Cash settlement offer for repairs after flexi hose burst; quality of builder's repairs and total loss claim
Text of the determination
Determination
Case number 780896
Financial firm AAI Limited
Determination | Case number: 780896 Page 1 of 8
Case number: 780896 20 October 2022
1 Determination overview
1.1 Complaint
The complainant holds a home and contents insurance policy with the financial firm (insurer).
and lodged a claim in March 2020 after a flexy hose in the powder room burst flooding the
house with hot water.
The insurer accepted the claim however significant concerns were raised with the quality of
the repairs. The complainant says the builder has cut into the concrete slab causing
waterproofing and structural issues. The complainant says the house requires demolition
The insurer acknowledges issues with the repairs but does not accept the structural integrity
of the home has been compromised or the home requires demolition.
The complainant is seeking for the house to be declared a total loss, plus compensation for
stress and inconvenience.
1.2 Issues and key findings
Is the insurer’s cash settlement offer for repairs fair in the circumstances?
No. While the panel accepts the house does not require demolition, the panel considers the
insurer should increase its offer of settlement to $90,107.52 based on the quote from the
complainant’s engineer BE of $75,089.63 plus a 20% uplift to cover contingencies.
The insurer is to also pay the complainant $6,600 to cover the costs of replacing the
complainant’s custom -made bed damaged by the insurers trades.
Is the complainant entitled to compensation?
Yes. The insurer is to pay the complainant $2,000 non-financial loss compensation and
$935.00 to cover the costs of obtaining the report from BE.
Why is the outcome fair?
The outcome is fair as there is no evidence the house needs to be demolished. The
settlement is based on the quote provided by the complainant’s engineer and includes an
uplift of 20% for possible contingencies which is fair in the circumstances.
1.3 Determination
This determination is in favour of the complainant. Within 14 days of the complainant’s
acceptance of this offer the insurer is to pay the complainant:
$90,107.52 for rectification of the house repairs
$6,600 for the replacement bed damaged by the insurers trades
$2,000 for non-financial loss pursuant to AFCA rule D.3.3
$935.00 professional costs pursuant to AFCA rule D.3.5
The insurer is otherwise not required to take any further action.
Determination | Case number: 780896 Page 2 of 8
2 Reasons for determination
2.1 Is the insurer’s cash settlement of fer for repairs fair in the
circumstances?
No. While the panel accepts the house does not require demolition, the panel considers the
insurer should increase its offer of settlement to $90,107.52 based on the quote from the
complainant’s engineer BE of $75,089.63 plus a 20% uplift to cover contingencies.
The insurer is to also pay the complainant $6,600 to cover the costs of replacing the
complainant’s custom -made bed damaged by the insurers trades.
Circumstances of claim
There is no significant dispute as to the circumstances leading to this complaint. The
complainant lodged a claim on 15 March 2020 after a flexi hot water hose in a powder room
of the home burst with water inundating several rooms.
An assessor was appointed and make safe and strip out of the property completed prior to
the insurer ’ s appointed builder BB commencing repairs.
The complainant first raised issues with the quality of the repairs in late May 2020. BB agreed
to rectify the repairs. By November 2020 issues remained with further issues identified.
The insurer had an engineer MCS review the repairs. MCS reported on 30 December that
there were several quality and compliance issues with BB’s work . The insurer agreed to fix all
the identified issues.
Issues continued to arise with the repairs with the insurer accepting in November 2021 that
there were repairs that required further rectification. Issues also arose with damage identified
to the complainant’s custom-made bed. The complainant says this was damaged by the
builder BB or removalist.
The insurer offered to cash settle the claim for $67,869.32 based on a quote from AB of
$45,973.32 plus an uplift of 15% ($ 6896.00) and an allowance of $15,000 for 5 weeks
temporary accommodation.
This offer was later increased to $86,353.07 based on a quote from the complainant ’ s
engineer of $75,089.63 plus a 15% uplift for contingencies.
The complainant says the home needs to be demolished as it is structurally unsound and
seeks settlement of $329,219.60 based on:
removalist, storage, insurance and return: $10,821.60
accommodation at the Quest in Narre Warren: $70,798
repair costs: $231,000.
bed replacement: $6,600
buffer for inflation costs: $10,000
Complainant says house is structurally unsound
The complainant says the insurer’s contractor BB made a hole in the slab during the repair
process to test for rising dampness .
