Home / Westpac / Determination 762975
Determination 762975
Lender accepted builder payment schedule, released progress payments and did not inspect build
Summary
The complainant built two townhouses with a construction loan and his builder failed, so he engaged a second builder at extra cost. AFCA found the lender had no obligation to check the payment schedule, inspect the build or police the builder, and ordered nothing.
A lender acting as a finance provider owes no duty to advise on or supervise building work, and the builder remains responsible for quality.
Issues
- Responsible lending failure primary · not upheld“The lender was not obliged to check the building contract payment schedule. The lender was not required to provide advice about the building contract and payment schedule.”
- Other secondary · not upheld“Alleged breach of internal lending procedure over builder licence and insurance details. The lender did not breach its internal lending procedure.”
- Payment error secondary · not upheld“The lender did not have to inspect the site or ensure the builder was entitled to payment before releasing progress payments.”
Subjects and remedies
no remedy
Related
Text of the determination
Determination
Case number 762975
Financial firm RAMS Financial Group Pty Ltd
Determination | Case number: 762975 Page 2 of 8
Case number: 762975 30 June 2021
1 Determination overview
Complaint
In 2016, the complainant applied for a $750,000 construction loan through financial firm M to
build two townhouses. During its loan assessment, M obtained a valuation report. The valuer
said that the payment schedule within the building contract did not meet the minimum building
industry guidelines. M alerted the complainant and suggested that he review the payment
schedule with the builder. The complainant did not proceed with the M application.
In 2017, the financial firm (lender) provided the complainant with a construction loan for
$830,000 to build the two townhouses. The complainant experienced problems with the
builder during the build to frame stage. The complainant‟s relationship with the builder
deteriorated and ultimately, he engaged a second builder to complete the construction at an
additional cost of $400,000.
The complainant has raised several complaints against the lender including it:
did not ensure the payment scheduled in the building contract met industry standards
failed to do a thorough check on the builder and the contract
did not inspect the property at frame stage.
1.1 Issues and key findings
Did the lender make an error when it accepted the payment schedule in the
building contract?
When it approved the loan, the lender was entitled to accept the payment schedule in the
building contract. M‟s comment that the payment schedule in the building contract “was not in
line with industry standard” did not require the lender to insist that the builder change it. M is a
separate legal entity to the lender and its comments did not bind the lender.
Did the lender breach its internal lending procedure?
The lender did not breach its internal lending procedure. It satisfied al requirements in
providing the loan and releasing payments to the builder.
Did the lender make an error by releasing the payments?
By signing the payment request forms, the complainant authorised the lender to release the
progress payments to the builder. The lender was not obliged to inspect the building site prior
to releasing the progress payments and was not required to inspect the quality of the build.
Why is the outcome fair?
The events the complainant experienced with the builder are unfortunate. However, the
lender has acted in accordance with industry practice and is not responsible for the actions of
the builder. In these circumstances, it would not be fair to require the lender to compensate
the complainant.
1.2 Determination
This determination is in favour of the lender. The lender is not required to compensate the
complainant or take any further action.
Determination | Case number: 762975 Page 3 of 8
2 Reasons for determination
2.1 Did the lender make an error when it accepted the payment
schedule in the building contract?
The complainant initially applied for a construction loan through M
At the end of 2016, the complainant approached M for funds to construct the townhouses.
Email correspondence passing between the complainant and M shows that the loan he
initially applied for was $750,000. Ultimately, this loan application did not proceed.
During this loan assessment process, M obtained a valuation from an external valuer. On
26 October 2016 (and following receipt of the valuer‟s report), M emailed the complainant:
Valuer also noted the progress [payment] schedule also (sic) not in line with
industry standard and should be as follows
…
please get the builder to amend.
The email trail confirms that M followed up with the complainant again on 3 November and
8 December 2016. The complainant did not proceed with the M loan, nor was the building
contract amended.
The complainant‟s contention is that M‟s email demonstrates the payment schedule in the
building contract did not comply with industry standard and that the lender‟s ultimate
acceptance of it was an error.
The lender and M are separate legal entities
The complainant ultimately did not follow through with M‟s comments that the payment
schedule in the building contract was not in line with industry standard.
Rather, in March 2017, he applied to the lender for the loan, which I note was for $830,000.
It is clear that M and the lender are separate legal entities. There is no suggestion that M was
acting as the lender‟s agent or that its comments and bound the lender in any way.
The lender was not obliged to check the building contract payment schedule
The complainant says the lender:
did not follow the procedure in place to value and inspect the progress schedule to make
sure it was in line with building industry standards, and
failed to do a thorough check on the builder and the contract.
