Dispute over cash settlement amount for rain inundation damage to rental property
Text of the determination
Determination
Case number 766162
Financial firm Insurance Australia Limited
Determination | Case number: «reference_id» Page 2 of 13
Case number: 766162 5 August 2021
1 Determination overview
1.1 Complaint
The complainants hold a landlord insurance policy with the financial firm (the insurer). They
lodged a claim for their investment property after the lower levels were inundated following a
rain event.
The insurer accepted liability for damage to the lower levels. However, a dispute has arisen
over the settlement amount. The complainants say the offer is insufficient to complete the
works. They seek for the insurer to honour their quote, accept the resultant structural
damage, pay loss of rent until the clam is finalised and pay non-financial loss for a poor
claims experience.
The insurer says its offer is fair and reasonable and the complainants are not entitled to
compensation. The insurer also says it has been unable to assess all of the items being
claimed because the complainants are not complying with their policy obligations.
Issues and key findings
Should the insurer increase its offer?
No. The complainants have not provided reasonable access to the property to enable the
insurer to properly assess all of the repairs sought. Therefore, the insurer is not required to
increase or reconsider its settlement unless the parties agree to proceed in the manner set
out in section 2.1.
Are the complainants entitled to additional loss of rent?
No. The insurer has already paid for almost six months of lost rent. The delays that have
occurred has been mainly due to the complainants’ failure to provide the insurer with
reasonable access and seeking a cash settlement.
Are the complainants entitled to non-financial loss?
No. The available information does not show the insurer has mismanaged the claim to the
extent it warrants an award for non-financial loss.
Is the insurer liable for the cost of expert reports?
To the extent the insurer has agreed to pay for any reports, it should reimburse these costs.
Beyond this, the insurer is not required to reimburse these costs at this time.
1.2 Determination
This determination is mostly in favour of the insurer.
The insurer is not required to increase its cash settlement offer at this time. Instead, the claim
should proceed in the manner set out in section 2.1.
The insurer is not liable to pay for any more lost rent or for non-financial loss.
The insurer is to reimburse the cost of experts reports to the extent it agreed to do so.
Determination | Case number: «reference_id» Page 3 of 13
2 Reasons for determination
2.1 Should the insurer increase its offer?
Complainants are seeking almost $400,000 for repairs
The complainants want the insurer to increase its cash settlement for repairs because it does
not address movement of the building’s frames, studs or bottom plates. The complainants
also say the insurer’s allowance for the accepted repairs are too low.
The complainants are seeking just under $400,000 for repairs and mould remediation. The
complainants say this is all related to the clai m. This is significantly higher than the insurer’s
initial assessments.
The insurer says it was prepared to do the repairs but the complainants insisted on a cash
settlement. Further, the insurer says the complainants have not provided it with reasonable
access so that it can fully assess all of the claimed damage. This includes additional issues
the complainants identified during the course of the dispute, one of which is the structural
movement the complainants say was caused by the claimed event.
The complainants provided two engineering reports confirming the claimed event caused the
structural movement. The insurer engaged an engineer, RCE, to review this issue. However,
RCE was provided with limited opportunity to inspect the damage. RCE’s report
acknowledged this several times.
Complainants have not complied with their obligations
The insurer maintains it has been prejudiced by the complainants’ failure to allow it to
adequately assess the damage. RCE was not able to do a complete inspection. The insurer
has been unable to inspect the property to assess all of the items the complainant is wanting
to be paid.
The complainants say the insurer has sent at least four of its various consultants or experts to
inspect the damage. This included the insurer’s assessor, RCE and builder J. The
complainants say they have sent many photos, reports and quotes to substantiate the claim.
As stated previously, the complainants are seeking a significant quantum. This does not
include loss of rent. The panel does not accept it is reasonable to expect the insurer to pay for
quotes without having an opportunity to engage its own experts to review all of the damage.
Further, the insurer has stated it is prepared to do the claim related repairs. However, the
complainants are seeking a cash settlement. The policy provides the insurer, not the
complainants, with the discretion as to how to settle the claim.
The available information shows the complainants did interfere with RCE’s ability to inspect
and review the damage. The com plainants raised concerns about RCE’s qualifications and
the fact they wanted to reconsider the cause of damage. However, the structural damage
being claimed was new. The insurer was entitled to consider whether this damage was
caused by the claimed event or by other factors. Further, it is clear an engineer was required
to assess this. However, the only engineer engaged by the insurer to inspect this was
provided limited access by the complainants.
