Home / IAG / Determination 762926

Determination 762926

Claim declined for cracked flooring tiles under faulty workmanship/structural defect exclusion

FirmIAG
Decided2021-11-12
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The complainant claimed under home and contents insurance for cracked floor tiles after the insurer's expert attributed the damage to defective building works. AFCA found the damage resulted from building defects and movement over time, which is excluded, and determined the complaint in favour of the insurer.

The loss was excluded under the policy exclusions for faulty workmanship, structural defects and gradual deterioration, as the damage resulted from a lack of movement joints and differential earth movement.

Issues

Subjects and remedies

broker or intermediaryhome or building damageno remedy

Related

All IAG determinations · Find similar determinations

Text of the determination

Determination Case number 762926 Financial firm Insurance Australia Limited Determination | Case number: 762926 Page 1 of 6 Case number: 762926 12 November 2021 1 Determination overview 1.1 Complaint The complainant holds a home and contents insurance policy which provides cover for accidental loss or damage caused by various listed insured events. The complainant lodged a claim for cracked flooring tiles at her property. The financial firm (insurer) declined the claim as it says the damage is a result of faulty workmanship or a building defect. The complainant disputes the insu rer’s decision and is seeking for the insurer to accept the claim. 1.2 Issues and key findings Are the cracked tiles caused by faulty workmanship, structural defects or faulty design and therefore excluded from cover? Yes, the evidence shows that the damage has occurred due to defective work and is expressly excluded from cover. Why is the outcome fair? Yes, the outcome is fair as the damage has been apparent for a considerable time due to a longstanding structural and building defect and which constitutes a common exclusion to general insurance policies. 1.3 Determination This determination is in favour of the financial firm. The claim for cracked tiles is excluded. Determination | Case number: 762926 Page 2 of 6 2 Reasons for determination 2.1 Are the cracked tiles caused by faulty workmanship, structural defects or faulty design and therefore excluded from cover? Damage to tiles accidental The complainant bears the initial onus to establish that a loss or damage has occurred and is covered under the policy. This is called a prima facie claim. Once the complainant establishes a prima facie claim, the onus shifts to the insurer to show the damage is not covered under the policy or it is entitled to decline the claim. The complainant purchased the property in 2008 and after a few years became aware of cracked flooring tiles. On 3 August 2020 the complainant engaged trades to replace the tiles with new vinyl flooring. When the tilers started removing the tiles, they observed moisture beneath the tiles and the tiles lifted easily at the junction where a new cement slab extension to the property joined the existing structure. The complainant was unsure of the cause of moisture. That same day she lodged a claim for damage to floor tiles and damage to carpet. Neither the complainant nor her broker have identified the section of the policy which they say provides indemnity. The claim is simply described as water damage to tiling. The policy states it provides coverage for accidental loss and accidental damage. Accidental is not defined. I am satisfied the damage to the tiles is accidental. Accordingly, the complainant is entitled to be indemnified subject to any applicable exclusions. Insurer relies on Exclusions The home and contents insurance policy says it will not cover accidental loss or damage caused by:  a fault in an item, faulty workmanship, structural defects or faulty design  settling, shrinkage or any movement of the earth  landslide or subsidence not occurring within 72 hours after a direct result of storm, flood, tsunami, rainwater, snow, wind, explosion, earthquakes or escaping liquid from a fixed pipe.  Water entering your buildings – because of a structural defect, faulty design or faulty workmanship when your buildings were constructed  Gradual deterioration The insurer engaged an expert P who attributed the cracking to defective building works including the lack of a control joint for the floor tiles between the new and old sections of the house. The claim for the broken tiles was declined on 30 August 2020 and the complainant herself then arranged invasive tests by her own builder M and passed on his report to the insurer. The complainant understood the insurer may do a further inspection but when this did not happen and she was suffering due to the presence of concrete dust, she authorised her builder to re commence his work on 18 September. The complainant claims for the costs of the invasive works and for the costs of repair and replacement of the tiles Determination | Case number: 762926 Page 3 of 6 I nsurer’s expert report The Insurer ’s expert (P) reported the tiles in the lounge/dining area had already been removed but P was able to assess the tiles present in the toilet and adjoining hallway. P reported:  a line of masonry brickwork embedded within the concrete slab, extending in a north to south direction across the intersection of the dining and living rooms, represented the original rear wall of the house prior to the extension being added  inspection of the embedded brickwork revealed the presence of a vapor barrier on the southern side of the brickwork, confirming the brickwork did form an external wall prior to the extension of the property.  