Home / IAG / Determination 776132
Determination 776132
Building claim settlement for water damage
Summary
The complainants claimed water damage to an investment duplex and disputed the insurer's building repair cash settlement offer, along with consequential loss and non-financial loss. AFCA found the offer inadequate, ordered a higher cash settlement with interest, $3,000 non-financial loss, and the previously offered $10,000 ex-gratia and $1,000 premium credit, but refused consequential mortgage losses under the policy.
The insurer must cash settle an amount sufficient to restore the property to pre-loss condition, allowing for missing scope items, variations and risk, while poor claim handling warranted non-financial loss.
Issues
- Claim amount dispute primary · upheld
“I am not satisfied the complainants could reasonably have the works completed for the amount offered by the insurer. The insurer is required to increase its settlement payment.”
- Poor claim handling secondary · upheld
“the claim could have been managed more professionally. Emails indicate the complainants raised concerns throughout the process and a number of those concerns were ignored.”
- Delay secondary · upheld
“the Complainants experienced delay and incompetence at times.”
- Repairs or contractors secondary · upheld
“certain contractors did not act appropriately throughout the assessment and remediation process.”
Subjects and remedies
health or medicalhome or building damagepay claimpay compensationpay interestpay non financial loss
Text of the determination
Determination
Case number 776132
Financial firm Insurance Australia Limited
Determination | Case number: 776132 Page 2 of 7
Case number: 776132 21 October 2021
1 Determination overview
1.1 Complaint
The female complainant held home and contents insurance with the financial firm (the
insurer) and lodged a claim for water damage from a cracked washing machine pipe in an
investment duplex. At different times the claim was managed by the complainant, her
husband and or their broker and this Determination for convenience refers throughout to
Complainants.
The insurer accepted the claim and paid out the full contents sum insured. The Insurer
offered the Complainants a cash settlement of approximately $145,000 for building repairs.
The complainants are dissatisfied with the insurer’s offer. They seek cash settlement of their
repair quote of approximately $165,000, in addition to consequential loss and $5000 non-
financial loss for poor claims experience. As at early 2021 the work remained incomplete.
1.2 Issues and key findings
Is the insurer’s offer fair and reasonable?
The insurer’s offer is not fair and reasonable. I a m not satisfied the complainants could
reasonably have the works completed for the amount offered by the insurer. The insurer is
required to increase its settlement payment as set out below.
Is the complainant entitled to non-financial loss?
I am satisfied the complainants established the actions of the insurer caused additional stress
and inconvenience outside that would usually be expected in an insurance claim. The insurer
is required to pay the complainants $3,000 non-financial loss.
Is the complainant entitled to consequential loss?
The policy does not cover consequential loss; however, the insurer is also required to honour
its offer of $10,000 ex-gratia and $1,000 towards a premium credit.
Why is the outcome fair?
The outcome is fair because if the complainants are cash settled, they must be able to restore
their property to its pre-loss condition for the amount offered by the insurer. The insurer did
not provide an appropriate level of service to the complainants.
1.3 Determination
This determination is in favour of the insured. The Insurer is required to cash settle the
complainants in the sum of $171,023.
Interest is payable on this sum as per section 57 of the Insurance Contracts Act 1984 (Cth)
(the Act) from 31 August 2020 to date of settlement.
The Insurer is to pay $3,000 compensation by way of non-financial loss.
The Insurer is to make the payment it offered of $10,000 and a $1,000 premium credit.
Determination | Case number: 776132 Page 3 of 7
2 Reasons for determination
2.1 Is the insurer’s offer fair and reasonable?
Insurer required to increase its settlement for building repairs
The insurer obtained two quotes; BMR at $122,616 and AB at $145,475 and offered cash
settlement based on the first quote which the Complainant rejected. The Insurer then offered
the complainants $145,475.00 in settlement of the building claim and to resolve their
complaint.
