Determination 769453

Defective hail repairs to commercial building roof and claim management

FirmHollard
Decided2022-02-16
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$68,200
Non-financial loss$3,000
Amount claimed$163,000
SourceAFCA PDF

Summary

A hail-damaged building's roof repairs by the insurer were disputed as defective, and delays occurred. AFCA ordered cash settlement of $62,000 plus a 10% uplift, $3,000 non-financial loss, and reimbursement of an engineer's report fee and scissor lift hire, but rejected the full replacement roof scope and loss of rent claims.

The insurer must rectify defects from poor workmanship under the policy's lifetime guarantee, but the complainant's expert did not justify full roof replacement over the insurer's expert's assessment.

Issues

Subjects and remedies

business interruptionhome or building damagenatural disasterpay compensationpay non financial lossrefund fees or charges

Related

All Hollard determinations · Find similar determinations

Text of the determination

Determination Case number 769453 Financial firm The Hollard Insurance Company Pty Ltd Determination | Case number: 769453 Page 2 of 12 Case number: 769453 17 December 2021 1 Determination overview 1.1 Complaint The complainant lodged a claim after his building was damaged by hail. The financial firm (insurer) accepted the claim and undertook the repairs to the property. Once the repairs were completed, the insurer requested that the complainant sign off on the completion of the repairs. The complainant would not agree to sign off on the completion of the repairs as he was not happy with the quality of repairs. The complainant has advised that there is significant damage to the building including the roof which still had not been rectified. The complainant notes that since he lodged his complaint with AFCA, the insurer has settled him for the claim to the office. However, the damage to the roof is still not fixed correctly. The complainant has advised us that the roof needs to be re-sheeted as Hollard contractors bent the sheets. The complainant has advised us that it has been four months and his roof is still not fixed. The complainant is seeking for his roof to fixed properly by the insurer. The complainant is also seeking compensation for the delays and for the way the insurer has managed the claim. 1.2 Issues and key findings Has the insurer managed the claim in accordance with the terms and conditions of the policy? Yes. The available information establishes the insurer managed the claim in accordance with the terms and conditions of the policy. The insurer made an offer to settle the matter based upon the cost of sheeting, in the sum of $48,835.33. The insurer has subsequently increased this offer to $62,000. I am satisfied that this sum is sufficient to rectify the balance of the claim. The sum is to be cash settled and the insurer is to pay an uplift of 10% to cover contingencies and loss of lifetime guarantee. Whether there have been any unreasonable delays in this claim? Delays by the complainants to sign off on the original repairs caused delay as they identified further possible repairs. Information on file show correspondence from the complainant later show that the further repairs were addressed and accepted by the insurer in a timely manner. The insurer acknowledged that the level of service warranted non- financial loss compensation and offered $3,000. I consider this amount is appropriate. Why is the outcome fair? The outcome is fair because the insurer has assessed the claim in accordance with the terms and conditions of the policy. Further, the insurer has offered to cash settle outstanding rectification works. Determination | Case number: 769453 Page 3 of 12 1.3 Determination This determination is partially in favour of the complainant. Upon acceptance of this determination the insurer is to pay:  the complainant $62,000  10% uplift of $6,200 to cover contingencies and loss of lifetime guarantee.  The insurer is entitled to deduct any amounts already paid in relation to the $62,000.  Non-financial compensation of $3,000.  Refund the repot of SJ $1,350 excluding GST. (if not already paid)  Scissors lift hire of $445.50 (if not already paid) Determination | Case number: 769453 Page 4 of 12 2 Reasons for determination 2.1 Has the insurer managed the claim in accordance with the terms and conditions of the policy? Circumstances of the complaint There is no dispute the complainant’s property sustained damage because of an insurable event. The complai nant has raised concerns regarding the insurer’s management of the claim following completion of the repairs. Upon notification of the claim, the insurer on appointed builder SK to provide a report and assessment of the damage. SK noted in its report dated 7 March 2019, that storm damage has occurred to the roof as noted below:  hail dented the metal roof sheets  broken through fibreglass roof sheets.  fixtures on the roof which will required removal and reinstallation  Remove and dispose of the foil sarking  Supply and install R3.0 ceiling insulation batts to the entire conditioned office space. A joint meeting was carried out on 17 May 2019 to discuss the scope of works and methodology for repairs in the presence of the complaint, broker, SK loss adjuster, SK building consultant and senior estimator from JL (builder). This meeting was to run through the scope of works and methodology for repairs. The roof repairs have been completed, however the complainants now seek further rectification works. The policy includes a lifetime guarantee on building repairs for which the insurer authorises and it requires the insurer to rectify any defects resulting from poor quality workmanship on any authorised repairs. The complainant says the damage is due to defective repairs by the insurer The available information shows that that over six reports and scope of works (SOW) variations, the parties agreed that repairs to the roof completed in late August 2020. On completion of the roof the complainant upon inspection of the roof and refused to sign the clearance certificate noting the below rectifications were required:  