Storm damage claim - insurer limited liability to heating unit and ducting; declined eroded subsoil and retaining wall works; claim management delays and make safe works
Text of the determination
Determination
Case number 780289
Financial firm Insurance Manufacturers of Australia Pty Ltd
Determination | Case number: 780289 Page 1 of 8
Case number: 780289 17 November 2021
1 Determination overview
1.1 Complaint
The complainant and her husband jointly hold a home insurance policy (policy) with the
financial firm (insurer). On 24 October 2020, a claim for storm damage to the insured property
was lodged by the complainant.
The insurer has accepted cover for the damaged heating unit and ducting located in the sub-
floor, but, has declined cover for the eroded and collapsed sub-floor soils and associated
rectification works recommended by the consultants appointed to the claim.
The complainant remains dissatisfied with the insurer’s assessme nt of its liability as well as its
management of the claim.
1.2 Issues and key findings
Is the insurer’s assessment of its liability under the claim reasonable ?
Subject to the insurer reimbursing the complainant for out of pocket expenses incurred in
appointing consultant ‘DL’ and removal of the front decking on the advice of the insurer, the
insurer is entitled to decline cover for eroded subsoils and recommended rectification
(maintenance) works ads these are not covered under the terms of the policy.
Are the complainants entitled to non-financial loss compensation?
The insurer’s management of the claim, especially relating to the make safe works, has
caused the complainant an unusual degree of stress, anxiety and contributed to delays in
bringing the claim to conclusion. It is fair in the circumstances that the insurer pays the
complainant $2,500 in non-financial loss compensation as per the AFCA Rules.
1.3 Determination
This determination is substantially in favour of the insurer.
The insurer is entitled to decline cover for costs relating to the eroded sub-soils and
recommended rectification works in line with the policy. The insurer is to cash settle the
complainant for the damaged heating unit and ducting in line with this determination.
The insurer is to reimburse the complainant $1,600 towards DL’s costs, $1,050 towards the
cost to remove the decking timbers and pay the complainant $2,500 in compensation for non-
financial loss.
Determination | Case number: 780289 Page 2 of 8
2 Reasons for determination
2.1 Is the insurer’s assessment of its liability under the claim
reasonable?
The insurer is entitled to rely on the policy provisions
The insurer provided the complainant with the relevant policy documentation including the
PDS and certificate of insurance (COI). Therefore, I accept the insurer is entitled to rely on
the policy provisions to assess its liability under the claim.
The policy is an insured events contract of insurance
The policy covers the insured property against loss or damage caused by one or more the
listed insured events, including ‘Storm’. Cover under these benefits is subject to the
conditions, limitations and exclusions specified in the product disclosure statement (PDS).
The parties do not dispute a valid claim exists under the policy for storm damage to the
insured property. However, the insurer is of the opinion that not all the damage claimed is
linked to the said storm event or any other event insured under the policy.
For this reason, the insurer is seeking to limit its liability under the claim to the cost to replace
the damaged heating unit and ducting only. Given a valid claim exists, the onus rests with the
insurer to show an entitlement to decline and/or limit its liability under the claim in line the
policy provisions or otherwise.
Consultants have provided conflicting opinions
The insurer appointed consultant ‘JP’ who attended the insured property on 27 October 2020.
JP says the damage noted was because of water running down the hill and under the insured
dwelling. Soils have subsided and collapsed causing water and mud to enter the heating unit
and squash the ducting.
JP provides a repair estimate for the damaged heating unit and ducting at $5,585.65. JP
completed temporary make safe works and says before any repairs being done, the
complainant will need arrange for the construction of a retaining wall based on an engineer’s
design and install additional drainage within the area of the heater.
Engineers ‘IL’ attended the ins ured property on 20 November 2020. IL noted the erosion of
the soils within the subfloor and resultant damage to the heating unit and ducting. IL says this
subsiding and erosion of the subfloor soils over time was due to inadequate batter (or
retaining method) of the soils at the southern end of the subfloor.
