Home / Allianz Australia / Determination 773363

Determination 773363

Water damage claim declined; delay sought replacement of bathroom and laundry

FirmAllianz Australia
Decided2021-08-26
ProductGeneral Insurance · Landlord
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed$20,000
SourceAFCA PDF

Summary

A landlord's water damage claim was declined because the damage was caused by an excluded shower waterproofing failure. She alleged the insurer's delay in deciding increased the repair cost, and AFCA found the delay was not the insurer's fault and ordered nothing.

The policy excludes the waterproofing failure, and the insurer's investigation timeline was reasonable with the scope of repairs unchanged throughout the claim.

Issues

Subjects and remedies

home or building damageno remedy

Related

All Allianz Australia determinations · Find similar determinations

Text of the determination

Determination Case number 773363 Financial firm Allianz Australia Insurance Limited Determination | Case number: 773363 Page 1 of 5 Case number: 773363 26 August 2021 1 Determination overview 1.1 Complaint The complainant holds a landlord insurance policy (policy) with the financial firm (insurer). On 17 March 2020, a claim was lodged for water damage to the insured building. The insurer has declined the claim. The complainant does not dispute the insurer is entitled to decline the claim in line with the policy provisions. However, she is of the view the insurer has unreasonably delayed informing her of the decision to decline the claim, which has resulted in the further damage to the insured building. She is seeking for the insurer to cover the cost of a complete replacement of the bathroom and laundry, which the insurer has refused. 1.2 Issues and key findings Is the insurer liable for the cost to replace the bathroom and laundry? No. The available information indicates that the ins urer’s manageme nt of the claim has not caused unreasonable delays. Further, the evidence does not show the insurer is responsible for any additional works that may be required to repair the damage to the building. 1.3 Determination This determination is in favour of the insurer. The insurer is entitled to decline the claim and is not required to any further action. Determination | Case number: 773363 Page 2 of 5 2 Reasons for determination 2.1 Is the insurer liable for the bathroom and laundry damage? The policy is an insured events contract of insurance The policy covers the insured property against loss or damage caused by one or more the listed insured events, including ‘Water or other liquid damage’. Cover under these benefits is subject to the conditions, limitations and exclusions specified in the product disclosure statement (PDS). The insurer is entitled to rely on the policy provisions The insurer provided the complainant with the relevant policy documentation including the PDS and certificate of insurance (COI). Therefore, I accept the insurer is entitled to rely on the policy provisions to assess its liability under the claim. There is no dispute the damage is excluded under the policy The complainant accepts the insurer is entitled to decline the cover for the original damage claimed because it was due to a failure of the shower’s waterproofing membrane , which is excluded under the policy. However, she is of the view, given the time it took for the insurer to decline the claim, it should be required to cover her for the cost to replace the damaged bathroom and laundry. The complainant says the insurer should have informed her of the decision to decline the claim on or about 8 April 2020. This is when she provided two consultants’ reports confirming the reason for the damage was a failure of the shower’s waterproofing membrane. The complainant says the insurer delayed informing her of the decision to decline the claim until October 2020, which has increased the cost of repairs from less than $1,000 to close to $20,000. For this reason, she believes the insurer should be required to cover the total repair costs as they stand now. The insurer disputes it is liable for the damage to the building The insurer has refused liability for the damage to the bathroom in line with the policy provisions. With respect to the delay in finalising the claim, the insurer says this was not due to its failure because:  on lodgement of the claim the insurer appointed loss adjusters ‘SG’ to arrange for the assessment of the insured building to determine the cause and extent of the damage  contact was made with the tenant of the property on 30 March 2020.Access to the property was denied sighting concerns relating to COVID-19  on 8 April 2020, the insurer received two reports from the complainant’s appointed consultants a dvising the damage is because of a failure of the shower’s waterproofing  the insurer says neither of these reports confirmed pressure testing of the bathrooms plumbing to eliminate this as a possible cause for the damage  the insurer’s representatives made several attempts to contact the complainant and the property manager to gain access to the property. However, access was not allowed until 9 June 2020  given the damage, initially makes safe works were authorised and subsequently consultants were appointed to complete testing to the plumbing. This confirmed there were Determination | Case number: 773363 Page 3 of 5 no leaks to the plumbing and the sole reason for the damage was a failure of the shower’s waterproofing membrane, which is excluded from cover under the policy  the insurer informed the complainant of this in July 2020, however, the complainant has raised concerns about the insurer’s management of the claim.  