Text of the determination
Amended determination
Case number 765099
Financial firm Allianz Australia General Insurance Limited
Amended determination | Case number: 765099 Page 1 of 15
Case number: 765099 13 September 2022
1 Determination overview
1.1 Complaint
The complainant holds a home and contents insurance policy with the financial firm (insurer)
and lodged a claim after the home was damaged during the Townsville floods in February
2019.
The insurer partially accepted the claim in March 2019 and authorised its builder to proceed
with some repairs and issued a payment to the complainant for other repairs it says it could
not repair due to the limitations of the policy‟s lifetime guarantee.
A complaint arose about the insurer‟s assessment of its liability and the scope of repairs
accepted by the insurer. The complainant says the insurer has mishandled the claim and this
has resulted in avoidable protraction of the matter, time taken, inconvenience and loss from
being unable to use a part of the property for the duration of the claim.
1.2 Issues and key findings
Is the insurer required to increase its offer of settlement?
Yes, the insurer is to increase the cash settlement of the claim to $189,974.89 as set out in
section 2.1 of this determination.
Is the complainant entitled to compensation for non-financial loss?
Yes. The claim has been ongoing since February 2019 and it is fair in the circumstances that
the insurer pays the complainant $5000 compensation for non-financial loss.
Is the insurer to contribute to the complainant ’ s professional costs?
Yes. If it has not already done so the insurer should reimburse the complainant ‟ s costs for
obtaining a geotechnical report from PG and the report from civil engineer (GT).
Why is the outcome fair?
The outcome is fair as it recognizes the issues in the complaint and provides a fair cash
settlement of the matters in dispute.
1.3 Determination
The determination is partly in favour of the complainant. Within 21 days of the complainant
accepting this determination, the insurer is to:
pay the complainant $189,974.89 in settlement of the assessed damage as outlined in
section 2.1
if it has not already done so pay 50% of the costs to repair the pool boundary fence
Obtain a quote to repair the bathroom tiling and cash settle the claim based on the quote
pay the complainant $5,000 compensation for non-financial loss
if it has not already done pay the complainant the professional costs of the reports from
PG and GT subject to provision of the relevant invoices.
Amended determination | Case number: 765099 Page 2 of 15
2 Reasons for determination
2.1 Is the insurer required to increase its offer of settlement?
Yes, the insurer is to increase the cash settlement of the claim to $189,974.89 as set out in
section 2.1 of this determination,
Complainant must establish a valid claim
The complainant has the initial onus to prove, on the balance of probabilities (that is more
likely than not) that the loss or damage claimed falls within the terms of the policy. This is
commonly called a prima facie (or valid) claim.
The complainants policy is a defined events policy and covers her building and contents for a
series of listed events including storm and flood subject to conditions and exclusions.
There is no dispute the insured property was inundated with water during a flood event on 9
February 2020. The panel accepts the complainant has established a valid claim under the
policy. The issue is the extent of the flood related damage.
Dispute as to extent of damage
Both parties have appointed experts to assess the damage. A summary of the reports is
contained in section 3 of this determination.
The insurer appointed builder (AG), restorer (MS) and initially, engineer (NJ) to report on the
cause and extent of damage. After the complainant disagreed with the insurer‟s assessment
and settlement proposal the insurer appointed engineer (NC) to inspect and report on the
cause of damage. The complainant also disagreed with NC‟s findings particularly in relation
to:
cracking damage to concrete foundation/slab,
movement/displacement of downstairs block walls
cracking in the pool shell/wall and surroundings
fencing (other than a portion of the boundary pool fence repaired by her neighbour‟s
insurer),
leaning foundation stumps/ posts
broken/leaking pipes
cracked tiles in the upstairs bathroom
sticking of windows and doors (upstairs) as well as a broken glass pane (also upstairs)
front staircase thread.
A dispute also arose about a hole in the ground floor kitchenette/storage room slab that the
complainant says was made when AG used a jackhammer to remove of floor tiles in that
room. The insurer did not accept liability for that hole but paid the complainant $500 in
addition to the amount it had cash settled for the repairs in the subject room, to allow for the
hole to be filled.
The complainant obtained her own geotechnical report from „ PG ‟ in June 2021. After
reviewing PG ‟s report, the insurer accepted the claims in relation to pool damage, the
concrete stumps and brick walls. In her recent submission (July 2022) the complainant also
indicated she has forgone some items claimed including compensation for financial loss and
claim “f or (still) dripping pipes”.
