Determination 762975

Lender accepted builder payment schedule, released progress payments and did not inspect build

FirmWestpac
Decided2021-09-13
ProductCredit · Home loan
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The complainant built two townhouses with a construction loan and his builder failed, so he engaged a second builder at extra cost. AFCA found the lender had no obligation to check the payment schedule, inspect the build or police the builder, and ordered nothing.

A lender acting as a finance provider owes no duty to advise on or supervise building work, and the builder remains responsible for quality.

Issues

Subjects and remedies

no remedy

Related

All Westpac determinations · Find similar determinations

Text of the determination

Determination Case number 762975 Financial firm RAMS Financial Group Pty Ltd Determination | Case number: 762975 Page 2 of 8 Case number: 762975 30 June 2021 1 Determination overview Complaint In 2016, the complainant applied for a $750,000 construction loan through financial firm M to build two townhouses. During its loan assessment, M obtained a valuation report. The valuer said that the payment schedule within the building contract did not meet the minimum building industry guidelines. M alerted the complainant and suggested that he review the payment schedule with the builder. The complainant did not proceed with the M application. In 2017, the financial firm (lender) provided the complainant with a construction loan for $830,000 to build the two townhouses. The complainant experienced problems with the builder during the build to frame stage. The complainant‟s relationship with the builder deteriorated and ultimately, he engaged a second builder to complete the construction at an additional cost of $400,000. The complainant has raised several complaints against the lender including it:  did not ensure the payment scheduled in the building contract met industry standards  failed to do a thorough check on the builder and the contract  did not inspect the property at frame stage. 1.1 Issues and key findings Did the lender make an error when it accepted the payment schedule in the building contract? When it approved the loan, the lender was entitled to accept the payment schedule in the building contract. M‟s comment that the payment schedule in the building contract “was not in line with industry standard” did not require the lender to insist that the builder change it. M is a separate legal entity to the lender and its comments did not bind the lender. Did the lender breach its internal lending procedure? The lender did not breach its internal lending procedure. It satisfied al requirements in providing the loan and releasing payments to the builder. Did the lender make an error by releasing the payments? By signing the payment request forms, the complainant authorised the lender to release the progress payments to the builder. The lender was not obliged to inspect the building site prior to releasing the progress payments and was not required to inspect the quality of the build. Why is the outcome fair? The events the complainant experienced with the builder are unfortunate. However, the lender has acted in accordance with industry practice and is not responsible for the actions of the builder. In these circumstances, it would not be fair to require the lender to compensate the complainant. 1.2 Determination This determination is in favour of the lender. The lender is not required to compensate the complainant or take any further action. Determination | Case number: 762975 Page 3 of 8 2 Reasons for determination 2.1 Did the lender make an error when it accepted the payment schedule in the building contract? The complainant initially applied for a construction loan through M At the end of 2016, the complainant approached M for funds to construct the townhouses. Email correspondence passing between the complainant and M shows that the loan he initially applied for was $750,000. Ultimately, this loan application did not proceed. During this loan assessment process, M obtained a valuation from an external valuer. On 26 October 2016 (and following receipt of the valuer‟s report), M emailed the complainant: Valuer also noted the progress [payment] schedule also (sic) not in line with industry standard and should be as follows … please get the builder to amend. The email trail confirms that M followed up with the complainant again on 3 November and 8 December 2016. The complainant did not proceed with the M loan, nor was the building contract amended. The complainant‟s contention is that M‟s email demonstrates the payment schedule in the building contract did not comply with industry standard and that the lender‟s ultimate acceptance of it was an error. The lender and M are separate legal entities The complainant ultimately did not follow through with M‟s comments that the payment schedule in the building contract was not in line with industry standard. Rather, in March 2017, he applied to the lender for the loan, which I note was for $830,000. It is clear that M and the lender are separate legal entities. There is no suggestion that M was acting as the lender‟s agent or that its comments and bound the lender in any way. The lender was not obliged to check the building contract payment schedule The complainant says the lender:  did not follow the procedure in place to value and inspect the progress schedule to make sure it was in line with building industry standards, and  failed to do a thorough check on the builder and the contract. It is important to consider the relationship between a financial firm and its customer. In general, a financial firm that is a lender or a credit provider does not have a „fiduciary‟ duty or responsibility to its customer. This