Text of the determination
Determination
Case number 770538
Financial firm Insurance Manufacturers of Australia Pty Ltd
Determination | Case number: 770538 Page 1 of 27
Case number: 770538 25 January 2022
1 Determination overview
1.1 Complaint
The complainants lodged a claim under their home insurance policy with the financial firm
(insurer) on 30 September 2019 for damage caused by a water pipe leak.
The insurer conducted inspections and informed the complainants the claim was accepted
however, a 6-month drying period was required.
The insurer reviewed the claim between April and May 2020 and informed the complainants
that the extent of damage caused by the leak is 30% of damage to two bedrooms and a
bathroom. It says available information shows other damage sustained across the building
was mainly „due to soil and foundation movement and ineffective civil draining‟ and other
factors excluded from cover.
The complainants disagree with the insurer‟s decision. They say:
the insurer‟s initial advice was that the claim was c overed
reports from their plumber, engineer, builder, underpinning contractor and geotechnical
engineer show the leak caused building foundations to destabilise, resulting in substantial
structural damage
the $151,744.50 cash settlement proposed by the insurer is insufficient
the insurer should indemnify them in full for all damage.
Additionally, they suggest the insurer delayed and mishandled their claim and should
compensate them for indirect and non-financial loss consequently.
1.2 Issues and key findings
Did the insurer mislead the complainants?
No. While the insurer advised the complainants of its acceptance of the claim in or around
November 2019, this does not constitute a blanket admission of its liability for any and all
damage to the property. It was always entitled to assess its liability in line with the policy
terms and available expert information.
Is the insurer required to increase its settlement offer?
Yes, to $182,093.4 0. The panel considers the proposed cash settlement of 50% of costs
based on the complainants‟ builder and under - pinner‟s quotes is fair and reasonable.
However, the insurer is to pay an additional uplift of 20% to take into account
contingencies/variations which may occur once repairs commence.
Should the insurer pay indirect financial loss claimed?
For the reasons set out under section 2.3 the insurer is not required to cover any further
temporary accommodation costs as indirect financial loss but is to pay 50% of costs to
remove and store contents.
Determination | Case number: 770538 Page 2 of 27
Should the insurer compensate the complainants?
Overall, the insurer did not unreasonably delay or mishandle the claim. However, the insurer
did not take adequate steps to address safety concerns raised by the complainants earlier in
the claims process. This is likely to have caused the complainants stress, and inconvenience.
It is fair that the insurer pays the complainants $2,000 non-financial loss compensation.
Should the insurer cover any other costs?
The insurer is not required to cover any legal costs as the complainants have not shown they
were incurred, or that legal assistance was necessary in these circumstances.
The complainants‟ reports have assisted their claim/complaint. The insurer is to pay the cost
of the reports ($4,989) plus interest.
1.3 Determination
This determination is partly in favour of the complainants. If the complainants accept this
determination, then within seven days of notification of acceptance the insurer is to make the
following payments to the complainants:
$182,093.4 0 for the cost of repairs
$2,400 to remove and store contents
$2,000 compensation for non-financial loss
$4,989 for expert reports
interest on $4,989 pursuant to section 57 of the Insurance Contracts Act 1984 (Cth) from
the date of payment of the reports until settlement.
Otherwise, the insurer is not required to take any further action in relation to the claim or the
complaint.
Determination | Case number: 770538 Page 3 of 27
2 Reasons for determination
2.1 Did the insurer mislead the complainants?
Complainants say insurer led them to believe claim was accepted in full
The complainants say the insurer cannot decline the claim (wholly or in part) because it
informed them the claim was accepted during a telephone call in November 2019. The
complainants consider the claim acceptance unequivocal and say the insurer‟s subsequent
correspondence supports their position.
Insurer’s liability for claimed loss/damage determined by policy
General insurance policies do not cover all eventualities. The terms, conditions and
exclusions which apply to cover are contained in the Certificate of Insurance (COI) and
Product Disclosure Statement (PDS) which together form the contract of insurance.
The panel has considered the legal doctrine referred to by the complainants and is familiar
with the caselaw relied on by the complainants. The panel does not agree this issue provides
a remedy to the complainants in all the circumstances of this claim.
Acceptance of any claim is subject to the contract of insurance. The complainants are aware
of this; in their own submissions they say they seek payment/indemnity as per the policy
terms and conditions.
Material does not show complainants were misled
The panel has reviewed the available information particularly the insurer‟s claim file notes and
correspondence referred to by the complainants. The information shows an acceptance of the
claim; this not in dispute.
The file notes show the male complainant contacted the insurer on 27 November 2019 to
follow up the claim. During that conversation he was informed the insurer‟s engineer‟s report
had been received which confirms damage had occurred due to several factors including the
leaking pipe. The insurer‟s notes say: „[a]s the pipe has been a main cause of damage we
would therefore cover the claim‟.
The claim file notes the leaking pipe has been repaired by the complainant and that the
insurer would return the engi neer‟s report to its assessor to complete a scope of works. The
insurer also advised the complainant the engineer recommended repairs commence after a
six-month drying out period.
Having considered the available information and the submissions of the parties, the panel
does not consider this to be an acceptance or an election that any and all damage to the
building irrespective of the cause or the policy terms would be covered. The panel does not
consider the available information establishes the insurer made an election to not exercise
the rights it has under the policy to rely on policy exclusions (if applicable) or to argue the
proximate cause of all the damage was not the leaking pipe.
Even if the complainants could establish they were misled, the available information does not
show they incurred loss as a direct result of reliance on the alleged misleading information,
prior to (or after) being informed of the extent of damage the insurer considers it is liable for.
Determination | Case number: 770538 Page 4 of 27
The complainants say they suffered detriment in reliance on the alleged misleading
information by remaining in an unsafe home. Even if this was accepted, the panel does not
accept the remedy is that the claim is paid in full.
2.2 Is the insurer required to increase its settlement offer?
Policy coverage
The complainants‟ policy documents show their policy covers insured events including „water
and oil leaks‟. Accidental damage cover is also available where an insured selects this option.
The complainants‟ COI shows they did not select the accidental damage option. Cover is
subject to conditions and exclusions in the PDS. Extracts from the relevant policy wording is
provided in section 3.2 of this determination.
Onus on complainant to establish valid claim
The complainant must show on the balance of probabilities (i.e., that it is more likely than
not), the loss or damage claimed occurred in circumstances for which the policy provides
cover. This is known as establishing a valid claim.
It is only if the complainant establishes a valid claim, that the burden shifts to the insurer to
show it is entitled to rely on a policy exclusion or is otherwise entitled to decline cover for the
loss/damage.
The insurer accepts there was a leak as reported and that the leak caused some damage to
the buildi ng. However, the complainants‟ onus to establish a valid claim extends to showing
all loss or damage claimed was caused by an insured event.
Evidence of pre-existing cracking and movement and other causes
The complainants do not dispute there were pre-existing cracks to the home. Their initial
complaint submission to AFCA includes that they:
purchased the home in 2005 and that at the time of purchase, there were minor cracks in
the main section of the home which was consistent with the age of that section (over 100
years old).
appointed a structural engineer to inspect the cracks in 2008. The engineer provided
verbal advice that the type of cracks all through the home was common in the area and
changed with the season. They say the engineer also advised them to ensure the local
Council installed a tree root barrier at the front of the property; this occurred in 2010.
However, they say there were no significant changes to the cracks in the main section of the
home until around August/September 2019 and new cracks also started to appear in the
annex (a 50-year-old building addition). They say previously minor cracks in the main section
of the home “widened substantially” and structural changes became evident.