Due to the vertical/near-vertical cut face of the soils being around 0.6m in depth, not of rock
material and less than 2m away from the dwelling wall, IL said it needs to be protected from
erosion in line with AS2870, which it was not. IL says the soils should be battered at an
appropriate angle to ensure that the soils are adequately protected from erosion.
Alternatively, IL recommended a retaining wall designed by a suitably qualified engineer
should be installed along the southern end of the subfloor to provide lateral support and
protect it from erosion. IL confirms there was no evidence of distress or significant movement
damage to the dwelling due the subsidence of the subfloor soils nor any immediate damage
of collapse. IL recommended the insurer appoint a geotechnical engineer to provide advice
Determination | Case number: 780289 Page 3 of 8
regarding slope stability at the site. Further, IL recommended additional make safe works be
completed as soon as possible for which it prepared drawings.
The insurer appointed building consultants ‘T’ and plumbing consultants ‘TP’ to complete
further make safe works as well as undertake investigations into the cause for the erosion
and collapse of subfloor soils. TP opined that the only potential for trapped moisture which
may be the cause for water ingress into the subfloor area was under a low-lying deck at the
front of the property. It recommended the deck be lifted for further investigation.
T says the damage was consistent with erosion of the soils over a period of time and not
consistent with a single isolated insured event. T completed further make safe works within
the subfloor area. The complainant remains significantly dissatisfied with the make safe works
completed by T as well as the finding o f the insurer’s other appointed consultants.
The complainant appointed DL, an engineering geologist, who has provided an embankment
stability geotechnical assessment report dated 5 May 2021. DL completed a site specific
geotechnical investigation regarding the stability of the existing earth embankment in the
subfloor area and claimed water ingress beneath the building.
DL found the collapse of the embankment had undermined some stumps supporting the
dwelling. He noted some make safe works were undertaken however says these were
insufficient and some areas completely ineffective. DL clarifies that the report is a
geotechnical report and is provided to help facilitate the planning, design and methodologies
of the remedial works required to stabilise the existing earth works.
With respect to the noted embankment failure, DL says this is due to a combination of two
main factors, these being the reported stormwater ingress into the subfloor on 24 October
2020 and the relatively steep and unprotected nature of the embankment. DL says it is not
possible to accurately calculate the degree of contribution from these two factors, however,
suggests that the water ingress is the dominant cause and attributes 66% of the embankment
collapse to this event.
DL recommended an immediate inspection by a suitably qualified engineer to determine what
further short-term protection works may be required to ensure the safety of the dwelling. He
says to stabilise the embankment, it will be necessary to remove all remaining loose soil and
rock and retain the lower/steeper section of the embankment with an engineer designed
retaining wall.
DL states as part of the works it will also be necessary to either replace the stumps in the
vicinity of the top of the embankment with deeper stumps founded well into the natural
bedrock below the base of the embankment, or convert the floor system into a long span
system supported on the wall of the lower ground floor section of the building with stumps
located at least two metres away from the top edge of the embankment.
The complainant has also made available a builder’s report from consultants ‘LB’ dated 11
May 2021. LB says the current make safe works were totally unsatisfactory and provides an
estimated scope of works including construction of a retaining wall at around $50,000.
However, LB notes in the absence of a design for remedial works from a suitably qualified
engineer, it is impossible to provide an accurate estimate.
The insurer is entitled to limit its liability under the claim
Having considered the available information, I accept the insurer is not obliged to cover all the
repairs and recommended remediation works needed to stabilise the subfloor soils. I accept it
Determination | Case number: 780289 Page 4 of 8
has been shown, on balance, an insured event has occurred, and which has damaged the
heating unit, ducting and contributed to the subsidence of the subfloor soils.
Cover under the policy is limited to the insured building and contents. The subfloor soils which
have subsided and collapsed do not form part of the insured building in line with the policy
definition specified in the PDS (relevant policy wording is provided in section 3 below).