means it is not obliged to advise a customer that a service or product is not in their best interests or that there may be other services that would better suit their needs. A fiduciary responsibility arises only where the lender ‟s role is seen to extend beyond that of finance provider and into the other area of advice. This happens if the lender provides advice or otherwise causes the customer to reasonably believe the lender has assumed that responsibility. Determination | Case number: 762975 Page 4 of 8 It appears the complainant was expecting the lender to form its opinion on the payment schedule meeting building industry standards. However, the lender was under no obligation under its lending procedure or the Banking Code of Practice to do so. In any event, the complainant was aware prior to lodging the loan application with the lender the payment schedule did not meet building industry guidelines. It was his responsibility to make his own independent enquiries to confirm the payment schedule met building industry guidelines. The lender is not accountable to its customers to enforce building industry guidelines. In this instance, the lender did not provide any form of advice to the complainant during the application and approval process. Rather it assumed (and maintained) its position as a lender assessing a credit application. T he lender‟s involvement extended to that of lender assessing and offering credit rather than that of advisor or project manager managing the construction of the townhouses. The lender was not required to provide advice about the building contract and payment schedule. This is a matter entirely for the complainant. 2.2 Did the lender breach its internal lending procedure? The complainant says the lender failed to comply with its internal policy The complainant says the lender failed to comply with its internal lending procedure because the:  building licence number did not match the building company and it should have identified this  builder noted on the contract had never been licensed or insured. The building license number matched the signed building contract On 21 March 2017, the complainant signed a building contract with the builder. The building contract was a standard Housing Industry Association (HIA) building contract. The building contract listed the builders name as B Pty Ltd. At the time of signing this building contract, the building plans and specifications had not been provided to the local council for approval. On 6 November 2017, a construction certificate was issued. The certificate noted the building plans and specifications had been approved on 24 October 2017 and 6 November 2017. I have reviewed the information provided by the parties and it would appear that between March 2017 and November 2017, the builder company changed its name. I have formed this view as there is a second undated and unsigned contract showing the builders name changing to B1 Pty Ltd. The signed building contract listed the builders name as B Pty Ltd and its builders license number was XXXXXXC. To verify the builders licence number, the lender‟s lending procedure required it to: Obtain a copy of the builder‟s licence *note this needs to be a photo of his licence same as drivers licence * or online proof The lender obtained the photo of the build er‟s licence which recorded the builders name as B Pty Ltd. It also confirmed the builders licence number as XXXXXXC. As this matched the signed building contract, the lender had satisfactorily completed this step of its internal lending procedure. Determination | Case number: 762975 Page 5 of 8 The lender was not responsible for ensuring information provided was correct The complainant says the insurance details were in the name of BC Pty Ltd and not B1 Pty Ltd. As set out above, the signed building contract recorded the builder as B Pty Ltd. I have reviewed the lender‟s procedure which outlines the requirements the lender must satisfy when providing a construction loan. The lending procedure required the lender to obtain the following insurance documents:  home owners warranty insurance, and  builder ‟ s public liability insurance. The lender obtained the home owners warranty insurance certificate (certificate) dated 28 August 2017. This certificate confirmed the:  details of the owners  property address, and  contract date and sum. The builder name listed on this certificate was noted as BC Pty Ltd and the builder‟s licence number as XXXXXXC. The lender was only required to obtain a copy of the certificate to satisfy its lending policy. The lender was not responsible for ensuring the information provided to the insurer was correct. It was in the complainant‟s best interests to confirm the details were accurate within the certificate as ultimately the insurance was for his benefit. A certificate of currency dated 20 September 2017 confirmed the builder B Pty Ltd held builders public liability insurance through to 1 September 2018. The policy was current, and the builder listed matched the builder details in the signed contract. For these reasons, I am satisfied the lender has not breached its internal lending policy as B Pty Ltd held the appropriate public liability insurance. 