This issue is also a significant aspect of the claim. The insurer was entitled to fully assess
this. Whilst the complainants had concerns about RCE’s qualifications, this could have been
raised when challenging the report. It was not consistent with the complainants’ policy
obligations to limit RCE’s inspection in the manner they did.
Determination | Case number: «reference_id» Page 4 of 13
Further, the insurer is entitled to obtain its own quotes for the repairs. This is because the
insurer is entitled to base a cash settlement on its own competitive rates given it was
prepared to authorise the repairs but the complainants are seeking a cash settlement.
However, the insurer has not been able to do so given there has been limited access
provided and it cannot confirm the full scope of works.
The panel is also not persuaded the complainants’ engineer reports conclusively show the
structural damage is all claim related. Their reports were focused on the claimed event and
how this could have led to the damage. However, RCE noted there could be site drainage
issues that could have caused the structural movement. This could not be fully investigated
given the limited access provided and the complainants’ interference with the inspection.
Insurer not required to increase cash settlement until complainants co-operate
Given all this, the panel does not accept the complainants are entitled to the amount being
sought.
The complainants are seeking a significant amount. This includes structural damage they say
is related to the claim. Limited opportunity has been provided to the insurer to investigate this
issue as well as the other additional items the complainants are seeking. Photos and reports
obtained by the complainants are not enough for the insurer to fairly assess the claim.
Instead, the insurer was entitled to engage its own experts and builders to review the items
and determine:
which areas it accepts is related to the claim, and
determine what the likely cost is to repair those items.
Therefore, until the complainants co- operate with the insurer’s request to undertake these
activities, the panel is not satisfied it is fair for the insurer to increase or reconsider its
settlement. This is because the complainants’ failure to comply with their policy obligations
prejudiced the insurer’s ability to fairly assess all aspects of the claim.
Claim should be resolved in this way
Given this, the panel considers it fair in all the circumstances for the claim to be resolved in
the following way.
The insurer should be given an opportunity to fully assess all aspects of the complainants’
claim. This will require the complainants providing access to the insurer and its contractors to
access the property. Such contractors would likely include an engineer, any builders to quote
for the claim related damage and its assessors.
Once this is done, the insurer must make a decision as to a fair cash settlement amount. As
the insurer would have conducted the claim related repairs, it is entitled to rely on quotes that
would have been available to it in making this assessment. Given the nature of the works are
complicated, it should also add a 15% contingency for the possibility of additional variations.
All of this should be done no less than 8 weeks after this determination is accepted. This
timeframe is subject to the complainants providing timely and full access to the property.
Whilst this timeframe is short, this is an investment property with a loss of rent component
attached to it that warrants this tight timeframe.
If the parties are unable to agree on the quantum, the complainants can lodge a dispute with
AFCA for a decision on this point.
If the complainants do not agree to this method, then the insurer is not required to increase its
cash settlement for this claim or take the matter any further.
Determination | Case number: «reference_id» Page 5 of 13
2.2 Loss of rent
Complainants not entitled to further loss of rent
The complainants want the insurer to extend its loss of rent payments from 6 January 2021
until the property is repaired.
The insurer has paid $24,314.28 for lost rent. This is for the period 5 July 2020 to 6 January
2021. This is almost six months.
The policy covers the rent you lose during the reasonable time it should take to repair or
rebuild your rental property, for up to 12 months from when the listed event took place.
The insurer says the policy benefit does not cover indefinite loss of rent. It only covers the
loss of rent incurred during the time it should take to repair or rebuild the property. The insurer
also says the complainants failed to mitigate their loss by not commencing repairs, preventing
the insurer from assessing the damage and insisting on cash settlement when the insurer
was willing to cover repairs.
The panel accepts the insurer’s position. The insurer has not been able to properly assess
the claim or been given the opportunity to repair the claim related damage. This is due to the
complainants providing restricted access to the property and seeking a cash settlement.
Further, these actions have delayed the claim and at this point, there is insufficient basis to
decide on a fair cash settlement.
Therefore, the panel does not accept the insurer is required to pay for any lost rent to date.
2.3 Is the complainant entitled to non-financial loss?
Compensation for non-financial loss payable in certain circumstances
The complainants seek compensation for stress and inconvenience (non-financial loss) due
to the way the insurer handled their claim.
We will only award compensation for non-financial loss where there has been an unusual
amount of physical inconvenience, time taken to resolve a situation, or interference with the
complainant’s expectation of enjoymen t or peace of mind.
