitled to base its offer on PB‟s quotations because the quotations were actionable and PB was willing to carry out repairs. I am als o satisfied the insurer has not taken sufficient account of the complainant‟s issues and that its cash settlement offer is insufficient to repair the fire damage. In those circumstances it is fair the insurer pays to the complainant as follows:  $92,896.9 7 PB‟s quotes (paid already)  $2,556.60 replacement of external cladding  $4,200 building permit fees  $4,102 landscaping  $10,124.23 pool equipment Determination | Case number: 788262 Page 11 of 21  $3,107.50 pool room window  $116,987.30 Total The insurer allowed and paid a 10% contingency ($9,289.70) on 2 June 2021. It says it will not take any price increases in the last 12 months into consideration as the claim was settled in October 2020 and the complainant did not arrange for the repairs to be done. It says it allowed for price increases, with the co ntingency that was provided as part of the cash settlement . I do not agree with the insurer‟s position. Although a cash offer was made and paid to the complainant in October 2020, as set out above, the offer was insufficient and made no allowance for any contingency. I acknowledge the insurer‟s submission that it paid for the removal and reinstallation of the spa as part of repairs despite SP‟s opinion. However, I consider once it adopted that position it still had to ensure its cash settlement offer was fair. Given the age of PB‟s quotes, the complexity of the complaint, the acknowledged variations by the insurer, the loss of the lifetime guarantee and the accepted increase of costs in material and labour because of COVID-19 I am satisfied it is fair that an uplift of 20% should be applied to the insurer‟s liability. The insurer‟s liability totals $116,987.30. A 20% contingency on this amount is $23,397.46. In conclusion based on the available information and for the reasons stated the insurer is to make the following payment of $38,198.09 to the complainant made up as follows:  $116,987.30 insurer‟s total liability  $23,397.46 - 20% contingency  $140,384.76  $92,896.97 - less amount paid October 2020  $9,289.70 - less amount paid June 2021  $38,198.09 balance due Should the complainant accept this determination then within seven days of notification of acceptance, the insurer is to pay to the complainant $38,198.09. The insurer is also to pay to the complainant interest pursuant to section 57 of the Act from 13 October 2020 (the date of its offer) until settlement. 2.2 Is the complainant entitled to compensation? Compensation paid in some circumstances The complainant says normal steps necessary to commence the repairs were stalled by the insurer‟s continuous attempts to deviate from their own “expert opinion” report on S‟s SOW prepared in November 2018. As a result, he says he and his family were denied the normal use and enjoyment of the property which included the use of the indoor pool room which caused much inconvenience and distress to the family. He refers to his elderly parents who were denied the use of the indoor spa they used and enjoyed for many years. The complainant says the insurer was aware his family was inconvenienced by not having access to two functional bathrooms and that they could not use the spa for their own health/wellness. The complainant seeks $5,400 for indirect financial loss. This is due to: Determination | Case number: 788262 Page 12 of 21  loss of use of his property  loss of the lifetime guarantee  the insurer‟s mismanagement of the claim  extensive delays resulting from the misleading and improper conduct by the insurer. The insurer says most of the delays in the claim were waiting for responses to emails and delays brought about by site meetings it attempted to set up that would have had all the relevant trades on site to immediately address all the scope queries the complainant had. It submits the complainant failed to attend as he had not wanted to allow the trades that could address the issues, on site. Regarding the additional portable bathroom request it says the policy does not provide cover for the cost of hiring an additional bathroom if the property already has a fully functioning bathroom. Fair the insurer pays the complainant $2,000 non-financial loss compensation Under the AFCA Rules, AFCA can award up to $5,400 compensation for indirect financial loss. The policy wording is clear. The policy excludes consequential loss (financial and non- financial loss) arising from or consequential to an insured event. But if the complainant suffered loss because the insurer mishandled the claim, we may require the insurer to compensate for the additional loss. As set out above, I do not accept the insurer mismanaged the claim or acted improperly. The available information shows the insurer tried to have all relevant parties on site to agree on the scope of works so it could arrange for its builders to quote on repairs. The parties were unable to agree and, in those circumstances, (as set out above) I am satisfied it was fair to offer a cash settlement. The claim was made in October 2018 and yet an offer to settlement was not made until October 2020. This is an unusually long time. Having reviewed the available information, I accept some of the delay was caused by the complainant‟s unavailability and by the parties being unable to agree on a course of action to bring the claim to conclusion. Although the insurer cash settled the complainant in October 2020, as set out above, the amount offered was insufficient to repair the fire damage. In those circumstances I accept some delay was caused by the insurer‟s claims management. The loss of the lifetime guarantee on repairs has been taken into consideration in this determination by allowing for a 20% contingency payment. With respect to the claim for indirect financial loss, I have not received any information which support this aspect of his claim. It is accepted