Claim declined for building movement damage after escape of liquid from a blocked council barrel drain
Text of the determination
Determination
Case number 786940
Financial firm AAI Limited
Case number: 786940 8 October 2021
Determination | Case number: 741225 Page 2 of 17
1 Determination overview
1.1 Complaint
The complainant holds home and contents insurance with the financial firm (the insurer). On
11 April 2019, a claim was lodged after the complainant noticed movement damage to the
insured building. The insurer initially accepted the claim after a blocked and overflowing barrel
drain was identified as the cause of the damage.
After investigating the cause of damage and a yearlong dry out period, the insurer declined
the claim. It says the damage was not caused by the blocked barrel drain but rather, concerns
relating to the construction of the footings and ongoing gradual ground movement. The
insurer says these causes of damage are excluded under the policy.
The complainant disagrees with the insurer‟s decision and wants it to accept the claim.
1.2 Issues and key findings
Has the complainant established a valid claim?
Yes. The available information shows the insured building has suffered some damage as a
result of the leaking/broken council barrel drain. The panel is satisfied the complainant has
established a valid claim under the insured event „E scape of liquid ‟.
Is the insurer ’s assessment of its liability reasonable ?
No. The available information shows that although the insurer has established an entitlement
to decline some of the damage to the insured building, it is not entitled to decline the claim in
its entirety.
In line with the evidence and what is considered fair in all the circumstances, the insurer is to
cover 50% of the cost of repairs to the master bedroom and walk in robe (WIR) section of the
building (hereafter referred to as the north eastern section). This is to be done in line with
section 2.1 of this determination.
1.3 Determination
This determination is partially in favour of the complainant.
The panel considers it fair in all the circumstances that the insurer is liable for 50% of the cost
of repairs to the north eastern section of the insured building.
The insurer is to reimburse the complainant for costs incurred in sourcing evidence from his
appointed engineering consultants, if any.
.
Determination | Case number: 741225 Page 3 of 17
2 Reasons for determination
2.1 Has the complainant established a valid claim?
The policy is an insured events contract of insurance
The policy covers the insured property against loss or damage caused by one or more of the
listed insured events, including „ Escape of liquid s‟. Cover under these benefits is subject to
the conditions, limitations and exclusions specified in the product disclosure statement (PDS).
The insurer is entitled to rely on the policy provisions
The insurer provided the complainant with the relevant policy documentation including the
PDS and certificate of insurance (COI). Therefore, I accept the insurer is entitled to rely on
the policy provisions to assess its liability under the claim.
The complainant has established a valid claim
The complainant is required to show, on the balance of probabilities, he suffered a loss
caused by a risk insured against under the policy. This is known as a valid ( prima facie ) claim.
If the complainant establishes a valid claim, then the onus shifts to the insurer to show, on the
balance of probabilities, it is entitled to rely on an exclusion under the policy to deny the claim.
The complainant‟s policy provides cover for insured events, subject to conditions and
exclusions. The policy will only cover damage if it was caused by one of these insured events
including „Escape of liquid‟ . The insurance schedule shows the complainant does not have
optional accidental damage cover.
The insurer has declined the claim and says the complainant has not established the damage
was caused by an insured event. The insurer says the damage was caused by ground
movement over time and non-compliance with building regulations in the construction of the
section of the insured dwelling in question.
Panel accepts a valid claim exists
The complainant lodged a claim after noticing significant cracking throughout the insured
building, especially to the eastern side of an extension added to the property in 2010. It is not
in dispute:
There is damage on to eastern side of the property caused by ground movement. The
settlement caused cracking to walls, ceilings and the floor slab.
The complainant‟s property contains an easement on the left /eastern side of the dwelling.
There is a council barrel drain located in the easement to the east of the dwelling (between
the eastern wall and the eastern boundary).
Many of the surrounding properties ‟ stormwater drains are connected to this barrel drain.
During heavy rain the drain was found to back up and overflow into the complainant‟s
property.
The council drain was found to be broken and blocked causing the overflow from the
grated stormwater pit in the complainant‟s property adjacent to the side entry door. This
was repaired by the council on 15 May 2019.
The panel is satisfied there is sufficient information to establish a prima facie claim for escape
of liquid. This is because:
Determination | Case number: 741225 Page 4 of 17
The location of the blocked barrel drain pipe aligns with the significant damage noted to
the north eastern side of the insured building.
While there is minor cracking elsewhere, it is significantly worse near the pipe.
