Insurer denied strata building claim for water damage, retaining wall, concrete slab and ventilation ducts under wear and tear, gradual deterioration, concrete cancer and tree root exclusions

FirmAIG Australia Limited
Decided2021-12-02
ProductGeneral Insurance · Strata
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

An owners corporation claimed under its strata policy for water damage, a retaining wall, a concrete slab and ventilation ducts after AIG denied the claim. AFCA found the damage was caused by excluded factors such as gradual deterioration, concrete cancer and tree root invasion, and ruled in favour of the insurer.

The insurer established on balance that the damage was caused by exclusions for wear and tear, gradual deterioration, concrete or brick cancer and invasion of tree or plant roots.

Issues

Subjects and remedies

home or building damageno remedy

Related

All AIG Australia Limited determinations · Find similar determinations

Text of the determination

Determination Case number 778237 Financial firm AIG Australia Limited Determination | Case number: 778237 Page 1 of 7 Case number: 778237 2 December 2021 1 Determination overview 1.1 Complaint The complainant is an owners corporation that holds a residential strata insurance policy with the financial firm (the insurer). The complainant lodged a claim on 3 August 2020 saying the insured building sustained water damage to common property, private garages and two townhouses. The complainant also reported damage to a brick retaining wall which it believes was caused by a tree trunk. The insurer engaged the services of a loss adjuster and engineer to assess and report on the damage being claimed. Upon receipt of the reports, the insurer denied the claim. It says the damage in relation to the two townhouses, brick retaining wall, concrete carpark slab, and ventilation ducts is not covered, as the proximate cause of all damage is factors which are excluded under the policy. The complainant accepts the insurer’s position in relation to damage to the two townhouses. However, they disagree with the remainder of the insurer ’ s claim decision and the findings of its engineer regarding the retaining wall, concrete slab and ventilation ducts. 1.2 Issues and key findings Is the insurer entitled to deny the claim? On the information provided, the panel is satisfied the different areas of claimed damage are the result of wear, tear, gradual deterioration/corrosion, concrete or brick cancer, rust, and invasion of tree or plant roots. Damage caused by those factors is excluded from cover under the policy. That means the insurer is entitled to decline the claim. Why is the outcome fair? The outcome is fair in all the circumstances as the insurer has established it is more likely than not that the damage to the building and retaining wall is related to or arose from an exclusion under the terms and conditions of the policy. It would not be fair to require it to pay the claim in those circumstances. 1.3 Determination This determination is in favour of the insurer. The insurer is not required to undertake any further action. Determination | Case number: 778237 Page 2 of 7 2 Reasons for determination 2.1 Is the insurer entitled to deny the claim? Onus on complainant to establish a valid claim under the policy The onus is on the complainant to establish, on the balance of probabilities, that they have suffered a loss caused by an event to which the policy responds. This is known as a prima facie or valid claim. If the complainant is able to establish a valid claim, the onus shifts to the insurer to show, on the balance of probabilities, an exclusion applies, if it is to seek to deny or limit its liability for the loss. The insurer must establish that all or some of the claimed loss was caused by an exclusion. The policy provides cover for accidental loss or damage. ‘Accidental’ is not defined in the policy, however the ordinary and usual meaning is loss or damage which is unintended and unexpected, happening by chance. The description of the damage indicates it would have been unintended and unexpected, as would damage to the retaining wall. In the circumstances, the panel is satisfied that the complainant has established a prima facie claim for accidental damage. The onus therefore shifts to the insurer to establish exclusions apply or that it is otherwise entitled to decline the claim. Cover is subject to certain exclusions The policy contains a number of exclusions. Relevantly, it excludes cover for any physical loss, destruction or damage directly or indirectly caused by or arising out of or in consequence of or contributed to by:  rust, wear and tear, gradual corrosion or gradual deterioration, concrete or brick cancer  the invasion of tree or plant roots. Initial inspections indicate on-going issues The complainant says that as soon as damage was identified, the o wners appointed engineer CH to assess the damage . CH inspected the two affected townhouses, and reported:  along the east side of the townhouses are a series of garden beds broken by entry paths to the front door of each townhouse. It is likely that the waterproofing under this external area is beyond its design life and in need of replacement.  