1 Determination overview
1.1 Complaint
The complainant is represented. For the sake of brevity and convenience, any references to
the complainant in this determination will include references to her representatives.
The complainant holds a home insurance policy with the financial firm (insurer).
On 13 July 2020, a claim was lodged for hail damage to her property.
The claim was accepted, and attempts made to remediate the damage.
A dispute has arisen over the repairs to the property and the work required to restore the
home to its pre-storm condition. The complainant also says the insurer failed to adhere to the
correct repair protocol and that there has been significant delays and aggravation in finalising
the repairs.
The insurer has made an offer of $89,190.96 to the complainant which it says is the
reasonable cost of repairs and other additional costs.
The complainant rejects the insurer‟s offer and is seeking compensation in the amount of
$248,000 to resolve the complaint.
1.2 Issues and key findings
Is the insurer required to increase its settle ment offer?
Based on the available information the insurer:
is required to increase its settlement offer for the cost of repairs by a further 10%
is not required to make any additional payments to compensate the complainant for
contents items.
Did the insurer’s handling of the claim cause unnecessary delays?
Based on the available information, the insurer‟s handling of the claim and repair process
caused some delays. The insurer is required to pay the complainant $3,000 compensation for
non-financial loss.
Why is the outcome fair?
The outcome is fair as it is based on all the available material and the outcome is in line with
AFCA‟s approach to these types of matters.
Determination | Case number: 788200 Page 2 of 17
1.3 Determination
This determination is partly in favour of the complainant.
Should the complainant accept this determination then within seven days of notification of
acceptance, the insurer is to pay to the complainant:
$81,950.13 for the cost of repairs
$6,174 for temporary accommodation
$7,896 for the damaged contents plus the listed contents from its suppliers
10 weeks further storage fees
the cost of her expert report
$3,000 compensation.
While the contents remain in storage until repairs are completed, the insurer is to pay a
further 10 weeks storage from the date of acceptance of the determination.
The insurer is to reimburse costs incurred by the complainant for her expert‟s (VA) report
costs subject to the complainant providing the insurer with the invoice for VA‟s report.
Otherwise, the insurer is not required to take any further action in relation to the claim or the
complaint.
Determination | Case number: 788200 Page 3 of 17
2 Reasons for determination
2.1 Did the insurer’s claims ha ndling cause delay?
Complainant says insurer failed to adhere to protocols and caused delays
The complainant says the insurer‟s handling of the claim caused unnecessary delays and this
caused additional damage and led to a further spread of mould throughout the property.
The complainant also contends delays were caused by the insurer‟s failure to adhere to
protocol number IICRC S520 (Standard and Reference Guide for Professional Mould
Remediation).
In support of her position, the complainant provided a report from her mould expert (VA) to
confirm if remediation works at the property had been adequ ately completed by the insurer‟s
experts and what works were required.
The insurer arranged for the mould remediation work to be reviewed by its own expert (P). P
also reviewed and commented on VA‟s report.
A summary of the reports from P and VA is included in supporting section 3.3 of this
determination.
VA attended the property on 16 February 2021 and provided a report. VA concluded:
Visual evidence and discernible odour suggests that mould remediation works have not yet
been adequately completed and further works are required.
Based on the site assessment and laboratory analysis, VA recommended further
remediation works be conducted at the property to return the internal environment to a
state normal fungal ecology.
Prior to the commencement of any remediation works, all excess/elevated moisture issues
are to be identified and rectified.
All remediation work should be conducted by an accredited remediator, employing
methods in accordance with the following reference or equivalent: IICRC S520.
Insurer says delays not caused by its claims handling
The insurer says there was an initial delay with restoration works and that the restoration
company was changed due to the delay.
The insurer says it does not agree that its handling of the claim has caused any intended or
unreasonable delays. However, it agrees there have been delays with the claim due to the
dispute that arose because of the issues raised by the complainant during the claim.
Following receipt of VA‟s report (from the complainant) the insurer r equested a review of the
report by its mould expert (P).