Amended determination | Case number: 765099 Page 3 of 15
The insurer has made several cash settlement offers for the accepted internal repairs as well
as the stumps replacement, block work and pool repair. The most recent offer on 8 July 2022
was $134,299.53 including a 15 % contingency fee plus a commercial payment of $5,000 for
the time and effort on their behalf to bring the claim to fruition
The insurer says the remaining damage (listed above) was not caused by the flood/storm
event claimed. Rather, it says:
cracks to the slab are pre-existing and due to workmanship or construction issues
hole in kitchenette slab was caused by pre-existing workmanship issues and tree roots
pipe leaks are due to age and deterioration
cracked tiles in the upstairs bathroom relates to workmanship issues
broken glass pane (also upstairs) was not caused by storm/wind as it is internal to the
property
sticking of windows and doors (upstairs) will likely resolve once re-stumping works are
completed.
The complainant says in addition to the above issues that the allowance for restumping and
pool repairs is inadequate.
Restumping allowance to be increased
The insurer changed it decision to decline cover for replacement of the stumps after it
reviewed the complainant‟s geotechnical report completed in June 2021. The insurer obtained
a scope of works (SOW) from NC in November 2021. NC‟s SOW provides for 40 stumps to
be replaced in line with its structural drawing.
Following reinspection with NC, AG provided a quotation which for replacing 28 stumps
based on a quote obtained from construction company „EC‟ in the amount of $44,505.69. The
panel notes EC‟s quote is dated 23 February 2021 (prior to re -attendance by NC in November
2021), therefore could not have taken NC‟s November 2021 SOW into account.
The insurer has not provided any explanation as to why its offer does not accord with NC‟s
SOW despite this being raised by the complainant. It is unclear why it ignored the SOW.
The panel considers it fair in the circumstances the insurer bases its settlement on NC‟s SOW
requiring the replacement of 40 stumps. Using AG ‟s quote of $44,505.59 to replace 28
stumps, the panel determines the insurer should increase its allowance for the replace of
stumps to $78,200.56, being 40 stumps ($59,242.85) plus a 20% builder‟s margin
($11,848.57) plus GST ($7,109.14).
Allowance for pool repairs to be increased
The insurer‟s pool expert (PW) inspected the pool on 26 February 2021 and reported the pool
wa s “severely leaking water”, there were huge cracks to surrounding pool surfaces from
ground movement, and the pebble-crete has hairline cracks (due to movement). However,
PW concluded the cracking appeared to be from general movement rather than the effects of
the flood.
The complainant‟s report from PG addressed loss of soil bearing around the premises,
including the pool area/surrounds and concluded this would have resulted in movement in this
area as well. After reviewing PG‟s report, the insurer overturned its decision to decline of
cover for damage to the concrete pool and surrounding pavers
The insurer offered settlement for the pool damage based on a quote obtained by the
complainant from a pool company (SS) of $17,817.50. The quote was obtained in March
Amended determination | Case number: 765099 Page 4 of 15
2021 and was largely for cosmetic finishes, replacement of elements such as pavers, granite
to benching, tiles and pipes as well as antibacterial cleaning.
PW had, in February 2021 , confirmed that the pool was “severely leaking”, there were “huge
cracks” to surrounding pool surface as well as hairline cracks due to ground movement. PW
concedes that “[t] here is no way of showing if these cracks were not there prior to the floods
due to the severe age of the pool”.
The insurer‟s proposed settlement is based on a quote which does not consider the cost of
repairing cracking damage (which the insurer has accepted). The complainant has provided a
quote from (LS) dated 31 May 2022 of $54,270 (inclusive of GST) for rectification of the pool.
The quote includes a statement from its author to the effect that their first attendance was in
2021 (complainant says this is the same person/organisation as PW).
LS says, “ upon reports sighted from PG and NC, we can only recommend replacement of the
pool as appropriate rectification ” . It recommended a replacement of the concrete pool with
one made of fibreglass.
The insurer has not disputed the quote from LS. The panel determines the settlement for the
pool should be increased to $54,270 (inclusive of GST) in accordance with the quote from LS.
Insurer to cover cracked floor tiles in upstairs bathroom
The insurer denied cover for cracked tiles in the subject bathroom. NJ considered the “ minor
cracking to plasterboard and tiles in the upstairs bathroom and the adjacent loose timber
window frame also located in this region appears to be consistent with damage incurred from
minor ongoing footing system movement and not directly flood related”.
