Home / QBE / Determination 775102

Determination 775102

Claim denial for water damage to specialised medical and computer equipment

FirmQBE
Decided2022-09-14
ProductGeneral Insurance · Other general
OutcomeFor the complainant in part
Amount awarded$5,000
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

A medical practice claimed for water damage from a washing machine leak to medical and computer equipment, which the insurer declined. AFCA found the water leak was the proximate cause of damage to the medical equipment, which must be covered, but not the computer equipment, and ordered a supplier report on repair or replacement plus a $5,000 contribution to expert costs.

Proximate cause of the damage to the medical equipment was the water leak event, so the medical equipment claim is covered under the office pack policy, while the computer equipment causation was not established.

Issues

Subjects and remedies

business interruptionhome or building damagepay claimpay compensationprovide documents

Related

All QBE determinations · Find similar determinations

Text of the determination

Determination Case number 775102 Financial firm QBE Insurance (Australia) Limited Case number: 775102 9 September 2022 Determination | Case number: 775102 Page 2 of 11 1 Determination overview 1.1 Complaint The complainant operates a medical practice and holds an office pack insurance policy with the financial firm (the insurer). On 23 June 2020, the complainant made a claim following extensive escape of water overnight from a washing machine valve. The insurer partially accepted the claim and has cash settled various aspects. However, the insurer has declined to cover claims relating to specialised medical equipment and computer equipment on the basis they did not sustain damage in the water leak event. The complainant disputes the insurer’s decision. It wants the insurer to cover the disputed items and reimburse it the cost of its expert reports. 1.2 Issues and key findings Is the insurer required to cover more of the claim? Yes. The proximate cause of the damage to the medical equipment was the water leak. The claim for the medical equipment is covered, but the claim for the computer equipment is not. Are further investigations required to enable settlement? Yes. The insurer is to obtain a report from a medical equipment supplier not previously involved in the claim. The report is to determine whether the medical equipment is repairable to a certifiable level and the associated costs in doing so or if the equipment must be replaced and the cost of replacement if required. The insurer is to pay that cost to the complainant (up to the applicable $500,000 AFCA compensation limit). Is the insurer to reimburse the complainant’s expert costs? Yes. The complainant’s expert reports have assisted it in establishing a more extensive claim entitlement. The insurer is to pay the complainant $5,000 in partial reimbursement of the costs it paid to PH, electrical engineers. Why is the outcome fair? The proximate cause of the damage to the medical equipment was the claim event. Therefore, it is fair that the insurer covers that damage (up to $500,000) once it is established whether the equipment can be repaired or must be replaced. In the circumstances, it is also fair that the insurer reimburses $5,000 of the c omplainant’s expert costs. 1.3 Determination This determination is substantially in favour of the complainant. Upon receiving written confirmation that the complainant accepts this determination (the notice), the insurer is to take the following steps:  within 21 days of receiving the notice, request a report from a medical equipment supplier not previously involved in the claim on: Determination | Case number: 775102 Page 3 of 11 > whether the medical equipment is repairable to a condition substantially the same but not better or more extensive than when new, and if so the cost of doing so. Any such repairs must render the equipment at a certifiable level and any repairs must come with a 12 month warranty > if the medical equipment cannot be repaired as per above, the cost to replace it with equipment to a condition equal to but not better or more extensive than when new (subject to the certification requirement)  w ithin 14 days of receiving the supplier’s report, the insurer is to : > provide a copy of the report to the complainant, and > pay the complainant the cost amount specified in it (but not exceeding $500,000)  within 14 days of receiving the notice, pay the complainant $5,000 in partial reimbursement of the costs it paid to PH. Determination | Case number: 775102 Page 4 of 11 2 Reasons for determination The complainant has acknowledged that the AFCA Rules limit the compensation amount AFCA may award. The limit that applies in relation to the c omplainant’s complaint is $500,000. The complainant has confirmed that it waives any amount of its claim that exceeds the monetary limit that AFCA is capable of awarding. 