The evidence indicates the movement continued during the dry-out period. The panel
disagrees with the insurer‟s consultants „ IL ‟ and favours the complainant‟s consultants‟
„ CSP ‟ opinion. CSP say s the movement noted during the drying out period is more likely
because of the drying out of the clay soils and associated settlement, which is natural and
expected.
While the report from the insurer‟s consultant „ MC ‟ is explicit that a storm drain leak did not
occur and did not cause any damage, this report is entirely inconsistent and less
persuasive than the various reports provided by consultants appointed earlier and who all
agree there was an issue with the barrel drain.
Therefore, to deny the claim, the insurer must show an excluded factor is the proximate
cause of damage.
2.1 Is the insurer ’s assessment of its liability reasonable ?
The property has been the subject of differential ground movement
The panel has considered the expert reports submitted by both parties, details of which are
contained in section 3 of this Determination.
All experts identified there was some damage to the insured building caused by differential
ground movement. They also agree the property is built on reactive clay soils. Reactive clay
soils can shrink when dry and swell when wet. They can also settle when a saturated building
foundation becomes a quagmire or experience movement when the clay soils start to dry out.
Following confirmation of the blocked barrel drain, the insurer obtained a report from engineer
IL in May 2019. IL advised water escaping from the council drain exacerbated damage and
movement in the eastern elevation of the dwelling. It attributed initial movement to the
presence of uncapped perimeter soils to the eastern elevation of the dwelling and natural
seasonal movement of reactive clay soils over an extended period.
IL initially said the leak contributed to localised soil saturation and exacerbated damaged in
the immediate vicinity only (north eastern section). IL attributed 80% of the damage to the
blocked council drain and 20% to inadequate surface drainage (uncapped perimeter soils)
and the natural seasonal movement of soil over an extended period.
A 12-month drying out period was recommended following the repair of the drain and paving
of perimeter soils. In May 2020, IL reassessed the property. IL found movement continued
despite the barrel drain being cleared (and therefore the escape of liquid from the stormwater
drainage was no longer an issue). IL conducted further investigations into the continued
movement.
The insurer‟s geotechnical investigation identified the footings to the WIR to be inadequate,
as say they do not penetrate the zone of influence. This they say indicates the escape of
liquid event had a lesser effect on the building movement than previously expected. IL
recognised the settlement in the north eastern area (closest to the barrel drain) was greater
than other areas of the insured building. IL reassessed its position and attributed 50% of the
damage to the drain and 50% to inadequate footings.
Determination | Case number: 741225 Page 5 of 17
The complainant provided evidence from his engineer „ CSP ‟ who had designed and
documented the 2010 extension. CSP reviewed the insurer‟s expert reports and disagreed
with IL. CSP noted the footings were not as deep as planned, however, were structurally
acceptable and were approved by the building surveyor/inspector on 5 February 2010.
CSP also said movement during the drying out period was expected given the nature of clay
soils. Once water ingress is stopped (leaking pipes repaired), wet clays progressively dry out,
often causing shrinkage and further settlement, explaining further settlements after the repair
of the adjacent storm water pipe.
CSP concluded IL presented insufficient evidence regarding concerns raised about the
footings ‟ depth and that geologist „ SG ‟ notes they are founded on natural clayey sand. CSP
says this is in accordance with accepted engineering standards, regardless of the existence
of any deepened concrete piers.
CSP notes the foundations had performed satisfactorily for some eight years prior to the
water leak event. Had the footings been inadequately founded or constructed, damage would
have appeared sooner. CSP concluded the damage along the eastern side was because of
the ingress of moisture from the blocked stormwater pipe and subsequent collapse of the
underlying clay sand founding material.
The insurer‟s building coordinator „ JB ‟ says given SG confirmed there is 500mm to 600mm of
fill material present at the site, the footings to the extension are currently founded on the
natural clay sand at 500mm below ground level as confirmed by CSP and SG. Further, the
floor level survey of the dwelling has identified that the entire eastern side of the rear
extension has settled 40 to 50mm relative to the opposite end of the extension.
The footings were originally founded at a depth of 450mm, for it to currently be at a depth of
500mm after settling by 50mm. JB says this means the footings along the eastern end of the
extension had been founded on uncompacted fill, and not into stiff clay. JB says the escape
of liquid event had a negligible contribution to the uniform settlement of the entire eastern end
of the extension. He attributes this to inadequate construction of the footings.
