Storm-collapsed masonry wall claim denied under building defects exclusion

FirmAuto & General
Decided2021-09-01
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded$3,200
Non-financial loss$1,500
Amount claimed$17,220
SourceAFCA PDF

Summary

The complainant's masonry wall collapsed in a storm and the insurer denied the claim as a building defect. AFCA found the exclusion not established, ordered the insurer to repair or cash settle the wall and pay $3,200 in site costs plus associated covered losses, and awarded $1,500 for non-financial loss.

The insurer did not show the storm damage resulted from a design or construction defect, given the wall had stood for over 50 years before a significant weather event.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay non financial lossrepair or rectify

Related

All Auto & General determinations · Find similar determinations

Text of the determination

Determination Case number 779698 Financial firm Auto & General Services Pty Ltd Determination | Case number: 779698 Page 1 of 7 Case number: 779698 24 August 2021 1 Determination overview 1.1 Complaint The complainant held a home and contents insurance policy with the financial firm (insurer). On or about 29 November 2020, a heavy storm caused a masonry wall at his home to partially collapse. The complainant lodged a claim which was denied by the insurer. The insurer considers the wall was not built to the appropriate code or standard. The complainant does not accept this position and says the replacement of his wall should be covered by the policy. 1.2 Issues and key findings Is the insurer liable for the damage to the wall? Ye s. The insurer’s expert agrees a heavy storm caused the masonry wall to collapse. There is no persuasive evidence the construction of the wall was defective or that the insurer otherwise had grounds to deny cover for the loss. What is the insurer required to cover? The insurer must either repair the damaged wall or cash settle the complainant at his discretion. It is also required to cover other costs. The parameters for settlement are set out in section 2.2 of this Determination. Is an award of compensation appropriate? Yes. The insurer should pay the complainant $1,500 in non-financial loss compensation. Why is the outcome fair? The complainant’s wall collapsed due to a heavy storm. Whilst the insurer says it was defective, its evidence did not confirm this. The failure to accept the claim meant the complainant incurred costs he should not have otherwise had to. It is fair in these circumstances that the insurer should cover the complainant’s loss. 1.3 Determination This determination is in favour of the complainant. The insurer is required to indemnify the complainant as outlined in section 2.2 of this Determination. As no evidence of payments having been made have been provided, there is no need for an award of interest. In addition to the repair (or cash settlement) for the damaged wall, the insurer must pay the specified amounts outlined in section 2.2 and compensation of $1,500 for non-financial loss. Determination | Case number: 779698 Page 2 of 7 2 Reasons for determination 2.1 Is the insurer liable for the damage to the wall? Yes. The insurer’s expert agrees a heavy storm caused the masonry wall to collapse. There is no persuasive evidence the construction of the wall was defective or that the insurer otherwise had grounds to deny cover for the loss. Complainant seeks cover for partially collapsed fence after storm There is no dispute the complainant’s masonry wall collapsed during a heavy storm which included high winds. The collapse affected an adjacent asbestos wall, which was also damaged. The insurer says the damage was due to defects in the design of the wall and the structure not being built in accordance with the relevant building code. The insurer says the loss would not have occurred if the wall had been constructed in accordance with the code. It relies upon an exclusion in the policy to say the loss is not covered. Policy provides cover for storm and wind damage subject to exclusions The complainant has the onus of establishing he suffered a loss from an event covered by the policy. If a claimable loss is established, the insurer then has the onus of establishing the application of any exclusion or condition it relies on to reduce its liability. The insurer’s policy is made up of the Insurance Certificate and the Product Disclosure Statement (PDS). There is no dispute the insurer sent these documents to the complainant. The policy provides cover for a series of listed events. It also has an option for ‘accidental damage’ cover, which the complainant select ed. ‘Accidental damage’ is defined as damage: caused by a sudden, unintended or unexpected event that is not the result of a deliberate act This cover is subject to the policy’s general exclusions and the exclusions applicable to each of the insured events. As there is no dispute the complainant’s loss was accidental, I accept there is evidence of an insured event under the terms of the policy. The onus turns to the insurer to show why the loss is not covered. Amongst the exclusions for claims covering the listed event for ‘ storms and rainwater ’ , the insurer will not cover loss or damage due to: defects in design, structure, materials, workmanship, or construction The insurer says this exclusion applies to the circumstances of the complainant’s loss. Attending builder said fence not built in accordance with building code The insurer arranged for builder ‘MC’ to attend the property and report on