Home / Westpac / Determination 783629

Determination 783629

Fees and interest charged on company account and bank guarantee debt; delay in reviewing home loan limit increase request

FirmWestpac
Decided2022-09-05
ProductCredit · Business lending
OutcomeFor the complainant in part
Amount awarded$1,010
Non-financial loss$1,000
Amount claimed—
SourceAFCA PDF

Summary

The complainants disputed fees and interest on their company's account and the interest on an unpaid bank guarantee debt, and alleged a promised home loan increase and delays. AFCA found the bank entitled to most fees and interest, ordered refund of two dishonour fees ($10), and ordered $1,000 non-financial loss for delay in reviewing the home loan limit request.

The complainants agreed under the account and bank guarantee terms to the fees and overdue interest charged, and the bank had discretion over credit to increase the home loan limit.

Issues

Subjects and remedies

business interruptionrelated party investmentpay non financial lossrefund fees or charges

Related

All Westpac determinations · Find similar determinations

Text of the determination

Determination Case number 783629 Financial firm Westpac Banking Corporation Determination | Case number: 783629 Page 1 of 9 Case number: 783629 5 August 2022 1 Determination overview 1.1 Complaint The complainants have a home loan with the financial firm (bank) under account number ending #856. The complainants also control a company which holds accounts with the bank including account ending #7277. In October 2019, the complainants made a request to the bank to increase their home loan limit for home renovations and other purposes. In October 2020, the bank declined the complainants‟ request to increase the home loan limit as it failed to satisfy its lending guidelines. In or about March 2020, the company requested a bank guarantee facility of $120,000 (bank guarantee). The bank guarantee was required for security for costs in relation to the legal proceedings between the company and a third party company (CP) at the Supreme Court of NSW. In May 2020, the bank approved and provided the bank guarantee. In March 2021, the bank paid the CP company $80,000 upon demand under the bank guarantee. The bank guarantee debt was then transferred to a separate account owed by the company. The complainants say the bank:  Charged fees and interest on the company‟s account ending #7277 without their authority.  Should not have treated the bank guarantee debt as an overdraft facility and charged interest on the unpaid bank guarantee amount. Rather, the unpaid debt should be added to their home loan.  Previously told them it would approve their loan application in 2019/2020 to increase their home loan limit to replace the funds they used for the home renovations.  Delayed in reviewing their requests for the bank guarantee and to increase the home loan limit. 1.2 Issues and key findings Was the bank entitled to charge fees and interest on account #7277? Save for two dishonoured fees, the bank was entitled to charge the relevant fees and interest on account #7277, being the fees and charges the complainants are disputing. This is because the complainants had agreed to the fees and charges under the terms of the relevant agreement. The two dishonoured fees totalling $10 should be refunded. Was the bank entitled to charge interest on the unpaid $80,000 bank guarantee amount? The bank was entitled to charge interest at the agreed overdue rate on the unpaid bank guarantee amount after March 2021, for the reasons set out in section 2 below, including because the bank had paid out on the bank guarantee and the amount remained outstanding. The interest rate does not have to be the same as the interest rate on the complainants‟ home loan and the bank is not required to add the debt to their home loan. Determination | Case number: 783629 Page 2 of 9 Did the bank agree to increase the home loan limit in 2019 or 2020? There is no information to show the bank agreed or promised to increase the complainants‟ home loan limit. Did the bank unreasonably delay responding to the request for the bank guarantee? The bank did not unreasonably delay responding to the complainants‟ request for the bank guarantee. Did the bank unreasonably delay its review of the request to increase home loan limit? The bank has unreasonably delayed in finalising its review of the complainants‟ request to increase home loan limit as it took 12 months to respond. The complainants should be awarded non-financial loss compensation due to the stress and inconvenience that caused. Why is the outcome fair? While I acknowledge the complainants are likely to be disappointed with this outcome, I am satisfied it is fair in the circumstances. The bank was entitled under the terms and conditions of the relevant agreement to charge fees and interest in accordance with section 2 below. There is no information to show the bank agreed or promised to increase the home loan limit in 2019 or 2020. The complainants are not entitled to any compensation save for the refund of dishonour fees ($10) and the $1,000 non-financial loss compensation for their stress and inconvenience, for the reasons set out in section 2 below. 