There has been debate between the parties as to whether the hole was drilled by BB or
whether it was pre-existing. BB says the cut in the concrete slab and plastic membrane wer e
Determination | Case number: 780896 Page 3 of 8
existing to allow for plumbing to the existing vanity unit in the powder room and were exposed
during removal of the flooring. BB says there is no structural damage and by filling in the hole
in the slab it has fixed the underlying moisture issue.
The panel accepts rectification works are required because of the inadequate repairs
following the insured event. The insurers building co-ordinator on 4 September 2020 following
an onsite review noted significant deviation of between 8-10mm to the north and south tiled
walls of the bathroom. BB was reported to have agreed to strip the entire room for timber wall
frame straightening at this time. The building co- ordinator’s subsequent report dated 11
September 2020 indicates that upon reattendance after the walls had been replastered, the
back wall was still out of plumb and had not been rectified as agreed with BB.
BB further says it engaged engineering expert HC who recommended the plastic waterproof
membrane in the hole in the concrete slab be taped and filled, and the hole filled with
concrete prior to completing flooring and tiling works. BB says this was carried out as per
advice from the engineer and the moisture levels did not increase after a final drying.
The building coordinator provided a photo showing evidence of a waterproof membrane
installed in the base of the powder room floor penetration achieving a continuous moisture
barrier. The building coordinator also commented that there was no evidence to support that
a waterproof membrane had been installed on the underside of the particle board substrate
(between the substrate and the slab) and that this could be considered defective building
works.
The complainant says the hole is beside a load bearing wall and cracks are appearing in the
ceiling and floor. The complainant notes damage to the laundry, bathroom, and powder room.
The complainant also says the bathroom walls are not straight and the quality of painting
completed throughout the house by the insurer’s contractor was poor and had to be redone.
The complainant says that as the load bearing wall and water proofing have been
compromised the home is no longer structurally sound and should be demolished.
Engineering reports indicate home structurally sound, but rectification repairs
required
In June 2020, HC had advised that following a site inspection, moisture levels in the concrete
floor slab near the water closet are elevated. HC was of the view that it is likely excessive
water from the leak event entered the soil beneath the slab in this vicinity through the square
hole in the slab, resulting in continued high moisture levels. HC recommended that the
moisture barrier in this vicinity be re-established and the penetration be infilled with concrete.
HC noted there were saw cuts extending from the penetration, which it said appear to be from
a previous slab cut to excavate a trench for a plumbing service. HC could not determine if the
moisture barrier in this area had also been compromised.
The insurer has provided a copy of the waterproofing certificate of compliance for the
bathroom dated 3 October 2020 which provides a 10-year warranty. The certificate says the
condition substrate was verified and corrected as needed prior to the waterproofing works
being undertaken.
Structural engineer MC reported on 30 December 2020 that there were defective works
notably:
delaminated, drummy floor tiles that had not adhered to the substrate,
uneven gaps to the wall tiles along with variation in shade
blemishes to the grout,
Determination | Case number: 780896 Page 4 of 8
painting blemishes throughout the house.
bath tub was scuffed and required replacement.
MC noted the complainant advised that the builder cut a saw hole into the concrete slab and
jack hammered out a portion of the concrete and was advised the works were undertaken to
check for rising damp. MC said in its opinion, the removal of a section of the concrete slab to
the centre of the house will not provide any information in relation to rising damp.
MC agreed the removal of the slab section and piercing the membrane under the slab may
exacerbate moisture percolation through to the slab from the ground soils if not properly
repaired prior to the patching of the hole. MC said the internal leak from within the house
would not cause rising damp. MC recommended further clarification with regards to the works
completed to the concrete slab be sought from the builder.
Although BB says it did not remove the section of the slab in a subsequent report dated 12
February 2021, MC said it remains unclear why a section of the concrete slab required
removal to facilitate plumbing to an existing vanity if it was pre-existing and had existing
plumbing to connect to.
The complainant obtained a structural engineers report from BE on 25 March 2020. BE’s
report like that of MC revealed issues with door openings, walls and finish. BE noted minor
settlement movement but no structural concerns at this stage.
BE considered most of the previous defects had been rectified although settlement type
distress remains. As for the concrete slab, BE noted it is apparent that the waterproof
membrane had been installed prior to the concrete being poured but it was unclear whether
the concrete had been tied into the existing slab.
The complainant says the damage to the house is continuing to worsen and supplied photos
which he says illustrate existing cracks in the internal plaster getting larger and new cracks
appearing, and in one of the photos a crack to a floor tile. The complainant further says there
is evidence in the photos showing that doors are starting to lean, and in his view, this is
evidence of the differential movement which was warned about in the reports due to the slab
not being reinforced correctly or the structural walls that BB completed works on not meeting
applicable building codes.