The complainants are dissatisfied because the scope of works (SOW) relied upon to settle
the claim is missing significant components. The complainant seeks the insurer to cash settle
it $165,477 including GST as per the quote from their builder CM.
The details of the missing items identified by the complainants are set out in section 3 of the
Determination. The complainant is concerned the Insurer’s quote from builder, BMR does not
include items such as the installation of wall frames, supply and installation of towel rails or
costings for removal of glue from the lino flooring.
The insurer reverted to BMR for additional comment who noted costs are standardised for
cabinetry and the cost to supply and install towel rails would not impact the overall price. BMR
has not commented on the alleged missing wall frames. The insurer says small incidental
items will be covered off in the costs and BMR confirmed their cost would reinstate the
property to its pre-loss condition.
Any cash settlement figure should allow for:
variations to the scope of works which may be required during the repairs given such
variations are not uncommon and the insurer would have been liable for any resulting
increase in costs, if the repairs had been carried out by its contractors)
the additional risks assumed by the applicant due to the absence of the lifetime guarantee
which is provided under the policy.
The insurer accepts there are items missing from the SOW. Whether they are considered
incidental or not, the insurer is required to cash settle the complainant the amount it would
take to restore it to a pre-loss condition. While BMR might absorb the cost of incidentals if it
was completing the work, the insurer is cash settling the complainants and it is unlikely an
independent builder would absorb these costs. Accordingly, I am not satisfied with the
insurer’s submission that the addition of missed items o n the scope of works would not
increase the cost of repair. I am also not satisfied the insurer has shown the works could be
completed for the amount offered to the complainants.
Neither BMR’s SOW, nor the quote from the complainant’s bui lder CM, includes a
contingency or builders uplift for unknown circumstances and transfer of risk. The insurer’s
quotes specifically say they do not cover any unforeseen circumstances. However, the
complainant has stated she is satisfied the quote from CM is complete.
Given this, I consider it appropriate the insurer increase its cash settlement amount to
$155,476 being the mid-point between AB and CM and allow a 10% margin on top which
produces the figure of $171,023. The insurer is also required to pay interest on the amount of
$171,023 as per section 57 of the Act from 31 August 2020, (being a date by which work
should have been completed) to date of settlement.
Determination | Case number: 776132 Page 4 of 7
2.2 Are the complainants entitled to non-financial loss?
Compensation for non-financial loss payable in certain circumstances
The complainant seeks compensation for stress and inconvenience (non-financial loss) due
to the way the insurer handled his claims.
AFCA can award compensation of up to $5,400 for non-financial loss where there has been
an unusual amount of physical inconvenience, time taken to resolve a situation, or
interference with the complainant’s expectation of enjoyment or peace of mind.
In assessing whether to award compensation, we expect complainants to be moderately
robust, bear the normal degree of inconvenience experienced when a problem occurs, and
take reasonable steps to minimise the inconvenience suffered. Where a complainant has
contributed to their loss arising from the financial firm’s conduct, their level of compensation
may be reduced accordingly.
Complainant entitled to non-financial loss
The Complainant seeks $5,000 non-financial loss for poor claims experience and claims
delays. The complainant says the insurer failed to adequately assess the property, failed to
address the issues raised throughout the claim process and further the actions of its
contractors caused additional stress and loss.
The complainant specifically said:
contents from the mould contaminated unit were moved into the uncontaminated unit,
contaminating further contents
on a random check of the premises, the property was left unsecure with the windows open
allowing water to penetrate
multiple references were made in correspondence between the parties labelling the
complainants as difficult, rude and volatile.
Certainly, the Complainants experienced delay and incompetence at times. The
Complainants’ own experience in building meant they were in a position to identify gaps in the
level of care and detail which they expected for their property. Other insureds may have been
more accepting. As a result, the Complainants came to be viewed as difficult. The
Complainants exhibited stress and impatient anger. Undoubtedly the handling of the claim
contributed to this stress and anger.