P undertook a review of VA‟s report and provided the insurer with its findings and
recommendations. Based on this, the insurer advised the complainant that it would comply
with P‟s review of VA‟s re port and recommendations
Further, the insurer says the IICRC S520 standard (raised by the complainant) is a guideline
used for remediation and this is noted in both VA‟s and P‟s reports and as such has been
followed by its remediation.
Determination | Case number: 788200 Page 4 of 17
The insurer says the complainant raised concerns regarding mould from the beginning of the
claim, and therefore the insurer took affirmative action to remediate the property. Due to
multiple service providers such as restorers, builders and hygienist required at each stage of
repairs and remediation, it says the claim process took time.
Insurer’s handling of the claim caused some delays
The claim was lodged in July 2020. Despite numerous attendances by restorers and
remediation experts, the property was not cleared for repair works to finally commence until
March 2021.
In its report (March 2021), P states that reinstatement of building materials can commence as
the remediation works within the work area are carried out to a satisfactory standard.
Whilst the insurer says it took affirmative action to remediate the property and commence
repairs, the evidence suggests this was not completed adequately and that further
remediation works were required.
The panel is satisfied the remediation works have been carried out to the appropriate
standard (IICRC S520) as referred to by both experts.
The panel accepts that the claims process took time due to multiple service providers
attending the property and undertaking repairs / remediation works. Additionally, the parties
could not agree on the scope of works. However, having reviewed all the available
information, the panel is satisfied the insurer‟s handling of the claim and its repair process
caused some delays.
On this basis, the panel has considered it appropriate for compensation to be paid, and
further consideration for non-financial loss is outlined in section 2.2 of the determination.
2.2 Is the insurer required to increase its settlement offer?
Policy provides cover for storm damage
The Product Disclosure Statement (PDS) outlines the circumstances under which the policy
provides cover. Extracts from the relevant policy terms are set out in supporting section 3.2 of
this determination.
The policy covers a series of insured events, with optional cover for accidental damage. The
Certificate of Insurance (COI) confirms the complainant did not take out cover for accidental
damage.
Under the insured event „storm‟, the policy provides cover for loss or damage caused by a
storm. This includes violent wind, cyclone, tornado, rain, thunderstorm, hail, snow and
landslide or subsidence that happens immediately because of a storm.
The panel accepts, and it is not in dispute, the home and contents were damaged by storm.
The dispute is about the extent of damage caused by the storm. The complainant must
establish on the balance of probabilities all the claimed damage was caused by the storm
event. The insurer must establish when settling the claim its settlement represents the
reasonable cost of repairs to the storm damaged part of the home and contents.
Insurer must pay for the reasonable cost of repair for storm damaged property
The PDS outlines how the insurer settles claims, namely:
Determination | Case number: 788200 Page 5 of 17
We will never pay more than the sum insured shown on your policy schedule, or any applicable
policy limits as noted in the PDS, plus the extra amounts shown under the Extra Cover section.
1. We can settle your buildings claim by:
paying for the reasonable cost of repair or rebuilding the damaged part of your
buildings.
paying you the reasonable cost of repair or rebuilding the damaged part of your
buildings.
rebuilding the building to its size and quality before the claim; or
any combination of the above.
Offer made by the insurer to resolve the complaint
Both parties agree a cash settlement is an appropriate method of settlement.
The issue in dispute is about the scope of works and cost of repairs.
Following its assessment, the insurer tasked its builder (B) to provide a scope of works for the
claim related repairs. The insurer requested B provide an estimate for the repair costs while
the complainant obtained her own quotes.
The complainant provided quotations from builder (TC) for $248,000 and builder (JS) for
$267,440.
Following its review, the insurer says it is unable to accept TC‟s quote as the scope of works
includes items that were not damaged by the storm and items that have already been
repaired (such as the sub floor, timber framing, sarking, roof tiles, wet areas and alfresco).
The insurer says there is insufficient evidence to establish all works claimed relate to the
damage caused by the storm. The insurer acknowledges the complainant‟s concerns that
there may be additional damage, but it says the evidence does not establish this is the case.