The insurer engaged a further engineer „MC‟ which attributes the damage to the absence of
piers/pad footing, incorrect construction of the building slab on unsuitable soils and the drying
effect of surrounding vegetation. MC says a stormwater drainage leak had not occurred to
the premises and is not the proximate cause of the building movement.
MC maintains the construction drawings and building permit clearly note the requirement for
the installation of deepened pad footings, however the mandatory inspections do not provide
a date for the concrete pad inspection leading to suggest the concrete pads were not installed
nor inspected.
Insurer has not established exclusions apply to all the damage claimed
As noted above, the panel accepts there exists a valid claim under the escape of liquid
insured event, given undisputed damage to the insured building in the proximity of the
blocked council barrel drain to the east side. The insurer bears the onus to show, on balance,
the proximate cause for the damage claimed is excluded under the policy.
The proximate cause of a loss is a question of fact depending upon the circumstances of
each case. It is reasonable to consider that there may be multiple contributing factors to the
ground movement and resultant damage to the different areas of the insured building.
Determination | Case number: 741225 Page 6 of 17
These include inadequate site drainage, cyclical wetting and drying of the ground,
construction of the footings and the blocked barrel drain. The insurer ‟s consultants initially
apportioned 80% of the damage to the blocked drain but since then has reduced this to 50%
with the remaining 50% to circumstances excluded under the policy. Despite this, the insurer
has sought to the decline the claim in its entirety.
There is no dispute the majority and more significant damage to the building is at the location
where the blocked barrel drain was found (north eastern section). In limiting its liability, the
insurer relies upon a combination of general exclusions including loss or damage arising from
ground movement or not complying with building regulations.
While the evidence shows there has been a degree of ground movement over an extended
period of time to sections of the insured building to the west and east side, the evidence
suggests this was minor with no significant structural damage. The evidence does not show
that this can reasonably be accepted to be the dominant cause for the more significant
damage found to north eastern section of the building.
The panel accepts there may be some evidence of minor previous ground movement relating
to the uncapped permitter soils and natural seasonal movement of reactive clay soils to the
insured building. However, the panel also notes there has been a significant drop near the
drain which is not consistent with the rest of the dwelling and has caused much more
significant damage. The panel is satisfied the saturation of the soils in the north eastern area
caused by the barrel drain significantly worsened any minor existing movement damage.
The insurer maintains the footings in the extension, completed in 2010, do not meet industry
standards as outlined in AS2870 -1996: Residential Slabs and Footings. MC says despite the
engine er‟s drawings indicating they were designed to comply, it is unclear whether the
concrete pads were viewed as part of the final inspection.
The onus is on the insurer to establish its entitlement to rely on the policy exclusions and
provide evidence in support of its desire to do so. The panel accepts there may be an issue
with the foundations, however, the panel is not satisfied this has been shown to be the main
or dominant cause of the damage to the north eastern section of the insured building.
Therefore, considering what is fair in all the circumstances, the panel is not satisfied the
insurer is entitled to rely on the general exclusions to deny the claim in its entirety.
Insurer to contribute towards the cost of repairs
In light of the conflicting evidence from the consultants and the matters discussed above, the
panel accepts not all the damage to the insured building is because of the insured event
giving rise to the claim. The panel is of the view there insured building has been the subject of
insignificant ongoing ground movement which has caused some minor damage to various
areas of the insured building and unrelated to the blocked barrel drain.
However, the panel is not of the opinion the insurer has shown an entitlement to decline cover
for all the damage to the insured building. In seeking to do this, the insurer is even going
against the evidence from its own appointed consultants who acknowledge the significant
impact the blocked/broken barrel drain has had on the north eastern section. It may not be as
significant as initially thought by IL but still remains significant and inconsistent with damage
to the other areas of the insured building.
For these reasons and considering what is fair in all the circumstances, the panel determines
that the insurer is to contribute 50% towards the reasonable cost to repair the damage to the
north eastern section of the insured building. In the interest of clarity, this 50% contribution
Determination | Case number: 741225 Page 7 of 17
does not extend to other areas of the building and is limited to the repairs and any associated
works needed to repair the damage to the north eastern section of the building only.
Within 14 days of the complainant accepting this determination, the insurer is to arrange for a
suitably qualified consultant to provide an actionable quote of repairs for the damage to the
north eastern section of the insured building. The insurer is to pay the complainant 50% of the
total cost of the quoted repairs plus a 10% mark up for contingencies.
The insurer is to also reimburse the complainant for any expenses incurred in obtaining
evidence from consultants CSP in support of his claim for cover, after the complainant
provides receipts to the insurer.