insurance law that the complainant has the onus to establish any claimed loss. Based on the available information, the insurer is not required to compensate the complainant for any loss he may have incurred which could be classified as indirect financial loss. AFCA will award non-financial loss compensation (capped at $5,400) if there has been an unusual degree or extent of physical inconvenience, time taken to resolve a complaint or interference with the complainant‟s expectation of enjoyment or peace of mind. AFCA takes a conservative approach to awarding compensation. We do not award compensation because the complainant has suffered some inconvenience and anxiety. AFCA expects complainants to be moderately robust and to bear the normal degree of Determination | Case number: 788262 Page 13 of 21 inconvenience experienced when a problem occurs and to take reasonable steps to manage the situation. I accept there was an unusual degree of physical inconvenience and time taken to resolve the complaint which would have interfered with the complainant‟s expectation of enjoyme nt or peace of mind. Based on the available information I accept both parties were responsible for the delay. Taking all matters into account I am satisfied it is fair the insurer pays to the complainant $2,000 compensation because I accept some delay was caused by the insurer‟s claims management as the amount offered was insufficient to repair the fire damage. 2.3 Why is the outcome fair? While the policy provides the insurer may cash settle the claim, when doing so it must act fairly and ensure the cash settlement is sufficient to repair the claimed damage. The available information establishes the cash settlement offer was insufficient to repair the claimed damage. In these circumstances based on the available information it is fair the insurer pays the complainant a further $38,198.09 plus interest. Determination | Case number: 788262 Page 14 of 21 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided. While the parties have raised several issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. It is an accepted principle of general insurance law that the insured bears the onus to establish on the balance of probabilities that they have suffered a loss caused by an event to which the policy responds. This is known as a prima facie or valid claim. Once so established, the onus shifts to the insurer to prove on the balance of probabilities that an exclusion applies if it seeks to deny or limit its liability for the loss. As advised to the parties, we have considered it appropriate to expedite this complaint in accordance with the Operational Guidelines to the AFCA Rules, due to the nature of the complaint. Accordingly, this complaint has not been the subject of a recommendation and has proceeded directly to determination. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. AFCA’s role AFCA is a complaint resolution service offered as a free alternative to the courts. We are not a regulator of the financial services industry. We can consider individual complaints regarding loss or damage caused by an insurer‟s actions. Determination | Case number: 788262 Page 15 of 21 The purpose of AFCA is not to punish or impose a fine on an insurer. We do not have the power to review a general practice unless the practice breaches a specific duty or obligation, or it is not consistent with industry practice. Organisations such as the Australian Securities and Investments Commission (ASIC) and the Australian Competition and Consumer Commission (ACCC) have a role in consumer protection and the regulation of the financial services industry. 3.2 Relevant Policy Terms The relevant policy extracts are referred to in the correspondence between the parties and in the insurer‟s Notice of Response. Both the policy document and the Notice have been exchanged with the complainant. Page 26 Other repair/rebuilding costs We cover When we are rebuilding or repairing damaged parts of the building, we will pay the reasonable and necessary costs:  of any temporary work required to make the damaged or destroyed building and insured address safe;  for the services of professionals, such as architects or surveyors, to repair or rebuild at the ins ured address;  to make the damaged parts of t he building comply with the current home building regulations and la ws.  We do not cover The cost of:  removing tree stumps and roots still in the ground;  removing or lopping fallen trees or fallen branches that have not damaged the building;  upgrading undamaged parts of the building to comply with the current home building regulations and laws;  making the building comply with home building regulations and laws that existed but were not complied with when the building was originally built or altered. 45 How we settle building claims If we agree to pay a claim for loss, theft or damage to the building, we will decide if we will :  repair damage to the building;  rebuild the building;  pay you what it would cost us to repair or rebuild the building;  pay you the building sum insured shown on your certificate of insurance; Note: This does not apply if you have selected the Complete Replacement Cover® option.  