Based on advice from its experts, the insurer made an offer to compensate the complainant
$81,294.96 for the reasonable cost of repairs (what it would have cost the insurer to complete
the works) and temporary accommodation.
The insurer also agreed to pay an additional $7,896 for contents items which were storm
damaged.
The insurer made a final offer to the complainant for the cost of repairs, temporary
accommodation and contents items totalling $89,190.96.
A breakdown of the insurer‟s offer is:
$75,120.96 - cost of repairs $68,291.79 + 10% margin to allow for contingencies (transfer
of risk and unforeseen issues)
$6,174 - temporary accommodation allowance of 6 weeks at $147 per night or $1,029 per
week
$7,896 – cost to replace contents
The comp lainant rejects the insurer‟s offer and seeks further compensation.
Complainant’s counter offer and material considered
The complainant seeks a cash settlement of the claim as she has lost trust in the insurer and
its trades. Further, the complainant sub mits the insurer‟s scope of works has not included all
damage requiring repairs and rectification.
Determination | Case number: 788200 Page 6 of 17
The complainant says several items/costs are not included in the insurer‟s scope of works
and quote including:
roof repairs not carried out to a professional standard
alfresco roof
laundry tile floor
salvaged materials used to complete repairs
not all mould affected materials have been removed
new materials cross contaminated by salvaged material use.
The complainant says the insurer should purchase the house as it is no longer liveable.
The complainant provided a quotation from the builder (JS) dated 19 January 21 in the sum of
$267,440. His scope of works includes replacement of the roof/guttering and refurbishment
and/or renewal including fit out of interior to all rooms including and not limited to stud walls,
linings, skirtings, architraves, doors, kitchen cupboards, new appliances, floor coverings and
painting.
The complainant also provided a quote from a builder (TC) to support her position. He quoted
on rectification works in February 2021 in the sum of $248,000.
TC reported on the damage as follows:
water damaged caused from severe storm to the exterior and interior of the property
property had not been completely dried for approximately three weeks
water still present in the kitchen, alfresco, bathroom, laundry, and roofing structure(s)
water damage has caused extensive mould, decay and dampness throughout the property
and appliances, including the roofing, walls, and floor structures
property is unsafe to be inhabited, especially for the owner who suffers from asthma.
TC says the following repairs are required:
removal of roof tiles, sarking and rafters and replacement with a new colour bond roof and
appropriate supports
removal of all interior coverings - including, but not limited to, stud walls, walls, floors,
supports, ceiling, and ceiling linings and replace with new
removal and replacement of complete kitchen - including appliances
removal and replacement of wet areas - including, but not limited to, laundry, bathroom,
toilet(s) where there is evidence of residual storm damage
allowance for replacement of all floor coverings to ensure cohesive flow throughout
all new skirtings, architraves, door jams and doors to match areas being replaced such as
kitchen, bathroom, and laundry
new roof in the alfresco area damaged from the storm and now exhibiting an evident and
potentially dangerous bow in the roof structure
new painting to damaged areas - but not limited to kitchen, laundry, bathroom, alfresco
area, as required to maintain style and cohesion throughout the house
rubbish removal
supply of all materials and labour.
TC says the property has highly visible water and mould damage throughout and a clearance
from the health expert is required before work is commenced.
TC also says the quoted price may increase due to a possible unforeseen further damage
which may arise during work.
Accordingly, as per TC‟s scope of works a nd quote, the complainant is seeking compensation
in the amount of $248,000.
Determination | Case number: 788200 Page 7 of 17
Fair the claim is cash settled
Based on the available information, it is evident that there has been a break down in the
relationship between the insurer and the complainant.
Accordingly, as the two parties have not been able to come to a resolution, the panel is
satisfied a cash settlement of the claim is appropriate and fair in all the circumstances.
Based on its review, the panel determines the insurer is required to increase its settlement
offer for the cost of repairs (which includes costs for temporary accommodation). The insurer
is also required to pay compensation to the complainant for non-financial loss.
However, the insurer is not required to increase its settlement offer or make any additional
payments to compensate the complainant for her contents items. The panel outlines its
reasoning and recommendations for each item in the determination below.