2.1 Is the insurer required to cover more of the claim? Yes. The proximate cause of the damage to the medical equipment was the water leak. The claim for the medical equipment is covered, but the claim for the computer equipment is not. Complainant must show a valid claim under the policy exists The complainant operates a medical and surgical facility with a particular focus on treatment of cardiovascular, venous disorders and degenerative disorders. The services it offers include specialist consulting, diagnostic imaging and the performance of medical procedures. The complainant is required to show, on the balance of probabilities (that it is more likely than not), that it suffered a loss caused by an insured event covered by the policy. This is known as a valid claim. Subject to its conditions and exclusions, the complainant’s office pack policy provides cover for loss or damage to contents caused by the defined events listed in the policy’s product disclosure statement (PDS). The defined events include ‘ water or other liquids or substances discharged, overflowing or leaking from apparatus, appliances, pipes or any other system at the premises…’ . Once the complainant establishes a valid claim, the insurer is liable for the loss unless it shows an exclusion or limiting condition applies. The insurer has the onus of proof in establishing the application of an exclusion. The standard of proof is the balance of probabilities. Proximate cause of the damage to the disputed items must be determined It is not in dispute that a significant amount of water leaked from the washing machine valve during the evening of 22 June 2020, or that the water flooded the complainant’s premises and caused damage. The water was ankle deep and took until 9pm on 23 June 2020 to clean up. The insurer has accepted the claim and paid some cash settlements. The issue in dispute between the parties is whether the flooding was the proximate cause of the damage to the following specialised medical and computer equipment (costings provided by the complainant):  three GE ultrasound machines at $140,000 each - $420,000  MX ultrasound machine Cardiac - $45,000  Esoate ultrasound machine Cardiac - $75,000  hand held Doppler and Plethysmography - $3,800  Veinlite infrared imaging and projector - $5,500  Gigaa Laser Systems Gbox 1470nm 400 micron SMA Generator - $35,000  data cabinets, laptop computers - $22,500  servers only, Touchpoint computer quote - $30,068 Determination | Case number: 775102 Page 5 of 11 Proximate cause is the dominant, efficient or operative cause of a loss. It is not required to be last in time or the sole cause. It is a question of fact that depends on the circumstances of each case. It requires a common sense evaluation of the evidence. Both parties rely on expert reports While both parties rely on numerous expert reports, the primary experts are electrical engineers – EV for the insurer and PH for the complainant. The parties and their respective electrical engineers have each provided extensive commentary on the other’s opinions. Both parties have a clear understanding of the position of the other. In the circumstances, it is unnecessary to refer to or detail in this determination all of the expert reports. Insurer denies the disputed items were damaged due to the claim event The insurer has provided a huge volume of material in a manner that has presented challenges for the panel. For example, the insurer’s Notice of Response dated 1 February 2021 (NOR) is 45 pages long and includes numerous lengthy extracts from various assessing and expert reports without a great deal of analysis. The NOR is accompanied by 160 annexures, which are not all the subject of meaningful submissions. All up, the NOR package is 2,500 pages long. The insurer is encouraged to present its position more succinctly. In essence, the insurer says that its expert reports establish that there was no damage or findings of condensation when the equipment was inspected in the initial stages following the claim event. Further, the insurer submits that if the equipment has failed, that is a result of the c omplainant’s actions not ensuring the safe storage of the equipment and the lack of restoration done. The insurer notes the manufacturer, GE, assessed the ultrasound machines on 29 June 2020, only a few days after the event. The machines were found not to be damaged – however, GE said that it was unable to warrant them. The insurer says the machines were not in warranty. The insurer’s expert EV inspec ted all major diagnostic and IT equipment at the premises on 9 and 10 July 2020 for evidence of condensation, corrosion or residues that may have the potential to cause deterioration to the equipment over time. This included a close visual inspection and testing with an Elcometer and chloride quick test strips for invisible anionic residues to see if corrosion causing contaminants were present. EV said no evidence of damage from the incident was detected on any of the items, or contaminants capable of causing corrosion. EV found corrosion to 2 of 12 screws on the base of the foot switch of the Esaote ultrasound scanner in the vascular operating room 2. However, EV said this was