Insurer is not required to pay non-financial loss
The complainants seek $5,000 non-financial loss for the poor claims experience. This
includes claims delays, the insurer’s failure to offer a reasonable cash settlement and the
insurer’ s failure to consider expert building reports submitted by the complainants at the cost
of the insurer.
The insurer says claim delays were caused by the complainants requesting a cash settlement
and not being satisfied with the settlement figures.
The panel has reviewed the claim file notes and submissions from both parties. The claim
notes indicate the insurer maintained contact and followed up assessment reports in a timely
manner. Most of the delays was due to the complainants seeking a cash settlement and
restricting access to the insurer’s contractors. This is not the insurer’s fault.
Given this, the panel is not satisfied there is any basis to award non-financial loss.
Determination | Case number: «reference_id» Page 6 of 13
2.4 Is the insurer liable for the cost of expert reports?
The complainants incurred professional costs
Under Rule D.5, AFCA may decide a financial firm contribute to the professional costs
incurred by a complainant in the course of a complaint. These costs can be awarded if the
complainant needed an expert to understand or establish their claim. These costs are
normally capped at $5,000 unless exceptional circumstances apply.
Insurer to pay for the invoices it agreed to
The complainants seek for the insurer to cash settle it the cost of quotes and expert reports
obtained to support their position. It appears the insurer has agreed to pay for some of these
costs.
To the extent the insurer has agreed to pay for these costs, it should do so. The complainants
have set out the costs they are seeking in their submission dated 30 March 2021.
To the extent the insurer has not agreed to the costs and quotes sought, the panel is not
persuaded it is fair for the insurer to reimburse them at this time. This is because the
evidence is unclear if these were reasonably incurred or assisted the complainants to
establish their case.
Determination | Case number: «reference_id» Page 7 of 13
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
3.2 Relevant policy terms
What we pay for – Buildings Insurance
If we agree to cover your claim under Buildings Insurance, then we will:
pay the cost to repair or rebuild the part of your rental property that was damaged
(whichever is lower)
pay for any extra costs we cover under ‘other benefits’ – see below.
The most we pay
The most we will pay for your rental property buildings is the Buildings sum insured.
Other benefits
We may also pay some costs on top of the Buildings sum insured under ‘other benefits’
for:
Loss of rent during repairs, see page 39
Mortgagee discharge costs, see page 41.
Determination | Case number: «reference_id» Page 8 of 13
How we settle your buildings claim
We will choose to settle your claim for loss or damage to your rental property and any
‘other benefits’ in one of the following ways:
1. Arrange for repairers, builders or suppliers to repair or rebuild your rental
property
If you agree, we can arrange for our preferred repairers, suppliers or builders to repair
or rebuild your rental property. We may enter into any contract with our selected
repairer, builder and/or supplier on your behalf.
2. Pay you the reasonable cost to repair or rebuild your rental property
We can choose to:
pay you
pay your nominated repairer, supplier or builder, or
provide you with store credits from one of our nominated suppliers.
For example, we may pay you directly when:
you decide not to repair or rebuild your rental property, or
you don’t start repairi ng or rebuilding your rental property within 6 months from when
the loss or damage takes place, or within any longer period we agreed to in writing.
3. Pay you the Buildings sum insured
We may pay you the Buildings sum insured when we consider your rental property to be
a total loss or when we choose to do so.
If we pay you the Buildings sum insured, then your policy ends and you don’t get a
refund of your premium.
We will continue your liability cover (see pages 45 to 47) for up to 6 months from when
the listed event took place. However, liability cover will end during this period if:
construction starts at your site, or
you sell the site or any portion of it, or
you take out a new Buildings Insurance policy for your site.
4. Pay for other benefits
Loss of rent during repairs
If a listed event causes loss or damage to your rental property and we agree your
tenants can’t live in it and need to move out so it can be repaired or rebuilt.
Covered under Buildings Insurance
the rent you lose during the reasonable time it should take to repair or rebuild your
rental property, for up to 12 months from when the listed event took place.
We pay this benefit on top of your Buildings sum insured.
Not covered
loss of rent during any time you live in the building
if you also make a claim for rent default and we pay your claim
loss of rent as a direct result of a claim under these listed events:theft or attempted
theft by a tenant or their guest, or
vandalism or a malicious or intentional act by a tenant or their guest.