The complainants also say:
the plumber they appointed when the cracking appeared found and repaired a leak to the
east side of the property believed to have caused water damage to the footing/foundations
engineering and other expert opinion they subsequently obtained confirmed among other
things that recent cracks in the eastern wall was due to movement caused by the leak.
The panel notes a photograph taken of the office in 2018. Otherwise, the panel notes the
complainants have not provided any information such as pre-purchase reports or any
Determination | Case number: 770538 Page 5 of 27
statement from the engineer from 2008 to show the condition of cracks within the home at the
time (or at any time prior to the leak event which is the subject of this complaint).
Insurer says damage is not largely due to leak event
The insurer says expert evidence obtained shows there was existing cracking to the insured
building caused by several factors. It says it is entitled to limit its liability under the claim as
proposed because there was existing major masonry/structural damage to the western and
eastern walls of the building and the leak only caused some additional movement.
Among other things the insurer says the reports show:
the building was in a general deteriorated condition
the building had damage consistent with aged foundation movement
there was poor drainage at the premises
the pipe had likely been leaking for an extended period.
The insurer says its engineer (RC) confirms 70% of damage to the accepted rooms was due
to poor civil drainage and other stated causes with the leak contributing to about 30% of the
damage. The insurer says the available information does not establish the remaining damage
was caused by the leak, rather it argues one or more excluded factors caused the damage.
Parties provided expert opinions on cause and extent of damage
The parties obtained and provided numerous reports from experts/trades/assessors on the
claimed damage, which are summarised in section 3.4 of this determination.
The complainants provided a report from builder (TD). TD‟s report shows it inspec ted the
premises on 23 September 2019 and found evidence of a recent leak as soil was still wet and
mushy around the leak. TD also noted bowing/settlement of brickwork on the north side of the
eastern wall of the building as well as sharp edged cracks which TD says shows the cracking
was recent.
Reports from the insurer‟s builder (UB), leak detection expert (TB) and engineer (RC)
following their attendance in early October 2019 confirm some damage has occurred which is
likely due to the reported leak. However:
UB‟s report includes that masonry and structural damage, and pre -existing cracks were
observed which were consistent with aged foundation movement.
TB reported inadequate drainage at the premises and estimated the damage it observed at
the premises had mostly occurred over time and the cause of water entry to the family
room is also from age and the deteriorated roofing.
Although RC did not conduct soil testing at the premises, it assumed the soil profile/class at
the insured premises was likely H1 with free swelly values ranging between 40mm and 60mm
based on his knowledge of the area. In conjunction with the level of survey it completed, RC
concluded issues (movement and cracking) at the premises relate not only to the leaking pipe
but to ineffective civil drainage, natural soil movement and tree drying effects. In reaching this
conclusion RC points out (and is supported by photographs and Google Street view):
subsidence has been occurring adjacent to the south-eastern most bedroom for an
extended period. This area is where the pipe was reportedly replaced
stormwater ingress into the footings of the building (due to drainage issues), as well as the
effect tree roots on moisture levels are “causing subsidence along the western external
wall” where the masters‟ and l iving/dining rooms are located
considering the age of the building and other observations, natural soil movement has
occurred and contributed to uneven floor level, resulting in damage across the building.
Determination | Case number: 770538 Page 6 of 27
RC said the percentage of damage from the leak is approximately 30% to 2 bedrooms and
bathroom; the remaining damage across the building was the result of general soil
movement, poor drainage, effects of tree roots and general deterioration (to varying degrees).
RC recommended a 6- month drying period and noted that „[t]he ceiling plaster does not
appear to currently be at risk of falling; however, the cornices should be removed immediately
to prevent the risk of them falling‟.
Following the drying period, UB reattended the premises. Its report of 8 April 2020 includes
that it found visible evidence of severe structural damage which was causing cracking and
collapse to ceiling in kitchen, dining and family room, a bay window and east elevation wall.
UB noted the „extremely poor‟ overall condition of the home however, recommended that
engineering opinion be obtained about the cause. UB also noted there was „high OH&S issue
and risks‟ and recommended the property be vacated.
RC re-attended the property twice in May 2020. Following its reattendances, it provided a
report including a level survey. RC says the survey showed little to no movement since its
initial attendance including in areas near the reported leak. RC also noted that other than a
bulkhead above the office space, there was also no change to cracking it previously saw.
RC concluded that movement which occurred was within the expected limit for the home on
H1 soil and considered minimal movement it observed meant the founding soil under the
dwelling was stable. RC did not consider the eastern masonry wall to be at risk of immediate
collapse but said the rotation may worsen over time and recommended its reconstruction.
In relation to the western wall/side of the building, RC maintained that ineffective civil
drainage, the cycle of stormwater ingress into the soil and then drying (including the effec t of
tree root on moisture) caused the damage. Further, it says the drainage issues have caused
movement in roof members and other damage observed. RC maintained the leak had not
contributed to any damage beyond the two bedrooms, bathroom, and adjacent external wall.
The complainants disagreed with the fin ding and the insurer‟s proposed settlement based on
30% of the estimated cost of repairs to the rooms identified. They provided a letter from their
engineer addressing the findings in RC‟s report. Notably, their engineer (TD) utilised the floor
level completed by RC and says this along with other information obtained as well as
observed shows a major portion of damage, assessed at approximately 75%, was due to the
leak contrary to the 30% of damage to limited areas in RC‟s report.
In reaching its conclusions TD says:
floor level drop of 30mm at eastern wall bedroom (water leak was on east side of building)
water will “seek the lowest point to flow to” with the “trench dug for the strip footing” being a
perfect channel
water has “run along/under the strip fo oting that supports the south wall of the master
bedroom and bedroom and spreading under the west side of the wall” (where there is a
66mm drop below the datum point) “indicating that water has ponded under the north -west
corner of the living room.
because of the size of the tree, tree roots unlikely to account for enough shrinkage to
66mm drop recorded in floor level
leak caused reduction in bearing capacity of the soil and resulted in footing subsiding and
rotating
The complainants obtained further input from under pinner (PP) and geo-technical engineer
(DM). They say these opinions along with previous reports sufficiently shows that the
Determination | Case number: 770538 Page 7 of 27
insurer‟s liability exceeds what it agreed to and that it should indemnify them fully in line with
the policy terms.
The panel reviewed the additional information from PP. It notes that PP provided a quote for
underpinning in which it says the east wall had significantly moved and was in danger of
collapsing upon further drying of underlying soil. PP does not address the cause of damage to
the walls, however, says underpinning was required due to age of property and the fact that
existing foundation was likely of poor quality.
The scope of DM‟s report included investigating the cause o f distress to the building. DM
conducted soil testing and confirmed the soil profile at the premises was „very wet silty clay‟. It
found the home was on „blue strip footings founded at a depth of approximately 600mm‟. DM
says the bearing capacity of the clay soil was compromised by the reported leak in the area
(east) and caused moderate to severe cracking. DM concluded the recent distress was due
to:
differential heave of reactive clay soil in the middle section of the east wall (original section
of the building) from increased moisture due to leak
horizontal cracking on brick on eastern wall is characteristic of heave in footing area and
“when a section of a footing is subject to localised heave, it causes that section of the
footing to move upward, which results in the brick work on either side going into tension,
which often causes horizon tal cracking in the brick work”
soil beneath north-eastern section of building is still very wet (due to leak incident) and
reduction in bearing capacity in the east section has likely caused some distress to the
building and accounts for recent cracks over entire building
movement likely transferred via roof structures to the west side of the building and service
trenches adjacent to east side of house has likely compounded this
„ While most of the water damage to the ceilings is likely to have been caused by the recent
movement of the footings as outlined above, it is also likely that some of the water ingress
is partly a function of age-related degradation and a lack of ongoing, effective
maintenance ‟
level of distress also partially influenced by „relatively brittle nature of solid brick/solid
plaster type construction‟ and lack of adequate brickwork articulation in brick cours e above
windows and doors which means the visible distress is higher than what would occur with
more flexible construction types.