Scope of works and reports considered
The insurer has offered to pay the complainant $81,294.96 for the cost of the remaining
repairs and temporary accommodation. The complainant seeks an amount of $248,000.
The panel accepts the complainant remains unsatisfied with the insurer‟s offer and is seeking
compensation as per TC‟s quote, to engage the necessary experts to finalise outstanding
matters. The panel also accepts the insurer is not willing to provide any further increase
based on the recommendations from its repairer and from P.
Having carefully considered all the exchanged material, the panel is satisfied the evidence
supports the insurer‟s position that its proposed scope of works is adequate to address the
claim related damages / required rectification work.
The insurer‟s offer is based on two quotations from the build er B. B prepared a detailed scope
and quote on 29 January 2021. This is after some mould remediation had occurred. The
scope of works is detailed. It describes work required in the kitchen, lounge, dining room,
hallway, family room, and two bedrooms. It al so includes a 19% builder‟s margin and GST.
B‟s second quote is for $18,647.10 and includes a builder‟s margin of 19% and GST. The
quote was prepared after the work recommended by P and VA was completed. The quote is
dated 21 April 2021 and includes removal and replacement of the kitchen joinery,
plasterboard sheeting and cornice and air conditioning cleaning.
Having considered all available material including photographs and the reports prepared by
VA and P, the panel is satisfied B‟s quotes represent the reasonable cost of repair of the
storm damaged part of the home.
Specifically, VA noted elevated moisture levels in February 2021 and further drying work was
undertaken. VA did not confirm the alfresco sarking, the timber framing and particleboard
floor ing was a direct result of the storm event. VA‟s report is very comprehensive , yet he
makes no mention of damage in the laundry.
Both experts agree the roofing tiles do not need to be removed.
VA does not support the complainant‟s contention the freezer needs to be replaced because
of storm related mould growth. He said the mould growth was “due to a lack of appropriate
cleaning.” No information from the complainant establishes the freezer or re frigerator was
damaged in the storm event or by storm related mould.
Determination | Case number: 788200 Page 8 of 17
The complainant has expressed dissatisfaction with the roof repairs. After providing a quote
for $23,287.44, and pursuant to P‟s recommendation, B conducted repairs to the roof in
December 2020. Based on the available information, the panel is not satisfied the insurer is
liable to replace the tiles with metal or is liable for any further repairs to the roof.
Having considered all the available material, the panel considers TC‟s quote and scope of
works is not an appropriate basis for settlement, as the panel is not satisfied all the noted
items relate to the claimed event or relate to items which have been repaired.
Insurer to increase its offer for repairs by a further 10%
The panel notes that the insurer‟s offer already includes an allowance of 10% for
contingencies.
The complainant says she is advised there has been a high cost increase in material costs
and labour shortages because of the pandemic. Because of this and the possible variations
and contingencies which may occur once repairs commence, the panel accepts it is fair the
insurer increases its settlement offer by a further 10%.
The panel considers this is fair also due to the transfer of risk which is in line with AFCA‟s
approach to these types of matters.
The insurer is required to increase its offer and pay the complainant a further $6,829.18 in
addition to its current offer. This brings the total for the cost of repairs to $81,950.13.
Should the complainant accept this determination then within seven days of notification of
acceptance, the insurer is to pay to the complainant $81,950.13 for the cost of repairs to the
storm damaged parts of the home.
Insurer to pay the complainant $6,174 for temporary accommodation
The available information indicates the complainant was paid temporary accommodation until
9 March 2021. On 5 March 2021 the insurer offered a settlement of $147 per night for 14
nights ($2,058) which offer was declined.
In its offer made on 23 April 2021, temporary accommodation was included in the settlement.
Repairs were noted to take 4 - 6 weeks so an allowance of 6 weeks at $147 per night ($1,029
per week) was made. The total offered for temporary accommodation was $6,174.
The complainant has not made any significant submissions in relation to temporary
accommodation costs. In an email of 27 September 21 the complainant indicates she had to
pay rent for months.