Determination | Case number: 741225 Page 8 of 17
3 Supporting information
3.1 The AFCA processes
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all the information the parties have provided.
While the parties have raised several issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
A panel determined this matter
Due to the nature of this complaint, we referred it to a panel for determination. The panel
includes:
an ombudsman
a member with significant experience in consumer and small business advocacy
a member with extensive insurance industry experience.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
3.2 Relevant policy terms
What you are covered for – Insured events
If you have a Classic, Classic Extras or Platinum insurance policy, we cover your
home and contents when covered under this policy for loss or damage at the
insured address caused by an insured event during the period of insurance.
Determination | Case number: 741225 Page 9 of 17
Escape of liquid
We cover
Loss or damage caused by liquid leaking, overflowing or bursting from any of the
following:
…
any drain, fixed pipes, roof gutters or guttering and rainwater downpipes,
drainage and sewage systems;
..
water main, fir e hydrant or water supply pipe;…
General exclusions
You are not covered under any section of this policy for damage, loss, cost or
legal liability that is caused by, arises from or involves:
Ground movement
erosion, vibration, subsidence, landslip, landslide, mudslide, collapse, shrinkage
or any other earth movement, but we will cover landslide or subsidence that is
specifically covered under the following insured events:
„Storm‟ (see page 22);
„Flood‟ (see page 20);
„Earthquake and Tsunami‟ (see page 23);
„Explosion‟ (see page 29).
…
Not complying with building regulations
your home or unit not complying with building laws or regulations, except those
laws or regulations introduced after your home or unit was originally built or last
altered which you were not required to comply with.
3.3 Relevant expert evidence
Determination | Case number: 741225 Page 10 of 17
Record Key points
Financial
firm’s expert
( A1 )
Report
22 - 04 - 2019
Attended site and placed the domestic water on a pressure test which
successfully passed.
The Insureds property contains an easement on the left - hand side of the dwelling.
The easement contains a council barrel drain (225mm in size).
All the Insureds stormwater is directly connected to the barrel drain.
During times of heavy rain, the council drain backs up and overflows from the
ground pit in the Insureds property.
Inspected plans of the recent house extension, the plans state that the
n eighbour‟s property sewer drain runs beneath the Insureds property.
Financial
firm’s expert
( IL )
Report
04 - 08 - 2018
Based on the visual inspection and information obt ained to date, we confirm the
escape of liquid from the broken stormwater pipe has exacerb ated the damage
and movement to the eastern elevation of the dwelling (master bedroom and the
walk - in - wardrobe). The initial movement can be attributed to the presence of
uncapped perimeter soils located on the eastern elevation of the dwelling and the
nat ural seasonal movement of reactive clay soils over an extended period .
However, the damage recorded to the remainder of the dwelling can be attributed
to the presence of uncapped soils and the natural seas onal movement of reactive
clay soils over an extend ed period .
We confirm the leak has contributed to localised soil . saturation and exacerbated
damaged in the immediate vicinity only.
Therefore, cracking and movement sighed in the master bedrooms and walk - in
wardrobe only are attributed to the block council barrel drain. However, the
presence of uncapped permitter soils and the natural seasonal movement of clay
soils have contribut ed to the distress and damaged sighted to the dwelling.
Blocked barrel drain caused sighted damage to the dwelling. D amage to the
eastern elevation of the dwelling, specifically the north - eastern area of the master
bedroom and the walk - in - wardrobe can be attributed to the combined effects of :
I nadequate surface drainage (uncapped perimeter soils), and the natural
seasonal movement of soil over an extended period (20%),
Blocked council barrel drain (80%).
Financial
firm’s expert
( A1 )
Report
20 - 08 - 2019
M aintenance Works (works to be carried out b y the insured), Perimeter soils must
be paved and graded away from the dwelling to comply with BCA standards and
prevent water pooling against the footings of the structure.
12 mont hs Drying out period for the soil to stabilize from when the drain has been
rectified and the perimet er soils have been paved.
Financial
firm’s expert
( BB )
Report
13 - 05 - 2029
When assessing the stormwater drains it has been found that pit #2 is full of root
and will need clearing.
When assessing the area, the next - door neighbour ‟s guttering and eves are
deteriorating wit h grass growing out of the pipe area. This is in line with the
insured‟s affected area in the bedroom.
When assessing the sewer, a section has been found to be damage #1 and will
need a patch liner installed.