1.3 Determination This determination is substantially in favour of the bank. If the complainants accept the determination within 30 days, then within 14 days of the acceptance, the bank has to:  Refund $10 to the company‟s account ending #7277.  Pay the complainants $1,000 to an account of their choice which they nominate with their acceptance. If the complainants do not accept the determination within 30 days, then the bank is not required to do any of the above. Determination | Case number: 783629 Page 3 of 9 2 Reasons for determination 2.1 Was the bank entitled to charge fees and interest on account #7277? Save for two dishonoured fees, the bank was entitled to charge the fees and interest that the complainants are disputing as they agreed to the charges under the relevant agreement. The complainants agreed to pay certain fees and interest for account #7277 The complainants provided a list of fees and interest charged to account #7277 which they are disputing. The list was provided to AFCA on 7 July 2021 and is set out in section 3.4 of this determination below. The complainants say the bank was not entitled to charge those fees and interest until the bank guarantee was claimed or paid out. However, under the contract for the bank guarantee, the complainants agreed to the bank using account #7277 to pay:  A service fee half-yearly in advance, from the date a bank guarantee was issued.  An establishment fee of $250 when the bank issued a bank guarantee.  A bank guarantee demand processing fee of $250 each time the bank was required to pay an amount under the bank guarantee. The complainants agreed when they accepted the bank guarantee to allow the bank to debit account #7277 for the fees listed above relating to the bank guarantee, which are not all dependent on the guarantee being paid out. In relation to account #7277 generally, the complainants also agreed for the bank to charge an overdrawn fee of $15 and debit interest when the account became overdrawn without arrangement. That agreement applied regardless of the status of the bank guarantee. I have reviewed the list of fees and interest that the complainants are disputing and the statements for account #7277. The bank is not required to refund the disputed fees (save for dishonoured fees) and interest because:  Although the bank incorrectly charged four $250 „Establishment & Processing‟ fee s, it refunded three of them as the complainants only agreed to pay one fee of $250.  The $506.85 charged on 28 May 2020, was the half-yearly service fee for a bank guarantee. However, according to the bank ‟s internal email, bank guarantee #7824 was a duplicate and not given to the complainants. On 7 October 2020, the bank refunded $506.85 to account #7277 and so there is no loss to the complainants for this error.  The $504.11 and $1,019.18 were the half-yearly service fees for bank guarantees #8238 and #9114 respectively, which the bank was entitled to charge for the reasons set out above.  The $884.27 debited on 15 September 2020, was a payment made to commercial loan ending #4001. As this was for a loan payment, the bank is not required to refund it as there is no loss to the complainants.  The $991.78 charged on 29 December 2020, was the half-yearly service fee for bank guarantee #9114, which the bank was entitled to charge for the reasons set out above.  On 22 March 2021, CP made a demand for the $80,000 under bank guarantee #9114.  On 30 March 2021, the bank paid $80,000 to CP.  The $250 charged on 4 May 2021, was a bank guarantee demand processing fee which the bank was entitled to charge for the reasons set out above. Determination | Case number: 783629 Page 4 of 9  The overdrawn fee of $15 and debit interest was charged every time the account was overdrawn in accordance with the terms and conditions of the account. The available information shows the bank was entitled to charge the fees it applied to account #7277 set out above which it retains. Dishonour fees for direct debits were to be “ fee free ” On 16 June 2020, the bank charged two $5 direct debit dishonoured fees. Under the terms and conditions of the account, the bank agreed that if the bank dishonoured direct debits then no fee would apply. Accordingly, the bank was not entitled to charge direct debit dishonour fees. If the complainants accept the determination, the bank has to refund $10 to account #7277 within 14 days of acceptance. 2.2 Was the bank entitled to charge interest on the $80,000 bank guarantee debt? The bank was entitled to charge interest at overdue rate on the unpaid bank guarantee amount. The interest rate does not have to be the same as the complainants‟ home loan. The complainants agreed to pay interest on overdue amount On 30 March 2021, the bank paid CP $80,000 pursuant to the bank guarantee. It then opened a Banker‟s Undertaking Unpaid account ending #8550 in the com pany‟s name with debit balance of $80,000. Interest was charged on the outstanding balance. The complainants say the bank should not have charged interest at 11.7% per annum, which was similar to an overdraft account. The complainants say the interest for the outstanding balance of the unpaid bank guarantee should be same as their home loan with the bank and request the bank add the amount to their home loan. Under the terms of the contract, the complainants agreed for the bank to charge interest on the