The insurer has since agreed to cover replacement of footing stumps but maintains its decline
for the tile cracks based on NC‟s reports . NC attributes the damage to incorrect installation or
workmanship issues. NC says damage to the tiles is a result of the wall tiles being installed
with no allowance for movement at the floor/wall intersection.
The panel is not satisfied the report shows how the conclusion was reached that the
installation of the tiles was not in line with applicable standards. As the complainant has
pointed out from a report she recently obtained from civil engineer (GT), there is no
information to show the standard which the insurer refers to applied at the time of the
construction. GT concludes that it is more likely cracks occurred due to foundation movement
(which the insurer has agreed to cover).
Based on the above comments by NJ and GT, the panel is not satisfied that the insurer has
established the exclusion for defective workmanship or construction of the bathroom tiles. It is
fair the insurer covers the cost to repair the bathroom tiles.
As there is no quote available for the repairs then within 21 days of the complainant‟s
acceptance of this determination, the insurer is to obtain a quote to repair the bathroom tiling
in accordance with the terms of the policy. The insurer may cash settle the claim based on
the quote.
Insurer should cover 50% of the pool boundary fence repairs
Available information shows the insurer previously paid the complainant for damage to her
front fence. The insurer has not provided much by way of submission in relation to damage to
the pool boundary fence.
Amended determination | Case number: 765099 Page 5 of 15
There is nothing to suggest the proximate cause of this damage was not the flood event. It is
fair the insurer is required to cover this damage
As this is a boundary fence, the insurer is to contribute 50% of the estimated cost of repairs.
Insurer is entitled to decline cover for the concrete slab
The complainant seeks the costs to replace a portion of the downstairs slab. The initial
engineer‟s report from GT does not comment on the slab. In the latest report GT concluded
the cracking of the slab either occurred or worsened significantly comparatively recently, in a
timeframe consistent with the flood event. GT concedes this is subjective and the prior
condition of the slab unknown.
The report from PG says that the area is showing signs of distress. The complainant is relying
on the comments made by PG in relation to the loss of soil strength as contributing to the
cracking.
The insurer relies on the report from NJ who says that the cracks have been caused by an
inadequacy of the construction with a lack of joints and isolation joints. NJ also found that the
cracks were not consistent with flooding. NC found that the damage was consistent with
plastic shrinkage.
NJ reported that concrete slabs of the age and condition of the one in question are expected
to present some degree of cracking, whether it be shrinkage related or otherwise. NJ
concluded the cracks are most likely pre-existing and not as a direct result of the recent flood
event.
NC attributes observed cracking across areas of the slab to factors including on-going soil
movement due to seasonal moisture along with the issues that arise due to installation of the
slab not being to code, not having damp or moisture protection and general workmanship
issues.
The panel accepts, on balance, that some movement is possible. The loss of soil bearing
capacity could have resulted in cracking. However most likely the cracking of the slab was
pre-existing. It is possible exacerbation of pre-existing cracks has occurred due to inundation
from the flood. However, the panel also accepts NC‟s explanation that th e cracks do not
require repairs. There is also no suggestion by the complainant‟s own experts that the slab
requires complete demolition and reinstatement.
Consequently, the insurer is not required to cover repair/replacement of the slab.
Hole in concrete fairly settled
In relation to the hole in the slab which the complainant says was created by AG, the panel
notes that the insurer paid the complainant $500 in the event this is what occurred.
After reviewing the available information, the panel is not satisfied there is sufficient evidence
to establish that AG or the insurer was responsible for the hole. The offer to pay $500 was fair
in the circumstances.
Insurer is entitled to decline cover for front stairs.
The insurer declined cover for damage to a front staircase thread. The complainant says the
damage was not present prior to the flood and should be covered as part of the claim.
Amended determination | Case number: 765099 Page 6 of 15
NJ provided photos labelled “ corrosion on front stair treads ” in its report of 14 May 2019. NC‟s
report of September 2020 also addresses the staircase. NC concludes that the damage to the
front stairs is due to poor workmanship due to a lack of direct fixing to the concrete supports.
In its report in November 2021, NC also says there is corrosion on the front stairs/steps which
is “ due to the lack of maintenance and deterioration of paint over time causing the steel to
become exposed and corrode.
Damage to this stairs/ stairs thread is not addressed in any of the complainant‟s engineer‟s
reports. In the circumstances the panel accepts the damage to the stairs was not caused by
the flood event and was most likely pre-existing.