unrelated to the water leak as otherwise all screws should be corroded. The three GE Logiq S8 ultrasounds were noted to be operational with no damage observed. EV said there were no plausible circumstances for condensation to occur on equipment surfaces based on the available information on temperature and humidity levels. The circumstances were also not plausible for mould development, as the humidity was non- condensing (except on windows) and brief (maximum 12 hours), and remediation of the environment was carried out promptly by removing the water and dehumidifying the area. IT ite ms removed from the premises by the complainant’s IT service provider , TT, following the event were inspected by EV on 14 July 2020. This included internal assessment and Determination | Case number: 775102 Page 6 of 11 testing for not-up operation. All but one server was found to be operating normally. EV acknowledged the server appeared to have a hardware fault unrelated to water or moisture exposure, although the cause of failure was not determined. The insurer refers to an email from TT to the complainant dated 14 July 2020, in which TT said there was no major damage to these items but there were signs of water intrusion. TT recommended replacing all items to be safe, as equipment will eventually fail once affected by water. No photos or description of this damage was provided by TT. EV reports contacting TT to ask what evidence was observed of moisture intrusion. TT advised there were only some stains on plastic surfaces and the recommendation to replace the items was based on the age of the equipment and information given by the complainant. A later email from TT stated the equipment was mostly very old. Complainant disagrees The complainant says that the insurer ’s assessors did not inspect the premises until after the water was cleaned up so did not experience the extremely high levels of humidity that were present on 23 June 2020 and the night before. The complainant says the insurer failed to properly consider the damage caused to the highly sensitive medical equipment. The complainant says the following equipment has failed on the first use since the event:  15 of 18 laptops  one of three GE Logiq S8 ultrasound machines  an Esoate ultrasound machine  one of two handheld Doppler and Plethysmography devices  a Veinlite infrared imaging projector  a Gigaa Laser Systems Gbox generator. The complainant says this was due to the water leak event. The following information has been provided by the complainant to demonstrate damage to these items:  a statement from WY, an IT engineer formerly employed by CD which provides IT services to the health industry, including to the complainant. WY said: > 15 of the 18 laptops tested experienced malfunctions not present before the incident, with 10 not booting when not connected to a power source, two not starting at all, the cooling fan on one not functioning, and two having spots displaying on the screen in various sizes > the suddenness of the laptop failures and the number of laptops which have failed is not something that can be explained by way of natural wear and tear or ordinary use, and is consistent with water damage > it is a commonly accepted view in the industry that computers will suffer damage when exposed to increased levels of humidity, and any heightened levels of moisture will cause, contribute to or accelerate corrosion in computers (although WY did not identify any corrosion).  a service report dated 30 October 2020 from ultrasound supplier EX noting the Logiq S8 was reported to have been sitting in water and high humidity for more than 24 hours, which may cause component failure or malfunctioning in the future. On this basis, EX deemed the machine unfit for use for medical diagnostic purposes Determination | Case number: 775102 Page 7 of 11  video of a handheld doppler device now making a loud noise when not in operation. The complainant says the device also distorts measurements taken and is not usable  the complainant reports the Esoate ultrasound machine screen has become glitched, erratic and unresponsive, as shown in photos provided  a photograph and video showing two fields greyed out on the screen of the Gigaa laser, which the complainant says occurred during surgery on 19 March 2021 during its first intra- operative use since the event, when it would not generate a laser  in May 2021, the complainant attempted to use one of the Logiq S8 ultrasound, but it could not be properly booted. The photo provided show an error message saying Windows cannot start as a file is missing or corrupt. The complainant advises the other two machines have not been used  a letter from the complainant advising the Veinlite device failed on 26 May 2021 after regular use following purchase in January 2020  Two reports from PH following a site inspection on 21 April 2021. PH identified: > mild corrosion in right hand seams of a GE ultrasound machine > extensive corrosion to Dermatascope machine > three laptops would not charge or power up, one due to a failed wifi card (resolved by replacing