garden beds outside townhouse No.4 do not have grated pit drainage outlets unlike those of the other townhouses.  it can be seen that the drainage outlets for the walkway paving merely consist of small circular outlets at around 6.0m centres. A previous garden bed along the south-east fence has been paved over. All this adds to the amount of rainwater building up between the building and the fence which, in turn, leads to increased water under the paving and garden. Determination | Case number: 778237 Page 3 of 7 CH provided a scope of works for all the building damage being claimed. They did not, however, provide a report on the damaged brick retaining wall, concrete and ductwork damage in dispute. The insurer engaged loss adjuster C who initially inspected the building and recommended the insurer appoint an engineer. CR says that after its initial building inspection, they received information from the complainant’s engineer CH who supported the belief that the claim fell under exclusions within the policy. An extract of what C says it received is in section 3.2 of this determination. Insurer ’ s engineer report indicates excluded causes On 2 October 2020, the insurer appointed engineer CRD to attend the property and provide a causation report. For the concrete carpark slab, CRD says:  the cracking in the concrete beam is due to water penetration through the concrete joint. The moisture causes the reinforcement within the concrete to corrode. Corrosion causes the reinforcement to expand and cause cracking to the concrete. This is also known as concrete spalling or sometimes referred to as concrete cancer  damage is the result of degradation of the waterproof joint and/or waterproofing through the concrete joint and courtyard areas above  the concrete spalling damage is a result of gradual deterioration of the waterproofing system to the balcony above. For the ventilation ducts, CRD says:  the corrosion is likely a result of prolonged exposure to moisture from wind driven rain, entering from the exhaust outlet at roof level above  it is also plausible that added moisture from the failure of the waterproofing of the courtyard slab and joint is contributing to the corrosion of the ductwork  the corrosion has developed gradually due to exposure to moisture, likely from moisture entering through the exhaust at roof level and contributed by the failure of waterproofing at courtyard level. For the brick retaining wall, CRD says:  the shape and direction of cracking to the wall is consistent with flexural and shear cracking of the wall due to out of plane loading. The out of plane loading could be due to: > lateral pressure exerted from the soil behind > lateral pressure exerted from roots of vegetation behind > lateral pressure exerted from hydrostatic head – i.e. water pressure. We do not consider this to be likely due to the lack of moisture damage to the wall  the shape and direction of cracking is not consistent with cracking resultant from differential settlement of the footings  the structural adequacy of the wall cannot be verified or assessed without destructive investigation  no evidence of impact damage from a tree or anything above ground bearing on the wall  as the wall has only failed locally and the remaining wall generally appears to be plumb and free from bowing and cracking, we believe that it is unlikely that there is a systemic inadequacy to the entire wall, such as the wall being structurally under designed. Rather, it is more likely that local lateral forces such as tree roots has caused the observed damage. Determination | Case number: 778237 Page 4 of 7 No expert information to persuasively support the complainant’s conclusions The complainant s ays they disagree with the CRD’s findings on the following basis:  their engineer CH advised via email that damage to the concrete slab is not and cannot be concluded as concrete cancer  the waterproof membranes in the courtyards which sat directly above the concrete slab and the ventilation ducts were replaced in 2015, should still be within their useful life and therefore any reference to damage being attributed to gradual deterioration of the waterproofing system is incorrect  damage would not have occurred to the concrete slab had the failure of the waterproofing not occurred  if damage to the brick retaining wall was caused by roots of trees or vegetation, damage would have slowly developed over time. However, the damage was sudden, and it is evident from a picture in CRD’s report that the damage was caused by a tree trunk rather than tree roots  their builder R concluded that the cause of damage is lateral pressure from the tree stem and not the roots or soil. Having considered all the information, the panel is not persuaded by the complainant’s submissions or evidence. Instead, the panel finds the information from CRD to be more compelling as to the likely causes of damage. This is because:  CH did not provide information to