Determination 772581
Insurer ceased repairs of water-damaged rental property flooring, disputing liability for subfloor batten replacement and loss of rent
Summary
The complainant claimed under a policy for water damage to rental flooring; the insurer ceased repairs over subfloor issues and disputed battens. AFCA found in favour of the complainant, ordering a new builder to complete repairs, loss of rent, re-letting fees, expert fees, non-financial loss compensation and policy additional benefits.
The insurer accepted the claim and agreed to install the floor, so installation must include compliant battens per the manufacturer's guide, and its discretion to repair rather than cash settle must be exercised fairly and in good faith given the circumstances.
Issues
- Repairs or contractors primary · upheld
“Insurer's builder's work was defective and it ceased works; insurer must appoint a new builder to complete repairs as recommended by complainant's builder.”
- Claim amount dispute secondary · upheld
“The insurer's decision not to cover the replacement battens was unfair and caused significant loss of rent.”
- Delay secondary · upheld
“The insurer failed to return the property to a liveable condition as required under the policy wording.”
- Third-party or outsourcing failure secondary · upheld
“The insurer and its repairers caused unnecessary inconvenience and stress to the complainant.”
Subjects and remedies
business interruptionelderly or capacityhealth or medicalhome or building damagepay compensationpay interestpay non financial lossrepair or rectify
Text of the determination
Determination
Case number 772581
Financial firm QBE Insurance (Australia) Limited
Determination | Case number: 772581 Page 1 of 8
Case number: 772581 15 October 2021
1 Determination overview
1.1 Complaint
The complainant lodged a claim in December 2018 with the financial firm (insurer) for
damage to her rental property flooring due to a burst pipe and for malicious damage. The
insurer accepted the claim and commenced repairs.
The insurer, after removing the floor a second time in March 2020, ceased works saying the
subfloor had underlying issues that needed rectification to enable repairs. The complainant
says the insurer should complete the repairs as agreed and pay her loss of rent for the period
the property was uninhabitable.
1.2 Issues and key findings
Should the insurer cover all repairs and associated costs?
Yes. The insurer accepted the claim and authorised repairs. Repairs required include
installation of new battens to enable proper installation of the new floor.
Should the insurer pay additional loss of rent?
Yes. The insurer failed to return the property to a liveable condition as required under the
policy wording and should continue to pay the loss of rent until repairs are completed.
Is compensation for non-financial loss and additional benefits payable?
Yes. The insurer and its repairers caused unnecessary inconvenience and stress to the
complainant. The insurer must pay non-financial loss compensation of $2,000, reimburse the
complainant ’s professional costs incurred and pay the additional benefits under the policy.
Why is the outcome fair?
The expert evidence provided by both parties shows the repairs were achievable within the
policy coverage. It is fair the insurer completes the repairs associated with the claimed event.
1.3 Determination
This determination is in favour of the complainant.
Within 21 days of the complainant’s acceptance of this determination, t he insurer must
appoint a new builder to complete the repairs as recommended by the complainant’s builder.
Loss of rent is payable from 17 January 2020 to completion of the repairs. Interest under
section 57 of the Insurance Contracts Act 1984 (Cth) is payable on the outstanding rental
payments beginning on 17 February 2020. The insurer is to pay the complainant $1500 re-let
fees in accordance with the terms of the policy.
The insurer must pay compensation for non-financial loss of $2,000, pay $2,200 for the
complainant’s expert invoice and pay the additional benefits set out under section 2.2. of this
determination
Determination | Case number: 772581 Page 2 of 8
2 Reasons for determination
2.1 Should insurer cover all repairs and associated costs?
Yes. The repairs required are reasonable for the insurer to complete under the terms of the
policy.
Circumstances leading to complaint
The complainant lodged a claim in December 2018 after water damage was discovered at the
property. The insurer accepted the claim and undertook to repair the damage, the majority of
it being to the timber floor.
The insurer's builder fixed the floor, but the complainant was not satisfied with the work. The
complainant also wanted the entire floor replaced, not just part of it, because the timber did
not match. The complainant noticed large gaps between the floor boards and raised this with
the insurer. The insurer agreed the works of its builder were defective and needed to be
replaced.