wifi card), one due to a failed inductor (resolved by replacing inductor), and another with poor connection between the power ribbon cable to the main circuit board connection due to corrosion on one of the contacts of the ribbon cable (resolved by cleaning). PH said the first two faults were caused by an electrical spike and the third likely as a result of the environment following the event. The complainant says it is reasonable to infer from these findings that all disputed items were damaged by the claimed leak event. The complainant says the disputed items have been or will be impacted by humidity and condensation from the event. In support of this, the complainant has provided photographs showing condensation on the windows and statements from individuals involved in the clean up on 23 June 2020. The complainant also notes the insurer’s restorer CG measured relative humidity at 63.1% when it attended the day after the event, confirmed in its report dated 29 October 2020. CG said if relative humidity remained at 63% it would possibly have resulted in mechanical damage or metal corrosion, but noted it reduced to 50% when initial remediation and building drying commenced the following day. CG did not observe any moisture on the electronic equipment but said it could have dried prior to its attendance. CG noted high moisture remaining in the wall cavities as the building remediation works had not been completed. The complainant submits the humidity would have been higher when the premises was flooded and describes the clinic as being uncomfortably humid when the event was discovered. Condensation on windows and windowsills was noted, and the complainant also reported some droplets forming on the ceiling. The complainant’s princ ipal, Dr G, has stated: A report submitted by EV fails to identify evidence of moisture or water damage to any of the equipment. It also fails to differentiate medical devices from other medical equipment. It does not make mention or provide an assessment of latent risk or latent liability for equipment failure resulting from moisture/humidity exposure in the near or intermediate future. There are no references to the ISO standards applied to the manufacturing of medical devices and the failure of the Determination | Case number: 775102 Page 8 of 11 exposed equipment in meeting them. As a medical practitioner and surgeon, I will not expose my patients to the risk of device failure based on my knowledge of the exposure and the absence of warranty or indemnification in the event of equipment failure. Insurer is required to cover the specialised medical equipment Based on the available information, the panel is satisfied that the proximate cause of the damage to the specialised medical equipment was the water leak event. On balance, the resulting condensation and humidity has adversely affected that equipment. The individuals involved in the clean up on 23 June 2020 have said they were working in very humid conditions (Dr G has described them as overbearing, akin to an indoor swimming centre). It is also notable in that regard that EV has conceded that the humidity level could have been up to 90% before clean up and climate stabilisation. The medical equipment appears to have been well maintained and operational before the claim event and issues have been experienced with the equipment afterwards. Medical equipment failure has serious potential consequences for patients. Very limited scope exists for risks to be taken on the equipment delivering inaccurate diagnostic outcomes or not performing during surgery. It is critical that such equipment is fit for purpose. It is notable that the National Association of Testing Authorities has apparently refused accreditation for the ultrasound machines as a result of the inundation. The complainant has conceded that the same considerations do not apply to the computer equipment. Taking into account TT’s comments outlined above, the panel is not persuaded that it has been established that the proximate cause of the damage to the computer equipment was the claim event. Accordingly, the insurer is required to cover:  three GE Ultrasound machines  MX Ultrasound machine Cardiac  Esoate ultrasound machine Cardiac  hand held Doppler and Plethysmography  Veinlite infrared imaging and projector  Gigaa Laser Systems Gbox 1470nm 400 micron SMA generator. 