give you a voucher, store credit or stored value card for the amount it would cost us to repair or rebuild an item. If we rebuild (or pay you what it would cost us to rebuild), we will do so on a `new for old‟ basis. Determination | Case number: 788262 Page 16 of 21 If we repair (or pay you what it would cost us to repair), we will at our option do so on a `new for old‟ basis or repair to a simi lar condition to what the building was in before the loss or damage occurred. Unless we tell you otherwise, we will deduct any amounts you owe us from any amount we owe you. We will not:  pay more than the relevant sum insured (unless you have the Comp lete Replacement Cover® option) or policy limit;  pay extra to repair or rebuild the building to a better standard, specification or quality than it was before the loss or damage occurred except as stated in the meaning of „new for old‟;  fix a fault that existed before the loss or damage occurred .” New for old means: • New materials, new items we rebuild or repair with new items or new materials that are available at the time of replacement or repair from Australian suppliers. • New for old, regardless of age we rebuild or repair regardless of age, with no allowance for depreciation. • Same type, standard and specification as when new we replace or repair to the same type, standard and specification (but not brand) as when new. If the same is not available, it means of a similar type, standard and specification (but not brand) when new. We can replac e with a different brand. New for old does not: • include paying the extra cost of replacing or purchasing an extended warranty o n any item; • mean of a better standard, specification or quality than when new. 3.3 Extracts from material relied on by the parties Date Action Fire reinstatement inspection report (S) 27 November 18  Licensed building consultant inspected and photographed property 2 November 2018  Most severe fire related damage was in the indoor spa room - originally constructed for injury rehabilitation.  Not viewed any documentation to confirm that the indoor spa ro om was constructed with the consent of the local authorities.  Smoke has spread throughout the residenc e from the indoor spa.  Hous e was being professionally cleaned at the time of my inspection; therefore, there is not an allowance in the scope of works i n this regard.  Damage was not ed to the timber floor frame and stump footings at the north - eastern corner of the spa room. There is limited clearance beneath the timber floor frame. This prevented an inspection of the Determination | Case number: 788262 Page 17 of 21 subfloor area generally. Therefore, there is an allowance in the scope of works to inspect the timber stump footings and floor frame after the flooring and spa are removed.  Upgrade to replace the damaged external sliding door with a self - closing, self - la tching, hinged door, which is compliant wit h current building regulations.  Unlikely glazing in the timber framed windows in the indoor spa room comply with current building regulations. The glazing is not damaged in the fire, therefore there is not an all owance to upgrade the glazing but recommended that the glazing is assessed and replaced where necessary to comply with current building regulations.  Significant asbestos throughout including the internal wall linings (spa hob wall lining) and suspected in eaves lining. Make safe arranged to remove damaged asbestos wall linings. Other building components containing asbestos may become apparent during construction and Builder must confirm presence of asbestos prior to demolition  Scope of Works is to be used as a guide to rebuilding the building to a condition equal to but not better or more extensive than when new.  Upgrades have been included where necessary to comply with current building regulations and requirements. S Scope of Works 27 November 2018  Was not able to obtain original architectural plans from local council  Scope includes work to the outside and inside of the indoor spa room; plumbing work required; and work in relation to the indoor spa and spa room access door.  Asse ssment report (SB)  5 August 19  Insurer‟s assessor met with customers with building coordinator (B) and builder (BB so can write a scope of works together as insurer did not want to use S‟s SOW  BB not allowed on site  Went through S‟s SOW and picked out errors but could not write a new scope of works without BB.  Complainant said pool needs to be removed to facilitate the recommended works. B says get pool expert to comment.  B says pool has not popped but needs a servi ce.  Com made notes of what items we removed and amended from the S‟s SOW.  Need to do the exact same thing with a new builder and B. Next available date that they can both be there was 9 September. All parties agreed to the next site attendance to be compl eted on this day. Determination | Case number: 788262 Page 18 of 21  B recommend appointing PB to attend with us to develop the SOW and quot e and bring in a pool specialist.  Next meeting will develop a SOW and quote together. Asse ssment report (SB) 10 September 19  B could not attend but PB and pool Spe cialist (SP) attended.  Went through Sow with additional notes from the previous meeting  PB agreed with the SOW/notes that has been provided and stated he will include the pool repairs once SP has submitted his report for review.  Explained that once quote is reviewed and pool report this will be reviewed by B, and we will determine the next steps on the claim. Asse ssment report (SB) 14 November 19  Copy of the SOW and pool report should address most concerns.  PB can proceed with repairs, but complainant would first have to agree to the SOW as signed off from B.  Further pool inspection would be done once repairs have started as floor needs to be removed.  Repairs will not be completed by Christmas due to delays in resolving the SOW.  Cash settlement was offered as complainant does n‟t agree wit h the cost/SOW  Asse ssment report (SB)  18 February 2020  As discussed on multiple occasions with the complainant S only meant to provide a SOW for the structural damage bei ng the foundation of the corner of the property. They have not done as requested and now have provided information that is incorrect on what is required to be fixed at the property.  