on the edge of the foil backed insulation, the fibre glass is exposed  the roofs ceiling tiles are stained and are different colours  the inner ceiling is full of dust and debris from removing of the sheets  overflow pipe is not sufficient and there should be two. On the 15 October 2020, at a reinspection with the complainant, JL and the SK building consultant established further damage, being:  all but one of the roof sheet to the main warehouse were crimped  several dents to lower and awning metal roofs. JL advised that the roof when completed was without any damage and provided photos to verify this. It further commented that the dents may be unintentional or intentional when the scaffold was removed after the initial repair. The insurer has submitted a response from the Determination | Case number: 769453 Page 5 of 12 roof installers, RR, also noting it takes no responsibility for the damaged roof sheets. To support its position it submitted photos of roof works which show completed works with no dented sheets. The insurer reviewed all photographic evidence and admitted responsibility for minor crimping seen in the completion photos from 10 October 2019.In resolution to the above the insurer via its legal representation instructed to provide the complaint with a commercial settlement offer of: Replacement cost of sheets $48,835.33 Non-financial loss $3,000.00 Total $51,835.33 In its Notice of Response, the insurer made a further cash settlement offer of $4,995.60 to the complainant. This was to cover the ceiling tiles and dust and debris aspects. This has already been paid. Evidence from the consultants’ does not support the complainant’s position In response to the offer from the insurer the complainant obtained a roofing report from its expert, SJ. AR also submitted an additional scope of works for the repairs to the cost of $121,000.00. The insurer then arranged for its expert SK to review and provide a response on the finding SJ report and AR SOW as noted below:  Skylights have been left in poor condition and partially covered - JL have agreed to clean and other loose sections.  Lower roof (office) has large dent to roof sheet and multiple other sheets with broken ribs- Creased and dented roof sheets are considered damaged and should be replaced.  Lower roof (office) and main roof capping and flashings have excessive gaps and should be tight fitting and weatherproof – JL agree for a replacement of the affected capping is recommended.  barge capping to the western corner of the higher roof is not fixed and the area can be lifted by hand. - JL note reification is required  Rear lower roof flashing against a brick wall is not chased in or a proper pressure seal.  Screws and fixings have been left on roof and not cleaned off this will cause rust over time. - JL Agree. All debris should be removed from the roof area  Original section of barge capping had been damaged with large gaps in the flashing and new roof put in underneath. - SK note these covers associated capping & flashings to the awning areas should be replaced The below works have not been considered by the insurer ’ s expert as it says this damage was not related to the original claim or has already been reimbursed:  Ceiling tiles to office area have been installed in different mismatching colours – these have already been cash settled -$4,995.60  Sarking to the main roof has been poorly installed with wrinkled areas - The insulation is not intended as a decorative finish for the underside of the roof sheets. Determination | Case number: 769453 Page 6 of 12  Main roof capping is not under flashed at base of parapet wall. - JL have asked for SJ meaning - absence of an appropriate flashing between the upper and lower gutters is considered an existing building defect, unrelated to the claim event  where it meets metal wall cladding is not flashed adequately and water is ponding in between the two sections of the external gutter. - unrelated to the claim event Having reviewed the evidence from SK, I am satisfied a detailed investigation was completed by the builder SK including investigating/assessing the roof reports. The expert SK does accept the above rectification works however details that there are repairs noted in the complainant’s expert AR ’ s SOW report not claim related. The complainant did further submit further expenses for AFCA ’ s review as noted below:  Loss of rent – sum of $18,190.52 incl. GST  The total sum of $121,000 AR SOWS  Rental of the scissor for SJ and AR inspection and estimate of repairs $445.50  SJ Building Consultant fee for invoice #1029 of $1,350 excl. GST  Compensation for the next five years due to the excess has increased significantly  Non-financial stress of the claim totalling the sum of $10,000  Administration fees managing the claim to the cost of $12,500. On 31 June 2021 the insurer further increased its offer to $62,000 for the roof and non- financial compensation of $3,000, in resolution of the complaint. The complainant did not accept the offer. In summary, the complainant ’s SOW from AR shows the cost of full replacement roof with all the costs involved for that replacement being erected. The insurer ’ s expert SK did assess the SOW and accept rectification that need to be completed. The insurer, as the relationship with the complainant has broken down, offers to cash settle the balance of the claim. The complainant did not accept the original offer of $51,835.33 or the increased offer of $65,000. The complainant’s expert SNJ or AR have not responded to SK to review of its report and SOW to agree or disagree on SK findings. However, confirming that it will only accept the AR quote in resolution. I am satisfied SK is adequately qualified to undertake the above noted investigations as well as provide expert opinion on the roof, the SOW and report. SK also concludes that there is rectification work to be carried out. However, there is an absence of justification provided to replace the whole roof in reification. Also, equally compelling is the lack of qualified evidence to the contrary which may bring SK ’ s findings into question. Nothing has been provided by the complainant