Insufficient evidence to show majority of damage caused by leak
It is not in dispute the water pipe leak resulted in damage to the building as discussed above.
The issue in dispute is to what extent the leak caused the claimed damage.
The panel accepts the experts relied on by both parties are suitably qualified to report on the
cause and extent of damage to the building and that the reports have followed their own
observation and testing as well as consideration of available information or input from other
experts.
The panel has carefully reviewed the reports with particular attention to those completed by
the engineers and DM. While the reports address issues with the building, their possible
causes and seek to reach conclusions about the extent of damage attributable to the leak, the
panel consider they do not sufficiently show all/majority of damage to the home was a result
of the leak. Further, these reports do not support the complainants‟ submission that the home
cannot be repaired and requires a complete rebuild due to damage caused by the leak.
Determination | Case number: 770538 Page 8 of 27
Notably:
the available evidence (including photographs) confirms the home was in an aged
condition, and had suffered long-term ongoing issues, separate to the leak
while DM says the damage was caused by leak, it reported following its inspection several
months after the leak, that soil beneath north-eastern section of building is still very wet
due to leak incident. This does not support a conclusion that wetness reported was due to
the leak. DM does not explain why the soil would still be very wet after the time that had
elapsed since the reported pipe leaked and had been repaired
while DM suggests movement of soil/footing where leak occurred likely transferred via roof
structures to the west side of the building, the panel considers there is insufficient evidence
or analysis of how this has occurred
DM confirms ongoing degradation, age, and lack of ongoing effective maintenance have
contributed to ceiling damage, while also saying movement due to the leak had mostly
caused the damage.
Even if the panel accepted DM has sufficiently shown how the conclusions about the cause of
damage in all areas of the home was reached (and it does not) the preponderance of the
evidence does not show the leak rather than the other factors were the proximate (or the
dominant or effective) cause of most damage to the property as claimed.
Further, the panel does not find the 75% attribution by TD sufficiently convincing. TD does not
sufficiently consider the fact all the western side of the house‟s levels are low and the
influence of the ineffective civil drainage on the western side of the house referred to by RD.
Additionally, the methodology adopted by TD to arrive at 75% is insufficiently persuasive. In
view of all the other issues, to simply assert that 75% be attributed to the leaking pressure
pipe (i.e., 66-17 = 49mm of the 66mm approximately) lacks compelling analysis.
As explained ab ove, the complainants‟ onus extends to showing all damage/loss claimed was
caused by the claimed event. The panel accepts it is reasonable that the complainants
provide sufficient evidence of the condition of the home prior to the leak in support of their
position about the extent of pre-existing cracks and movement. This is particularly crucial
given the information available suggests movement and damage across areas of the home
(other than the two bedrooms and a bathroom on the eastern end) probably pre-dates the
claimed leak and were caused by the other factors such as inadequate drainage as described
in the insurer‟s reports.
In all the circumstances, based on the available information, the panel considers an offer
based on a 50% contribution by the insurer is fair.
Policy allows insurer to decide how to settle claim
Under the terms of the policy, if the insurer agrees to pay a claim, it will decide whether to
repair/rebuild the part of the home that was damaged or pay the complainants the reasonable
cost to repair/rebuild the home.
The panel accepts the insurer is entitled to exercise this discretion under the policy terms
however, it is required to exercise such discretion fairly, reasonably, and consistent with
utmost good faith.
Having carefully considered the available information, the panel is satisfied the application of
the insurer‟s discretion to propose to cash settle was reasonable, given:
not all the damage was caused by the leaking pipe
Determination | Case number: 770538 Page 9 of 27
the insurer‟s builder indicated it would not be abl e to warrant any repairs due to ongoing
issues and condition of the property
there is a history of complaints made by the complainants through the claim process. The
complaints include claim handling and conduct issues and the complainants‟ have clearly
expressed loss of trust in the insurer
while expressing concern that they are not out of pocket with a cash settlement, the
complainants do not appear to be explicitly seeking for the insurer to complete repairs but
seek “indemnity under the policy”.
Complainants say settlement amount is insufficient
Following the 6- month drying period and after further review by the insurer‟s builder and
engineer, the insurer decided only 30% of damage to 2 bedrooms and a bathroom was
attributable to the leak in or around September 2019. It initially offered 30% of a quote
provided by the complainants from their builder MB. The complainants have explained that
this quote was for make-safe and not repairs.
The insurer subsequently offered to pay 50% of repair estimates which the complainants
provided from MB and PP in a total amount of $151,744.50.
The complainants maintain this offer is insufficient, does not cover damage which their
experts say was due to the leak, or make allowance for MB‟s quote being subject to changes
during repair works.
Relying on their builder, the complainants say the house should be knocked over because the
cost of works to replace remedial actions on the house are significant. The complainants rely
on a quotation from MB in the sum of $711,518.14 but say they will accept the maximum sum
AFCA can award ($500,000).
The panel notes the insurer offered further investigation by experts (including any which the
complainants may wish to have in attendance) as an alternative to its proposed settlement
and the complainants have declined this option.
The complai nants rejected the insurer‟s proposal for reinspection to determine scope of works
required due to leak saying:
the insurer‟s engineer had opportunities to assess the premises over about a year
they un derstood the engineer‟s assessment to be independent and now question this
given the insurer‟s suggestion that further „independent‟ assessments occur
they have lost trust in the insurer and/or its experts to properly deal with the claim
there are reports from three engineers, two plumbers and two builders. These should be
sufficient for the insurer to properly assess its liability.
The panel has considered the complainants ‟ reasons for declining both the settlement offer
and reassessment. The complainants also say the insurer has not adequately established
what the cost of repairing the damage is, but the panel notes the insurer based its proposed
cash settlement on the complainants‟ own quotes. Other than the possibility of variation, the
panel is satisfie d it is fair to base the settlement offer on the complainants‟ own material.
Insurer’s proposed settlement plus 20% uplift is fair in the circumstances
Under section 13 of the Act, parties to a contract of insurance (the complainants and insurer)
are required to act towards one another with utmost good faith.
The insurer does not consider the available reports which it says includes conflicting opinions
about the percentage/proportion of damage from the leak, sufficient. To settle the
Determination | Case number: 770538 Page 10 of 27
claim/complaint, it proposed reassessment of the premises to definitively establish
apportionment of damage or pay 50% (or $151,744.50) of the complainants‟ total repair
quotes. It offered this negotiated amount although it considered the quotes included
maintenance items which are excluded from cover.
The panel notes the amounts in the repair quotes include all the make safe works action,
long-term remedial building work without the need for variation and the cost to underpin both
the east and west walls.
As discussed above, t he panel does not agree that the insurer‟s proposal is unsubstantiated
given it is based on quotations obtained by the complainants themselves. It is not uncommon
for unexpected/unforeseen work to become evident during repairs; this is always a
consideration irrespective of whether the insurer or complainants appointed the builder and
does not render the quote invalid.