unpaid bank guarantee at the overdue rate as applied. There is no information to show the bank has agreed to charge interest on the unpaid bank guarantee amount at the same rate as the complainants‟ home loan. It wa s the bank’s discretion to increase the home loan limit to repay the bank guarantee debt The complainants requested the bank to „transfer‟ the outstanding balance of the unpaid bank guarantee to their home loan by increasing the home loan limit accordingly. Account # 8550 is in the company‟s name where the unpaid guarantee debt currently sits. The obligation to repay the bank guarantee debt rests with the company. By increasing the home loan limit, the bank would be basically providing a loan to the complainants to repay the company‟s debt. It is a commercial matter for the bank to decide whether it wants to provide a loan to the complainants in their personal names for the above purpose in accordance with its policies and legal obligations. This involves the bank‟s own credit risk assessment, which AFCA cannot review under its Rules. Determination | Case number: 783629 Page 5 of 9 2.3 Did the bank promise or agree to increase home loan limit? There is no information to show the bank agreed or promised to increase the complainants‟ home loan limit. There is no information to support the complainant s’ claim The complainants say that in 2019 and in February 2020, the bank promised that it would provide a loan to them and/or advised their request for loan funds had been approved to replace the personal funds used for renovations and other purposes. To support their claim, the complainants say:  The bank valued their property three times and it had sufficient equity for the loan application.  They were told that the bank would give them the full loan sheet and application and were asked to sign a final signing page without anything further.  The bank advised them that they could afford to repay the increased loan and there was significant equity on the property. The bank said the only documents that had to be provided were tax returns.  The bank has not provided any information to refute this claim. This means AFCA must find in their favour for this claim. The complainants are also unhappy with the bank ‟s request for information to support their loan application which they say was excessive as the bank asked about their expenses when it was considering their limit increase application. The bank in response says that it never approved the top up loan and, on 1 October 2020, it told the complainants their limit increase request was declined as it failed to satisfy the bank ‟s lending guidelines. The bank stated that was entitled to request further information in relation to the application to ensure it met its responsible lending obligations. There is no information to show the bank promised to provide the limit increase or agreed to increase the limit for the home loan in 2019 or 2020. Even if the bank conducted valuations on their property three times, or suggested they may have been able to afford to repay the increase home loan limit, does not mean the bank had promised or formally agreed after a credit review to increase the home loan limit. The bank does not have obligation to provide credit even though the complainants say they could afford to repay an increased home loan limit. I also note that the bank has legal obligations in relation to assessing an application for regulated credit which requires it to request sufficient information from applicants to make that assessment. Generally, AFCA will not review a lender‟s reasonable request for further information from a loan applicant as this relates to the lender‟s credit risk assessment and policies more generally. It has not been established that the bank made unreasonable requests in this regard. Further, while AFCA conducts investigations based on the available information and submissions, it is not required to find in favour of one party simply because they consider the other party ‟s response inadequate. Determination | Case number: 783629 Page 6 of 9 2.4 Did the bank unreasonably delay reviewing the request for the bank guarantee? The bank did not unreasonably delay reviewing the complainants‟ request for a bank guarantee. The bank considered the request for bank guarantee within a reasonable period The complainants say the bank unreasonably delayed their request for bank guarantee. It is unclear from the documentation provided the exact date the complainants formally made an application for bank guarantee for security for costs in relation to a court hearing. The bank says the complainants requested the bank guarantee in March 2020. The complainants provided a copy of their letter dated 1 April 2020 to the bank. This letter was in support of their application to increase home loan limit. Relevantly, in that letter, the complainants told the bank that their original request had not changed other than the court requiring security for $120,000. Based on this limited information, it is more likely than not that the complainants made an application for bank guarantee in or around March 2020 as the bank has confirmed. The bank guarantee was approved in May 2020. The bank says it was facing significant delays in processing such applications due to priority of