The insurer agreed to replace the timber over the whole floor, as a gesture of goodwill.
However, when the insurer's builder went to complete the works, it noticed that there were
issues with the subfloor, which it did not relate to the claimed water damage.
The insurer says the slab is not level due to installation failures and the complainant is
responsible for the upgrade to the slab. The insurer also says the existing battens are suitable
for the boards to be installed, if the slab is rectified.
The insurer's builder said that it could not warrant the works. The insurer offered a cash
settlement figure representing the cost to lay the new boards on the current floor. It did not
account for replacement of any battens or any other sub floor work.
The complainant says that if there was any problem with the sub floor, this should have been
identified by the initial builder, which it was not. She also says that the battens should all be
replaced and be hardwood in line with the views of her expert (TFR).
No need to upgrade the concrete slab.
The complainant provided a report from TFR who says the slab does not require repairs. TFR
explains to lay the boards the insurer agreed to install, the manufacturer requirements say the
battens are to be 450mm apart. The current battens are 500mm. The expectation should be
for the repairer to replace the battens as part of laying the new floor.
TFR also says the battens should be hardwood rather than softwood. He says this is required
to give enough space to drive a nail into the batten to specific depths. He further explains any
levelling issues with the sub floor can be addressed by plaining and packing the battens as
they are replaced. The insurer expert says battens can be either soft or hardwood.
The insurer obtained a report from a flooring expert (AT) to comment on what works were
required to either the slab or the battens for the floors to be laid. AT said the floor as is could
be used to lay new boards, however recommended an engineer be appointed to understand
the suitability of the concrete slab. An engineer was not engaged by either party.
TFR ’s report is persuasive in explaining that any unlevel areas of the slab can be managed
through planing and packing the battens. This view is supported by AT who went so far as to
say the floor was suitable as is.
Determination | Case number: 772581 Page 3 of 8
This is further supported by the manufacturers installation instructions which say any levelling
issues with the sub floor can be remedied by packing and planing the battens.
The question then becomes whether the insurer is liable for the replacement of the battens,
and whether the battens need to be hard wood.
Battens should be replaced as part of the repairs
The Panel is satisfied the insurer agreed to install the boards selected by the complainant and
that installation should include preparation of the support structure of the floor. It is
reasonable that the insurer covers the costs to install the battens required for the flooring.
The Panel is further satisfied the levelling issues of the sub floor can be addressed as part of
the batten installation process.
The installation guide from the manufacturer of the floor boards indicates the current battens
are not suitable. The guide recommends the battens be placed at 450mm distances. The
insurer says the Victorian Building authority says battens should be within a certain range and
not exceed 520mm. It says the current battens are suitable.
TFR explains the manufacturers ’ installation guide should always be considered before the
Victorian Building Authority and that is why he has recommended battens be installed at
450mm. The insurer has not provided any information suggesting this is incorrect. The Panel
is satisfied the battens should be installed in accordance with the manufactures guide and
placed at 450mm distances.
Insurer should complete the repairs as recommended by TFR
The policy provides the insurer with a discretion whether to complete the repairs or cash
settle a claim. Such discretion must be exercised fairly, reasonably and consistent with the
duty of utmost good faith.
It is clear from the information exchanged that there has been a breakdown in the relationship
between the insurer ’ s builder/ repairer P1 and the complainant. Normally the Panel would
agree that in these circumstances a cash settlement may be appropriate. However, when
considering the complainant ’s circumstances, the Panel considers it fair that the insurer
completes the repairs.
The complainant is a single person, over 70 years old and living in in Country Victoria while
the rental property is in central Melbourne. The complainant describes several health issues
affecting her mobility as well as levels of anxiety. The complainant does not believe she is
capable of organising or supervising the repair of the property. Her difficulties are
exacerbated by the current Covid 19 travel restrictions.
The complainant also says there are other parts of the repairs that have not been completed
awaiting the resolution of this complaint. Those repairs include reinstatement of the skirting,
reinstatement of the carpet steps, plaster repairs and painting.