In view of the above, the panel considers the insurer‟s reliance on the complainants‟ available
repair quotations fair and reasonable. The panel has carefully considered all the available
information. Save for MB, none of the expert opinion support the contention the house is a
total loss which must be demolished and rebuilt because of damage from the leaking pipe.
Insurer to pay the complainants a total amount of $182,093.4 0
The panel acknowledges the complainants‟ concern that a cash settlement transfers risk of
the repair process to the complainants. Where an insurer chooses to cash settle a claim then
the panel accepts it is fair the insurer makes an allowance for contingencies/variations which
may occur in the repair process.
In all the circumstances, the panel is satisfied it is fair the insurer pays an additional
$30,348.9 0 (being 20% of $151,744.50 ) in addition to the $151,744.50 offered to take
account of contingencies/variations which may occur once repairs commence.
In short, the insurer is to pay to the complainants a total payment of $182,093.4 0 to settle the
claim and the complaint. The panel has made no allowance for statutory interest in the
settlement sum because it has allowed a 20% uplift. Further, the panel is not satisfied the
insurer has unreasonably withheld payment in view of its offer being open for acceptance
since 29 June 2020.
2.3 Should the insurer pay indirect financial loss claimed?
Insurer paid policy entitlement for temporary accommodation
The complainants are seeking further payment for indirect loss for further rental costs they
say they have incurred due to the time this matter has taken to resolve.
They say the insurer should pay the maximum indirect loss which AFCA can award ($5,000)
because of its handling of the claim which they consider has been poor.
The insurer arranged for and/or covered the complainants‟ temporary accommodation costs
from April 2020.
The insurer continued to cover temporary accommodation for the remaining period of policy
entitlement (12 months) while attempting to negotiate settlement of the claim.
The insurer communicated its final decision to the complainants in June 2020. While the
complainants are entitled to dispute its decision, it is unreasonable to conclude the insurer is
Determination | Case number: 770538 Page 11 of 27
responsible for any further accommodation costs while the complainants continued to pursue
the claim/complaint but refused reasonable options which were put forward to try to resolve
the claim/complaint.
As will be explained below, the panel does not consider there has been overall poor claims
handling by the insurer. Consequently, the insurer is not required to cover any indirect
financial loss (for temporary accommodation) claimed by the complainants.
Insurer to pay complainants $2,400 for removal and storage of contents
The panel notes the relevant policy benefit for temporary accommodation allows not only for
temporary accommodation costs under buildings insurance but also allows for the cost to
remove and store contents and then return them to the home.
The parties have not addressed this policy benefit.
Item 1 of MB‟s quote allowed for “ All of clients‟ belongings to be moved out, packed and
stored for a 4-month period. Estimated cost $4, 000 including GST”
The panel considers it is fair for the insurer to indemnify the complainants for this policy
benefit. Adopting its earlier analysis, the panel is satisfied it is fair the insurer pays to the
complainants $2,400 for this policy benefit (calculated as 50% of $4,000 +20% uplift).
2.4 Should the insurer compensate the complainants?
AFCA can award compensation for insurer’s conduct in some circumstances
Where a complainant raises issues with the insurer‟s handling of a claim/complaint or its
conduct, AFCA will consider whether the insurer acted in accordance with its obligation under
the Act or General Insurance Code of Practice (Code).
For our purposes compliance with the Act/Code are not distinct issues to be considered
separately in relation to claims handling; they are appropriately addressed by answering the
question whether the insurer mishandled the claim or caused unreasonable delay.
Where AFCA finds an insurer has not conducted the claim appropriately or failed to act in
accordance with relevant Act/Code we consider whether an award of non-financial loss
compensation is appropriate.
Under its Rules, AFCA may award compensation (capped at $5,000) for non-financial loss
where complainants have suffered an unusual degree or extent of physical inconvenience,
time taken to resolve the situation or interference with the complainants‟ expecta tion of
enjoyment or peace of mind.
Insurer did not unreasonably delay in making claims decision
The complainants say the insurer failed to act towards them with utmost good faith as
required under section 13 of the Act, mishandled the claim, and did not meet obligations
under the Code.
The Code allows an insurer to correct any errors made during a claim if it informs the insured
of the error or change as soon as possible. As such, any changes in the insurer‟s position
through the course of the claim (which the panel notes have occurred based on additional
information) does not of itself constitute a breach under the Act or Code.
Determination | Case number: 770538 Page 12 of 27
The insurer formally communicated its claims decision to the complainants by letter dated
15 May 2020. This was approximately 8 months after the claim was lodged on 30 September
2019; however, a 6-months drying period (approximately until 30 March 2020) needed to be
allowed following the pipe leak. There is no dispute the insurer clearly informed the
complainants of the drying period requirement.
Following the drying period, UB reviewed RC‟s report and provided variations and a report in
April 2020. The insurer subsequently made its claims decision. Other than the recommended
drying period, there is no evidence of extended periods of inaction by the insurer.
The panel has carefully reviewed the available information and does not accept there was
unreasonable delay. The time taken was reasonably to be expected given the circumstances
of the loss and drying period required (there was not much the insurer could have done until
the drying period elapsed).
The panel also notes that the complainants maintain the insurer did not act in good faith
because it kept changing its position with no real evidence to back the change.
The insurer made a claims decision in May 2020. It subsequently made amendments to its
assessed cash settlement offer in June 2020 to negotiate resolution of the claim. The panel is
not satisfied on the information provided if the insurer‟s conduct breache d the Act or the
Code.
Fair the insurer pays $2,000 non-financial compensation
The panel notes the time taken to review and address the concerns about the home‟s safety
was not optimum.
The insurer did not investigate safety concerns earlier in the claim although it appears to have
been first raised by UB in October 2019. While it arranged for this to be investigated after
prompting by the complainants, this did not happen until UB‟s re -attendance in early April
2020.
The complainants say the uncertainty and concerns about safety impacted on them
negatively particularly given the location of their son‟s room in the damaged area. The panel
accepts this would have caused the complainants stress, inconvenience and would have
interfered with their expectation of enjoyment or peace of mind.
The panel notes the insurer accepts a level of inconvenience to the complainants due to the
time in which the matter remained outstanding. In March 2021, the insurer offered $2,000
outside of policy entitlements in acknowledgement of delays and inconvenience which offer
was to remain open for 21 days.
The panel acknowledges the 21 days has long expired since the offer was made.
Nonetheless, taking all matters into account, and, the failure to investigate the safety
concerns sufficiently and promptly, the panel considers it fair that the insurer pays the
complainants $2,000 non-financial loss compensation.
2.5 Should the insurer cover any other costs?
Under its Rules, AFCA can require insurers to reimburse complainants for costs incurred in
making a complaint. This may include legal costs, expert report fees, or travel expenses. If a
complainant asks the insurer to contribute to these costs, we will consider whether they were
reasonable and whether they helped resolve the complaint.
Determination | Case number: 770538 Page 13 of 27
We try to make our service accessible and understandable, without any need for legal
representation. If a complainant chooses to be legally represented, AFCA will generally
require a complainant pay for these costs. However, we may still require the insurer to
contribute to legal costs if the complaint raises complex legal issues, or if the complainant
could not have reasonably handled the complaint without getting legal advice.
Legal assistance not required/necessary to pursue claim and complaint
While the claim presented some complexity in relation to the technical issues surrounding the
cause of damage, the panel does not consider the complainants‟ claim and complaint
presented complex legal issues. The reports and the documents (including the PDS) are
reasonably clear and would not reasonably require legal input.
Further, while the complainants seek payment for legal advice they say was obtained in
relation to the claim and/or complaint, they have not provided any material showing:
they obtained legal advice
any costs incurred in doing so.