that I consider disputes SK’s findings. I am satisfied that there are other issues with the roof but, nothing has been provided which confirms these were as the result of the storm damage. The insurer is also entitled, under the terms of the policy, to cash settle the remaining rectifications. The insurer has further included non-financial loss of $3,000 in its offer to the complainants, which I will address further below. However, the cost of the report at $1,350 excl. GST and scissor lift of $445.50 should be reimbursed to the complainants as the insurer has accepted in part the rectification works. Determination | Case number: 769453 Page 7 of 12 Nothing has been provided to me, on balance, which justifies the complainant’s claim for the full SOW provided by AR, administration fees of $12,500 and compensation for the next five years. T he complainant’s claim for the loss of rental has not been supported by a satisfactory reason as why the rectification work resulted in the sum the complainant claims. Further to this the complainant Tenants should claim with their own insurer, under business interruption section of the policy if there is a period of disruption due to the rectification works. The insurer is to:  Pay $62,000  10% uplift of $6,200 to cover contingencies and loss of lifetime guarantee.  The insurer is entitled to deduct any amounts already paid in relation to the $62,000.  Refund the repot of SJ $1,350 excluding GST. (if not already paid)  Scissors lift hire of $445.50 (if not already paid) 2.2 Has there been any unreasonable delays in this claim? There has been an unusual amount of delay The available information shows that the complainant lodged a claim on 31 January 2019 in relation to a storm event on the insurer accepted the claim on 13 March 2019. On 12 April 2019 the insurer sent its experts to assess, inspect the damage. We note from that date to the 4 December 2019; several variations of SOWs were agreed including variations to work on weekends. The roof was repaired on 11 September 2020 however, there appears to be further delay after the reinspection of the roof in 5 October 2020. The complainant notes rectification issues on 8 January 2021 and a delay in regards the insurer responding to this. Information on file shows that the legal representation forwarded correspondence on 18 January 2021. The insurer then further cash settled the rectification works that same day. There are experts from both sides that review rectification which will I am satisfied will inevitably cause delays as they are third parties involved. However, it was the insurer ’ s responsibility to repair the roof correctly the first time. The complainant has sought $10,000 for non-financial loss. AFCA will only award compensation for non-financial loss where there has been an unusual amount of:  Physical inconvenience  Time taken to resolve a situation  Interference with a complainant’s expectation of enjoyment o r peace of mind. In assessing whether to award compensation for non-financial loss, AFCA expects complainants to:  Be moderately robust  Bear the normal degree of inconvenience experienced when a problem occurs, and  Take reasonable steps to minimise the inconvenience suffered. In that respect, I am satisfied the insurer ’ s handling of the claim had caused an unusual degree of inconvenience and stress for the complainant. However, the complainant has also refused entry to the premises on occasions. The insurer has offered $3,000 for non-financial loss, which I consider is fair and reasonable in this instance. Determination | Case number: 769453 Page 8 of 12 2.3 Why is the outcome fair? Given the absence of persuasive evidence by the complainant’s expert to warrant the cost of whole roof, it is fair in all the circumstances to permit the insurer to pay the rectifications only. 3 Supporting information 3.1 The AFCA processes AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. Determination | Case number: 769453 Page 9 of 12 3.2 Supporting information Original Sarking with Wrinkles Determination | Case number: 769453 Page 10 of 12 Shows the crushed gutter prior to replacement of the roof covering Determination | Case number: 769453 Page 11 of 12 Sump and overflow pipe (only one prior) Determination | Case number: 769453 Page 12 of 12 No damage to box gutter noted AR scope of work We are pleased to offer this quote which includes the following items:- 1. All work will be carried out in accordance with Workcover Regulations. 2. Site mobilisation and Demobilisation including a Supervisor onsi te always whilst Works are being carried out. 3. Supply and installation of Edge Protection and Harnesse s where required around perimeter. 4. Supply and installation of Temporary Fencing around perimeter of Work Areas to create exclusion zones. 5. Removal and disposal of all existing Roof Sheeting, including all associated Flashings, Box Gutters, Fascia Gutters and all accessories to entire area of Factory. 6. Supply and installation of Safety Wire Mesh and 55mm Insulation Blanket where required. 7. Supply and installation of Zinc alume .48 BMT Trimdek Roof Sheeting where required to replace existing. 8. Supply and installation of new Fibreglass Skylight Roof Sheeting (Ampelite Wonderglas Gelcoat 3050GSM Industrial Grade) where required . 9. Supply and installation of 1x Skylight Dome including all Flas hings and Trays. 10. Supply and installation of all new Zincalume Apron Flashings, Parapet Cappings, Barge Cappings and all associated Moulds and Trims to make Roofs watertight. 11. Supply and installation of Colorbond Box Gutters and Fascia Gutters to replace existing – deepen and widen where possible, including Rainwat er Heads and Sumps where required. 12. Supply and installation of all Zincalume Flashings, Trays, Back Trays to Exhaust Fans and all Penetrations. 13. Supply of all Plant and Equipment hire i.e. scissorlifts, boomlifts, scaffold. 14. Removal of all our Building and Roofing Waste from Site. We will provide all the above including labour and materials for the total sum of Total Price incl. GST $ 121,000.00 SJ Roof report Inspection date 12 May 2021 Report date 20 May 2021