Covid-19 pandemic and staffing impacts at the time. I do not consider the bank has unreasonably delayed the bank guarantee application given the Covid-19 pandemic, staffing issues across all industries, and uncertainty at the time. 2.5 Did the bank unreasonably delay the request to increase home loan limit? The bank has unreasonably delayed in finalising the compla inants‟ request to increase home loan limit. The application to increase the home loan limit was submitted in October 2019 The bank says the complainants contacted it in October 2019 to seek to increase the home loan limit. However, the complainants claimed they contacted the bank much earlier, nominating July 2018. Based on all the available information, it is likely the complainants made an application to increase their home loan limit in or about October 2019 and there is no information to show any formal application commenced prior to that date. I note that on 7 March 2021, the complainants wrote a letter to the bank in which they alleged that they were “ advised ” by the bank that funds would be provided based on a “ pre-approval ” and documentation provided in October 2019. Therefore, it appears that date is likely to have been when the loan process commenced and I cannot find any information suggesting they applied for the increase in 2018. The complainants may have contacted the bank to discuss their banking needs in July 2018. However, based on the limited information available, the formal application to increase home loan limit was likely submitted in October 2019. Determination | Case number: 783629 Page 7 of 9 It took the bank almost a year to finalise the application In July 2020, the bank requested financial information to consider the complainants‟ request to increase the home loan limit from the previous year. As stated above, the request likely originated in October 2019. On 1 October 2020, the bank told the complainants it had declined their request. I consider the bank has unreasonably delayed finalising its review of the complainants‟ request to increase home loan limit. This delay in providing a response has caused some degree of inconvenience and stress on the complainants. The bank must compensate the complainants by paying them $500 each for non-financial loss (total $1,000). It has not been established this delay caused them any financial loss. If the complainants accept the determination, the bank has to pay the complainants $1,000 to an account of their choice, within 14 days of acceptance. 2.6 Why is the outcome fair? The outcome is fair I have considered all available information and I am satisfied the bank was entitled to charge fees and interest that it has retained, including in relation to the unpaid bank guarantee debt. The bank did not have an obligation to approve the complainants‟ request to increase their home loan limit even after the complainants provided all the required information to support their application. There is no information to show the bank promised the increase would be approved. I acknowledge the complainants disagree with the bank‟s decision to not approve their application to increase home loan limit. However, as explained above, the decision to provide credit rests solely with the bank based on its policies and its assessment of credit risk. Even the complainants believe they have enough equity in the property or that they could afford to repay a higher home loan limit, this does not mean the bank has to approve their application. Determination | Case number: 783629 Page 8 of 9 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. 3.2 Relevant terms and conditions for the bank guarantee You have to reimburse us You have to reimburse us for any amount claimed or paid under the bank guarantee/SBLC or any amount we pay to cancel it. You‟ll have to pay these amounts within a reasonable time after we ask. We‟ll generally give you at least 5 business days to do so. However, if you‟ve given us a cash depos it as security for obligations under your facility, we can immediately use the deposit to satisfy your obligation to reimburse us. We may also charge you interest at the overdue rate (or a lesser rate we determine) on any amount have to reimburse us under this clause. Determination | Case number: 783629 Page 9 of 9 3.3 Relevant terms and conditions for the company’s account #7277 13.4 Interest that is charged to you If your account becomes overdrawn without arrangement, debit interest will be charged to that account. It will be calculated daily on the debit balance (and deducted on the last Business day of each month) using the then current Unarranged Loan Rate (ULR) until the account balance is positive again. The ULR is set out in the interest rate leaflet available by contacting Business Telephone Banking or from any branch. 3.4 The disputed fees and interest Date Description Amount 11 - 05 - 2020 - $250 12 - 05 - 2020 - $250 28 - 05 - 2020 - $250 28 - 05 - 2020 - $506.85 03 - 06 - 2020 - $504.11 09 - 07 - 2020 - $250 14 - 07 - 2020 - $1,019.18 15 - 09 - 2020 - $884.27 29 - 12 - 2020 Processing fee $991.78 26 - 02 - 2021 Interest $10.70 31 - 03 - 2021 Interest $12.88 30 - 04 - 2021 Interest $5.59 04 - 05 - 2021 Processing fee $250 31 - 05 - 2021 Interest $0.49

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.