In any case, available information shows the complainants were familiar with the issues and
were reasonably able to deal with the claim and complaint themselves.
Consequently, the panel does not consider any legal costs (if incurred) were reasonably and
necessarily incurred to pursue the claim or complaint. While it was always open to the
complainants to engage a solicitor or obtain legal advice, the panel is not satisfied the
available material establishes legal advice was necessary nor that it has been shown to have
assisted the claim/complaint.
The insurer is therefore not required to contribute to any legal costs.
Insurer to pay $4,989 and interest for the complainants’ expert reports
The complainants‟ geo -technical report includes soil testing result which have been
considered by the insurer in its assessment. AFCA considers this report and other reports
relied on by the complainants were useful and provided some assistance in making this
determination. Further, the panel considers it is fair for the insurer to pay the complainants‟
expert report costs in view of the expert reports obtained by it and in view of the technical
nature of the issues surrounding causation.
The complainants claim $4,989 for the cost of expert and consultant fees. The panel is
satisfied it is fair the insurer meets this claim.
In addition, assuming the complainants paid for the reports, the insurer is to pay interest
pursuant to section 57 of the Act, from the date of payment until the date of settlement on
$4,989. Should the complainants accept this determination then within seven days of
acceptance the complainants are to provide the insurer with relevant proof of payment of the
reports (tax invoice/receipt) so the interest component can be calculated.
Determination | Case number: 770538 Page 14 of 27
3 Supporting information
3.1 The AFCA process
AFCA’s approach to this complaint
This complaint has been determined based on what is fair in all the circumstances, having
regard to the legal principles, applicable industry codes or guidance, good industry practice
and previous decisions of AFCA or its predecessor schemes (which are not binding).
A full exchange of the relevant information has taken place between the respective parties.
Each party has had the opportunity of addressing any issues raised. All the provided
information has been reviewed and considered. The parties have raised numerous issues in
their submissions to AFCA. However, commentary in this determination is restricted to those
issues considered relevant to the outcome.
It is an accepted principle of general insurance law that the insured bears the onus to
establish on the balance of probabilities that they have suffered a loss caused by an event to
which the policy responds. This is known as a prima facie or valid claim. Once so established,
the onus shifts to the insurer to prove on the balance of probabilities that an exclusion applies
if it seeks to deny or limit its liability for the loss.
This complaint was determined by a panel
Due to the nature of this dispute, it has been referred to a panel for determination. The panel
comprises the ombudsman, a member with significant experience in consumer and small
business advocacy and a member with extensive experience in the insurance industry.
The panel has decided this complaint based on what is fair in all the circumstances, having
regard to legal principles, applicable industry codes or guidance, good industry practice and
previous relevant determinations of AFCA or predecessor schemes (which are not binding).
How we assess complaints
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence. When we assess complaints, we consider available
documents, the recollections of the parties, and all relevant circumstances. We give more
weight to documents created at the time the events occurred. If there is no relevant
documentation, we will decide what is most likely to have occurred based on the information
provided to us. If there are conflicting recollections and these are evenly weighted, we may
find that a claim cannot be established.
Caselaw and proximate cause
Case law establishes:
The proximate cause of the loss is the dominant or effective or operative cause of the loss
whether or not that be the last in time or the sole cause.
If there are several causes operating contemporaneously, each must be examined for the
qualities of reality, predominance and efficiency as the active, efficient cause that sets a
relevant chain of events in action. If one cause would have caused the harm in any case,
and the other would not have done so in the absence of the first, the first is the proximate
cause.
A common-sense approach is taken to determine proximate cause.
Determination | Case number: 770538 Page 15 of 27
3.2 Policy terms
The relevant policy extracts are referred to in the correspondence between the parties and in
the insurer‟s Notice of Response. Both th e policy document and the Notice have been
exchanged with the complainants.
Document/page Wording
PDS/ page 33 Water and oil leaks
Buildings Insurance
Cont ents Insurance
If loss or damage is caused by water or oil leaking or escaping from an item
shown here.
Covered
• water leaking or escaping from:
–– house gutters, drainpipes or pipes
–– sanitary fixtures – for ex ample, baths or toilets
–– appliances – for example, washing mac hines or dishwashers
–– waterbeds
–– aquariums
–– water tanks
–– swimming pools
–– oil leaking from a fixed heating system or sealed portable heater
–– costs to locate the cause of damage (if we agree to pay these costs before you
make any arrangements).
Not covered
• water leaking or escaping from a shower rec ess or shower base
• co sts to repair or replace the item that the water or oil leaked or escaped from
PDS/Page 45 Temporary accommodation for homeowners
Buildings Insurance
…
If a listed event causes loss or damage to your home and we agree you can‟t live
in it and you need to move out so it can be repaired or rebuilt.
We pay this benefit on top of your Buildings sum insured.
Covered under Buildings Insurance
• costs for temporary accommodation that we agree are
reasonable and appropriate for you, your family and your pets
that you normally keep at your site
• any additional living expenses that we agree are appropriate
• costs to remove and store your contents and then re turn them to
your home.
Conditions
• you must have lived in your home permanently before the listed event took place
• we must agree to pay the costs before you make any arrangements
• we won‟t cover costs caused by unreasonable delays in repairing or rebu ilding
your home.
Determination | Case number: 770538 Page 16 of 27
PDS/ Pages 62 - General exclusions and your re sponsibilities
There are certain situations when we won‟t provide cover under your policy.
This section outlines the general exclusions that apply to all cover we provide
under your policy.
….
This section also outlines your responsibilities.
You may put your insurance claim or cover at risk if you do not meet your
responsibilities to us.
…
General exclusions for all cover
The exclusions set out in this section apply to all cover under your
p olicy.
What we don’t cover
Loss, damage, injury or death arising from:
…
tree roots
the settling, shrinkage or ex pansion in buildings, foundations, walls or pavements
…
Maintaining and occupying your home
We don't cover loss, damage, injury or deat h arising from:
• faulty design or workmanship
• previous damage that has not been repaired
• …..
• you not maintaining your home in good repair and condition. This
means your home must be watertight, structurally sound, secure
and well maintained
• you not maintaining your site in good repair and condition
• ,,,,,
• you not taking reas onable care to protect your home or contents
against loss or damage.
Your re sponsibilities
…
Co - operate
You must:
…
• co - operate fully with us, even if we have already paid your claim which includes:
–– providing us with all the information, documents and help we need to deal with
your claim
…
–– giving us access to your home for a repairer or other specialist we choose so
Determination | Case number: 770538 Page 17 of 27
they can assess your home.
Prevent further loss or da mage
You must do everything reasonable to prevent further loss or damage to your
home or contents.
Inspections and quote s
If we ask you, you must:
• let us or our representative inspect your home or contents.
3.3 Extracts from expert reports
Record Key points
Insurer’s expert (UB)
Scope of works
Undated
a ttended to make safe cracking bedroom walls and buckling
bedroom ceiling
e astern side copper pipe repaired
u nrelated work – engage specialist to carry out roof repairs
Complainant’s plumber (TE)
13 - 09 - 2019
carried out leak detection service and replaced section of cold -
water supply pipe
cause for the water plumbing to leak below ground is inconclusive
but it has caused substantial damage to the footings/foundation to
the left - hand side including t he left - hand front section which has
resulted the brick wall/ façade to crack and have a lean making it
unsafe.
recommended an engineer is engaged
Complainant’s expert (TD)
Engineer consultant letter
23 - 09 - 2019
attended premises on 19 September 2019 to report on cracking and
movement and provided annot ated photographs of east wall.
reportedly, „copper water supply main had been found to be leaking
recently and has now been by - passed with a new above ground
main‟.