Fin ancial
firm’s expert
( IL )
D rop in floor level in master b edroom and WIR
As a noticeable change in floor levels have been recorded in the WIR and north -
eastern area of the Master Bedroom, this office has considered the possibility that
Determination | Case number: 741225 Page 11 of 17
Record Key points
Report
27 - 05 - 2020
th ere may be ongoing leaks previously unidentified that may still be causing
localised movement.
We note that the additional plumbing investigation conducted by BB has identified
further leaks to the sewer pipework. However, the soil moisture sampling in the
north - eastern corner of the WIR did not find elevated moisture levels in the soils
in the area . Based on this, we can confirm that the additional breaks to the sewer
have not cont ributed to the further damage recorded to the dwelling.
Due to a noticeable „kink‟ in the floor having developed since our last inspection
despite nine months having ela psed since the blocked barrel drain was
unblocked, this office had further suspicions that there may be issues with the
footings to the dwelling, particularly, considering the pres ence of an easement
directly adjacent to the dwelling.
Based on the drawin gs that we were provided during our initial inspection, we
note that the drawings have not ed the stormwater pipe in the easement to have
an invert depth of 0.6m at the rear and 0.8m at the front (see below).
based on the distanc e between the front and rear ends of the property and
assuming a constant fall in the pipe between these two ends, we estimate the
invert depth of the pipe adjacent to the WIR (located approximately in the middle
of the block) to be approximately 700mm.
Typically, when structures a re built within an easement zone of influence, the
foundations of the structure are carried through the zone of influence into stable
ground. The reason for this is two - fold:
1. It prevents any damage to the assets contained within the easement from
the lo ading of the new structure above.
2. It prevents settlement of the new structure by not relying on the bearing
capacity of the unstable and uncontrolled fill within the eas ement.
T o verify the depth of the footings in the area and if they penet rate the ang le of
repose, this offic e has also instructed SG to conduct a footing probe in the
localised drop.
With SG‟s footing probe investigation, we can confirm that the footings to the
dwelling in this area are founded at 500mm below ground level.
We can there fore confirm that the footings to the dwelling in the WIR do not
adequately penetrate zone of influence, resulting in the ongoing settlement of the
footings in this area.
In initial report, this offic e had previously attributed 80% contribution of the
es cape of liquid from the blocked barrel drain to the movement in the north -
eastern area of the master b edroom and the WIR, based on its proximity to most
of the recorded damage.
However, as significant movement had continued to occur despit e the blockage to
the barrel drain having been cleared (and therefore the escape of liquid from the
stormwat er drainage no longer an issue), we have now conducted further
investigations into the continued movement.
As discussed above, the geotechnical investigation has now identified the
footings to the WIR to be inadequat e, as they do not penetrate the zone of
influence. Considering the further investigation this additional information that has
come to light, this office confirms that the escape of liquid event has had a lesser
effect on the building than previously expected.
We recognise, however, that the settlement record ed in the WIR and master
Determination | Case number: 741225 Page 12 of 17
Record Key points
b edroom (closest to the barrel drain) is noticeably greater than the north - eastern
area of the dwelling, even though the e asement runs along the entire east
elevation of the dwelling.
We can therefore confirm that initial movement of the dwelling occurred becaus e
of the inadequate footings (as discussed above; 50%), wit h the escape of liquid
from the blocked barrel drain (5 0%) having exacerbated the damage and
movement in the immediate vicinity (i.e. the north - eastern area of the Master
Bedroom and the WIR
Financial
firm’s expert
( A1 )
Report
27 - 05 - 2020
We recommend that the ins ured engages a suitably qualified engineer to assess
the adequacy of the footings to the entire dwelling and provide recommendations
on addressing the footings that do not currently penet rate the zone of influence of
the easement.
We also reiterate that perimeter soils must be paved and graded away fr om the
dwelling to comply with the NCC, such that water is adequately directed away
from the footings and not allowed to pool near the footings.
All plumbing issues must be rectified as stated in the BB report by a suitably
qualified and licensed plumber.
Whilst they have not caused any damage to the property, we noted the pres ence
of trees near the east elevation of the dwelling, along the eastern property
boundary.
As the trees mature and absorb a great er amount of water from the clay bearing
strata, they can induce minor foundation movements of the founding soils. We
therefore recommend that the trees be regularly pruned and maintained. Where
this is not possible, their removal, or the installation of between the trees and the
building may be required. We recommend that the insured engages an arborist to
provide recommendations on ways to address the drying effect of the trees.