For the reasons set out above, the panel considers the offer made on 23 April 2021 was
substantially fair. In those circumstances, and in the absence of any material to the contrary,
the panel accepts the amount offered for temporary accommodation was fair and reasonable.
The insurer is not required to increase the offer.
Should the complainant accept this determination then within seven days of notification of
acceptance, the insurer is to pay to the complainant $6,174 for temporary accommodation.
In addition to contents from its suppliers, insurer to pay the complainant $7,896
The i nsurer accepted some of the complainant‟s contents we re damaged in the storm event.
In its August 2020 report, L indicated a scope of works will be provided regarding relocating
the contents from within the affected rooms to allow building works to commence. During
August and September 2020 (at the insurer‟s expense) L continued with photographing,
Determination | Case number: 788200 Page 9 of 17
sanitising, cleaning, and packing contents for transfer off site. Some contents were removed
to the garage.
The insurer says it has included all items stored in the garage which were catalogued and
included in the contents settlement even though some were noted as possibly restorable.
By letter dated 11 May 2021, the insurer advised the complainant it had received the
additional inventory from the garage and added those to the contents claim and had them
costed for replacement.
By letter dated 7 June 2021 the insurer sent the complainant the 2 inventory lists provided
from the restorer for all items considered non- restorable. L‟s inventory included spreadsheets
and photos.
The offer includes items to be replaced by the suppliers listed and items to be cash settled for
$7,896.
The insurer asked the complainant to review and advise how she would like to proceed.
The complainant said she could not make sense of this and will forward it to AFCA. She also
said she rejected this offer as it had to be undervalued. She later said the contents quote is
“laughable” noting 2 pair of shoes cost $1,000 alone.
The insurer says it is unable to further validate the complainant‟s items and concerns for the
contents settlement without the assistance of the complainant and feedback on which of the
items she believes are undervalued. The complainant has not provided any evidence in
support of her position.
The policy provides a contents claim can be settled as follows:
2. We can settle your contents claim by:
• replacing lost or damaged items;
• repairing damaged items;
• paying you or providing you wit h a store voucher for the reasonable cost of repair or
replacement of lost or damaged items; or
• any combination of the above;
The panel has carefully considered all the information in relation to this issue. Although the
complainant has rejected the insurer‟s offer, she has not provided any information to
substantiate her claim the offer is undervalued. The panel can only make its decision based
on the available information. Pursuant to the policy terms, the insurer is entitled to pay the
complainant or provide her with a store voucher for the reasonable cost of replacement of the
damaged items. Based on the available information, the panel is satisfied the offer made by
the insurer to replace the contents items is reasonable.
Should the complainant accept this determination then within seven days of notification of
acceptance the insurer is to pay to the complainant $7,896 and the complainant is to arrange
with the insurer to access the other contents items from the suppliers as listed in the insurer‟s
letter of offer of 11 May 2021.
The complainant expresses concern that contents remain in storage until the repairs are
undertaken and the contents can be returned to the home. She also requires when the
contents are returned they are inspected and where necessary cleaned before being returned
to the home.
Determination | Case number: 788200 Page 10 of 17
The insurer says the restorer has confirmed all contents were cleaned, boxed, wrapped, and
removed from site. It says the contents were boxed and larger furniture items were wrapped.
The insurer also says it has continued to incur storage fees whilst the dispute is ongoing, and
the contents are stored in a safe, clean storage facility at the restorer‟s facility.
The panel accepts it is fair the contents remain in storage until repairs are completed.
However, a fair time frame needs to be established. The panel notes the insurer allowed up to
6 weeks for repairs. In addition, the panel considered that it is fair the insurer allows another 4
weeks for the complainant to make necessary arrangements for repairs. Therefore, should
the complainant accept this determination then the insurer is to pay a further 10 weeks
storage for the contents from the date of acceptance of the determination.
The insurer says the contents are stored in a safe clean storage facility. In those
circumstances it is unlikely the stored contents will need to be cleaned before return to the
home. The parties are to work together to ensure the safe and clean delivery of the
complainant‟s stored contents to her home at the appropriate time.
