The complainant claimed under its business insurance for the cost of repairing a collapsed 10m external wall, which it attributed to a storm. A panel found the wall collapsed due to pre-existing deterioration and roof alterations, which fall within the accidental damage exclusions, so the insurer was entitled to decline.

The complainant must first establish the loss is covered, and the expert evidence showed the collapse resulted from wear, deterioration and faulty alterations that fall within the policy exclusions.

Issues

Subjects and remedies

home or building damageno remedy

Related

All Hollard determinations · Find similar determinations

Text of the determination

Determination Case number 767327 Financial firm The Hollard Insurance Company Pty Ltd Determination | Case number: 767327 Page 2 of 13 Case number: 767327 10 May 2021 1 Determination overview 1.1 Complaint The complainant has a Business Insurance Policy (policy) with the financial firm (insurer) which provides cover for numerous commercial properties. On 18 January 2020, the complainant lodged a claim after a wall collapsed at S Street, (the property) which the complainant says occurred during a storm. The insurer has declined the claim. It says the wall did not collapse because of the storm but rather it collapsed because of its pre-existing poor condition and previous alterations that had been made to its roof structure. It says these circumstances are clearly excluded from cover in line with the policy exclusions specified in the product disclosure statement (PDS). The complainant disputes the insurer ‟s declinature and is seeki ng cover for the cost to repair/reinstate the wall. 1.2 Issues and key findings Is the insurer entitled to decline the claim? Yes. The available information establishes, on the balance of probabilities, that the wall collapsed because of the changes made to the building‟s roof structure and deterioration of the brick mortar over time, which is excluded under the policy. Accordingly, the insurer is entitled to decline the claim. 1.3 Determination This determination is in favour of the insurer. The insurer is entitled to decline the claim and is not required to take any further action. Determination | Case number: 767327 Page 3 of 13 2 Reasons for determination 2.1 Is the insurer entitled to decline the claim? The complainant bears the onus to establish a valid claim It is established law that in order to seek cover under the policy the onus first rests on the claimant to establish, on the balance of probabilities, the loss claimed is covered by the terms of the policy. Only once this has been established, will the onus shift to the insurer to establish, on balance, that it is not responsible to cover the claimant for the loss in line with a provision or exclusion present in the terms o f the policy. The policy is an insured events contract of insurance The policy covers the insured property against loss or damage caused by one or more the listed insured events, including Storm. It also extends cover for accidental damage, provided the loss or damage is not already covered by, or able to be insured by, or is not excluded by any other sections of the policy. Cover under these benefits is subject to the conditions, limitations and exclusions specified in the PDS. The insurer is entitled to rely on the policy provisions to assess its liability The insurer provided the complainant with the relevant policy documentation including the PDS and certificate of insurance (COI). Therefore, the panel accepts the insurer is entitled to rely on the policy provisions to assess its liability under the claim. Different expert opinions as to cause for the wall collapse It is not in dispute, an approximately 10m section of a wall of the property collapsed on 18 January 2020. The complainant says this was during and/or or because of a storm. The insurer says the collapse of the was not because of the storm. Rather, it was due to its compromised existing condition and alterations that had been made to the property‟s roof structure. The complainant‟s broker arranged for consultants „S‟ to investigate the cause and extent of the damage. S found the property to be in poor condition and noted the original timber roof trusses had been cut away to make room for mezzanine floor arrangements. The collapsed wall had broken into individual bricks with the mortar between the bricks found to be friable. S having reviewed the relevant Bureau of Meteorology (BoM) weather data, states the recorded wind speeds in the area were not strong Determination | Case number: 767327 Page 4 of 13 enough to cause such structural damage. The dominant cause for the collapse is the poor pre-existing poor condition of the wall. The complainant dissatisfied with S‟s findings appointed engineers „CA‟, which investigated the cause and extent of the damage and provided a report dated 13 May 2020. CA notes there were severe and abnormal thunderstorm activities in January 2020. It refers to multiple storm events on 4 January, 5 January, 10 January, 11 January, 17 January and 18 January 2020. CA‟s report significantly focuses on disproving S‟s findings and says S had not taken all relevant information and data into consideration. CA says it is probable the damage to the wall was the result of storm activities on or about 18 January 2020. The report refers to possible stormwater