Conditions
Determination | Case number: «reference_id» Page 9 of 13
you must have a rental agreement that states the:term of the rental period, and
amount of rent and bond your tenant needs to pay.
3.3 Relevant Law
INSURANCE CONTRACTS ACT 1984 - SECT 57
Interest on claims
(1) Where an insurer is liable to pay to a person an amount under a contract of
insurance or under this Act in relation to a contract of insurance, the insurer is also
liable to pay interest on the amount to that person in accordance with this section.
(2) The period in respect of which interest is payable is the period commencing on the
day as from which it was unreasonable for the insurer to have withheld payment of the
amount and ending on whichever is the earlier of the following days:
(a) the day on which the payment is made;
(b) the day on which the payment is sent by post to the person to whom it is
payable.
(3) The rate at which interest is payable in respect of a day included in the period
referred to in subsection (2) is the rate applicable in respect of that day that is
prescribed by, or worked out in a manner prescribed by, the regulations.
(4) This section applies to the exclusion of any other law that would otherwise apply.
Determination | Case number: «reference_id» Page 10 of 13
3.4 Relevant expert evidence
Record Key points
Financial
firm’s expert
(JLE )
Report
04 - 05 - 2020
Upon inspection of the residence there was found to be damages sustained to the
first floor timber floating floors throughout from what appears to be water ingress
coming up through the concret e slab of the property. During our inspection it
appears that somewhere throughout the property the storm water drainage has a
blockage which appears to be causing water to back flow beneat h the concrete
slab and cause moisture to rise through it and affected the timber floating flooring.
Due to the mould growth bene ath the timber flooring it appears that this has been
an underlying issue present to the property for a period of time.
It is my professional opinion that due to a blockage in the stormwater system
located at the front, right corner, water would not be dra ining away correctly and
as a result, I believe it is backing up and overflowing from the stormwat er points
located at the rear of the property. As a result, I believe the water has leaked
back into the property from this area and has caused the damage to the timber
floor. I would recommend having the entire stormwater system jet cleaned to
remove any blockages, to ensure that the drain can drain away correctly. I also
found that there is a cracked junction located at the back, left side of the property,
as well as roots growing int o a section of the drain at the back of the property. I
recommend that this section of drain be removed and replaced to ensure that
water does not leak out through the crack in the pipe, and to ensure that the roots
do not grow in to the drain any further and cause issues in the future.
Damages appear to be caused by an unforeseen issue to the property and not a
maintenance issue however please note the insured is to have the issue
regarding the storm wat er drainage repaired as reco mmended in the professional
CCTV report prior works commencing to the property to allow a warrant able
outcome
Financial
firm’s expert
(SP )
Report
07 - 05 - 2020
Upon inspection I found evidence of water damage to the timber flooring
throughout the ground floor of the property, which can be seen below
During my inspection of the stormwater system, I found that there is a blockage at
the front, right side of the property. Due to the pipe being blocked at this point,
water would not be able to drain away cor rectly and as a result, I believe it can
easily back up within the system and overflow. I believe the water has overflowed
from the stormwater points at the rear of the property, which I believe has then
leaked back into the property, causing the large ex tent of damage found.
Financial
firm’s expert
(EHS )
Report
05 - 06 - 2020
The floorboard throughout the lower level have swollen and popped in several
locations. The particle board subfloor remains wet (top left). There is visible
mould below the floorboards (bottom left, centre) and behind skirting (bottom
right) in areas where access was available. Where access was not available there
is a strong assumption that mould is present, this is true for both the floor and the
wall cavity. Visible mould beneath the particle board flooring is expected
throughout the bottom floor however, the full extent will be unknown until more
access is available. Bathroom and stairs can remain until further investigation can
be completed.
Determination | Case number: «reference_id» Page 11 of 13
Record Key points
Financial
firm’s expert
(L )
Report
06 - 06 - 2020
During our review of the hygienist report, it was noted that the air levels within
Bedroom 2 and the Master Bedroom were significantly higher than the external
comparis on, particularly in the count of as pergillus, indicating that there is likely
an active water issue occurring at the property.
There is no visual mould growth within either room to indicate where a water
ingress issue may be occurring and as such, it is recommended that invasive
testing is carried out.
Envirofree report recommends a plumbe r also attend to identify water ingress
issues, including an inspection of the first floor column heater.
It was also noted that the surface samples taken to form the scope of works were
taken at the entry point of each bedroom, deeming the carpet non - res torable.