without conducting an invasive inspection, it cannot conclusively confirm if a vapor barrier has been installed beneath the extension concrete slab  a lack of a control joint to the floor tiles which is required at discontinuities in the substrate (the intersecting point between two separate substrate surfaces), which in this instance is the original concrete slab and the extension concrete slab  cracking to the cornice is at the intersecting point between the original rear wall and the new extension and is the result of differential movement between the two structures  a lack of control joints in the ceiling which are required to absorb movements in the underlying substrate and minimise potential stress and cracking in plasterboard surfaces. P has concluded in the report the cracking and dislodgement of floor tiles at the intersection of the original house and the extension is due to lack of movement joints to the tiles. P stated this is a requirement under Australian Standards (AS). P says the applicable standard is AS 3958.1, 2007 Guide to the installation of ceramic tiles. P says the presence of moisture at the intersection of the original house slab and extension is a result of poor building practice and is not a result of water escaping within 72 hours of a single event. P says the cracking to the cornice and ceiling is a result of naturally occurring ground and structural movement. Complainant evidence and submissions The complainant engaged a builder (M) to conduct an invasive assessment. M jackhammered into the area where the two slabs joined. M reported the new slab has dowel bars joining the 2 slabs together. The new slab has been poured over the existing set down slab and it has its own footing and plastic membrane. The complainant disputes the insurer’s decision and says:  the insurer ’s decision pre ceded the invasive testing  M conducted an invasive investigation and has confirmed a waterproof membrane was installed during construction of the extension to the property and  A construction joint has also been provided to secure the original concrete slab to the extension slab. The complainant also says she had requested the insurer conduct a second visit to the property prior to the replacement of the flooring, however the insurer did not conduct a second visit. Determination | Case number: 762926 Page 4 of 6 Further evidence and submissions P has reviewed the report provided by M and says the existence of moisture beneath the tiles proves either the waterproof membrane was incorrectly installed or breached. P acknowledges the presence of a construction joint installed during the extension to the property. However, P says it is not an answer to the lack of movement joints for the installation of ceramic floor tiles. The complainant has rejected P’s ar gument. The complainant says, at the time the extension to the property was constructed, there was no building standard in existence for movement joints to be used. The complainant says the dowel bars used as construction joints were a better option than the movement joints. The insurer has subsequently provided information confirming the requirement for movement joints to the installation of ceramic tiles exists since 1991. In response to this new information the complainant now says:  the tiles were remov ed prior to the insurer’s property visit and there is no evidence to establish the absence of movement joints to the floor tiles  insurer’s decision -making is not based on evidence and the insurer needs to accept the claim. Damage is caused by building defect I have reviewed all information provided by both the parties. When the claim was lodged, the flooring tiles had already been removed in the living/ dining area which made it impossible to visually inspect and confirm the presence or absence of movement joints. The reason for this is because the complainant had already decided to repair the damage and only realised there may be an insurance claim during the course of the work. I am satisfied that a second visit by the insurer would not have yielded any new information other than what is available now. Both the parties have acknowledged the cracking to tiles has occurred in vicinity of the area where the extension slab connects to the original slab. P was able to assess the tiles in the toilet and the adjoining hallway where tiles were laid directly on the intersecting point where the original slab meets the extension slab. P has provided images showing cracking to grout and drummy tiles and the absence of any movement joints to the tiles in this area. The cracking to the cornice and ceiling is also located at the point where the extension to the property starts and P has confirmed there is no control joint in this area. In consideration of all the information available, on balance it is more likely than not, movement joints were not included when the tiles were installed. I am also satisfied differential earth movement over time has caused delamination and cracking to the floor tiles and cracking to the cornice and ceiling. I am satisfied the damage is a result of building defects and movement over a period of time. Accordingly, the insurer is entitled to decline the claim and is not required to take any further action. Determination | Case number: 762926 Page 5 of 6 2.2 Why is the outcome fair? The outcome is fair as the damage has been apparent for a considerable time due to a longstanding structural and building defect and which constitutes a common exclusion to general insurance policies. Determination | Case number: 762926 Page 6 of 6 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.