pooling against the wall and probable expansion of soils around the wall as a contributing factor. CA found that the sections of the wall that remained standing were in structurally adequate condition with no signs of prior structural distress, fretting or unacceptable deterioration or aging. The insurer appointed engineers „SW‟ who completed a site as sessment on 21 July 2020. SW notes the collapsed wall was an external perimeter wall with no abutting structures. SW inspected the remaining section of the wall, it noted loose and delaminated brickwork along the top course of the masonry wall consistent with the removed timber roof joists. Similar delaminated and loose brickwork was noted to the north west walls shared with a neighbouring commercial unit. In SW‟s opinion the damage to the walls was consistent with an intrinsic building issue caused by the alterations that had been made to the roof structure. SW says because of a removal of the original ceiling joists, over an extended period of time, the roof rafters had relaxed and spread across the top course of the walls. This has resulted in a lateral load being placed on the brickwork, leaving the wall in a structurally precarious state. SW reviewed the relevant BoM weather data for the dates referred to by CA. SW notes the storms on these days would not have caused the structural damage and outwards collapse of the wall. These weather events were not significant enough and were well below the walls design wind speed. The wind on 18 January 2020, may have triggered the collapse, however, but for the alterations made to the timber roof structure and the w all‟s pre -existing inadequate condition, the wall would not have collapsed. The wall did not collapse because of the storm Having carefully considered the available consultants‟ report s and photographic evidence, the panel finds the evidence from SW to be the more persuasive. The panel also accepts the evidence from S does, on balance, shows the mortar in the brickwork was showing signs of deterioration, weakening the structure. This is further Determination | Case number: 767327 Page 5 of 13 confirmed by SW as it noted loose and delaminated brickwork in remaining sections of the walls. The BoM data does not support CA‟s opinion. Rather, the data when considered having regard to the Beaufort Wind scale, shows that wind speeds similar to the event in January 2020 were normal and common in the area of the property. As such, the wind speeds were not abnormal for the area nor so significant to have caused such structural damage. CA‟s report, although seeks to discount S‟s findings, does not provide any conclusive findings and opinions provided are quite general in nature. SW‟s opinions are clear, well -reasoned and supported by persuasive and conclusive evidence. The panel is satisfied that on balance the wall did not collapse because of the claimed storm on 18 January 2020. The policy includes cover for accidental damage The policy includes cover for accidental damage, provided the loss or damage is not already covered by, or able to be insured by, or is not excluded by any other sections of the policy. As the wall was not damaged because of the storm or any other insured event listed in the PDS, the issue arises whether the damage triggers cover under the accidental damage benefit being unexpected and occurred within the period of insurance, this The panel accepts for the damage was accidental damage. However, cover under this benefit remains subject to the limitations and exclusions specified in the policy, in particular: Our exclusions Accidental loss or damage caused by or involving: 3. wear and tear, fading, scratching, marring, gradual deterioration, developing flaws, normal upkeep or making good; 6. error or omission in design, plan or specification or failure of design; 7. faulty materials or faulty workmanship; 9. incorrect siting of buildings as a result of incorrect design or specification; Given the expert evidence, the panel accepts that the dominant reason for the wall collapse is deterioration of the brickwork mortar over time and the error made in making the alterations to the property‟s roof structure to facilitate the mezzanine floor set-up. Determination | Case number: 767327 Page 6 of 13 The damage falls within the exclusions under accidental damage cover and accordingly, the insurer is entitled to decline the claim. Determination | Case number: 767327 Page 7 of 13 3 Supporting information 3.1 Process AFCA’s approach to this complaint This complaint has been determined based on what is fair in all the circumstances, having regard to the legal principles, applicable industry codes or guidance, good industry practice and previous decisions of AFCA or its predecessor schemes (which are not binding). A full exchange of the relevant information has taken place between the respective parties. Each party has had the opportunity of addressing any issues raised. All the provided information has been reviewed and considered. The parties have raised numerous issues in their submissions to AFCA. However, commentary in this determination is restricted to those issues considered relevant to the outcome. This matter was determined by a panel Due to the nature of this dispute, it has been referred to a panel for determination. The panel comprises the lead ombudsman, a member with significant experience in consumer and small business advocacy and a member with extensive insurance industry experience. How we assess complaints AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider available documents, the recollections of the parties, and all relevant circumstances. We give more weight to documents created at the time the events occurred. If there is no relevant documentation, we will decide what is most likely to have occurred based on the information provided to us. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. 3.2 Relevant Policy Terms Page Product Di sclosure Statement 7 – Storm, wind and water Our exclusions Loss or damage caused: … 4. by water entering the building due to inadequate maintenance, or through an opening made for any building renovation or repair, or because of a structural defect, fault design or faulty workmanship when the building was constructed Determination | Case number: 767327 Page 8 of 13 3.3 Relevant Expert Reports Record Key points S Loss Adjuster & Structural Engineer Report 6 February 2020  The northern end of the western external wall has collaps ed outwards on to an open grassed area. The length of the collapsed section of external wall was approximately 10m. Note that the southern end of the western wall was an internal wall between two com mercial units, but the collapsed section was an external wall.  The collapsed wall was a double brick wall with no cavity, however, the wall was built as two single skins of brickwork with the occasional brick bonding the two skins.  The collapsed wall has m ainly broken up into individual bricks with the mortar bet ween the bricks noted to be friable. In some of the bricks the mortar has completely detached from the brickwork indicating poor adhesion bet ween the mortar and the bricks. The actual bricks were no ted to be in reasonable condition.  A t the northern external wall there was a vertical crack in the brickwork approximately 2.5m from the north west corner. It was not possible to get a close view of this crack due to furniture stored in this area. It was t herefore not possible to determine whether this crack was pre - existing or new.  The original timber roof trusses had been altered to install the mezzanine floor. The alterations included raising the bottom tie chord of the original truss to provide headroom for the mezzanine floor and the original truss was no longer wholly supported on the external wall wit h the external wall only providing support to the rafter ends.  Photographs provided by the Loss Adjuster show large circular white items leaning on the collapsed wall. At the time of the inspections these items had been moved.  A wind gust of 48km/hr equates to a wind speed of 13. 3m/s which is substantially lower than the minimum u ltimate design gust wind speeds.  The outward collapse of the western externa l wall indicates that there was negative lateral pressure on the wall that caused the wall to fall away from the building.  The weather summary in the Australian Government Bureau of Meteorology (BOM) website confirmed that  was thunderstorm activity between the 16 th and 18 th January 2020.  The actual rainfall data from the local weather station in Marrick ville recorded 34mm of rainfall on the 17 th January and 18mm of rainfall on the 18 th January 2020. This is a reasonable volume of rain, however, this volume occurs on a regular basis and is not considered to be an abnormal rain event. Heavy rainfall would not result in negative lateral pressure on an external wall that would cause the wall to collaps e.  Wind gusts cause lateral pressure on external walls. At th e subject property a leeward (suction) wind pressure would be required to cause the western external wall to collapse away from the building Determination | Case number: 767327 Page 9 of 13 Record Key points i.e. the wind gust would need to act on the eastern side of the building (windward pressure) and flow over the roof from west to east to cause leeward pressure on the collapsed wall.  A maximum wind gust of 48km/hr was recorded at the nearest weat her station at Cant erbury during the thunderstorm activity between the 16 th and 18 th January 2020. A wind gust of 48km/hr occ urs on a regular basis in the Summer Hill area and is not considered to be a destructive wind event that should cause structures to collapse.  There will be local variations in wind gusts, however, the subject property is in very sheltered location and ther efore we would not expect the actual wind gusts at the subject property to be greater than the wind gusts recorded at Canterbury.  If the western external wall collaps ed as the result of the wind gusts during the thunderstorm activity then this indicat es that the external brickwork wall was in very poor condition and this particular event was the eventual trigger for the wall to collapse.  The construction of the double brick external wall as two single skin walls with the occasional brick bond bet ween the two skins is poor. Ideally this wall should have been fully brick bonded with header bricks in every 5 th course, however, the wall construction was probably typical of the wall construction at the time.  The friable mortar of the collapsed brickwork and the collapse of the wall into individual bricks indicate that the mortar adhesion between the brickwork was very poor.  