Insurer can decline claim for damage to windows and French doors.
Photographs exchanged show very aged and deteriorated windows. There is no information
to indicate the windows were damaged by the flood.
NC reported that the windows and doors sticking and not closing is associated with the
high moisture environment at the time of the event and movement of the stumps.
The restumping of the residence should be re-level the property and once re-levelled the
windows and door are likely to return to their initial state.
NC reported the damaged glass panel of the internal doorway to the bedroom is not related to
the event. The wind speeds during the event did not exceed 76 km/hr. The damaged door is
internal and providing the door was restrained, the wind pressure would be reduced and not
have been of enough strength to damage the door. There is no evidence to dispute these
findings. The panel is not satisfied the complainant has established a valid claim for damage
to the doors or glass.
Insurer is to increase settlement offer
Given the above findings the panel determines that within 21 days of the complainant‟s
acceptance of this determination the insurer is to pay the complainant $189,974.89 being:
$78,200.56 for the restumping being 40 stumps ($59,242.85) plus a 20% margin
($11,848.57) plus GST ($7,109.14).
$54,270 for the pool (inclusive of GST)
$3,100 removal of debris (as per AG quote)
$720 Home owners warranty (as per AG quote)
Total $136,290.56 plus 15% contingency ($20443.58) = $156,734.14
Plus, repairs already agreed of $33,240.75 = $189,974.89
The insurer is to cover 50% of the pool boundary fence if it has not already done so and
obtain a quote to repair the bathroom tiling damaged by the movement in accordance with the
terms of the policy. The insurer can cash settle the claim for the tiles based on the quote
obtained.
2.2 Is the complainant entitled to compensation for non-
financial loss?
Yes. The insurer has offered $5,000 in recognition of the delays. The claim has been ongoing
since February 2019.It is fair in the circumstances that the insurer pays the $5,000 it
previously offered.
Amended determination | Case number: 765099 Page 7 of 15
AFCA can award compensation for non-financial loss
Under AFCA‟s Rules, we may award an amount of compensation (capped at $5,400) for non -
financial loss where a complainant has suffered:
an unusual degree or extent of physical inconvenience
time taken to resolve the situation
interference with their expectation of enjoyment or peace of mind.
However, we expect a complainant to be moderately robust and bear the usual stress and
inconvenience associated with an insurance claim.
Delays have caused an unusual degree of inconvenience
The complainant says the insurer took too long to assess the damage and finalise the claim.
As part of its review, AFCA asked the complainant to identify the specific areas of delay and
mishandling. Her response included:
insurer‟s request for response to “unnecessary” communication. She says she cannot be
held responsible for any delay in her responding as she had to manage this along with her
work and busy life
the insurer‟s continued emphasis on the construction is sues in relation to the pool and
stumps which did not accord with some of its experts‟ views
insurer maintaining over a long period that a hole jackhammered into the slab in room near
kitchenette was pre-existing when it was made by AG, as well as the insurer conflating
issues with the downstairs bathroom floor with the rest of the flooring when it had already
accepted the bathroom flooring repairs.
While the insurer says there was no unreasonable delay it has previously offered the
complainant $5,000 for the inconvenience suffered.
The panel notes the claim was first lodged in February 2019. Because of the ongoing dispute
as to the SOW, additional reports and SOW‟s were obtained. There have been extensive
periods of unexplained inaction by the insurer. This progressed throughout this complaint with
the insure r‟ s latest settlement proposal being made in July 2022. Having reviewed all the
submissions (including reports) it is also clear that the insurer could have handled its
assessment better.
It is reasonable to conclude that the claim would not have taken as long as it has, had the
complainant not been required to obtain additional expert evidence to point out the flaws in
the insurer ‟ s decision. The panel accepts the delays have caused the complainant an unusual
degree of physical inconvenience. In the circumstances it is fair that the insurer pays the
$5000 compensation which it previously offered.
2.3 Is the insurer to contribute to the complainant’s
professional costs?
Yes. If it has not already done so the insurer should reimburse the complainants costs for
obtaining a geotechnical report from PG and the report from civil engineer (GT).
Insurer is to pay the complainant ’s civil engineer’s report cost
Paragraph D.5.1 of our Rules provides that AFCA may determine an insurer contribute to
legal or other professional costs incurred by a complainant during an AFCA complaint. Unless
exceptional circumstances apply, AFCA will not require an insurer to contribute more than
$5,000 to these costs.
