The complainant claimed storm damage to her home and disputed the insurer's cash settlement offer for roof, kitchen and front entry works. AFCA accepted the insurer's roof scope and quote with a 20% contingency, but required the insurer to pay the complainant's quotes for the kitchen, front entry and rear porch, with interest.

The fair cash settlement amount was determined by comparing the parties' expert quotes and scope of works, with interest payable under section 57 of the Insurance Contracts Act 1984.

Issues

Subjects and remedies

pay claimpay interest

Related

All QBE determinations · Find similar determinations

Text of the determination

Determination Case number 774447 Financial firm QBE Insurance (Australia) Limited Determination | Case number: 774447 Page 1 of 5 Case number: 774447 3 November 2021 1 Determination overview 1.1 Complaint The complainant lodged a claim for storm damage to her property with her home insurer, the financial firm (insurer). The insurer accepted the claim. However, the parties dispute the extent of the insurer’s liability. The insurer has made a cash settlement to pay for the damage to the roof and other areas. The complainant disputes the amount offered. 1.2 Issues and key findings What is the extent of the insurer’s liability ? The insurer is entitled to rely on JL’s quote for the roof subject to a 20% contingency. For the other works, it is fair for the insurer to cash settle the complainant based on her quotes. 1.3 Determination This determination is partially in favour of the complainant. The insurer is to settle the claim as set out in section 2.1. Determination | Case number: 774447 Page 2 of 5 2 Reasons for determination 2.1 What is the extent of the insurer’s liability ? Parties dispute the extent of damage to the roof One of the issues in dispute is the damage to the roof and the scope of works for this. Both parties have provided expert evidence to support their positions. I do not propose to reiterate their findings in detail as their evidence has been exchanged. The insurer is relying upon a report from roofer, RC. RC has provided several reports. For the main roof, RC identified there was about 25 tiles broken. These would need to be replaced. This would also affect the ridge cement work, which would need to be reinstated. He also found another 5 broken tiles for the freestanding garage. RC also identified maintenance issues with the roof. This included other older broken tiles as well as considerable deterioration of the cement work. The complainant is relying upon AP’s evidence. AP found about 32 broken tiles. AP said the integrity of the remaining tiles were likely ‘affected by the sudden impact of 3 extreme weather elements simultaneousl y’. AP also said the Cordova tile, being the tile on the complainant’s roof, is designed to come apart from the ridge and work down the tiles. AP did not recommend a partial rectification. The complainant also referred to a specialist roof report from I, obtained by the insurer, that said the entire side of the roof would have to be stripped and re-laid. I only identified two broken tiles. RC’s evidence is persuasive Having carefully considered the expert evidence, I note the following. AP’s evidence that the whole roof has been affected by the storm is not compelling. RC did not accept this. RC provided evidence to show there were maintenance issues and old damage. RC provided photographs, with comments in support. In these photos, it showed there were broken tiles with extensive weathering and lichen in the cracks and surface. There was also clear evidence that parts of the ridge cement work failing through deterioration. Therefore, I do not accept the whole roof has been affected by the storm. Regarding the scope of works to replace the 30 broken tiles, I note the following. RC said replacing 30 tiles is a simple and basic undertaking. RC does not agree that it is reasonable, or necessary, to replace entire roof facades. RC says this having 43 years ’ experience as a roof tiler and being a roof plumber of 30 years. AP and I say otherwise. I am not persuaded by their evidence. I only identified two broken tiles and it is clear the damage was more extensive. Further, it is difficult to understand why an entire roof façade needs to be replaced as part of replacing broken tiles. This, on the face of it, appears excessive. Also, RC is the most experienced experts. RC has specialised roof experience of 43 years. Whilst AP is a registered builder who has held an unlimited licence since 1996, it is not clear he has the extensive experience with roofs that RC does. It is unclear what I’s experience is. Determination | Case number: 774447 Page 3 of 5 Therefore, I find RC’s evidence more persuasive about the scope of works necessary for the roof. Insurer can settle roof based on JL’s quote The insurer is relying upon JL’s quote totalling $9,324.89. This includes labour, materials, preliminaries and handrailing allowance. The complainant says JL’s quote provides insufficient allowance for labour and is missing materials, such as scaffolding. The complainant also says it does not include the garage. I do not agree. JL’s quote allows for 32 hours of labour. It is not clear why this would not be sufficient. AP’s quote does not include how many hours are needed. Further, JL’s quote includes the replacement of 50 tiles. This would include the tiles on the garage. It is not clear why scaffolding is needed given there will be handrails on the roof. I am not persuaded it is necessary to have both. JL’s quote appears to accept handrails are sufficient. This was evident in both its quote to repair the tiles and in its more extensive quote to replace the roof. Further, AL’s quote to repair the roof includes $25,340 for scaffolding. AL’s quote does not include handrails. Given AL ’s quote for scaffolding comprises more than 58% of the total cost to repair the roof, I do not accept the use of scaffolding is necessary or reasonable. Therefore, when I compare the two quotes, I agree it was reasonable for the insurer to rely on JL’s qu ote to cash settle the roof repairs. An AFCA case analyst issued a preliminary assessment saying there should be a 20% contingency on the quote. The insurer accepted this. I agree this contingency is fair. This means the insurer can cash settle the roof for the total amount of $11,189.87. The insurer should also pay interest on this amount pursuant to section 57 of the Insurance Contracts Act 1984 (the Act). Interest is payable from 17 October 2020, being one month after JL issued its quotation, until payment is made. Other works to be settled in this way The other works remaining include the kitchen, front entry and rear porch. The insurer has agreed to the complainant’s cost for the rear porch, totalling $2,934. For the kitchen and front entry, the complainant is seeking $14,256 whilst the insurer has offered $4,026.53. On these points, I note the following. The complainant says the insurer’s quote does not include insulation to the kitchen . This is incorrect as JL’s quote specifically has an item for ‘Re move and replace Insulation Batts – ceiling’. I do acknowledge there is a significant discrepancy between both quotes totalling more than $10,000. There does not appear to be any dispute they are for the same scope of works. As the insurer is seeking to cash settle the repairs, it is fair to rely on the complainant’s quotes. This is because it is clear AL’s quotes are actionable . This does not appear to be the case for JL’s quote. There is no dispute they are based on the same scope of works. Given this, I am persuaded the complainant’s quote more likely represents the cost the complainant will incur to repair these items. Determination | Case number: 774447 Page 4 of 5 Therefore, for these other works, it is fair in all the circumstances that the insurer pays the complainant’s quotes totalling $17,190. The insurer should also pay interest on this amount pursuant to section 57 of the Insurance Contracts Act 1984 (the Act). Interest is payable from 30 April 2021, being one month after the complainant’s quotes were issued, until payment is made. Determination | Case number: 774447 Page 5 of 5 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.