The proximate caus e of the wall collapse was due to the expected poor condition of the wall caused by a combination of the original poorly b onded wall construction and long term deterioration of the mortar in the brickwork. Complainant’s Engineer ( CA ) Report 13 May 2020  There were severe and abnormal thunderstorm activities in Sydney in early January 2020. This and much other relevant weat he r data including t wo more severe storms which occurred just before the wall collapsed is not reported nor considered in the S report.  Also wind directions are not reported, such that discussions of leeward (suction) pressure effects on the wall discussed in the report are speculative and not tenable. Also many of the possible weat her factors which may have contributed to the damage and collapse of the wall on the18th January 2020 are not presented nor considered in the report.  Besides the omission of crit ical weather data, much of the relevant forensic data evident from site obs ervations appear to have been overlooked in the S report.  The available data and forensic evi denc e overlooked in the S report is of a structural nature. Its omission is of conc ern as it indicates the wall was designed and built according to good building and acceptable structural engineering practice. Further when considered it serves to provide a more credible engineering assessment of the wall‟s condition that would go to contrave ne the c onclusions given in the S report. Determination | Case number: 767327 Page 10 of 13 Record Key points  The conclusion in the S report that the wall failed on the 18 th January 2020 because it was not in good structural condition is not substantiated with any reliable structural engineering analysis.  Based on my observations and considerations of all the relevant data and forensic evidence the wall was structurally adequate and had not deteriorated  A summary of the BOM at Observat ory Hill of three storms activities periods, (4th and 5th January, 10th and 11th January and 17th and 18t h January) which are considered not eworthy is given in Table 1 below. The two earlier storms are considered notewort hy not only because of their greater severity, (Strong Gales conditions) but also because of their wind dir ections and hence possible contribution to structural damage to the wall prior to its collapse. However, while there is ample circumstantial evidence prior severe thunderstorm activities capable of doing structural damage to the wall there is no conclusive evidence to confidently confirm or rebut any prior damage to the wall  The brickwork has collapsed outwards into the enclosed quadrangle and abnormally scattered some distance from the base of the wall duri ng the storm.  The condition of the brickwork still standing on either side of the collapsed section, and at the base of the wall pres ented structurally adequate and did not show signs of prior structural distress, fretting or unacceptable deterioration from weathering or ageing  My inspection was limited t o a visual inspection of the remaining brick wall and a small pile of bricks still remaining on site. No exploratory inspection or materials testing was considered necessary at this point in time. However, mortar attached to some of the remaining bricks an d in the brick walls still standing was scratch tested, to gauge its quality. The mortar in the joints has not deteriorated. It presented in good condition and considered typical of a lime mo rtar and structurally adequate.  Further the mortar type and its i nherent properties are als o not disclosed in the report. Based on my on - site scratch test of the mortar (often made on - site by experts to mitigate laborat ory costs and time) and my expertise in brick research and construction I am of the opinion the mortar is a typical Class M1 lime mortar and is considered structurally adequate. If tested it would probably comply favourably with current requirements for a Class M1 mortar in accordance with all the relevant requirements of AS 3700 - Masonry structures .  CA does not agree with the c onclusions in the S report, particularly that the wall was not in a good structural condition. The c onclusions are not bas ed on any reliable evidenc e and not verified by any structural engineering analysis or assessment of the wall . The report simply chooses to “ class ” the damage as a “long term maintenance issue” . It is not clear if the “class” refers to a criteria or classification for a prescribed or audited maintenanc e regime required under the Insurance Policy or is an in - house S maintenance criteria. Determination | Case number: 767327 Page 11 of 13 Record Key points  Cont rary to the findings in the S report, based on CA‟s observations and considerations of th e data and forensic evidence, it was of the opinion the wall was structurally adequate.  While the destructive winds and possibly lightn ing during the severe thunderstorm activities in early January, including those on the 4 th and 5 th and on the 10 th and 11 th January 2020 were capable of causing structural damage to the wall there is no conclusive evidence to confidently confirm or rebut a ny prior damage to the wall.  In the circumstance having considered the various viable contributing factors to cause probable damage to the wall CA is of the opinion the wall collapsed as a result of storm activities on or about 18th January 2020. Insurer ’s Engineer (SW) Report 29 July 2020  Upon close inspection of the remaining non - collapsed section wall, we noted loose and delaminated brickwork along the top course of the masonry walls consistent in location with the removed timber ceiling joists .  