the damage. Determination | Case number: 779698 Page 3 of 7 MC’s report of 9 December 2020 noted the cause of damage as ‘Strong Wind’. Despite this, the builder said the fence had not been built in accordance with the relevant building code as:  the fence was laid directly on a footpath with no footings  it had no starter bars and no infill  the side gate/door was not properly fixed to the frame and post. MC quot ed $4,864.75 to repair the fence but marked the matter as ‘unknown’ as to policy coverage. The insurer says the maximum recorded wind speed on the day of the loss was 74kmh. On the Beaufort Scale this is considered a ‘gale’, meaning it is sufficient to cause twigs to break off trees but no structural damage. I note 74kmh also borders on a ‘strong/severe gale’ on the Beaufort Scale. This is where wind is strong enough to cause ‘slight structural damage’. Noting the closest observation point was 10km from th e complainant’s area, I accept it is possible that wind speeds could well have been higher. MC later submitted an amended report to expand on the issues it considered were present with the wall. It maintained the wall had not been built in accordance with building code AS/NZS 1170.2. This requirement had been in place since ‘at least the year 2002’ according to the insurer. The insurer further cited AS3700 for the construction of masonry walls. This was referred to in MC’s first report but omitted from its second. The insurer says this has been in force since at least 2011. The complainant says the wall had stood for more than 50 years. A statement from a neighbour (‘MN’) attests to it being built in 1968. This clearly predates the insurer’s reliance on the stated codes. In response, the insurer determined AS CA2-1963 applies to the construction. It says the relevant code requires reinforcement of a wall to provide resistance to ‘any calculated stresses’ in the construction. Insurer has not established the exclusion applies Critical to the insurer’s position about the masonry wall was the absence of starter bars within the structure and suitable footings. These serve to stabilise the construction against external forces which may affect its standing. Whilst the insurer and MC initially confirmed the masonry wall did not comply with standards implemented since 2002, they did not realise the wall was built in or about 1968. The insurer’s third review of the damage, based on knowledge of the build date, introduced a further building standard for consideration. It notes this standard requires that all buildings and structures ‘shall be designed to withstand wind loads’. The submissions from the insurer on the 1963 building code are without reference to expert opinion. It is also without a copy of the full code extract or context in how this relates to the construction of masonry walls. Even if I accept the reference to the code establishes a design flaw in the wall’s original construction, I am not satisfied the exclusion applies. It is accepted by the parties:  the wall stood for more than 50 years  it collapsed because of a significant storm, with high winds. Determination | Case number: 779698 Page 4 of 7 The insurer says th e wall was ‘in an unstable condition at the time of the loss’ but provides no evidence to support this assertion. Given the nature of the exclusion, I am not satisfied the insurer has shown the damage was due to a defect in design (even if a building defect was present). That the structure stood for more than 50 years, and was felled by a significant weather event, attests to it not being structurally deficient. Based on this, I am not satisfied the insurer has established it has grounds to deny the claim. 2.2 What is the insurer required to cover? The insurer must either repair the damaged wall or cash settle the complainant at his discretion. It is also required to cover other costs. The parameters for settlement are set out below. Complainant seeks cover for replacement of wall and additional costs The complainant has not yet replaced the damaged masonry wall. He says he has incurred costs to clean up the site and generally make the area safe. PF assisted him with some of these expenses, attending to the work for cash. The complainant seeks:  cover for the replacement of the fence – he provided qu otes from ‘RR’ for $9,020 (using reinforced steel) and ‘TB’ for $7,700  reimbursement for $3,200 paid to PF in cash for temporary fence installation, removal of asbestos and installation of a new sheet  the costs incurred to empty, clean and refill the pool due to asbestos contamination ($1,500)  the costs to remove rubbish, obtain a bin and remove damaged cladding (estimated at $1,500)  estimated costs to paint the wall ($500)  estimated costs to purchase ceramic pots and a fence hedge ($1,500). Insurer to repair the wall or cover the cost to repair the wall Given the complainant’s wall has not yet been rebuilt, I am satisfied the insurer should attend to this. The MC quote is no longer valid as it has expired. This means the insurer will need to commission a new quote. A decision then needs to be made on how the matter is resolved. I am satisfied the complainant may choose to have the insurer complete the work, or be cash settled. Either way, this should be based on a new quote commissioned by the insurer, unless the insurer prefers to cash settle based on the TB quote. I have allowed the insurer to obtain a new quote as it may be able to obtain a more competitive quote to complete the work. For the insurer to prepare a new quote, pursuant to the terms of the PDS, the