The foundations do form part of the building, but this is limited to the timber and concrete
components of the foundations that are connected to and form part of the insured building.
This does not extend to or include the land (soil) upon which the insured building sits. The
available evidence shows there is no damage to the structure or foundations of the insured
building because of this storm event, other than the possible undermining of two stumps close
to the area of soil collapse.
The consultants are consistent in recommending that a suitably designed retaining wall by an
adequately qualified engineer is needed to ensure the safety of the area in question and to
prevent future events of soil erosion. A retaining wall was not originally present and as such I
accept the installation of a retaining wall now would be considered maintenance or
improvement works, which are not covered under the policy.
The consultants’ evidence establishes that to construct such a retaining wall would require
replacement of the existing stumps with deeper stumps founded well into the bedrock below
the base of the embankment. Given the fact that there is no damage to the foundation stumps
and the remediation works (retaining wall) will include replacement of the stumps, I accept
these costs for to the complainant outside the scope of the policy.
I am satisfied the only damage covered under the claim is limited to the heating unit and
ducting. I accept given the works needed within the subfloor area which are not covered
under the policy, it is fair that the insurer cash settle the complainant for the heating unit and
ducting under the claim.
I acce pt the complainant’s concerns regarding the quote from T for the heating unit and
ducting. It is fair that the insurer settles this component of the claim based on the quote
provided by JP in the amount of $5,585.65.
I acknowledge the concerns raised by the complainant regarding the make safe works
completed by the insurer, these will be addressed in more detail within section 2.2 below.
I determine the insurer is entitled to limit its liability for damage from the storm event to the
cost to replace the heating unit and damaged ducting. It is not obliged to cover the
recommended maintenance/remediation (construction of a retaining wall) works nor does the
policy extend to cover the collapsed soil.
Insurer is to reimburse the complaint for out of pocket expenses
Under the AFCA Rules (Rule D.5), AFCA can determine an insurer contribute up to $5,000 to
professional costs incurred by the complainant in the course of the complaint.
Despite the recommendation by its appointed engineers IL, the insurer did not appoint a
geotechnical engineer and it was left to the complainant to arrange and pay for this
information. DL’s report assisted in the assessment of the claim and as such it is reasonable
that the insurer reimburses the complainant $1,600 incurred in obtaining this report.
I note the complainant’s concerns regarding the additional works and expenses incurred in
having the front deck lifted on the advice of T and TP appointed by the insurer. These
investigations were found to be unhelpful and did not support the presumed source of water
Determination | Case number: 780289 Page 5 of 8
ingress into the subfloor put forward by these consultants. It is fair in all the circumstances
that the complainant be reimbursed for this cost ($1,050), subject to providing proof of such
cost to the insurer.
The complainant also seeks $1,485 towards electricity costs over the relevant period which
she says is more than what they normally paid for similar periods in the past. The
complainant says given the delays and the fact they had to use three electric heaters to keep
their home warm over this period, the insurer should reimburse them for the difference in the
cost of electricity they have had to pay.
The policy excludes cover for consequential loss. The insurer, from quite early in the claim
acknowledged and accepted liability for the heating unit and damaged ducting. It was the
complainant’s decision to dispute the insurer’s assessment of its liability which has
contributed to the delay in bringing the claim to conclusion. In the circumstances it would not
be fair or consistent with the policy provisions to require the insurer to cover these expenses.
2.2 Is the complainant entitled to non-financial loss
compensation?
The insurer is to pay $2,500 in non-financial loss compensation
The AFCA Rules (Rule D 3.3) allow for an award of up to $5,400 for non-financial loss
compensation, if the insurer caused the complainant to suffer an unusual degree or extent of
inconvenience, delay or interference. AFCA takes a conservative approach when considering
any award of compensation.
In this instance and considering AFCA’s approach to compensation, I accept the insurer’s
overall management of the claim was not up to the expected standards of a professional
organisation.