Amended determination | Case number: 765099 Page 8 of 15
When determining whether an insurer should contribute to the payment of professional fees
incurred, AFCA will consider the complexity of the dispute, whether the advice was
reasonably needed and whether the costs incurred were because the expert advice was
genuinely required.
The complainant obtained professional reports from PG and GT. In the panel‟s view, the
complainant needed to incur the cost to obtain reports as it was important to assist in
establishing her case that flood related damage and cost of repairs exceeds what the insurer
had agreed to cover under the claim. Both reports have assisted and been relied upon in
reaching this determination
The insurer agreed to pay the costs of the geotechnical report from PG of $2,750. If it has not
already done so it should reimburse the complainant this amount.
The complainant also incurred costs of $660 in obtaining the report from GT. The panel is
satisfied the insurer should pay the costs of this report of $660. The invoice has been
exchanged.
2.4 Why is the outcome fair?
The outcome is fair as it recognizes the issues in the complaint and provides a fair cash
settlement of the matters in dispute.
The complainant ‟ s house is a typical Queenslander which is built on stilts. The underneath
area has been converted to a habitable space, although it appears without the necessary
approvals. Therefore, most likely the concrete slab did not have the necessary reinforcement
and waterproofing required for the wet areas and the need therefore for a cash settlement.
The insurer has cash settled the complainant for her contents (the full sum insured in the
amount of $35,404.20), bathroom repairs in the amount of $964.20, external fence repairs
$8,610 and a replacement of a letterbox in the amount of $100. The further cash settlement of
$189,974.89 including the agreed damage represents a fair settlement of the flood related
damage identified in the various reports.
Amended determination | Case number: 765099 Page 9 of 15
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all the information the parties have provided.
While the parties have raised several issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
A panel determined this matter
Due to the nature of this complaint, we referred it to a panel for determination. The panel
includes an ombudsman, a member with significant experience in consumer and small
business advocacy and a member with extensive industry experience.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
Expert report
Record Key points
Amended determination | Case number: 765099 Page 10 of 15
Record Key points
Financial firm’s expert
(NJ)
Engineer’s report
14 - 05 - 2019
Inspection date: - 11 April 2019
“ Concrete s la b
concrete slabs of age / condition expected to “ present some degree of
cracking whether it be shrinkage related or ot herwise ”
while “ flood loadings over a slab do not load the slab in such a way as to
cause tensile forces in the plane of the slab which would caus e this type
of cracking, ongoing swelling (heaving) and shrinking of the founding
material could ”
“ these cracks are most likely pre - existing and not as a direct result of the
recent flood event. With that said, it is reaso nable to conclude that the
existing cracks may have worsened because of the recent flood event.
Determination of the extent of the flood impact, if any, is inconclusive
and unable to be determined without prior knowledge of the construction
and condition o f the slab. ”
Pipe crack
cast iron pipe leading to the upstairs bathroom has a crack
the crack “i s considered general maintenance for the age and condition
of the dwelling ”
“ no visual evidence to suggest any significant footing system movement
or the like had occurred becaus e of the recent flood event in this region
necessary to provide the potential failure mechanism responsible for this
type of damage to occur ” .
Cracks to plasterboard and tiles - upstairs bathroom
“ appears to be consistent with damage incurred from minor ongoing
footing system movement and not directly flood related ”.
“ Det ermination of the extent of the flood impact on this damage, if any, is
inconclusive a nd unable to be determined. However, it is not
unreasonable to consider that some degree of footing system movement
may have occurred becaus e of the recent flood event and that this minor
damage may be attribut ed”.
Front stairs tread
The moderate to severe corrosion to the steel stair treads and stringers
leading to the front entrance is not consistent with damage incurred from
a one - time flood event.
The magnitude of the corrosion indicates this damage has developed
over an extended period .
Amended determination | Case number: 765099 Page 11 of 15
Record Key points
Financial firm’s expert
(NC)
Engineer’s report
08 - 09 - 2020
inspection on 3 August 2020 to determine caus e and extent of damage
as well as repairs required due to flood event on February 2019
First Floor - Bathroom Floor Tiles
The damage is not because of the rain/floo d event,
“damage to the tile is caused by the wall tiles having been installed with
no allowance for movement at the floor/wall intersection. ”
“Wall tiles are generally of a lower quality than floor tiles as they are not
required to be trafficked. The lo wer quality can result in increased
expansion due to tile growth.”