2.3 Is the complainant entitled to compensation?
Compensation paid in some circumstances
AFCA will award compensation (capped at $5,400) if there has been an unusual degree or
extent of physical inconvenience, time taken to resolve a complaint or interference with the
complainant‟s expectation of enjoyment or peace of mind.
AFCA takes a conservative approach to awarding compensation. We do not award
compensation because the complainant has suffered some inconvenience and anxiety. AFCA
expects complainants to be moderately robust and to bear the normal degree of
inconvenience experienced when a problem occurs and to take reasonable steps to manage
the situation.
The complainant says the delays and overall claims experience has caused her stress and
inconvenience. She refers to several incidents during the claims management including
issues with temporary fencing, change of locks, and a complaint about the letterbox.
The insurer does not agree its handling of the claim caused intended delays. It accepts there
was initial delay with restoration and the restoration company was changed due to delay. It
says however it took affirmative action to remediate the property. Due to multiple services
providers, it says the claim process took time. It acknowledges there were delays with the
claim but says it continued to work with the complainant to minimise delays.
Insurer to pay the complainant $3,000 compensation
The panel accepts that there were disagreements in relation to the appropriate scope of
works and that much time has elapsed since the storm. The panel acknowledges the insurer
was balancing multiple trades and that the complainant no longer wished to use the insurer‟s
builder to complete repairs in January 2021. The panel considers significant progress to a fair
resolution of the claim was not made until the complainant provided the report from VA.
Based on the available information the panel accepts the insurer‟s handling of the claim
caused delays, stress, and inconvenience.
Taking all matters into account, the panel considers an award of compensation is warranted.
The panel is satisfied it is fair the insurer pays the complainant $3,000 compensation.
Determination | Case number: 788200 Page 11 of 17
Insurer to pay the complainant’s fees for the expert report from VA
Under Rule D5, AFCA may decide an insurer is to contribute to the professional costs
incurred by a complainant during a complaint. This is normally capped at $5,400 unless
exceptional circumstances apply.
The complainant engaged VA in support of her position.
The panel considers it was reasonable for the complainant to engage VA given the extent,
nature, and mechanism of damage and in view of the insurer‟s expert evidence from P.
VA greatly assisted the panel in forming its view on the complaint. This is particularly because
VA‟s report extensively discussed and photographed the mould damage and assisted the
insurer in arriving at a final position.
Given this, and in line with AFCA‟s Rules, it is fair the insurer reimburses costs incurred by
the complaina nt for VA‟s fees subject to the complainant providing the invoice or receipt(s) for
VA‟s report.
2.4 Why is the outcome fair?
This outcome is fair because both parties have had the opportunity to provide information to
support their position. The insurer is entitled to rely on the available expert material and its
policy terms. In circumstances where the expert material establishes on the balance of
probabilities all the claimed damage was not caused by an insured event it would not be fair
to compel the insurer to pay the amount claimed by the complainant.
Determination | Case number: 788200 Page 12 of 17
3 Process
3.1 AFCA’s approach to this complaint
This matter was determined by a panel
Due to the nature of this dispute, it has been referred to a panel for determination. The panel
comprises the ombudsman, a member with significant experience in consumer and small
business advocacy and a member with extensive experience in the insurance industry.
The panel has decided this complaint based on what is fair in all the circumstances, having
regard to legal principles, applicable industry codes or guidance, good industry practice and
previous relevant determinations of AFCA or predecessor schemes (which are not binding).
A full exchange of the relevant information has taken place between the respective parties.
Each party has had the opportunity of addressing any issues raised. All the provided
information has been reviewed and considered. The parties have raised numerous issues in
their submissions to AFCA. However, commentary in this determination is restricted to those
issues considered relevant to the outcome.
It is an accepted principle of general insurance law that the insured bears the onus to
establish on the balance of probabilities that they have suffered a loss caused by an event to
which the policy responds. This is known as a prima facie or valid claim. Once so established,
the onus shifts to the insurer to prove on the balance of probabilities that an exclusion applies
if it seeks to deny or limit its liability for the loss.