The evidence shows there were delays on the part of the insurer in progressing the claim
through each of its stages as well as in its communications with the complainant and/or
consultants. This includes the claim having been managed by more than 14 different staff
members over its life and with whom the complainant had to deal with. This only further
contributed to delays and the level of stress, anxiety and inconvenience experienced by the
complainant.
In addition to the above, the available information shows the insurer failed to arrange suitable
temporary make safe works throughout the life of the claim. This is despite the numerous
times the complainant raised concerns in this regard as well as having been provided with the
required make safe plans and mapping of the required make safe works by its appointed
engineer.
The photographic and video evidence made available by complainant clearly establishes the
unacceptable and poor quality of make safe works completed. I accept given the location of
the area requiring make safe works, this failure by the insurer will have caused the
complainant and her family significant stress, anxiety and inconvenience over the life of the
claim.
Although I accept the insurer is not required to continue to cover any further costs towards
needed make safe measures under the claim, I remain highly concerned regarding its
management of and responsibility or lack off in this regard.
Determination | Case number: 780289 Page 6 of 8
For these reasons and in line with the AFCA Rules, I determine the insurer is to pay the
complainant $2,500 in non- financial loss compensation within 14 days of the complainant’s
acceptance of this determination.
Why is the outcome fair?
Given the available information, it is fair in all the circumstance to permit the insurer to rely on
the policy provisions and limit its liability to only that damage which has been shown to be the
result of the insured event (Storm).
As the complainant’s out pocket expenses relating to the lifting of the decking and
appointment of DL are because of failures of or incorrect advice from the insurer and its
appointed representatives, it is fair that insurer reimburse the complainant for these
expenses. The policy excludes consequential loss, and it is fair to accept the additional
electricity costs to be just that in these circumstances.
Finally, it is fair in all the circumstances, to require the insurer to pay the complainant non-
financial loss given the impact its poor management, failings and incorrect advice has had on
the complainant and her family.
Determination | Case number: 780289 Page 7 of 8
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
3.2 Relevant policy provisions
The buildings we insure
Under Buildings Insurance, we cover loss or damage to the buildings that you
own and live in.
Your home
Your home includes:
- domestic residential buildings at your site that can be locked up
- home improvements at your site – for example, garage, carport or in-ground
pool - fixtures or items permanently attached or fixed to your home – for example,
light fixtures, built in wardrobes, kitchen cupboards and floating floorboards.
…
Contents we don’t insure
We don’t insure any of t hese items under Contents Insurance:
- … plants, trees or shrubs growing in the ground
- Grass, rocks and soil on your site
…
Home
Determination | Case number: 780289 Page 8 of 8
any enclosed building at your site that has walls and a roof and can be locked up
which you use mainly for domestic purposes
- for Buildings Insurance, your home includes any home improvements or fixtures
...
General exclusions for all covers and benefits
The exclusions set out in this section apply to all covers and benefits under your
policy.
What we don’t cover
Loss, damage, injury or death arising from:
- rust, corrosion, gradual deterioration, depreciation, wear or tear
- erosion, including coastal erosion…
3.3 Relevant AFCA Rules
D.3.3 An AFCA Decision Maker may decide that the Financial Firm is to compensate
the Complainant for non-financial loss:
a) for a complaint relating to an individual’s privacy rights - injury has occurred to
the Complainant’s feelings or humiliation has been s uffered by the Complainant;
or
b) for other complaints – an unusual degree or extent of physical inconvenience,
time taken to resolve the situation or interference with the Complainant’s
expectation of enjoyment or peace of mind has occurred.
…
D.5.1 An AFCA Decision Maker may decide that the Financial Firm is to
contribute to the legal or other professional costs or travel costs incurred by the
Complainant in the course of the complaint.
D.5.2 Unless special circumstances apply, AFCA will not require the Financial
Firm to contribute more than $5,000 to these costs.