Again, no visual mould was found, nor were moisture readings taken to indic ate
damage to the carpet. Thes e readings may be a result of cross contamination
from the downstairs affected area to upstairs carpet given that this is a high traffic
area .
It would be recommended prior to any strip out works, that further sampling is
taking of the upstairs premises of this property to determine the extent of works
further (ie. Condition 2 or condition 3 remediation).
Complainant’s
expert (JPE )
Report
11 - 11 - 2020
Area Damag
e
category
Comment
Ground Floor
Entry C2 Door frame cracked, door sticks lightly
No cracks visible on walls but out of plumb by about 15 mm
Bedroom C2 Door frame cracked and buckled, door sticks lightly
Hairline cracks on ceiling, out of plumb wall by about
5 mm
Stairs N/A Water stains and mould on bottom part of the stair and the
stair cavity.
Kitchen
Living
C4 Cracks up to 30 mm on party wall, out of plumb by 25 mm
Skirting parting apart on most walls, with the most damage on
the eastern wall (up to 30 mm)
Loss of
bearing
capacity
Small
cracks
on
ceiling
First Floor
Bedroom C2 Door frame cracked, door sticks lightly
No cracks visible on walls but out of plumb by about 6 mm
Retreat C1 Small cracks on ceiling
Bathroom C0 No visible crack
Master
bedroom C3 Cracks on ceiling
Out of plumb w all by
about 15 mm
Possible loss of
bearing capacity
Ensuite C0 No visible crack
The house was subject to a stormwater ingress through rear courtyard
flooding during March - April as stated by the owner. The house now
shows sign of movement. There is no known modification to the house
since constructed in 2011 - 2012.
According to the own er, the house was vacated few months ago
following the presence of mould, resulting from the flood. Owner stated
that cracks on the ground floor party wall were not noticeable in June -
July. Since then, cracks on walls became noticeable and more cracks
star ted to appear on the partywall such as corner skirting boards splitting
at joints.
Based on the observations made during the inspection and available
Determination | Case number: «reference_id» Page 12 of 13
Record Key points
documents:
> House was damaged by a flooding event which took place in March -
April 2020;
> Party wall show s excessive cracks (up to 30 mm) on the ground floor;
> Eastern external walls, on both ground floor and first floor are out of
plumb;
> Cracks are visible on most door frame, few cracks on ceilings.
> No other known event was recorded.
The following structural distress is the most probable chain of events:
> Due to the flooding event, all timber members on the ground floor,
including underlay of the flooring, skirting boards, timber flooring and
bottom plates started swelling.
> As the eas tern wall is a solid earth retaining structure, the only way for
timber flooring to expand was towards the party wall.
> The additional stresses on the bottom of the party wall, associated
with weaken bottom plate lead to movement of the bottom of the party
wall.
> As the ground floor party wall moves, the first floor party wall and first
floor joists move too.
> As the first floor party wall moves, it leads to roof movement, which is
then transferred to first floor external wall.
> Difference in load pattern a nd transfer on the first floor will be
transmitted to the eastern external load bearing wall, leading to out of
plumb wall.
Financial
firm’s expert
(RCE )
Report
01 - 12 - 2020
Civil drainage
During rain events, water is collected from roofs; however, significant
amounts of water are also generated from the walls, pavements and
land. The purpose of civil drainage is to direct water away from the
structure. Some examples of functioning civil dra inage include roofs
collecting water and transporting it to the legal point of discharge, or
Determination | Case number: «reference_id» Page 13 of 13
Record Key points
paving diverting water away from the dwelling’s edges. Where adequate
civil drainage doesn’t exist adjacent to external walls, stormwater can
migrate below the foo tings or enter the structu re.
The soil is roughly one meter higher than the slab at the northeastern
corner of the dwelling. This height difference is due to the Insured’s
property being cut level prior to construction in 2010. The moisture from
this soil appears to be permeating through the masonry and into the
floorboards, causing them to expand. The expansion of the floorboards
has caused a build - up of pressure within the flooring, resulting in the
tenting. The expansion has also pushed the eastern archi traves into the
wall, cracking the plaster in the process. The migration of the water
through the masonry indicates that no wat erproof membrane was
painted on.
The translation of the architraves into the wall has may have moved the
bottom plate and studs s lightly. Based on the extent of the cracking, it is
believed that the wall may have translated up to 10 mm. As this
movement is minor, it does not pose a structural risk and does not
require make - safe works. The cracked plaster will need to be removed to
d etermine if the framing is water damaged and needs to be rectified
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.