„soil base was soft and mus hy and readil y able to be penetrat ed by
a piece of timber. Water immediately appeared in the hole‟
noted settlement bowing out of east side brickwork, at the northern
(front ) end of the house‟
affected walls have „sharp crack edged indicating recent movement‟
wall move ment is „quite large for new cracking, and it is our opinion
that the water leaking from the mains pressure pipe is the cause of
the localised damage to the house‟
unknown „how far or how deep the leaking water has penetrated the
soil profile, however this should become apparent during the works‟
repair works will include stabilisation of foundation soils and
underpinning of existing house footing. Outer skin of brick wall
needs to be removed and re - set wit h new brick ties fitted across the
wall cavity. Cos t estimate $35,000 to $50, 000 plus extra cosmetic
works about six months after repairs are completed.
soil test recommended in the first instance, to reveal the soil
condition on the east, west and north sides of the building.
Determination | Case number: 770538 Page 18 of 27
Record Key points
large gum tree in front nature strip should be removed or install a
root barrier
Insurer’s expert (UB)
Building report
02 - 10 - 2019
attended and photographed premises 2 October 2019
complainant reported cracks in 100 - year - old house widened mostly
in front (older) part of the building. There were some cracks to the
rear extension (1970s addition) but not as much as the front
complainant had repaired leaking pipe located at the front (east
side) of building two week prior
observed:
> building generally „quite deteriorated however the major
masonry/structural damage was to bot h eastern and western
walls from around halfway back towards the front (north)‟.
> damage consistent with aged foundation movement and possible
additional movement related to leaking pipe
> lea k appears to have added to existing cracks - the extent of
which needs to be established by a specialist
> Annotated photograph 10 notes damage from aged movement to
the western elevation
Insurer’s expert (TB)
Leak detection report
16 - 10 - 2019
conducted pres sure test, CCTV inspection of stormwater and
wastewater systems and inspected roof/gutters for leaks
pressure test passed
no leak detected
CCTV (s ewer) unable to gain access
CCTV (stormwater pipe):
> no evidence of subsoil drainage, adequate surface catchment,
tree root entry
> evidence of broken pipework and drain run on grade
location and extent of damage – front left side elevation (from
plumber cutting up concret e slab), family room ceiling, estimated
the damage is „long term gradual‟
general proper ty condition – aged
cause of damage: previous burst pipe, roof leaks, no sign of subsoil
drainage or surface catchments
roof aged and deteriorated
cause of water entry to family room is from age, deterioration of
roofing
visual inspection of perimeter of dwelling confirmed insufficient
surface catchments and subsoil drainage
Insurer’s expert (RC)
Civil engineering report
06 - 11 - 2019
inspection occurred on 4 October 2019 to provide causation report
and scope of works (SOW)
photographed damage and undertook level survey
describes the damage (see Figure 2) and state of building saying
overall the house was in very poor condition for its age
reviewed reports provided
six months drying out period is required following plumbin g repairs
Determination | Case number: 770538 Page 19 of 27
Record Key points
and civil drainage upgrade
recommended repair identified plumbing leaks in stormwater
system and fill in the missing sections of the paving and without civil
drainage upgrade an appointed builder may not be able to warrant
repairs
plumbing repai rs report edly completed two weeks prior following a
leak. Complainant also advised flas hing above the western side
extension had buckled, allowing water into the ceiling cavity but
water ingress stopped after he weighed the flashing down.
soil classificati on testing not conducted but geological maps for the
property suggest „it is in an area of Sandstone, siltstone, minor
shaley siltstone; thinly and regularly bedded altered to horntels in
vicinity of South Yarra intrusion‟, therefore underlying soil expect ed
to be „class H1m with free swelly values ranging between 40 and
60mm‟
undertook a floor level survey, measured the finished floor levels
throughout the dwelling to identify the gene ral movement of the
foundations
„general finished floor level fell towar ds the middle of the structure,
both in the eastern and western edges. The highest point was near
the eastern edge of the bathroom and low points near the north -
eastern corner o f the south - eastern bedroom and at the north -
western corner of the living area. ‟
„The floor level varied bet ween 18 mm and - 66 mm ac ross the
dwelling, relative to the arbitrary zero. The total variance in floor
level was 84 mm. These levels have been appropriately adjusted to
account for steps and changes in the floor finis hes‟
noted from inspection that subfloor ventilation, maintenance,
material deterioration, watertightness and construction
method/issues were acceptable
civil drainage was not as „effective civil drainage did not surround
the entire perimeter of the dwelling‟.
Concl usion
no evidence of a leak sighted now but „subsidence appears to have
been occurring adjacent to the southeasternmost bedroom for an
extended period of time. Paragraph 13 annotated “ Timber has been
placed under the window frame of the south - eastern bedro om,
indicating the subsidence has occurred over an extended period of
time”. This area also contains part of the pressurised system that
was replaced without being exposed. Based on the information
provided by the Insured and the location of damage, a leak appears
to have been present in the section of pipe that was replaced. This
section was not exposed during the works; therefore, the only way
to confirm this would be to remove the concrete along the eastern
wall, expose the disused pressurised pipe and e xamine it for leaks‟.
„Stormwater appears to be ingressing through the uncapped soil
along the western wall of the dwelling and migrating below the
nearby footings, causing subsidence along the western external
Determination | Case number: 770538 Page 20 of 27
Record Key points
wall. The roots of the trees in the western n eighbouring property
appear to be sucking moisture out of the soil below the master
bedroom and living area, contributing to the damage in these
rooms.‟
„Due to the age of the structure and the pattern of the level survey,
natural seasonal soil movement ap pears to have contributed to the
uneven floor levels and resulting damage across the dwelling‟.
„The ceiling plaster does not appear to currently be at risk of falling;
however, the cornices should be removed immediately to prevent
the risk of them falling ‟.
Caus e of damage including based on area & % caused by leak
> master bedroom, the living area, and the adjac ent external wall:
ineffective civil drainage (60%)
> natural soil movement (20% )
> tree - drying effects (20%)
> bedroom 1, bedroom 2, the bat hroom and the adjacent external
wall natural soil movement (70% )
> a possible leak in the pressurised system (30%)
> dining area and office and the adjacent external walls ineffective
civil drainage (65%)
> natural soil movement (35% )
> kitchen, hallway, and adjacent external walls natural soil
movement (100%)
> recommended neighbour to remove tree near the northeast
corner of the property and the tree midway along the eastern
boundary
> provided scope of works and a percent age of damage allocated
to each cause was defined in the s ummary
Insurer’s expert (UB)
Variation notes
07 - 04 - 2020
Reviewed engineers report provided by insurer and recommended:
„ - The cornices affected should be removed to prevent risk from
them falling.
- Seal the cuts to the stormwater pipe to prevent the stormwater
from escaping.
- The holes along the western wall should be filled in and covered
with concret e.
- The defective roof sheets should be replaced.
- Contact the body corporate of … and request measures be
taken, by removing the 2 trees drawing water away from the
foundations of the property.
Once these steps have been taken, a six - mont h drying out period
is to commence.
- After the drying out period is complete, these steps are to follow -
- Engage a qualified trade to relevel the dwelling. A hatch may
n eed to be cut in the floor for access. Allow a 30 - day settling
period after releveling.