The insurer still has not specifically addressed the issues raised by the complainant regarding
the management of the claim. It acknowledges there were unavoidable delays due to the
discovery of asbestos and errors with the first hygienist report.
Having reviewed the evidence submitted by both parties, I am satisfied the claim could have
been managed more professionally. Emails exchanged between parties indicate the
complainants raised concerns throughout the process and a number of those concerns were
ignored. The insurer is responsible for the actions of its contractors and unfortunately certain
contractors did not act appropriately throughout the assessment and remediation process.
Further, the insurer failed to address a number of the specific concerns during the complaints
process.
Given this, I consider the actions of the insurer have interfered with the complainants’
expectation of enjoyment or peace of mind and has inconvenienced the complainants beyond
Determination | Case number: 776132 Page 5 of 7
that which would be usually expected with an insurance claim. Therefore, I consider it
appropriate the insurer pay the complainants $3,000 non-financial loss.
2.3 Is the complainant entitled to consequential loss?
Policy does not cover consequential loss
The complainants seek the insurer cash settle them $29,277 being the cost of mortgage
repayments for an uninhabitable property for 13 months less $1,794.57 for water and power
payments already covered.
The policy does not contain a provision for this type of consequential loss and only covers
mortgage repayments if the property is a total loss. Given the property was not deemed a
total loss and there is no alternative insuring provision which would cover the claimed loss,
the complainant does not have an entitlement under the policy to consequential loss.
In effect the Complainant is arguing it is entitled to damages for breaches by the insurer of its
contract of insurance. However not every delay and handling error is a breach of contract and
it is difficult to identify specific damage resulting from alleged breaches.
Reviewing the file, it is very apparent that the Complainants’ broker was instrumental in
providing clear communication and facilitating the steps required to progress towards
resolution. Ultimately the insurer offered the complainants a $10,000 ex-gratia payment and
$1,000 credit on premium to resolve this dispute.
Given the circumstances, I consider it fair and reasonable the insurer honour this offer and
pay the complainant an additional $10,000 as well as the premium credit of $1,000 and the
above non-financial compensation of $3,000.
2.4 Why is the outcome fair?
Outcome is fair
The outcome is fair because if the complainants are cash settled, they must be able to restore
their property to its pre-loss condition for the amount offered by the insurer. The insurer did
not provide an appropriate level of service to the complainants and compensation is
warranted.
Determination | Case number: 776132 Page 6 of 7
3 Information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
3.2 Missing items from insurer’s scope of works as identified
by complainant
Record Key points
Determination | Case number: 776132 Page 7 of 7
Record Key points
Financial firm’s quote
(BMR )
Unit 1
No Walls allowed for.
Sliding Doors with plasterboard p anels for Laundry, BD1, BD2?
Why is the WC floor different to the Hall Floor?
No towel Rails in bathroom
Unit 2
No painting in Unit 2 Bathroom, Hall, WC, Linen
Air Conditioner cont ractor for Lounge AC but not BD1 AC. 7k w
loun ge $3,840 , 2.5kw BD1 $3,000
Plaster Board for Bathroom Wall s?
Sliding Doors with plasterboard panels for Laundry, BD1 , BD2?
No Flooring allow ed for in Laundry.
No towel Rails in bathroom
Financial firm’s quote ( A B) Unit 1
No Walls allowed for.
Sliding Doors with plasterboard p anels for Laundry, BD1, BD2?
Why is the WC floor different to the Hall Floor
No towel Rails in bathroom
Unit 2
No painting in Unit 2 Bathroom, Hall, WC, Linen
Air Conditioner cont ractor for Lounge AC but not BD1 AC. 7k w
lounge $3,8400, 2.5kw BD1 $3, 000
Plast er Board for Bathroom Walls?
Sliding Doors with plasterboard p anels for Laundry, BD1, BD2?
No Flooring allowed for in Laundry.
No towel Rails in bathroom