Notwithstanding the above, loos e and delaminated brickwork along the top course of the north western walls were further apparent through our inspection of the abutting neighbouring commercial unit which shares a common party wall.  Furthermore, new sect ions of brickwork were noted to have been installed correspond to the locations of the aforementioned observed loose and delaminated masonry.  Considering our finding, in our opinion, the aforementioned damage noted above to the top course of brickwork is consistent with an int rinsic building issue as a result of alterations and additions noted to the roof structure  Further to our inspection, we noted the timber roof construction methodology is consistent with one of a coupled roof system through the clear distinct inclusion of collar tie spanning between the timber rafters.  In ascert aining the adequacy of the existing roof configuration, we have referred to AS1684.2 – Residential Timber Framed Construction, which outlies ceiling joist and collar ties must be fixed to the opposing pair of ra fters.  During our inspection of the roof structure, we not ed the ceiling joist had been removed in facilitating the installation of the mezzanine floor.  As a result of the removal of the timber ceiling joist, the timber roof structure over an extended period of time has relaxed and spread applying a lateral load to the masonry wall.  Notwithstanding the above, in our opinion, this is consistent within the observed damage noted along the top course of the masonry wall as previously mentioned within the obser vation section of this report.  In our opinion, through the removal of the ceiling joist over an Determination | Case number: 767327 Page 12 of 13 Record Key points extended period of time the roof rafters have spread and subsequently applied a lateral load onto the brickwork leaving th e subject masonry wall in a structurally precarious state prior to any claimed storm event  In analysing the failure method of the subject brick wall, we noted the wall has collapsed away from the property, and as such Leeward (suction) would be required f or the wall to pull away from the remaining structure.  In saying this we refer to AS 1170. 2:2010 – Structural Design Actions, which illustrates for leeward (suction) to occur we would require the windward direction to be on the corresponding façade of the building.  In illustrating the aforementioned requirement, we provide the following excerpt from AS 1170.2:2010 as Figure 5 :  Considering our findings, in our opinion, the observed remaining applicable wind conditions in the above table from Cantali and A ssociates should not have caused structural damage and outwards collapse of the subject wall as they are not significant enough in magnitude and are well below the design wind speed outlined in AS 1170.2:2010 – Structural Design Actions  In saying this, wi nd speeds between 50 – 74 Km/Hour are common wit hin the Summer Hill region and based on the Beaufort chart attached under Appendix B should not cause structural damage to structurally adequat e buildings.  Furthermore, we have reviewed the climate data obtained from the Bureau of Meteorology (BOM) from November 2019 with respect to the collapsing brick wall on 18 January 2020.  The obtained dat a is taken from the BOM website form the Cant erbury weather statio n, which is approximately 3km away from the subject property.  In saying this, a wind gust of 69km/h was recorded on 8t h of November and is classified as „No.8 – Gale‟ in accordance with the Beaufort Scale  In our opinion, based on our review of wind data obtained from the Bureau of Meteorology, if the subject wall collapsing was attributable to single one - off wind event, the wall would have collapsed during November 2019 which yielded higher winds within required windward directions than January 2020.  Not withstanding the above, we advise the building well pre - dates the inception of the above code and any reference made to above standard has been used in the explanation of the collapse of the subject wall.  In our opinion, full brick masonry wall at the sub ject property has collapsed as a result of the alterations and additions to the timber portion of the couple roof structure.  Through the installation of the mezzanine storage floor, the roof ceiling rafters were removed to allow for adequate head height t o facilitate storage.  As a result, the timber roof has relaxed over an extended period of time applying lateral loading to the masonry wall which was Determination | Case number: 767327 Page 13 of 13 Record Key points consistent with the loose and delaminated brickwork noted along the top cours e of the non - collapsed secti on of wall.  To end, in our opinion, the wind event on 18 January 2020 may have triggered the collapse of the subject masonry, however, we opine, if the timber roof was not altered and the masonry wall was in a structural adequate condition prior to the wi nd event, the masonry wall would not have collapsed and as such the collapse of the masonry wall is not attributable to a single one off insurable event

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.