- Inspect the roof and determine where the rafters are located,
prop with timber props as per engineer‟s
Determination | Case number: 770538 Page 21 of 27
Record Key points
report.
- Demolish and rebuild the brickwork to strengthen its
su pporting capabilities. Then paint to match existing.
- Patch all plaster, render, and cornice to the affected areas.
Causation Report .
The engineer has allocat ed different degrees of cause for each
area of the house…‟
As a result of these findings by the en gineer we have det ermined
that the only aspect covered by the leak is 30% to bedrooms 1
and 2 and the adjacent wall. To confirm additional causation by
removing concrete along the eastern wall and exposing the pipe
and examine it for leaks and without this additional testing the
true measure of causation cannot be confirmed
Insurer’s expert (UB)
Attendance report and
photographs
08 - 04 - 2020
visible evidence:
> of severe structural damage causing cracking and areas to
collapse in the kitchen din ing and family‟s room ceiling and full
glass bay window.
> of severe structural damage causing cracking and collapse to
east elevation wall.
> the main roof has severe maint enance issues e.g., deterioration
to external flashing and roof sheets, deterioration to flashi ng in
and around roof mounted sky light.
Conclusion
> „overall condition of the home is in extremely poor, and the
structural damage is severe, and it is not possible for me to
determine what has caused the damage, therefore is
recommended an engineer be app ointed to determine the best
course of action‟.
> „Due to the severity of damage and the present condition of the
home it is my expert‟ opinion there is a high OH&S issue and
risks, it is recommended the owners vacate the property.
Insurer’s expert (UB)
Variation notes
04 - 05 - 2020
review of engineer‟s report shows cause of damage:
> „Bed 1, bed 2 and bathroom - 70% soil movement / (30% possible
leak from water pipe)
> Dining room - 65% civil drainage / 35% soil movement
> Dining room - 65% civil drainage / 35% s oil
> Kitchen - hall way - 100% soil movement
> Master bedroom - living room - 60% civil drainage / 20% soil
movement /20% tree drying roots‟
based on above:
> „damaged areas of bedroom 1 / bedroom 2 and bat hroom have
been allocated 30% coverage due to an insurabl e event of an
escape of water‟.
> „All other areas have no coverage as the damage has been
attributed to soil movement, civil drainage and tree root issues
along with general deterioration of the building‟
Determination | Case number: 770538 Page 22 of 27
Record Key points
> Cannot carry out prescribed works because of pre - ev ent
condition of the building and recommend settlement of the claim.
Essential that stormwater and civil drainage issues are rectified
along with the tree roots from the western side.
> Prepared a total scope of works (total $22,925.83) but damages
due to leaking pipe are $2,214. 84 including GST and builder‟s
margin.
Complainant’s expert (TD)
Engineer consultant letter
29 - 05 - 2020
commented on RC‟s report
reviewed relative floor level in RC‟s report and says that combined
with other information in the report gives a “whole - of - house
picture…of the existing structural condition of the building”
water supply pipe leaked along east side of building where floor
level dropped 30mm at the eastern wall of bedroom 2 and water will
“seek the lowest point to flow to” with the “t rench dug for the strip
footing” being a perfect channel
in present case water has “run along/under the strip footing that
supports the south wall of the master bedroom and bedroom w and
spreading under the west side of the wall” (where ther e is a 66mm
drop below the datum point) “indicating that water has ponded
under the north - west corner of the living room.
tree shown in neighbouring property is no higher than that
property‟s roof and is unlikely to “account for drying shrinkage of the
und erlying clay to equate to a 66mm drop”
says in relation to bearing capacity of soil reducing and “allowing
footing to subside and rotate” that:
> it considers this is what happened at the insured premises
“especially given the localized large drop in floor l evels near the
leaking pressure pipe”
> as there is a “large 66mm drop, the pressure on the house
framing is very large, causing cracking and movement throughout
the ceiling structure and walls”.
contrary to various percentages of movement due to leak assigned
to specified areas in RC‟s report, it “estimates that 75% be
attributed to the leaking pressure pipe i.e., 66 - 17 = 49mm of the
66mm approximately”
Leakage from stormwater pipe can be discounted
In summary, its view is that “the major portion of d amage to the
property has been caused by the leaking water pipe, which has now
been repaired” and the major portions has been assessed at
approximately 75%.
Insurer’s expert (RC)
Civil engineering report
04 - 06 - 2020
re - attendances occurred 15 & 27 May 2020 „to determine if the
dwelling is currently safe to live in, and if not, what impact the leak
has had. Signs of possible rotting prompted a second reattendance
with a builder to inspect the ceiling plaster‟.
on 15 May 2020
> floor - level survey was conducted, and measurements taken at
Determination | Case number: 770538 Page 23 of 27
Record Key points
approximately the same location as previous attendance. Res ult
is that there has been little to no movement of the building
(including in areas near the reported leak) since previous
inspection.
> Also, aesthetic damage around the dwelling did not appear to
have changed however one crack (western end of the bulkhead
above the office space) noticeably widened
> at the external southwestern corner of the dwelling, noted half of
incorrectly graded gutter had detac hed from wall (western h alf of
the south wall), a timber beam protruding from the end of the
southern wall, vines growing inside roof cavity and staining (and
possible rotting) in roof cavity timber.
on 27 May 2020
> met with complainant and carpenter onsite
> hole cut in ceiling wh ere plaster has dropped, and roof cavity
visually inspected.
> found plaster fixings still in place but ceiling plaster had fallen
away.
> also, stains observed in previous inspection identified as tannins
upon closer inspection (tannins occur due to moistur e in treated
timber surfac es over time and is not indicative of damage).
> complainant provided letter from engineer (TD) dated 23
September 2019 and photo of ceiling plaster (near office) dated
15 July 2018 showing no damage at the time.
> reviewed letter fr om TD which shows the pipes which report edly
leaked had been bypassed prior to TD‟s attendanc e, however TD
says soil near pipe could be penetrated wit h timber and that the
leak caused localised damage.
Conclusion
level survey shows „little - to - no movement h as occurred across the
dwelling‟ Based on location and assumed soil type (H1 class) which
is highly reactive „the movement that has occurred in the dwelling is
within the ex pected limits of a dwelling built on H1 class soil. The
minimal movement indicat es that founding soil below the dwelling‟s
interior is stable‟.
damages parts of eastern masonry wall not at risk of collapse at the
time, but it does have a slight lean. „The rotation may continue to
get worse over the following years‟ therefore recommended that the
wall is deconstructed from the top down and rebuilt‟
civil drainage along the western wall of the dwelling is ineffective
and there is a „medium - sized tree was present adjacent to the
southwestern corner‟; these are allowing damage from
> large vo lume of stormwater ingress to the soil at the southwestern
corner of the dwelling, and
> tree pulling out moisture from the founding soil resulting in
„cyclic wetting and drying of the soil below the western wall,
especially near the sout hwestern corner‟
> „masonry wall is not currently at risk of collapsing; however, the
Determination | Case number: 770538 Page 24 of 27
Record Key points
rotation may continue to worsen over subsequent years. It is
recommended that the masonry wall is deconstructed from the
top down and rebuilt‟.
„Although the lean in the western wall is mi ld, it has caused the roof
members to move. This slight movement has caused the ceiling
fixings to move relative to the plaster, causing the fixings to punc h
through and the plaster sheets to sag‟
The leak has not contributed to the damage beyond bedroom 1 ,
bedroom 2, the bathroom and the adjacent external wall.
provided Google Street view and said the crack in the eastern
masonry wall can be seen as far back as 2009.