SOW is redundant, and repairs will not proceed based on their SOW, as we decide how the repairs will proceed based on our builders (PB)  As for a second quote, this is not required as we agreed and approved the SOW based on the assessor and building coordinators review  In response to complainant‟s request work completed by panel builder says cash settlement requested because the customer attempted to make the builder and assessor sign a document that the SOW wouldn‟t be changed from the S report even though onsite we agreed this was incorrect and complainant still hasn‟t agreed t o the SOW, without consent on the works we are forced to offer a settlement. As per page 45 of the policy document we decide the outcome of the claim whet her repair or settlement, as this has been a drawn - out process not agreeing to the SOW we have Determination | Case number: 788262 Page 19 of 21 no choi ce but to settle as the SOW will not change to what has been approved.  PB have confirmed that they are happy to complete the works but cannot do so unless the SOW is agreed. PB are reluctant to commence the works as an agreement can‟t be reached wit h the SOW.  Asse ssment report (SB)  12 October 2020  Assessor and building coordinat or (B) reviewed queries about the repairs/SOW  On - site Assessor and B went through S‟s SOW with complainant and agreement was reached in relation to the timber wall cladding that 25.8m2 was not required  Refer to amended quote in relation to removal disposal and replacement of cement wall lining  Asses sor and B agreed to add a contingency of $2,200 to move the new pool from the front of the property.  Pool will be transported by truck then craned to the backyard and a pool installer will determine the best way to manoeuvre the pool into the final positi on.  If the floor is damaged during installation this will be added and fix ed by the builder – an engineer is not required  Regarding pool installation a concrete slab is not required. We have allowed for the sump pit as per amended quote  As for pool equi pment, this included in reconnecting the spa (specialist said no damage to current equipment) > if there are damages this will be an unforeseen cost pending what equipment needs to be replaced  Nort h wall window does not need to be replaced  Quote inclusive of all costs to replace the pool  No engineering requirements to repair the damage at the property. All associated cost for installing the pool have been included in the spa replacement quote.  Scope and costs have been checked off multiple times by the a ssessor and building coordinator these are deemed accurate.  Complainant has voided his opportunity to discuss the SOW due to multiple cancelled site inspections.  ASSESSORS OUTCOME: Our liability for the works are Spa replacement: $44,720. 51 Building repa irs: $45,976.46 Contingency: $2,200 Asse ssment report (SB) 2 February 2021  Reviewed complainant‟s quote.  It was agreed additional cladding not required  Quote includes a soil test which is not required  Various costs difficult to justify as provide no breakdown  Pool specialist confirmed there was no damage with Determination | Case number: 788262 Page 20 of 21 the indoor spa and pipes/equipment would be checked once removed  Part A Unable to justify the $13,641.38 difference as no cost break down on the customer‟s quote. The additional cladding that the customer has raised would only cost an additional $1,200 however this has been deemed not required.  Part B Outcome: Difference in the quot es is $24,669.36: $15, 397 is for the pool equipment and landscapin g. Due to lack of breakdowns provided by the customer unable to justify the cost difference.  We have gone above and beyond by accepting the S original SOW even though this was exaggerated  Accepted replacement of the Indoor Spa when a pool specialist has c onfirmed it is not damaged which increased the settlement cost to $40,000  Quoted amount provided by PB is more than adequat e to return the home back to a pre - loss condition. Pool report (SP) Inspection 9 Sept ember 2019  Inspected and photographed fibreglass plunge pool and surrounds 9 September 2019  Did not identify any resultant damage to the shell of the pool, or its interior.  Observed discolouration of the shell as a result of age and improper water balance.  Upon removal of chipboard flooring substrate to the interior of the pool room, a further site inspection will be required to have a look at the pipe work, and testing and reporting as required.  Did not identify any defects to the floor of the plunge pool as a result of damaged substrate.  Recommend all repair works to the pool room be conducted with the spa left insitu, as would have been the case during initial construction. PB building repair quotation 13 September 2019  Total including GST and builders‟ margin of 13% $45,976.46 PB bu ilding repair quotation for indoor spa 13 September 2019  Total including GST and builders‟ margin of 13% $44,720.51 Complainant’s quotation (NH) 12 January 2021  Scope of works for Building works (see Part A) $59,617.84  Scope of works for SPA replacement (see Part B) $69,389.87  TOTAL $129,007.71 includes GST and builder‟s margin 10% Complainant’s quotation (NH) 3 June 2021  Scope of works for Building works (see Part A) $58,213.48 Determination | Case number: 788262 Page 21 of 21  Scope of works for SPA replacement (see Part B) $72.414.87  TOTA L $130,628.35 includes GST and builder‟s margin 10% Email from NH to complainant 21 March 22  Due to inc reased materials and labour costs, we will not be able to undertake the building works in accordance with the quotation provided back in June 2021.  Ex pect a revised quotation for the same building works to be around the $145,000 - $155,000 range reflecting price increases in building costs over the last 12 months.  Once you have confirmed your intention to proceed, we shall provide you with a firmer price on a revised quotation. 3.4 Other documents considered  Parties‟ submissions/emails and all attachments to all submissions/emails .  Correspondence between the parties.  Claim notes.  Assessor‟s reports .  Certificate of Insurance.  Product Disclosure Statement.  Insurer‟s Notices of Response .  Insurer‟s expert reports, quotes, and scopes of works .  Photographs and invoices.  Complainant‟s submission November 2021 .  Complainant‟s quotes .