2.2 Are further investigations required to enable settlement? Yes. The insurer is to obtain a report from a medical equipment supplier not previously involved in the claim. The report is to determine whether the medical equipment is repairable to a certifiable level and the associated costs in doing so or if the equipment must be replaced and the cost of replacement if required. The insurer is to pay that cost to the complainant (up to the applicable $500,000 AFCA compensation limit). Policy sets out how the insurer will settle claims Page seven of the PDS sets out the manner in which the insurer will settle property damage claims and relevantly states: Determination | Case number: 775102 Page 9 of 11 a. where property (excluding stock and customers’ goods) is destroyed, if a building the rebuilding thereof or, if property other than a building the replacement thereof by similar property, in either case to a condition equal to but not better or more extensive than its condition when new; b. where pro perty (excluding stock and customers’ goods) is damaged, the repair of the damage and the restoration of the damaged portion of the property to a condition substantially the same as but not better or more extensive than its condition when new; Further investigations are required to enable settlement The insurer has submitted: Whilst the insurer refuses liability for the items, in the event it is found liable, it reserves its right to assess the amounts claimed to determine whether they are fair and reasonab le, and in line with the complainant’s entitlements under the policy. Noting the critical importance of certification to the question of whether the medical equipment is repairable or requires replacement, the panel regards the insurer’s position to be reasonable. Therefore, the insurer is to take the following steps: the insurer is to take the following steps:  request a report from a medical equipment supplier not previously involved in the claim on: > whether the medical equipment is repairable to a condition substantially the same but not better or more extensive than when new, and if so the cost of doing so. Any such repairs must render the equipment at a certifiable level and any repairs must come with a 12 month warranty > if the medical equipment cannot be repaired as per above, the cost to replace it with equipment to a condition equal to but not better or more extensive than when new (subject to the certification requirement)  within 14 days of receiving the supplier’s report, the insurer is to: > provide a copy of the report to the complainant, and > pay the complainant the cost amount specified in it (but not exceeding the AFCA compensation limit of $500,000). 2.3 Is the insurer to reimburse the complainant’s expert costs? Yes. The complainant’s expert reports have assisted it in establishing a more extensive claim entitlement. The insurer is to pay the complainant $5,000 in partial reimbursement of the costs it paid to PH. AFCA may require insurer to contribute to a complai nant’s professional costs The AFCA rules enable AFCA to require an insurer to contribute to the professional costs incurred by the complainant. These costs are, however, usually capped at a total of $5,000, unless special circumstances apply. Determination | Case number: 775102 Page 10 of 11 When considering whether to require an insurer to make a costs contribution, AFCA takes into account the complexity of the complaint and whether the particular complainant needed to incur costs to understand or establish their claim. The insurer is to reimburse the complainant the costs charged by PH The complainant seeks to be reimbursed for the cost of PH’s services. An invoice dated 20 July 2021 from PH for costs totalling $20,967.50 has been provided. The complainant requests that the cost of PH’s services be treate d as part of the claim (rather than the subject to a costs award) as the cost ought to have been incurred by the insurer. The panel is not satisfied that is the case given that the insurer did engage an electrical engineer, EV. It is also noted that the insurer previously paid the complainant the claims preparation sum insured available under the policy. Accordingly, PH’s costs are to be considered by reference to AFCA’s ability to require an insurer to contribute to the professional costs incurred by a complainant. PH’s reports have assisted the complainant in establishing an entitlement to claim coverage more extensive than the insurer had accepted. In the circumstances, the panel is satisfied that it is fair and reasonable for the insurer to reimburse to the complainants $5,000 of the amount PH charged for its services . 2.4 Why is the outcome fair? The proximate cause of the damage to the medical equipment was the claim event. It is therefore fair that the insurer covers that damage (up to $500,000) once it is established whether the equipment can be repaired or must be replaced. In the circumstances, it is also fair that the insurer reimburses $5,000 of the complainant’s expert costs. Determination | Case number: 775102 Page 11 of 11 3 Supporting information 3.1 The AFCA process The complainant is a company with a single director and has a legal representative assisting with the complaint. Unless the context requires otherwise, the complainant, its director an legal representative are all referred to as the complainant for the purpose of this determination. AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. A panel determined this matter Due to the nature of this complaint, we referred it to a panel for determination. The panel includes:  an ombudsman  a member with significant experience in consumer and small business advocacy  a member with extensive experience in the insurance industry. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.