the complainant’s concerns were considered as well as the matter referred to the insurer’s internal dispute resolution process  after this, the complainant was provided with a formal letter of declinature with respect to the claim in October 2020, as well as, the insurer’s decision not to accept liability for the bathroom and laundry relating to is management of the claim. The insurer is entitled to decline the claim in its entirety I have carefully considered all the information provided by the parties and am satisfied it establishes, on balance:  the insurer is entitled to decline the claim for the water damage in line with the policy  the insurer has not been shown to be responsible for a significant portion of the delays experienced under the claim  there is no evidence to show the scope of repairs needed to rectify the water damage have increased any more than what was required at lodgement of the claim in March 2020. I accept the claim has taken longer to finalise than what would reasonably be expected for a claim of this nature. I accept the complainant provided the insurer with two reports providing the opinion that the water damage was because of a failure of the shower’s waterproofing membrane. However, I accept the insurer’s position that in assessing the claim it is obliged to ensure a complete investigation and assessment into the cause and extent of the damage is completed. This, I accept, includes an inspection and pressure testing of the shower’s plumbing, which the complainant’s consultants failed to complete. Accordingly, I accept it was reasonable and in line with the insurer’s obligations under the policy to undertake a complete and thorough investigation of the damage before providing the complainant with a final decision under the claim. Further, the available information shows the insurer acted within a reasonable timeframe in appointing consultants to attend the insured property after the claim was lodged in March 2020, as well as, after it was granted access to the property in June 2020. The insurer informed the complainant of its decision to decline the claim in July 2020, which again I accept is a reasonable timeframe from when it was allowed access to the property. The delay of several months between March 2020 and June 2020 is not the fault of the insurer and more so relates to the unfortunate impact of the COVID-19 outbreak and a reluctance of the tenant not to allow access to the property. For the reasons discussed above, I am not satisfied it would be fair in all the circumstances to require the insurer to cover the cost of the complete replacement of the bathroom and laundry under the claim. Additionally, even if I were of this view which I am not, there is no evidence which establishes the extent of repairs needed to repair the water damage to the insured building have increased over time. The evidence from SG and its appointed consultants provides that the repairs referred to by the complainant at a cost under $1,000 relate to only a temporary solution i.e. sealing of the shower recess and do not address the damaged waterproofing. However, the works needed to actually repair the damaged waterproofing would have required stripping of the bathroom Determination | Case number: 773363 Page 4 of 5 and laundry at all times. These were the works that were required at claim lodgement and remained the same at the time the claim was declined. So, no prejudice has been caused because of the time which has passed over the course of the claim. The complainant has not provided any information refuting these findings and in the absence of compelling evidence to the contrary, I accept the insurer’s position in this regard. Accordingly, I determine the insurer is entitled to decline the claim in line with the policy and it is not obliged to cover the cost to replace the bathroom and laundry because of its management of the claim. Why is the outcome fair? The determination is fair in all the circumstances because:  the available information shows the water damage caused to the insured building is due to the failed waterproofing membrane, which is excluded from cover  the available information does not establish the insured is liable for the significant portion of the delay experienced under the claim; and  the available information shows the scope of works to repair the damaged waterproofing membrane remained the same through the life of the claim and did not increase because of the time it took for the claim to reach finality. Determination | Case number: 773363 Page 5 of 5 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.