It is important to consider the relationship between a financial firm and its customer. In
general, a financial firm that is a lender or a credit provider does not have a „fiduciary‟ duty or
responsibility to its customer. This means it is not obliged to advise a customer that a service
or product is not in their best interests or that there may be other services that would better
suit their needs.
A fiduciary responsibility arises only where the lender ‟s role is seen to extend beyond that of
finance provider and into the other area of advice. This happens if the lender provides advice
or otherwise causes the customer to reasonably believe the lender has assumed that
responsibility.
Determination | Case number: 762975 Page 4 of 8
It appears the complainant was expecting the lender to form its opinion on the payment
schedule meeting building industry standards. However, the lender was under no obligation
under its lending procedure or the Banking Code of Practice to do so. In any event, the
complainant was aware prior to lodging the loan application with the lender the payment
schedule did not meet building industry guidelines. It was his responsibility to make his own
independent enquiries to confirm the payment schedule met building industry guidelines. The
lender is not accountable to its customers to enforce building industry guidelines.
In this instance, the lender did not provide any form of advice to the complainant during the
application and approval process. Rather it assumed (and maintained) its position as a lender
assessing a credit application. T he lender‟s involvement extended to that of lender assessing
and offering credit rather than that of advisor or project manager managing the construction of
the townhouses. The lender was not required to provide advice about the building contract
and payment schedule. This is a matter entirely for the complainant.
2.2 Did the lender breach its internal lending procedure?
The complainant says the lender failed to comply with its internal policy
The complainant says the lender failed to comply with its internal lending procedure because
the:
building licence number did not match the building company and it should have identified
this
builder noted on the contract had never been licensed or insured.
The building license number matched the signed building contract
On 21 March 2017, the complainant signed a building contract with the builder. The building
contract was a standard Housing Industry Association (HIA) building contract. The building
contract listed the builders name as B Pty Ltd. At the time of signing this building contract, the
building plans and specifications had not been provided to the local council for approval.
On 6 November 2017, a construction certificate was issued. The certificate noted the building
plans and specifications had been approved on 24 October 2017 and 6 November 2017.
I have reviewed the information provided by the parties and it would appear that between
March 2017 and November 2017, the builder company changed its name. I have formed this
view as there is a second undated and unsigned contract showing the builders name
changing to B1 Pty Ltd.
The signed building contract listed the builders name as B Pty Ltd and its builders license
number was XXXXXXC. To verify the builders licence number, the lender‟s lending procedure
required it to:
Obtain a copy of the builder‟s licence *note this needs to be a photo of his licence
same as drivers licence * or online proof
The lender obtained the photo of the build er‟s licence which recorded the builders name as
B Pty Ltd. It also confirmed the builders licence number as XXXXXXC.
As this matched the signed building contract, the lender had satisfactorily completed this step
of its internal lending procedure.
Determination | Case number: 762975 Page 5 of 8
The lender was not responsible for ensuring information provided was correct
The complainant says the insurance details were in the name of BC Pty Ltd and not B1 Pty
Ltd. As set out above, the signed building contract recorded the builder as B Pty Ltd.
I have reviewed the lender‟s procedure which outlines the requirements the lender must
satisfy when providing a construction loan. The lending procedure required the lender to
obtain the following insurance documents:
home owners warranty insurance, and
builder ‟ s public liability insurance.
The lender obtained the home owners warranty insurance certificate (certificate) dated
28 August 2017. This certificate confirmed the:
details of the owners
property address, and
contract date and sum.
The builder name listed on this certificate was noted as BC Pty Ltd and the builder‟s licence
number as XXXXXXC.
The lender was only required to obtain a copy of the certificate to satisfy its lending policy.
The lender was not responsible for ensuring the information provided to the insurer was
correct. It was in the complainant‟s best interests to confirm the details were accurate within
the certificate as ultimately the insurance was for his benefit.
A certificate of currency dated 20 September 2017 confirmed the builder B Pty Ltd held
builders public liability insurance through to 1 September 2018. The policy was current, and
the builder listed matched the builder details in the signed contract.
For these reasons, I am satisfied the lender has not breached its internal lending policy as B
Pty Ltd held the appropriate public liability insurance.
2.3 Did the lender make an error by releasing the progress
payments?
The complainant signed the progress payment requests
The complainant signed the following progress payment requests:
Progress Claim Date Stage Amount
1 29 November 2017 Part Deposit + Slab $171,005.60
2 17 May 2018 Frame $50,000
3 28 May 2018 Balance of Deposit $61,500
The complainant says the builder did not build according to the council approved and
engineering plans and used cheaper building materials. The complainant informed the lender
of his concerns on 20 March 2018, when he emailed the lender about the frame stage
payment
The next stage of progress payment is due soon which is the framing stage.