Uncapped soils adjacent to the building must be removed and perimeter soils
must be paved and graded away from the building to pre vent water pooling
against the footings of the structure.
We note that the risk of significant damage occurring in the future is higher if the
uncapped soils and the drying effect of the trees are not addressed.
Whilst the soil sampling has determined the soils to no longer be saturated
because of the leaks in the area, we note that any repairs conducted before the
above ongoing maintenance issues cannot be warranted.
Financial
firm’s expert
( IL )
Report
23 - 06 - 2020
As already discussed in our second report (22157 - S R - LK01), the footing probe to
the WIR area confirmed that the footings do not adequately penetrate the zone of
influence, resulting in the ongoing settlement of the footings in this area. We had
therefore attributed movement to the dwelling to inad equate footings (50%) and
the escape of liquid from the blocked barrel drain (50% ).
However, when superimposing the areas of this first extension and the floor levels
recorded during our inspection (see attached mark ed - up floor plan), we note that
the noti ceably lower areas of the dwelling were clearly only in the areas of this
extension that were right next to the easement, with the floor levels in the entire
eastern end of the extension being uniformly lower.
We also note that the drawings have specified for the strip footings to the
extension to be minimum 500mm deep, with these strip footings to be founded on
Determination | Case number: 741225 Page 13 of 17
Record Key points
mass concrete piers. However, the drawings only specified for these mass
concrete piers to be deepened “to stiff clay”, instead of specifying that they are to
be founded at a specific depth outside the zone of influenc e of the
services within the easement.
The engineer‟s design is therefore actually extremely vague – whilst they have
acknowledged the presence of an easement, they have essentially lef t it up to the
builders to build it correctly without any direction on the actual depth the piers
needed to be founded at.
Regardless, based on the geotechnical investigation, we can confirm that these
concrete piers were not present. We can therefore conf irm that the footings to the
extension have not been constructed such that they penetrate the zone of
influence of the services wit hin the easement.
Complainant’s
expert ( CSP )
Report
08 - 06 - 2020
We note that the Independent Link report of 4 August 2019 concluded that the
damage to the dwelling was caused by water leaks from the adjacent stormwater
pipe. Their subsequent report of 27 May 2020 concluded that the foundation
movements were partly due to inadequate footings (alt hough their report
references the wrong - footing drawing), and partly the water leak, but we note that
they did not investigate the footing or adjacent pipe thems elves. They also note
further settlements between their inspections, some nine months after the
blocked drain was repaired. In their email of 23 June 2020, they go further to
suggest that the foundation movements are now attributed to "inadequate
engineering and/or construction with negligible contribution from the escape of
liquid event". We disagree with IL .
The mechanism of soil movements in clayey soils is usually swelling upon the
initial ingress of water. If the water ingress continues over time, the clays become
over saturated, resulting in a breakdown of the clay m atrix and subsequent
collapse.
(Similar to modelling clay becoming unworkable when too much water is added).
Once the water ingress is stopped (leaking pipes repaired), the wet clays then
progressively dry out, often causing shrink age and further settleme nts. This would
explain further settlements after the repair of the adjacent storm water pipe.
Independent Link claim that the footings are founded within the zone of influence
of the services but did not carry out any site investigations. Our investigations
show that the footings are founded outside of the zone of influence, and SG note
that they are founded on natural clayey sand. This is in accordance with accepted
engineering standards, regardl ess of the existence of any deepened concrete
piers. We also note that the foundations had performed satisfactorily for some
eight years prior to the wat er leak event. Had the footings been inadequately
founded or constructed, damage would have appeared so oner.
We conclude that the movements along the eastern side are a result of the
ingress of moisture due to the blocked/ broken stormwater pipe, and the
subsequent collapse of the underlying clayey sand founding material. We would
recommend underpinning and jacking back to level of the eastern wall. This offic e
can provide further details if required.
Financial
firm’s expert
As discussed in our report 22157 - S R - LK01, the purpose of considering a “z one of
influence” or “angle of repos e” when building structures near an easement is to
Determination | Case number: 741225 Page 14 of 17
Record Key points
( IL )
Report
21 - 08 - 2020
prevent the settlement of the new structure by not relying on the bearing capacity
of the unstable and uncontrolled fill within the easement. In other words, when
specifying that the footings of th e structure must penetrate this “zone of
influence”, it essentially means that the footings must not be founded on unstable
and uncontrolled fill material.
