Home / IAG / Determination 786064
Determination 786064
Mishandled storm repairs, delay and use of a contractor the insurer had agreed not to use
Summary
After a hail storm the insurer's repairs were delayed and later found defective, and the insurer reneged on its agreement not to use one contractor for the rectification. AFCA awarded $4,000 for non-financial loss.
The insurer's handling of the claim and rectification fell below good industry practice and caused an unusual amount of inconvenience and interference with enjoyment, so non-financial loss compensation is warranted.
Issues
- Poor claim handling primary · upheld“The insurer's overall handling of the claim and rectification repairs was below the standard expected and not in line with good industry practice.”
- Delay secondary · upheld“The initial repairs were not completed until more than eight months after the claim was lodged. This is a significant amount of time.”
- Repairs or contractors secondary · upheld“The insurer specifically agreed to not appoint A and yet A was appointed. Less than a year after the repairs, rectification was required.”
Subjects and remedies
home or building damagenatural disasterpay non financial loss
Related
Text of the determination
Determination
Case number 786064
Financial firm Insurance Australia Limited
Determination | Case number: 786064 Page 1 of 5
Case number: 786064 16 August 2021
1 Determination overview
1.1 Complaint
On 16 December 2018 the complainant lodged a claim with the financial firm (insurer) for
storm damage to his property.
The insurer accepted the claim and arranged for the property to be repaired.
In July 2020 the complainant reported several issues with the quality of the repairs. The
insurer accepted rectification repairs were required and sought to arrange these repairs.
Various service issues arose, and the parties agreed to cash settle the rectification repairs in
March 2021.
The complainant seeks compensation for the service issues and has raised concerns with
both the insurer’s and its appointed repairers’ actions.
1.2 Issues and key findings
Is the complainant entitled to compensation?
Yes. The complainant is entitled to $4,000 compensation for non-financial loss.
Why is the outcome fair?
The outcome is fair because:
the insurer’s overall handling of the claim and rectification repairs was below the standard
expected and not in line with good industry practice
the insurer specifically agreed to appoint a different contractor but the same one was
appointed
due to the time taken to reach a resolution, and the extent of rectification repairs the
complainant must now arrange himself, he is likely in a worse position than he was prior to
lodging the claim
the insurer’s actions have caused an unusual amount of interference with the
complainant’s expectation of enjoyment or peace of mind
in the circumstances it is fair for the insurer to pay the complainant $4,000 compensation
for non-financial loss.
1.3 Determination
This determination is in favour of the complainant.
Within 14 days of the complainant accepting this determination the insurer is required to pay
him $4,000 compensation for non-financial loss.
Determination | Case number: 786064 Page 2 of 5
2 Reasons for determination
2.1 Is the complainant entitled to compensation?
Yes. The complainant is entitled to $4,000 compensation for non-financial loss.
AFCA may award compensation in certain circumstances
Under paragraph D.3 of the AFCA Rules, we may award compensation for non-financial loss
(capped at $5,400 ) where the insurer’s actions have caused an unusual amount of:
physical inconvenience
time taken to resolve the situation
interference with the complainant’s expectation of enjoyment or peace of mind.
We take a conservative approach to compensation and expect a complainant to bear a
normal degree of inconvenience during a claim.
Insurer accepted claim and authorised repairs
The complainant’s property was damaged in a hail storm on 15 December 2018 and a c laim
was lodged on 16 December 2018.
The insurer arranged for a builder (R) to assess the damage to the complainant’s property .
On 29 January 2019 the insurer accepted the claim and authorised R to complete the repairs.
The insurer says the delay in accepting and authorising the repairs was due to the number of
properties damaged in the hail storm and the volume of claims received. I accept this is
reasonable.
R subcontracted the repairs to another company (A).
AFCA expects parties to work together to resolve a claim
Despite authorising the repairs on 29 January 2019, they were not completed until September
2019. The claim notes show there was contact between the complainant and the insurer
approximately monthly during this time.
The complainant has raised concerns about the contact being initiated by him and not the
insurer in most cases. While the claim notes show this to be the case they also indicate R
was in contact with the complainant to some extent.
It is expected an insurer will be pro-active in contacting its insured during a claim. However,
common-sense should be applied. There may be little benefit in an insurer contacting its
insured if they have recently spoken with them, even if the insured person initiated that
contact.