“If the appropriate separation has not been provided between the wall
tile and the floor tile, any expansion of the wall tile will place pressure on
its edge causing it to crack, or the flo or tile to crack, due to the build - up
of compression forces in the wall tile.
In the case of this bathroom, the necessary gap has not been installed at
the cracking damage location, such that any expansion of the wall tiles
from tile growth, would cause th e crack in the tile”.
Pool structure
no damage identified to shell
Pool Coping Pavers
“it is likely that the cracks/gaps between the pavers have shown
indications of variance with the ongoing moisture and thermal changes”
which did not occur within 72 hours of the flood event. Further,
“AS3958.1 - 2007, Ceramic tiles — Part 1: Guide to the installation of
ceramic tiles, Clause 5.4.5 requires movement joints to be installed in tile
systems”,
the pool was “constructed prior to the implementation of a standa rd for
ceramic tiles, no movement joints have been installed”.
Lack of “movement joints would result in significant compression forces
in the tile and grout system, which commonly results in grout fractures
and in some cases drummy pavers”.
Pool – concrete concourse
The concourse slab has been damaged by several factors, including
initial shrinkage of the concrete, lack of adequate saw - cut or control
joints and ground movement.
Ground Level bathroom & kitchenette floor
built - in on the original concrete sl ab/s.
the existing slab/s are not designed in accordance with 'AS2870:
Residential slabs and footings'
Entertainment Area Concrete Slab
cracking is not the result of the flood/rain event.
typical types of plastic shrinkage cracks. Minor shrinkage crackin g of
concrete as seen here is to be expected, particularly with no joints in the
slab provided.
given lack of joints and thickness of the slab, the shrinkage cracking is
not unexpected and is not a structural issue .
Timber Stair Tread
“the stair tread is supported by two small concrete plinths, one to each
end of the stair tread (Photograph 38). However, the timber stair tread is
not directly fixed to the concrete plinths and is able to be moved/rotated”.
The repair for the stair tread is covered by Item 1 1 of the current Scope
of Works”.
“However, the movement of the timber stair tread is due to poor
Amended determination | Case number: 765099 Page 12 of 15
Record Key points
Financial firm’s expert
(RN)
Building consultant
07 - 10 - 2020
reviewed NC report and spoke with its author
Bathroom Floor Tiles:
damage caus ed by incorrect installation as wall tiles are largely hard
grouted against the flooring with minimal allowance given for the tiles to
expand. This means there was no allowance for movement to prevent
pressure from cracking tiles.
Pool Coping Pavers:
There is no installed flexible "movement joints" installed in the perimet er
of the pool coping, whi ch means that the gaps between the paving is the
allowance for movement associated with thermal and wet/dry cycles on
the pavers.
Concrete Concourse (Slab):
there is no steel reinforcement was installed to this area.
evidence of poor workmans hip in the sl ab and work not compliant with
“the Structure and Damp and Weatherproofing requirements of Volume
2 of the National Construction Code” or “with AS2870: Residential slabs
and footings'”
“The habitable rooms of the area should have been constructed in
accord ance with a Development Approval for Building Work, however
this has not occurred”.
based on current standards the “existing slab/s are not designed in
accordance, they are not considered to be suitable for "building in" and
should not be part of a habitable, Class la residence, as has been done
in this instance”.
Pool
“Given the condition of the pool and aligning with the Engineers findings
the leak in my opinion would be more from leaking pipework connected
into pool rather than cracking in the po ols surface. Further investigation
would be able to confirm this using the appropriate tradespeople”.
Amended determination | Case number: 765099 Page 13 of 15
Record Key points
Complainant’s expert
(PG)
Geotech engineer’s
report
08 - 06 - 20
Foundation stumps, swimming pool and general surrounds
insurer‟s engineer (NC) confirmed the stumps/post were leaning and that
this was due to the storm.
scope of its appointment is to report “on movement of the building‟s pier
foundations/stump and any distress caused as well as any distress to in
ground poo l and its surrounds”
Findings
based on the soil type at the premises (moderately reactive), the soil
movement which occurred is due to soil strength being reduces and the
reduction was “likely attributable to inundation of the foundation strata in
the floo ding that occurred in January 2019”, and:
the duration of flood water inundation in the locality (more than 1 metre
in places) was sufficient to result in the advers e effect in soil strengt h in
the areas of soil sampled at the ins ured premises.
the “dwelli ng, pool and in - built undercroft had been constructed
adequately to cope with commonly expected characteristic soil
movements”. It suggests this and serviceability of the building member
have been adversely impacted by the flood event claimed.
the movement /rotation of the piers show the bearing capacity of
surrounding soil has reduced to less than what is recommended for
structures of the type
regardless of any age - related dilapidation prior to the flood, the flood has
accelerat ed the dilapidation and cause d damage to areas of the building
which were previously unaffected such as the „undercroft‟ and pool.