quote must be to replace the wall to: the same standard, specification or quality as it was when it was new Further, the insurer must ensure (as detailed in the PDS): the repaired or rebuilt parts of [the] home comply with current building regulations and laws Determination | Case number: 779698 Page 5 of 7 Insurer must also cover certain additional costs The complainant says he paid $3,200 (net of GST) to PF for temporary fencing, removal of asbestos and installation of a new sheet. PF is prepared to accept $3,200 in the absence of providing an invoice (for which there would be added GST). As I am satisfied the work was required and undertaken, I accept the claimed costs are reasonable. The insurer should pay the complainant $3,200. If it requires an invoice from PF, this amount may increase and the insurer would need to pay any increased amount to account for GST. The complainant says he incurred about $1,500 for rubbish removal, removal of cladding and to obtain a bin. The insurer should cover these costs, subject to evidence of these items being paid for. This may be achieved by way of quotes/invoices, copies of bank transactions or a statutory declaration to confirm how payment was made. The complainant also seeks the costs to repaint the new wall. There is no basis for the $500 estimate. The insurer does not dispute the wall was painted. I am satisfied the insurer can choose to either pay this amount or have someone quote to attend to the work and settle on this basis. Insurer must cover the cleaning of the pool and neighbour’s damage The insurer says the complainant is not covered for water in the swimming pool. I disagree. There is no dispute that portions of asbestos sheeting fell into the swimming pool due to the fence’s collapse. I accept this meant the pool became a potential safety hazard and required the removal of the asbestos and cleaning. Within the insurer’s policy cover for ‘storms and rainwater’, the PDS excludes cover for: water in a swimming pool or spa and their liners and/or covers The insurer relies on this exclusion to say the pool costs are not covered under the policy, but the claim is not for storm damage to the pool. It is for damage to the wall. The effect of this damage caused probable contamination of pool water with asbestos-laden materials. As the damage to the wall is covered, so is the damage it caused elsewhere. To the extent the complainant has incurred a (reasonable) loss to correct the damage potentially caused to the pool, I am satisfied it is covered. As with the rubbish removal costs, the complainant will need to provide evidence to the insurer of what he spent to attend to this work. Subject to receipt of sufficient evidence, the insurer should reimburse him for this. Similarly, the insurer denied the complainant’s claim for cover to the pots, plants and the hedge owned by MN. Photos from the scene clearly show damage to these items caused by the wall’s collapse. I accept the policy generally excludes contents cover for: garden beds, hedges, lawns, plants, shrubs and trees Given the claim damages relate to the nei ghbour’s items, these are covered under the legal liability section of the complainant’s policy. As the owner of the damaged structure, the complainant is liable for the damage caused through the collapse of the wall. The PDS says: Determination | Case number: 779698 Page 6 of 7 we will cover your legal liability as owner… of your home… for loss or damage to other people’s property caused by an accident. The insurer is required to cover the complainant for the cost to indemnify his neighbour. To the extent the complainant will incur costs to replace these items for the neighbour, the insurer should indemnify the complainant under the terms of the policy. 2.3 Is an award of compensation appropriate? Yes. The insurer should pay the complainant $1,500 in non-financial loss compensation. AFCA can award compensation for non-financial loss Under our Rules, AFCA can award up to $5,400 compensation for non-financial loss. This must relate to poor claims handling or other actions of the insurer which cause an unusual degree of stress, delay, or inconvenience. AFCA takes a conservative approach to compensation for non-financial loss. We expect complainants to be moderately robust, and we will not award compensation for the ordinary degree of inconvenience involved in making a claim. The insurer’s actions caused unnecessary inconvenience for the complainant The complainant says he has been significantly inconvenienced by the insurer’s refusal to pay his claim. This meant he had a mess at the home for about six months. He had to obtain money from a cousin to remove the asbestos due to the risks involved with it being left on the property. I accept the denial of this claim caused distress and hardship for the complainant. This was exacerbated by the presence of the damaged asbestos on the property. I consider the insurer should have accepted the claim but it should also (even when denying the claim) done more to ensure the home and the site was safe. Whilst this has now been addressed by the complainant, I accept the issues involved caused him distress. The actions (and inactions) of the insurer caused an unusual degree of inconvenience and interference with his expectation of enjoyment and peace of mind. I am satisfied an award of compensation is warranted, in addition to the cover provided for the claim. The insurer should pay the complainant $1,500. Determination | Case number: 779698 Page 7 of 7 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.