Whilst the exact location and depth of the stormwater pipe within the easement is
currently unknown, we note that the exact extent of this theoretical “zone of
influence” is less relevant as the geotechnical investigation that has been
conducted onsite has already confirmed:
> The actual depth of the footings that have been constructed, and,
> The actual dep th of the fill material present at the site, at the location of the
footings.
With reference to the geotechnical investigation conducted by SG in 2019, they
found there is 500mm to 600mm of fill mat erial present at the site, and that the
footings to the ex tension is currently founded on the natural clayey sand at
500mm below ground level. This footing depth has also been confirmed by CSP‟s
own investigation.
However, it is crucial to note that our floor level survey of the dwelling has
identified that the e ntire eastern side of the rear extension has settled 40 to 50mm
relative to the opposite end of the extension (south - western corner of the Dining).
Specifically, the footings at the location of Borehole 1 (north - eastern corner of the
WIR) has settled by 48 mm, relative to the south - western corner of the extension.
Therefore, it stands to reason that the footings were originally founded at a depth
of 450mm, for it to currently be at a depth of 500mm after settling by 50mm (see
attached Footing Settlement Illu stration). We can therefore categorically confirm
that the footings along the eastern end of the extension had been founded on
uncompacted fill, and not into stiff clay. Over time, the uncompacted fill material
has naturally settled under the normal load o f the superstructure, ultimately
resulting in the recorded settlement of the structure. The only reason the
extension has settled by only 50mm is becaus e the footings have now reached
the much more solid clayey sand layer; if there had been more fill material, then
the dwelling would have settled more.
We reiterate that, when superimposing the areas of this first extension and the
floor levels recorded during our inspection, the noticeably lower areas of the
dwelling were clearly only in the areas of this extension that were right next to the
easement, with the floor levels in the entire eastern end of the extension being
uniformly lower. This was also physically noticeable with the „kink‟ in the floor that
could be felt underfoot, on the eastern side of the master bedroom.
We therefore maintain our conclusions as previously advised, that is, that the
escape of liquid event has had a negligible contribution to the uniform
settlement of the entire eastern end of the extension. Rat her, it is most definite ly
attributed to the inadequat e construction of the footings.
Complainant’s
expert ( CSP )
Report
28 - 08 - 2020
The transcript from the IL report notes that the "exact location and depth of the
stormwat er pipe within the easement is currently unknown". This is incorrect. As
mentioned in our report of 8 August 2020, the pipe and footing were exposed and
measured by the undersigned, adjacent to the side entry. Refer to the attached
photo 1 showing the top of the pipe towards the top of the photo, and the edge of
Determination | Case number: 741225 Page 15 of 17
Record Key points
the existing rib footing at the bottom of the phot o. The location of the pipe
exposure was adjacent to the side entry. Because the pipe falls towards the north
(front ) of the site, this location will be at the lowest point of the pipe with respect to
the d amaged section of the residence, so the angle of repose will only get better
further towards the sout h. At our inspection, we also lifted the grated pit lid in the
street to view the pipe outlet and confirm its alignment. Independent Link have
made no such investigations, and their comment that the pipe loc ation is
unknown is false.
The transcript from the IL Report, t he SG Report of 2019, and our site
investigations adjacent to the side entry, all concur that the edge rib is founded on
natural clayey sand. IL then conclude "categorically" that the footing has been
founded on a layer of uncompacted fill, and this fill has subsequently settled until
the footings bears n the natural material below. Any engineer, experienced in the
compaction of fill, will be a ware that this is not plausible, unless a significant layer
of fill material is found. Filling does not simply "disappear" when it is loaded or
compacted, but it does compress. Typically, this compression may be in the order
of 20%, depending on the loosen ess of the fill, which would mean a fill layer of
some 250mm thick would be required to obtain the near 50mm settlements
observed. Had it existed, the fill layer would still be present, although compressed
somewhat, but this was not found by SG.
We further note that the foundations were inspected and approved by the Building
Surveyor on 5 February 2010, and we would expect that they would have rejected
them at that time, had any fill been obs erved. Again, we note that IL have made
no det ailed on - site investigations of the ground conditions, and their suggested
causation methodology is incorrect.
The transcript from the IL report also suggests inadequat e construction of the
footings is the cause of settlement, becaus e the settlement was uniform along the
entire eastern end of the extension. This can also be caused by a wat er leak
event. When underground services are installed, the pipe trenches are backfilled.