It is fair given the complainant ’ s circumstances and the incomplete repairs that the insurer
completes the repairs to the complainant’s property in accordance with the recommendation
of TFR. As the relationship with the insurer ’ s builder has broken down, the insurer must within
21 days of the complainant’s acceptance of this determination, appoint a new builder,
appropriately qualified, to complete the outstanding repairs.
Determination | Case number: 772581 Page 4 of 8
2.2 Should the insurer pay additional loss of rent?
Yes. The insurer ’ s decision to cease works when the property was unliveable and not pay the
reasonable cost to repair the home caused additional loss of rent.
The property was unliveable due to the insurers repairer
The insurer initially accepted loss of rent coverage for the period its repairers were completing
remediation repairs. Its offered to cover loss of rent to 30 May 2020, representing the
approximate time it communicated its unwillingness to complete repairs.
The insurer ’ s repairer initially replaced only a section of the floor, being the section directly
water damaged. The insurer then agreed to replace the whole floor, because the repairer had
not laid the new section of flooring in a compliant manner.
The repairer returned and removed the floor boards before notifying the insurer they would no
longer complete repairs due to the perceived sub floor issue. The complainant was not able to
complete repairs with the cash settlement offered as the battens required replacement. The
insurer ’ s decision not to cover the replacement battens therefore caused the ongoing rental
loss the complainant has suffered.
The insurer is to pay rental loss from the date it is currently paid to (17 January 2020) up to
the date of this determination and to continue to pay until the repairs are completed. The rate
of rental loss is $2,389 per calendar month, or $78.54 per day. The insurer should also pay
interest on the rental payments based on when the amounts should have been paid monthly,
beginning on 17 February 2020.
The insurer has agreed to pay re-letting fees as per the policy wording. As the policy provides
a limit of $1,500 for reletting fees the insurer should pay the complainant the policy limit of
$1,500.
2.3 Should the insurer pay compensation for non-financial loss
and additional benefits?
Yes. The actions of the insurer and its repairer caused unreasonable stress and
inconvenience for the complainant.
The insurer should pay non-financial loss
The insurer says the matter was complex and it handled the claim reasonably overall. The
complainant says the process of organising repairs was very stressful and the communication
received from the insurer was unreasonable.
The complainant pointed out comments from the insurer insinuating she was intentionally
looking for issues to slow down repairs. The complainant says she worked hard to
substantiate the issues she was observing. This included the initial issues with the floor
repairs, other issues with the finish of the repairs and finally the issues with the battens. Each
of these issues has been substantiated and either accepted by the insurer or a matter for this
determination.
While AFCA requires complainants to expect a certain level of inconvenience when lodging a
claim, the degree of issues the complainant encountered on this claim were excessive and
avoidable with proper care and consideration by the insurers repairer. The Panel determines
Determination | Case number: 772581 Page 5 of 8
it fair that the insurer pays the complainant $2,000 in compensation for non-financial loss
pursuant to Rule D3.3 of the AFCA rules.
The insurer has agreed to pay the complainant ’ s reasonable expert fees. The complainants
invoice was provided to the insurer on 19 April 2021. If it has not reimbursed this fee already,
it should do so immediately.
Additional benefits payable under the policy
The policy provides the insurer will pay up to $2,000 a Lot/Unit:
“for contributions, levies, maintenance and other fees You are required to pay during the
period Your Lot/Unit is made unfit to be occupied for its intended purpose by Damage to Your
Insured Property that is admitted
This is in essence a refund of normal fees payable by the Complainant during the period the
unit could not be occupied up to $2,000. The panel considers in view of the period that has
now transpired an award $2,000 is fair subject to the complainant providing proof of payment
of the Lot Owners fees.
The policy provides for Lot Owners’ travel costs of up to $250.00 incurred in visiting the
Lot/Unit to consult with claim adjusters and/or building repairers. As the Complainant lives in
Shepparton and the property is in Brunswick the panel considers it fair the insurer pays the
maximum benefit of $250 subject to the complainant having proof of travel.
The policy also provides payment of up to $2,000 for the cost of increased usage, accidental
discharge or additional management charges of metered electricity gas, sewerage, oil and water a
Lot owner is required to pay following damage to insured property. No evidence has been
provided of additional costs incurred although this is likely. If the complainant can provide
proof of additional costs incurred, then the insurer is to pay those costs in accordance with
the policy.