How we assess complaints
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence. When we assess complaints, we consider available
documents, the recollections of the parties, and all relevant circumstances. We give more
weight to documents created at the time the events occurred. If there is no relevant
documentation, we will decide what is most likely to have occurred based on the information
provided to us. If there are conflicting recollections and these are evenly weighted, we may
find that a claim cannot be established.
3.2 Relevant policy terms
The relevant policy extracts are referred to in the correspondence between the parties and in
the insurer‟s Notice of Response. Both the policy document and the Noti ce have been
exchanged with the complainant.
Storm
What is covered?
Loss or damage to the insured property caused by storm, lightning, wind, hail, snow and
storm water overflow from roof gutters and their downpipes or from the area
immediately around the premises. This includes instances where the storm causes
mechanical, electrical, or electronic (including computer software) breakdown or failure.
Determination | Case number: 788200 Page 13 of 17
Where you have increased your sum insured on this policy within 72 hours of a storm
occurring, cover will be limited to the sum insured that was effective 72 hours prior to
the event.
What is not covered?
Any loss, damage or legal liability caused by:
• storm during the first 72 hours of your policy commencing, unless:
o you had another policy that expired immediately before the start of your
policy with us and there was no break or change in the level or type of
cover; or
o you moved into the premises or signed a purchase or lease agreement for
the premises on the same day your policy with us started.
• storm surge, actions of the sea or tides or other oceanic activity.
• rising damp or seepage of water from the ground.
• rain, wind, hail, or snow entering the building through open windows, doors or
openings made for alterations, renovations, or repairs; or
• rain, wind, hail, or snow entering the building unless through an opening that was:
o created by the storm; or
o not created by the storm and that you could not have been reasonably
aware of even though the building is in good condition.
• The cost of removing or pruning fallen trees or branches or other objects that
have not damaged the insured property.
If you claim under your policy, we have the choice to settle your claim in many
ways.
We will never pay more than the sum insured shown on your policy schedule, or any
applicable policy limits as noted in the PDS, plus the extra amounts shown under the
Extra Cover section.
1. We can settle your buildings claim by:
• paying for the reasonable cost of repair or rebuilding the damaged part of
your buildings.
• paying you the reasonable cost of repair or rebuilding the damaged part of
your buildings.
• rebuilding the building to its size and quality before the claim; or
• any combination of the above.
2. We can settle your contents claim by:
• replacing lost or damaged items;
• repairing damaged items;
• paying you or providing you with a store voucher for the reasonable
Determination | Case number: 788200 Page 14 of 17
cost of repair or replacement of lost or damaged items; or
• any combination of the above;
Exclusions
General exclusions
General exclusions apply to all sections of your policy and describe circumstances
where your policy will not provide cover for any loss, damage or liability arising directly
or indirectly from any cause noted below.
We will not pay for death or bodily injury to any person, or loss or damage to
property caused directly or indirectly by:
13. wear and tear, rust, corrosion, or deterioration.
14. rising damp or seepage of water from the ground.
15. mould, rot, damp or the effects of the climate or weather.
18. poor or faulty design specification, materials, plan, or workmanship.
Home Cover Exclusions
Home cover exclusions apply to all sections of your policy and describe circumstances
where your policy will not provide cover for any loss, damage or liability arising directly
or indirectly from any cause noted below.
We will not pay for any loss, damage or legal liability caused directly or indirectly:
19. by any failure to keep your property in good condition through appropriate
maintenance and repair
3.3 Supporting information
Document Key points
Roof report
16 July 2020
Inspected and photographed roof.
2 valleys over kitchen and living room filled with ice from hail
causing blockage which overflowed into rooms.
Over hallway, slipped tile due to batten underneath not installed
correctly
Two broken tiles not causing water entry but need replacement.
Insurer’s building consultant
(B) Report
21 - 07 - 2020
Inspected and photographed - water had come through ceiling
and damaged plasterboard ceilings in lounge and dining, flooring
to lounge, hallway, and dining. Plasterboard to wall in dining. 2
damaged tiles.
Scope of works to remove roof tiles, and repair work in
kitchen/lounge/dining/hallway family room and preliminaries:
$24,044.34.