Would it be in our best interest to have a copy of approval of that stage from the
certifier before we draw down the payment?
Determination | Case number: 762975 Page 6 of 8
The loan terms and conditions confirm to pay the builder, the complainant
[…] must make any progress payment claim by completing a Progress Payment
Request substantially in the form of the documents we provide to you and
attaching the relevant builder‟s invoice.
The payment instructions recorded on progress claim 2 and 3 recorded the complainant‟s
bank account. I am of the view the lender did address the complainant‟s concerns at the time
of lodging progress claim 2 and 3. This is because the lender‟s contact notes from April 2018
recorded it
woul d not release any payment to the builder without the customer‟s consent
suggested the complainant should seek out legal advice or contact the Ombudsman
regarding the building dispute.
On 29 May 2018, the lender released $110,000 to the complainant‟s bank account. In this
situation, the lender‟s actions in response to the complainant‟s concerns were fair and
reasonable. It did not release the payments directly to the builder but rather released them to
the complainant himself. The complainant‟s decision to subsequently make these payments
to the builder is a matter for himself and the lender is not responsible for this.
Accordingly, I am satisfied that the:
lender did not make an error in releasing the progress payments
complainant did not incur a loss as a result of the lender‟s conduct.
The lender did not have to inspect the site or ensure the builder was entitled to
payment
The loan contract terms and conditions state
[…] if we make a progress payment, it does not mean that the building work is
necessarily satisfactory. You are responsible for ensuring that all plans are
followed and that all materials and workmanship are satisfactory.
The loan contract and authority to commence construction letter makes it clear the
complainant was responsible for ensuring the build was progressing satisfactorily before
authorising the lender to pay the builder. In short, when signing the payment requests, the
complainant acknowledged the build has reached the staged indicated by the builder and he
was authorising payment.
There was no independent obligation on the lender to inspect the build or satisfy itself the
builder should be paid. There was nothing in the loan contract which required it to do so
before it released the payments (other than the final payment which was not released). In the
ordinary course, a lender does not act as a “project manager” when construction is being
undertaken. The complainant was responsible for ensuring the build was progressing
satisfactorily before the builder was paid and it was at his discretion to instruct the lender to
pay him.
In other words, the lender was not required to inspect the site to ensure it met quality
standards. Ultimately, the builder is responsible for the quality of the construction.
A progress payment inspection was not required at frame stage
The complainant says the builder
claimed variations on excavation and steel beams, and
Determination | Case number: 762975 Page 7 of 8
took too much money upfront and the quality of work to frame stage was poor.
The lender‟s policy stated it would order a progress payment i nspection at frame stage if the
loan to valuation ratio (LVR) was equal to or greater than 80%. The complainant‟s LVR on the
loan application was 51.49%. In the circumstances here, the lender was not required to
complete a progress inspection at frame stage.
It is also important to bear in mind that when a lender does undertake a building inspection
part-way through a construction, it does so for its own purposes to ensure that the
construction is progressing as payments are being drawn down and that its security position
is adequate. The level of the lender‟s inspection does not need to be to building standards.
The lender is not responsible for the builder’s conduct
On 15 June 2018, the complainant and the builder entered into a deed of settlement and
release, ending the building contract. It is unfortunate the complainant found himself in the
position that he did with the builder. I sympathise with the complainant. However, the lender
did not breach its obligations to the complainant. It provided him with a loan that met his loan
requirements. The lender is not responsible for the builder‟s conduct.
2.4 Why is the outcome fair?
AFCA’s outcome is based on fairness
The outcome is fair in all the circumstances because the lender acted as a prudent and
diligen t lender when it accepted the complainant‟s application for a construction loan.
There was no obligation on the lender to provide advice to the complainant on the contents of
the building contract, including the payment schedule not meeting building industry standards.
It was in the complainant‟s best interests to review the contents of his building contract upon
receipt of the 2016 M email. The complainant had an opportunity to amend the progress
payment schedule with the builder but chose not to do so when he signed the building
contract in March 2017.
It would not be fair for the lender to compensate the complainant as it was not responsible for
the quality the build or conduct of the builder.
Determination | Case number: 762975 Page 8 of 8
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
3.2 Progress payment schedule
Stage Percent Amount
Deposit 10.00% $76,200
Slab 20.00% $152,400
Frame 20.00% $152,400
Enclosure 25.00% $190,500
Finishe s 20.00% $152,400
Practical Completion 5.00% $38,100
Total 100.00% $762,000
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.