Amended determination | Case number: 765099 Page 14 of 15
Record Key points
Financial firm’s expert
(NC)
Building consultant
statement
01 - 11 - 2021
reinspection on 7 October 2021 to:
> provide scope of works (SOW) for accept ed stump and pool damage
and
> determine which internal damage is related to movement of stumps
first floor bathroom tile damage
not claim related or due to flood. It is because:
there is no allowance for movement at the intersection between wall and
floor tiles and possible expansion due to tile growth,
if allowance provided between joint, cracks would not have occurred,
and the installation not compliant with AS3958.1 Ceramic Tiles code
based on above
first floor win dow and door sti cking
is due to high moisture and movement of stumps
re - stumping to occur which will include relevelling and windows “may
return to initial” state once this occurs
damaged glass panel internal bedroom doorway
unrelated to flood or winds as damage is inside and wind pressure would
be reduced (at time of event wind speed was approximately 76kms/hr)
concrete pool and associated paving
to be repaired in line with “Scope of Works of a specialist pool
contractor”.
ground level entertainment area slab
no flood relat ed cracking
typical plastic shrinkage cracks. Shrinkage is minor and expected given
the lack of joints in the slab and thickness as well as the dimensions of
the area which exceeds recommended size.
the cracks are not a structural issue
ground floor concrete stumps
moved and subsided due to loss of bearing capacity and restraint
“stumps will continue to provide support for the residence in their current
state, however they may continue to move with the changes in moisture
content of the reactive soils”
stumps to be repaired in line with SOW and structural drawing provided
front stairs
corrosion is due to the lack of maintained and deterioration of paint over
time causing the steel to become exposed and corrode.
The paint protects the stee l from oxidiz ation and if the paint layer is not
adequately maintained, the steel becomes exposed and rusting occurs.
The section between the stringer and treat dues not allow drainage of
the water, which further accelerates the deterioration of the paint and
oxidization of the steel once exposed.
Finding:
1 ) Tiles in Upstairs bathroom
more likely cracks occurred due to foundation movement
Amended determination | Case number: 765099 Page 15 of 15
Record Key points
insufficient evidence to prove cracks were due to incorrect installation
AS3958. 1 is not mandatory but good practice
even if AS applied, the insurer‟s reports do not show when tiles were
installed and what standard applied at the time
no evidence floor tiles different from wall tiles to support conclusion that
different quality tiles resulted in different outcom es
the explanation about impact on lack of expansion joints “has no
relevance in this instance because the extent of tiling that could possibly
contribut e to this is less than half a tile, and its top edge is unrestrained.”
2) Stumps
NC identified 40 stum ps but AJ has quoted 28 stumps wit hout
explanation as to which stumps are being replaced and which ones
aren‟t
3) Concrete slab cracks
considered whet her the pattern of cracking and displacement is
consistent with flood, the apparent age of the cracks cons istent with the
timing of the flood. Also considered evidence of the date of construction,
and of what standards or reasonable workmanship would have been
applicable at that time.
The “observed pattern of cracking and displacement is consistent with
subsid ence in the rear left corner of the residence, in the vicinity of the
upstairs bathroom.”
concrete can be weak when subjected to tensile strength, tension stress
“can arise because of shrinkage strains, or as a result of bending, which
produces tension on one face and compression on the other. When
considering the ground floor slab in its entirety, subsidence in the back
left corner of the residence would create top - face tensile bending
stresses consistent with the observed pattern”
pre - flood slab levels un known but measurements taken on inspection
“show around a 35 mm settlement in this area relative to the centre of
the slab”
pattern of cracking from shrinkage not predominant in the observed
cracks based on appearance (c olour and degree of spalling)
cracks “either occurred or wors ened significantly comparatively recently,
in a timeframe consistent with the flood event”
time of construction unknown therefore cannot establish whether
construction standard contributed to damage .