When a leak in the pipe occurs, the trench acts as an undergroun d "agricultural"
drain which fills with water, if the leak remains undetected. Subsequently, the
entire length of the footing, adjacent to the stormwater pipe, will have its subsoils
saturated until the clay matrix breaks down and collapses. Given the evid ence
noted above, we do not agree with the Independent Link suggestion that uniform
settlement indicates inadequat e footing construction.
Financial
firm’s expert
( JB )
Report
22 - 09 - 2020
I have concluded that the movement of t he edge footing and concrete slab is due
to the lack of critical structural support to the building i.e. absence of mass
concrete piers beneath the concrete slab edge a requirement as this is within the
zone of influe nce.
This requirement was designed to provide structural integrity and stability to the
building. The lack this structural foundation is the cause of the building sinking.
The escape of liquid in this instance (blocked barrel drain) and the uncapped soil s
have not been an influencing factor.
The reason for the movement is clearly the lack of structural support.
I refer to the approved Engineering drawings dated 20/ 1/2010 (attached) which
require “15MPa mass concrete piers to found into natural stiff cla y capable of
safely supporting 200kPa.” Structural support to the zone of influence.
Determination | Case number: 741225 Page 16 of 17
Record Key points
And the Building Coordinator‟s Specialist Report dated 23/6/ 2020 stating:
“Following advice from the newly presented information to Independent Link
regarding the absenc e of bored piers beneath t he concrete slab edge, it has now
been established that wat er ingress from the stormwater pipe, if any, has had a
negligible contribution to the building distress.”
Clearly the approved structural support drawings from CSP have n ot been
followed by the contracted builder.
Financial
firm’s expert
( MC )
Report
20 - 10 - 2020
The proximate c aus e of the building movement and damage is because of the
following cumulative issues:
> Presence of the nearby trees to the east side neighbour‟s property.
> Building footings not constructed in accordanc e with the approved construction
drawings.
> Pad footing/ piers omitted from construction.
> Building footings constructed within angle of repose of stormwater drainage
trench.
> Pre - existing pres ence o f neighbouring west side trees.
> The property has not incurred a stormwater drainage leak and is not the
proximat e cause nor a contributing factor to the building movement .
Complainant’s
expert ( CSP )
Report 20 - 01 -
2021
B uilding slab/footing is not within t he angle of repose of the storm water drainage
trench. We refer to the sketch SKI from our previous report of 8 August 2020.
Since that report the same geot echnical eng ineers (SG ) have carried out a further
report. It is unknown why a second report from th e same geotechnical engineer
was required, but in their later report, SG have amended their earlier
recommendations regarding angle of repose. With the new information provided
by SG, the slab/footing is still not within the angle of repose. Refer sketch S KIA
with amended notes in red. It should also be noted that the test borehole 2 in the
SG Report is not repres entative of the as - built situation, as this borehole has
been taken in the area that was excavated and backfilled by this office in August
2020, t o verify footing and pipe dept hs. The more correct situation is borehole 1
from the earlier SG Report.
We note the trees to the east side neighbouring property , noting that the damage
to the property occurred rapidly in early 2019, while a blocked council barrel drain
was causing water to back - up and overflow into the pr operty, adjacent to the area
in question.
Damage caused by tree effects is gradual and, should the adjacent trees ha ve
been the primary ca u se, CSP would have expected movements to occur ear lier
(and gradually) when Melbourne was during more severe drought conditions.
The presenc e of the stormwater drain bet ween your building and the trees will
partially act as a cut - off for tree effects.
A stormwater drainage event ha s occurred. The comment from MC ha ve not
been justified. In the IL Report of 4 August 2019, BB reported that, in heavy rain,
the council drain backs up and overflows from the ground pit ont o the property
(near the eastern side entry door). I L then confirmed the blockage of the co uncil
drain with the loc al council and confirming it was repaired on 14 May 2019.
Further plumbing investigations noted a break in the pipe junction, to the
easement pipe (adjacent to the eastern side entry door), and they provided a
Determination | Case number: 741225 Page 17 of 17
Record Key points
quote to repair same ( refer attached quote dat ed 3 August 2020). With the
blocked council drain, stormwat er was backing up the pipe into the property (for
an unknown period ) whenever it rained and was leaking into the backfilled ground
around the pipe, either through the broken junction pipe or overflowing from the
grated trench.
This has never been in dispute and was agreed with the previous IL Repor ts. We
cannot understand how MC can now make a statement that a leak has not
occurred, without any justification.