Complainants’ expert (PP)
Report
15 - 06 - 2020
attended site on 10 June 2020 and quot ed to install 50 underpins
2m deep to exterior walls in the total sum of $137,148
to underpin east wall only with 16 underpins cost $43,180 plus GST
which does not include brickwork or plasterwork
foundation to all exterior walls have moved. This has resulted in
cracking to brickwork
due to age of property existing foundation likely of poor quality and
underpinning will be required to resolve issue
east wall has most significant movement and needs urgent
attention as the wall is in danger of collapsing if “clay in the ground
dry out further, (long periods with no rain)”.
Complainants’ expert (DM)
Geotechnical distress report
28 - 08 - 2020
appointed to investigate soil profile, carry out soil testing and
moisture analysis, report on site features, nature, and level of
distress and if possible, cause of distress, recommend remedial
action
complainants owned the house for about 15 years. They report
some cracking was evident in some sections soon after they
bought. Confirm by our recent site inspection whic h revealed
various stages of previous crack repairs which indicat es some
distress had been occurring in the house over considerable period .
previous distress includes large internal masonry crack that is still
present in the north - western bedroom because of significa nt
gumtree in the nature strip
A different stage of movement and damage developed in the home
and extension in 2019 including water damage in the ceiling and
recent cracking along the eastern and northern eastern section of
the building – edges of crack a re sharp which confirms recent
damage
soil in the area of the leaking pipe is still abnormally wet which
confirms this is the predominant cause of the more recent
movement and distress
based on the natural soil profile encountered at this site, from
previous experience and after considering the appropriate
geological map it is evident that thi s site is located in an area of
Silurian Siltstones.
Determination | Case number: 770538 Page 25 of 27
Record Key points
borehole undertaken - no water table encountered
soil samples analysed for moisture and show „silty clay take n from
borehole one are wet‟ and significantly wetter than what would
normally be expected for the period of the year when the sample
was taken
from bore taken around outer edge of home‟s footing “it is evident
that the original section of this building is supported on bluestone
strip footings founded at a dept h of approximat ely 600 mm. At the
location investigated, the strip footing was obs erved to be founded
on very wet silty clay. It is evident that the bearing capacity of this
clay has been compromised by the reported water service leak in
this area”.
distress to building based on classification under AS 2870 2011 is
moderate to severe with thes e classifications described as:
moderate: “Cracks can be repaired and possibly a small amount of
wall will need to be replaced. Doors and windows stick. Service
pipes can fracture. Weather tightness often Impaired.” Severe:
“Extensive repair work involving breaking out and replacing
sections of walls, especially over doors and windows. Window
frames and door frames distort. Walls lean or bulge noticeably,
some loss of bearing in beams. Service pipes disrupt ed.”
Findings
recent distress in the building a res ult of:
“Differential heave of the reactive clay soil beneath the middle
section of the east wall of the origin al building” due to heave in
reactive clay soil from increased moisture in the following the
reported leak. Horizontal cracking of brick on east side of building is
characteristic of heave in footing area and “when a section of a
footing is subject to loca lised heave, it causes that section of the
footing to move upward, which results in the brick work on either
side going into tension, which often causes horizontal cracking in
the brick work”.
“the foundation soils benea th the north - eastern section of the
original building was still very wet, due to the previous water service
leak in this area” and in this case reduction in bearing capacity of
the foundation soil along the east side of the building is likely to
have caused some of the distress in the buildi ng and explains the
more recent movement and distress evident in various sections of
the building
Further, some of the movement is “likely to have been transferred
via the roof structure to the west side of the house. This issue is
likely to have been comp ounded by the presence of service
trenches adjacent to the east side of the house.”
“While most of the water damage to the ceilings is likely to have
been caused by the recent movement of the footings as outlined
above, it is also likely that some of the w at er ingress is partly a
function of age - related degradation and a lack of ongoing, effective
maintenance”
Determination | Case number: 770538 Page 26 of 27
Record Key points
“the level of visible distress in this building has also been partially
influenced by the relatively brittle nature of the solid brick/solid
plaster type construction, in conjunction with the lack of adequate
articulation, particularly in the brick courses above and below
window and door openings. As this type of building is less able to
tolerate even minor footing movements the level of visible distre ss
tends to be higher than would normally be expected in a more
flexib le type of construction.”
Recommendations include
permanent repairs to water service line to be completed ASAP
entire roof drainage system be thoroughly investigated
root barrier at the front of the building effective and no further works
required
“strong consideration should be given to re - supporting the eastern
side of the building on a system of engineer designed underpins”
Prior to underpinning, important to note likely issues will be
encountered under the original sections of the building as it
“appears to be of discontinuous bluestone strip system which has
little spanning capabilities”. Following underpinning, plumbing work
need to be checked to ensure in good order and concrete p aving
along east side removed and replaced.
after underpinning, time needs to be allowed for moisture content to
reach a relative equilibrium/stability, any short - term stabilisation
work required carried out, and flooring re - aligned. Brickworks
cracks also need to be repaired/reappointed and replacement may
be required for areas where rot ation has occurred. Further window
opening should be adjusted, and internal cracking plastered (or in
some severe instances, sheeting replaced).
“It should be noted that mi nor soil movements due to seasonal
fluctuations are likely to continue to occur beneath this building in
the fut ure. The distress associated with these movements is only
likely to be slight to moderate but can be expected to continue to
occur over the life of the building. Although such movements are
virtually impossible to prevent, footing performance will be
enhanced if all of the guidelines listed in the following Construction
and Landscaping Recommendations sections are followed over the
life of the bui lding.”
Complainants’ builder (MB)
26 February 2020
Met complainants 26/2/20 to discuss remedial building works
Masonry crack to bed one/ bed two and bat hroom require urgent
stitch and prop. Wall dangerous and needs to be addressed as
soon as possible
Roof needs to be propped to take roof load in the event the wall
does go over
Living and dining ceiling need to be battened to the underside
Masonry crack in master bed appears to be forming from overall
ground movement from the water leak. As a result, y ou can view
large caps in roofing and flashing
Determination | Case number: 770538 Page 27 of 27
Record Key points
Perform reinforcing to brick wall in kitchen area
Advise occupants to vacate property budget permitting
Variations may occur to remedial building works as there are a lot
of variables in repairing a structu re: make safe works action
immediat ely $17,480 including GST long - term remedial building
work without need for variation det ermined at strip out phase 1 of
quote $148,8861 including GST excluding pack and storage of
contents.,
Subject to final inspection depending on timing more damage may
arise/movement and may need to reconsider .
Complainants’ builder (MB)
29 July 2020
house should be knocked over bec ause the cost of works to
replace remedial actions on the house are significant
cost projections of the works are provi sional. This means our
proposals in the form of a contract would be allowances only. Due
to the nature of the works, it is highly likely that these methods
would cost more to make the dwelling safe and liveable and al so
protect us as the builder from a warranty perspective. This means
ensuring the building work is to a standard at whic h we can provide
our warranty and are satisfied it will last beyond warranty period.
With the recommendations by engineer we think this is highly
unlikely that the project will run on budget and also be to a
satisfactory standard .
Complainants’ builder (MB)
undated specifications and
draft quote
23 February 21
Building work quoted as per specification document subject to
formal plans en gineering and supporting documentation total
including GST $711,518.40.
3.4 Other relevant material considered and relied on
Parties‟ submissions/emails and all attachments to all submissions/emails .
Parties‟ expert reports .
Photographs and video.
Claim notes.
Scopes of work and quotations.
Correspondence between the parties.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.