In recognition of this AFCA expects parties to work together to resolve a claim. This includes
tailoring communication to an appropriate level for the specific circumstances.
Insurer agreed rectification repair were required
The complainant first contacted the insurer to raise concerns about the quality of the repairs
in July 2020 after the awning leaked.
Determination | Case number: 786064 Page 3 of 5
The insurer reopened the claim in August 2020 and one of its assessors reviewed the claim
and confirmed rectification was required. The insurer appointed a building consultant to
provide an independent opinion on the quality of the repairs.
The insurer appointed R to complete the rectification repairs.
Complainant requested different contractors
The complainant says he told the insurer he did not want R or A involved in rectification
repairs however, the insurer said R needed to be given the opportunity to rectify the repairs.
The claim notes support this.
The complainant says he did not want A involved due to p oor workmanship and one of A’s
employee’s allegedly being intoxicated and falling off a ladder.
Insurer continued to use A despite agreeing not to
The c laim notes show the complainant raised the allegation of A’s employee being intoxicated
on at least three occasions (11 August 2020, 13 August 2020, and 22 September 2020). They
also show the complainant told the insurer he did not want A at his property again on at least
one occasion (22 September 2020).
There is insufficient information to establish A’s employee was intoxicated however, given the
complainan t’s belief they were , I accept it was a reasonable request for A to no longer be
involved with the rectification.
The claim notes on 6 October 2020 say:
NEXT ACTION… * [R] to allocate a different trade and NOT [A] to conduct all
works…
And on 21 October 2020 say:
…[complainant] doesn’t want to make an appointment with [R] until he is
absolutely sure that they are NOT sending [A] out to do the job * I confirmed that
[J…]’s notes clearly states [R] is aware of this and won’t be using [A] to tend to
the remediation …
These notes show the insurer agreed to the complainant’s request to not have A involved.
The complainant only agreed to R completing the rectification repairs after this assurance
was given.
The rectification repairs eventually started on, or around, 2 March 2021 however, despite
agreeing to not use A, the insurer (or R on its behalf) engaged A to complete the rectification.
Insurer cash settled the rectification repairs
On 3 March 2021, following the complainant discovering A had been engaged to complete
the rectification repairs, the insurer removed R from the rectification and cash settled the
complainant based on rectification repair quotes the complainant had obtained.
Determination | Case number: 786064 Page 4 of 5
Complainant is entitled to $4,000 non-financial loss compensation
The initial repairs were not completed until more than eight months after the claim was
lodged. I acknowledge the damage was caused by a major hail storm however, this is a
significant amount of time.
Less than a year after the initial repairs were completed it was discovered they required
rectification. The available information indicates the rectification repairs may be more
substantial than the initial repairs.
The insurer specifically agreed to not appoint A and yet A was appointed.
Ultimately, the complainant has been left with a property requiring rectification repairs and a
cash amount to complete these. The complainant now has the inconvenience of having to
arrange repairs to fix the insurer’s repairer’s errors. Arguably, the complainant is in a worse
position than he was prior to lodging the claim given the likely extent of the repairs he needs
to arrange.
Having considered all available information, I am not satisfied the insurer ’s (or its
representative ’ s) handling of the claim and subsequent rectification repairs is in line with good
industry practice and I am satisfied it is below the standard expected. I am satisfied it caused
an unusual amount of:
physical inconvenience
time taken to resolve the situation
interference with the complainant’s expectation of enjoyment or peace of mind.
Accordingly, I am satisfied the complainant is entitled to $4,000 compensation for non-
financial loss.
2.2 Why is the outcome fair?
The outcome is fair because:
t he insurer’s overall handling of the claim and rectification repairs was below the standard
expected and not in line with good industry practice
the insurer specifically agreed to appoint a different contractor but the same one was
appointed
due to the time taken to reach a resolution, and the extent of rectification repairs the
complainant must now arrange himself, he is likely in a worse position than he was prior to
lodging the claim
the insurer’s actions have caused an unusual amount of interference with the
complainant’s expectation of enjoyment or peace of mind
in the circumstances it is fair for the insurer to pay the complainant $4,000 compensation
for non-financial loss.
Determination | Case number: 786064 Page 5 of 5
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.