While the panel acknowledges the complainant ’ s concerns, the expert reports including the
complainant’s reports do not indicate the property is structurally unsound. The reports do not
indicate any issue with the structural integrity of the home.
Rectification issues identified
The building coordinator confirmed the various defective works, and amongst other things,
that the drummy floor tiles and installation of the bathtub were defective.
MC reported that the installation of the particleboard flooring within the wet areas does not
comply with the relevant Australian Standards and recommended that the bathroom/wet
areas be demolished and reconstructed to an approved standard. MC considered the
remaining issues w ere mostly cosmetic and could be addressed by ‘competent trades’.
The insurer’s assessor advised that following consultation with MC and the building
coordinator, it was agreed that most of the issues identified by the complainant are
rectification issues due to poor workmanship and/or not complying with current building
codes. According to the building coordinator, the main concern identified was the installation
Determination | Case number: 780896 Page 5 of 8
of particle board flooring directly over the concrete slab in the powder room and bathroom
without a waterproof membrane and this is non-compliant.
At a minimum, the assessor recommended that rectification works should consist of:
remove floor tiles to powder room and bathroom and particle board subfloor
re-install floor tiles to powder room and bathroom over appropriate base (concrete
screed/mortar base)
re-grout floor tiles and wall tiles to bathroom and powder room (sectional repair is
possible).
repair bathtub and shower screen to bathroom
repair bathroom sliding door
prep and repaint the hallway and three bedrooms
repair kitchen cabinetry panel
flooring report to be arranged to determine if flooring requires rectification or if within
tolerances.
The building coordinator also advised the complainant would require temporary
accommodation for the duration of the rectification works, which were expected to take
approximately three months. MC provided a scope of works for the rectification.
Fair for the insurer to cash settle the claim for rectification of the repairs
The complainant indicated they would not have BB back to complete any works, so the
insurer offered cash settlement.
The insurer obtained a quote from AB for rectification works totalling $45,973.32, inclusive of
a 15% builder’s margin. The insurer then added a further 15% uplift to this to allow for transfer
of risk, along with five weeks temporary accommodation allowance totalling $15,000, for a
final offer totalling $67,869.32.
The complainant provided a quote from BE based largely on the SOW from MC. BE quoted
$75,089.63 for the rectification works , inclusive of a 20% builder’s margin , temporary
accommodation at $15,600 and removal and storage of contents at $8,000. The insurer
increased its offer to $86,353.07 based on a quote from BE $75,089.63 plus a 15% uplift for
contingencies.
In response to this offer, the complainant sought further quotes for repairs, removalist,
storage and is now seeking a total of $329,219.60. The panel does not consider this is an
accurate representation of what it will cost to repair the house and allow for associated costs
such as temporary accommodation and storage of contents. The panel notes PC’s quote for
$231,000 is significantly higher than any of the other quotes, including the quote previously
provided by the complainant from BE.
The latest quotes are not detailed or consistent with the damage identified by MC and BE.
PC’s quote includes an allowance of $38,000 to d emolish and replace the bathroom, which is
significantly higher even than the total amount quoted for works to the bathroom by BE (which
amounted to $11,156.10). Amongst other things, PC’s quote also included $18,000 to replace
all flooring throughout the house (which the complainant has not shown is required as a result
of the previous works undertaken by the insurer), $17,000 to ‘fix walls that have been built
incorrectly’ (the complainant has not shown the insurer rebuilt the walls), and a $55,000
allowa nce for unspecified ‘building fees and insurances’ . The panel considers these amounts
to be unsubstantiated and excessive.
Determination | Case number: 780896 Page 6 of 8
In the panels view it is fair that the insurer relies on the quote from BE on which to base the
cash settlement of the claim. The panel notes the quote includes a 20% builders margin and
3.5 % allowance for price increases to 30 June 2022.
In the panel view the insurer should increase the uplift to allow for contingencies to 20% given
the significant increase in building costs over recent times and to cover other possible
contingencies. In the circumstances the panel considers it fair that the insurer pays the
complainant $90,107.52 for rectification repairs based on the quote of $75,089.63 and
including a 20% uplift for contingencies.
Insurer required to compensate complainant for custom-made bed
The complainant has mentioned several times throughout the claim and complaint process
that his custom- made bed was damaged during the previous repair process by the insurer’s
contractors. Me ntion of this is made in the insurer’s assessor’s report dated 13 January 2021
where it was noted that the assessor had reviewed the bed and seemingly accepted that it
was damaged. The report indicated the assessor was awaiting a response from BB in relation
to this. An email from the assessor to the complainant on the same date acknowledged
photos of the damaged bed.