Determination | Case number: 788200 Page 15 of 17
Document Key points
Insurer’s building consultant
(B) Report
05 - 11 - 2020
Attended after remediation works actioned in accordance P‟s
remediation report (9/10/020) and requirements.
Variation costs to original submission now $36,780.81.
Note that these costs have been based upon attendance on
Tuesday 3/11/2020 and are subject t o change after the final P
Hygienist report is confirmed and clearanc e is finalised.
Insurer’s building consultant
(B) scope of works
29 - 01 - 2021
Scope of works outlined for work in
kitchen/lounge/dining/hallway/family room including preliminaries
Cost of repairs $49,644.69 including 19% builders margin and
GST
Insurer’s building consultant
(B) scope of works
21 - 04 - 2021
Scope of works to remove and replace previously installed kitchen
to closest matching equivalent as outlined.
Cost of repairs $18,647.10 including 19% builders margin and
GST.
Insurer’s hygienist reports
(P)
March 2021
Report outlines review of VA report (page 5 and 6) and section 8. 2
outlines P‟s recommendations following its review.
Reviewed moisture measurements and mould sampling.
Addressed VA‟s findings.
P agrees with VA that roofing tiles do not need to be removed due
to the very low levels of fungal spores identified.
Lists site specific recommendations in table 2.
Undertook a post mould remediation verification to evaluate
whet her the wat er damage and mould remediation works
undertaken by insurer‟s restorer‟s (L) work was completed to a
satisfactory standard.
Undertook visual ins pection, moisture meter testing of b uilding
materials, total airborne mould sampling and mould surface
sampling.
Throughout, no visual mould identified and has been remediated.
Remediation works within the work area appear to have been
carried out to a satisfactory standard. As such, reinst atement of
building materials can commence
Technical framework denot es which industry standard and
guidance documents that have been considered by P.
This includes the IICRC S520 Standard and Reference Guide for
Professional Mould Remediation.
Determination | Case number: 788200 Page 16 of 17
Document Key points
Complainan t’s hygieni st
report (VA)
24 - 02.2021
Executive summary
Evidence obs erved and collected on the day of assessment
suggests abnormal fungal ecological environment still exists within
areas of the property.
Further remediation works required including moisture levels and
mould contamination.
1.7 Observations include
Items in garage has visible mould growth
Intact wet areas in reasonable condition
Mould growth in dining area
Mould growth in freezer in lau ndry but not storm relat ed.
Conclusions
Visual evidence and discernible odour documented in the report
suggest that mould remediation works have not yet been
adequately completed and further works are required.
Recommendations
Based on the site assessment and laboratory analysis, VA
recommends that further remediation works be conducted at the
property to return the internal environment to a state normal fungal
ecology.
VA also recommends that, prior to the commencement of any
remediation works, all excess/elevated moisture issues are
identified and rectified.
All remediation work should be conducted by an accredited
remediator employing methods in accordance with the following
reference or equivalent: IICRC S520
Following remediation, retesting o f the premises and cont ents to
confirm post - remediation verification should be performed.
From a mould perspective, replacement of framing and flooring
not required.
Insurer’s offer to the
complainant
23 - 04.2021
Email from the insurer to the complainant
Offer of $81, 294. 96
Complainants’ building
consultant (TC) quote
16 - 02 - 2021
Scope of works outlined.
Quote total $248,000.
Determination | Case number: 788200 Page 17 of 17
Document Key points
Complainants’ building
consultant (JS) quote
19 - 01 - 2021
Scope of works outlined including replacement of roof/guttering
and interio r refurbishment/renewal
Valid upon receipt of hygienist report.
Quote total $267,440
Complainants’ email
28 - 06 - 2021
Complainant‟s email (2 excel spreadsheet prepared by restorer L)
with images of damaged contents items
Insurer’s email
11 - 05 - 2021
Insurer‟s offer of settlement for contents items totalling $7,896
3.4 Other relevant material considered and relied on
Parties‟ submissions/emails and all attachments to all submissions/emails.
Expert reports and statutory declaration.
Photographs, estimates and quotations.
Correspondence between the parties and contractors.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.