2.4 Why is the outcome fair?
The insurer ’ s decision was unfair
The insurers decision to deny coverage of the batten replacement was unfair and resulted in
significant loss for the complainant. It is fair she receives compensation for her loss of rent
and the reasonable about to repair the claimable damage.
Determination | Case number: 772581 Page 6 of 8
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all the information the parties have provided.
While the parties have raised several issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
A panel determined this matter
Due to the nature of this complaint, we referred it to a panel for determination. The panel
includes:
an ombudsman
a member with significant experience in consumer and small business advocacy
a member with extensive industry experience.
3.2 Significant reports considered
AT report
The insurer organised attendance by AT on 24 June 2020. The findings were:
- Existing timber battens are not defective and do not need replacement to install the
new floor. Some minor issues were evident that should be rectified before installation
(such as some fixings missing and some sections damaged during previous
installation and removals)
- Despite the slab not being level, battens can be packed and sanded to create a level
floor for installation
- Battens over the service trench appeared stable, however final judgement should be
made by installer
- Slab condition did not interfere with previous floor at all which indicates it should be
fine for new floor to be laid, however recommend an engineer to inspect the floor to
confirm integrity
- Battens for this type of floor can be either soft wood or hard wood
- Recommends an engineer to determine the appropriate scope of works and if any
slab remediation is needed.
Overall the expert was unable to definitively say whether the subfloor required remediation,
but confirmed the battens were in sound condition and could be reused for new flooring.
Determination | Case number: 772581 Page 7 of 8
TF Report
The complainant organised attendance by TFR which was completed on 12 April 2020. The
findings were:
- The existing battens were not secured properly when partial floor replacement was
done by the insurers builder
- The distance between the battens is 500mm where the maximum distance should be
450mm
- The battens should be a minimum of 49mm thick, this ensure the flooring can be
secured properly with the correct sized nails
- The builder’s decision to ins tall partial flooring on these battens was non-compliant
- The levelness of the battens/slab are within tolerances for existing floors, the builders
were quoting new floor tolerances that are not applicable
- Battens that span the void completely are compliant as they are supported on either
side of the void
- The concrete pad in the second trench is at the required level to support the existing
batten, replacement battens can be installed in the same position
- The void by the front door has a batten running perpendicular to the other battens in
the house, this batten is not fixed
- Battens in this area should be replaced to run the full length of the floor and the
perpendicular batten should be removed
- The concrete pad in this area is functional and any levelling issues can be addressed
by plaining or packing.
In summary, the expert disagrees the slab or concrete pad require repairs. They believe the
battens require replacement as they are not spaced correctly or the correct size, and any
levelling issues can be addressed by planning and packing the replacement battens.
In an email from TFR to the complainant, TFR confirms:
- The manufacturers installation instructions take precedence over the Victorian
Building Authority
- The manufacturers guidelines allow for a level variation of the slab of no more than
3mm over 3m
- Any level variation of the joists can be remedied by planning and packing
- The Victorian Building guidelines require builders to raise any known issues with the
owner before repairs begin, as the floor level should have been known before repairs
begun, the builder has a responsibility to rectify the issue and complete repairs
- The thickness of the batten does not allow enough space for nails to be driven at an
appropriate angle to allow for serviceability and future sands
- Hardwood battens provide the thickness required
- Maintains 450mm spacing of battens is required and 500mm is not compliant
PO report
The insurer’s builder provided a report on 25 March 2020. They summarised:
- The slab is out of level exceeding the tolerances set out in the Victorian Building
Authorities guidelines
- Battens are fixed directly to the slab with no grinding or packing completed
- The service trenches in the slab are not compliant as battens hang into the void
- Concrete pads have been installed to support the battens, however they are out of
level and one is failing
Determination | Case number: 772581 Page 8 of 8
- To lay the floor, removal of battens and re-levelling of the concrete pads is required
Australian standards excerpt
The insurer provided an excerpt from the Australian Standards referencing joist spacing in
new hardwood floors. The maximum distance listed is 520mm. This indicates the current joist
spacing (500mm is adequate).