The insurer has not addressed this issue directly or explained why an allowance for the bed is
not included in any of the offers it has made. Given its assessor seemingly accepted that the
bed was damaged (presumably by the insurer’s contractors), the panel considers it fair in the
circumstances the insurer adds an allowance to its settlement for this.
The complainant provided a quote from FW for replacement of the bed totalling $6,600. In the
absence of any other information to ascertain the cost of the bed, the panel considers this
quote reasonable. The insurer is therefore required to pay the complainant $6,600 in
settlement of the claim for the custom-made bed.
2.2 Is the complainant entitled to compensation?
Yes. The insurer is to pay the complainant $2,000 non-financial loss compensation and $935
to cover the costs of obtaining the report from BE.
AFCA may award compensation in certain circumstances
Under paragraph D.3 of the AFCA Rules, we may award compensation for non-financial loss
(capped at $5,400) where there has been an unusual amount of physical inconvenience, time
taken to resolve the situation or interference with the complainant’s expectation of enjoyment
or peace of mind.
AFCA take a conservative approach to compensation and expect a complainant to bear a
normal degree of inconvenience during a claim.
AFCA can also determine under AFCA rule D.5 that an insurer contributes up to $5,000 to
professional costs incurred by a complainant in the course of a complaint.
Insurer required to provided $2,000 compensation for non-financial loss
The panel accepts the process towards finalising this claim has been significantly protracted.
More recently, after the complaint came to AFCA, both parties have requested additional time
to make further submissions. However, in it is the panel’s view that this does not negate the
fact that the initial repairs were not completed to a satisfactory standard. Numerous aspects
of the repairs were indeed identified by the insurer’s assessor as requiring rectification, and
Determination | Case number: 780896 Page 7 of 8
the process towards agreeing to rectification of all these issues has been particularly drawn
out.
The complainant has been required to move out of his house on previous occasions to allow
for repairs (and rectifications) to take place and will need to do so again to facilitate
rectifications following settlement as set out in section 2.1 of this determination.
The panel notes the complainant had to raise some issues multiple times with the insurer and
its contractors to ensure a satisfactory response, and as noted above, the insurer still missed
including at least one item in its final settlement offer.
The panel considers some of the insurer’s recent submissions (especially where settlement
offers were made) to have been lacking in detail, and seemingly lacking in consideration of all
the various aspects and issues relating to the claim.
The panel accepts this drawn out process has contributed to additional and avoidable stress
and inconvenience for the complainant. As such, the panel considers it fair in the
circumstances that the insurer provides the complainant with $2,000 compensation for non-
financial loss.
Insurer to pay cost of report from BE
The panel is satisfied the complainant acted reasonably in obtaining his own report from a
structural engineer. The report was reasonably necessary to help establish the complainant ’ s
claim.
The report has assisted the panel in determining this complaint and in the circumstances, it is
fair the insurer pays the complainant $935 as contribution to the complainant’s costs of
obtaining the report.
2.3 Why is the outcome fair?
Complainant has not established the house is a total loss
The panel is not satisfied the complainant has established that the house is structurally
compromised in any way because of works undertaken by the insurer or the original escape
of liquid event (or for any other reason). Nor is the panel satisfied that the complainant has
established that the house cannot be repaired, or that the cost of repairs will amount to
anything close to approaching the building sum insured amount.
Complainant’s quote from BE is the fairest reflecti on of all costs
The panel considers the quote the complainant provided from BE to be the fairest reflection of
what it will cost to rectify the issues with the insurer’s repairs and for associated costs such as
temporary accommodation and removal and storage of contents. The panel notes this quote
includes allowances to rectify the issues the complainant raised such as replacing the floor
and wall tiles in both the powder room and bathroom, and rectify any cosmetic issues with the
walls, with allowances to ‘plumb walls’ and ‘supply and install plasterboard’ in both these
rooms.
The panel considers settlement based on this quote plus a 20 % uplift for contingencies to be
fair in all the circumstances.
Determination | Case number: 780896 Page 8 of 8
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all the information the parties have provided.
While the parties have raised several issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
A panel determined this matter
Due to the nature of this complaint, we referred it to a panel for determination. The panel
includes an ombudsman, a member with significant experience in consumer and small
business advocacy and a member with extensive experience in the insurance industry.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.