2.3 Did the lender make an error by releasing the progress payments? The complainant signed the progress payment requests The complainant signed the following progress payment requests: Progress Claim Date Stage Amount 1 29 November 2017 Part Deposit + Slab $171,005.60 2 17 May 2018 Frame $50,000 3 28 May 2018 Balance of Deposit $61,500 The complainant says the builder did not build according to the council approved and engineering plans and used cheaper building materials. The complainant informed the lender of his concerns on 20 March 2018, when he emailed the lender about the frame stage payment The next stage of progress payment is due soon which is the framing stage. Would it be in our best interest to have a copy of approval of that stage from the certifier before we draw down the payment? Determination | Case number: 762975 Page 6 of 8 The loan terms and conditions confirm to pay the builder, the complainant […] must make any progress payment claim by completing a Progress Payment Request substantially in the form of the documents we provide to you and attaching the relevant builder‟s invoice. The payment instructions recorded on progress claim 2 and 3 recorded the complainant‟s bank account. I am of the view the lender did address the complainant‟s concerns at the time of lodging progress claim 2 and 3. This is because the lender‟s contact notes from April 2018 recorded it  woul d not release any payment to the builder without the customer‟s consent  suggested the complainant should seek out legal advice or contact the Ombudsman regarding the building dispute. On 29 May 2018, the lender released $110,000 to the complainant‟s bank account. In this situation, the lender‟s actions in response to the complainant‟s concerns were fair and reasonable. It did not release the payments directly to the builder but rather released them to the complainant himself. The complainant‟s decision to subsequently make these payments to the builder is a matter for himself and the lender is not responsible for this. Accordingly, I am satisfied that the:  lender did not make an error in releasing the progress payments  complainant did not incur a loss as a result of the lender‟s conduct. The lender did not have to inspect the site or ensure the builder was entitled to payment The loan contract terms and conditions state […] if we make a progress payment, it does not mean that the building work is necessarily satisfactory. You are responsible for ensuring that all plans are followed and that all materials and workmanship are satisfactory. The loan contract and authority to commence construction letter makes it clear the complainant was responsible for ensuring the build was progressing satisfactorily before authorising the lender to pay the builder. In short, when signing the payment requests, the complainant acknowledged the build has reached the staged indicated by the builder and he was authorising payment. There was no independent obligation on the lender to inspect the build or satisfy itself the builder should be paid. There was nothing in the loan contract which required it to do so before it released the payments (other than the final payment which was not released). In the ordinary course, a lender does not act as a “project manager” when construction is being undertaken. The complainant was responsible for ensuring the build was progressing satisfactorily before the builder was paid and it was at his discretion to instruct the lender to pay him. In other words, the lender was not required to inspect the site to ensure it met quality standards. Ultimately, the builder is responsible for the quality of the construction. A progress payment inspection was not required at frame stage The complainant says the builder  claimed variations on excavation and steel beams, and Determination | Case number: 762975 Page 7 of 8  took too much money upfront and the quality of work to frame stage was poor. The lender‟s policy stated it would order a progress payment i nspection at frame stage if the loan to valuation ratio (LVR) was equal to or greater than 80%. The complainant‟s LVR on the loan application was 51.49%. In the circumstances here, the lender was not required to complete a progress inspection at frame stage. It is also important to bear in mind that when a lender does undertake a building inspection part-way through a construction, it does so for its own purposes to ensure that the construction is progressing as payments are being drawn down and that its security position is adequate. The level of the lender‟s inspection does not need to be to building standards. The lender is not responsible for the builder’s conduct On 15 June 2018, the complainant and the builder entered into a deed of settlement and release, ending the building contract. It is unfortunate the complainant found himself in the position that he did with the builder. I sympathise with the complainant. However, the lender did not breach its obligations to the complainant. It provided him with a loan that met his loan requirements. The lender is not responsible for the builder‟s conduct. 2.4 Why is the outcome fair? AFCA’s outcome is based on fairness The outcome is fair in all the circumstances because the lender acted as a prudent and diligen t lender when it accepted the complainant‟s application for a construction loan. There was no obligation on the lender to provide advice to the complainant on the contents of the building contract, including the payment schedule not meeting building industry standards. It was in the complainant‟s best interests to review the contents of his building contract upon receipt of the 2016 M email. The complainant had an opportunity to amend the progress payment schedule with the builder but chose not to do so when he signed the building contract in March 2017. It would not be fair for the lender to compensate the complainant as it was not responsible for the quality the build or conduct of the builder. Determination | Case number: 762975 Page 8 of 8 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. 3.2 Progress payment schedule Stage Percent Amount Deposit 10.00% $76,200 Slab 20.00% $152,400 Frame 20.00% $152,400 Enclosure 25.00% $190,500 Finishe s 20.00% $152,400 Practical Completion 5.00% $38,100 Total 100.00% $762,000

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.