support why the concrete slab cannot be concrete cancer  CH provided additional information to the insurer via email but did not provide a report on the concrete carpark slab, ventilation ducts or brick retaining wall  the information CRD says it received from CH s upports CRD’s findings  in stating the damage would not have occurred had the failure of the waterproofing not occurred, the complainant acknowledges its failure  although it is not disputed the waterproofing of the courtyards was replaced in 2015, there is no evidence to show they cannot suffer gradual deterioration since being replaced  there is no expert information available which concludes damage to the retaining wall or waterproof membranes was sudden  upon CH’s inspection of the townhouses, it also found waterproofing issues and noted other circumstances which could lead to increased water under the paving and garden  photos in CRD’s report show cracking to the concrete carpark slab and corrosion to the ventilation ducts indicating, it is more likely than not this damage occurred over a period of time  the photo in CRD’s report does not establish damage to be caused by a tree trunk  while builder R says the bowing to the retaining wall appears to be the result of a mature tree placing lateral pressure against the north western perimeter of the brickwork wall, R is not a qualified engineer and does not conclude damage to be caused by a tree stem or trunk. Having considered all the available evidence, the panel is satisfied the insurer has established, on balance, it is entitled to decline the different elements of the claim based on the policy provisions for damage caused directly or indirectly by rust, wear and tear, gradual corrosion or gradual deterioration, concrete or brick cancer and the invasion of tree or plant roots. Determination | Case number: 778237 Page 5 of 7 2.2 Why is the outcome fair? It would not be fair to require the insurer to pay a claim for damage which is caused, on balance, by factors excluded under the policy. Determination | Case number: 778237 Page 6 of 7 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. This matter was determined by a panel Due to the nature of this dispute, it has been referred to a panel for determination. The panel comprises the ombudsman, a member with significant experience in consumer and small business advocacy and a member with extensive experience in the insurance industry. The panel has decided this complaint based on what is fair in all the circumstances, having regard to legal principles, applicable industry codes or guidance, good industry practice and previous relevant determinations of AFCA or predecessor schemes (which are not binding). We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. 3.2 Extract from CR’s report - 8 September 2020 Since our First Report dated 20 August 2020, we continue to monitor progress of the claim. We have received additional informat ion from the Insured’s engineer CH, which we attach for your review. In summary, they have advised the following: Determination | Case number: 778237 Page 7 of 7 Concrete repair • Defects to the concrete slab and beam over the garage can be attributed to water penetration into the concrete as a result of a failed waterproofing membrane to the slab immediately above the basement. • The moisture in the slab and beam have led to the deterioration of the concrete by way of reinforcement rusting and concrete spalling (concrete cancer). • The damage has occurred over a long period of time and not from a single event. Brickwork repair to the northwest wall of the garage. • The brickwork defects on the external basement wall is considered to be due to long -term footing movement, which has caused cracking and rotation on the wall. • The footing movement can be attributed to volumetric changes in the foundation soil due to changes in moisture contents that causes expansion and shrinkage. Rusted Ventilation Ductwork • The damage cannot be attributed to a single event but rather a series of water penetration events that has resulted in the damage. Waterproofing Repairs • The engineer has advised that the waterproofing has reached the end of its designed life, which we consider to be consistent with wear and tear. Joint Sealing • The problems arising can be generally attributed to the failure of the waterproofing on to p of the slab, which we consider to be consistent with wear and tear. 3.3 Relevant policy provisions Exclusions We will not be liable in respect of any physical loss, destruction or damage directly or indirectly caused by or arising out of or in consequence of or contributed to by: … 7.16 wear, tear, fading, gradual corrosion or gradual deterioration, concrete or brick ‘cancer’, wet or dry rot, rust, oxidation, chipping, scratching or marring, normal upkeep, making good or any developing flaws; … 7.27 the invasion of tree or plant roots, but if such invasion blocks Your drainage system this exclusion will not apply to any subsequent damage to Your Building or Common Area Contents caused by the escape of water or liquids there from.