Determination 761117

Cash settlement amount for bathroom water damage claim

FirmIAG
Decided2021-07-19
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded$33,700
Non-financial loss—
Amount claimed$38,430
SourceAFCA PDF

Summary

The complainant's bathroom water damage claim was accepted, but the insurer offered $13,395.95 based on a builder's quote not actionable by him. AFCA ordered a cash settlement of $33,699.99 plus statutory interest.

A cash settlement must reflect the reasonable cost to a retail customer, so the insurer's builder quote was not a proper basis and the complainant's own quote, less his maintenance share, was the better reference.

Issues

Subjects and remedies

home or building damagepay claimpay interest

Related

All IAG determinations · Find similar determinations

Text of the determination

Determination Case number 761117 Financial firm Insurance Australia Limited Determination | Case number: 761117 Page 1 of 4 Case number: 761117 16 July 2021 1 Determination overview 1.1 Complaint The complainant holds a home and contents insurance policy with the financial firm (insurer). He lodged a claim in April 2020 for damage to the bathroom flooring, following an escape of liquid from the shower. The insurer accepted the claim and offered $13,395.95 , based on its builder CC’ s quote. It says it is prepared to authorise CC to conduct repairs at the amount quoted, but the cost of the defective items which caused the escape of liquid is not covered under the policy. The complainant is not happy with that decision. He says the ins urer’s offer is not based on an actionable builder’s quote . He obtained his own quote totalling $38,430, and wants the insurer to cash settle based on that quote (which incorporates both claim-related and other repairs for which he is responsible). 1.2 Issues and key findings Is the insurer’s settlement offer reasonable in the circumstances? The insurer’s settlement offer is not fair or adequate. The insurer is required to cash settle the claim by paying $30,636.36 + GST, based on the applicable portion of the complainant’s builder’s quote. I am satisfied that amount also adequately allows for the transfer of risk, loss of the insurer’s lifetime guarantee, other contingencies /possible unforeseen damage for which the complainant will now be responsible. Why is the outcome fair? In the circumstances of the claim (with interconnected claim-related and other maintenance repairs) a cash settlement is the fair and appropriate resolution, but the amount must reflect the cost of repairs to the complainant as a retail customer. 1.3 Determination This determination is in favour of the complainant. The insurer is required to cash settle the claim by paying the complainant $33,699.99 (being $30,636.36 + GST), together with statutory interest on that amount calculated from 17 August 2020 (the date of the insurer’s IDR response), until the date of settlement. It is entitled to retain the excess if that has not already been paid. Determination | Case number: 761117 Page 2 of 4 2 Reasons for determination 2.1 Is i nsurer’s settlement reasonable in the circumstances ? Insurer must settle the claim fairly The policy wording gives the insurer the option of settling a claim by either repairing the damaged portions of the building to the same condition as when new, or paying the cost of rebuilding or repairing the building to the same condition as when new. The insurer must, however, exercise that discretion fairly. When making a cash settlement, it must ensure the amount being offered is fair and appropriate. That will require it to take account of the fact the complainant loses the benefit of the insurer’s lifetime guarantee on workmanship and materials and is effectively accepting the transfer of risk for the repairs. Any cash settlement therefore needs to allow for contingencies, and it must also be based on a quote that is actionable by the complainant as a retail customer (who would not have access to any trade or industry discounts such as might be available to the insurer). In other words, the cash settlement must reflect the likely reasonable cost to the complainant of returning the property to the same condition as when new. Insurer ’s quote not shown to be actionable by complainant The insurer has accepted liability to the extent of $13,395.95 for the claim-related damage, based on the scope of works and quote from its builder CC (covering the costs required to strip - out the affected bathroom, repair the water damaged subfloor, and reinstate the toilet room; but not the reinstatement of the shower rece ss and bathroom, which requires continuous waterproof membrane ). The insurer says it is willing to authorise CC to repair the relevant part of the damaged bathroom, with the complainant remaining responsible for maintenance repairs (including the waterproofing), which it expects would be completed first before CC could commence. However, CC indicated the claim should be cash settled, since the maintenance repairs needed to be conducted in conjunction with the repairs that are covered under the policy. So while a cash settlement amount of $13,395.95 might be what it would cost the insurer to undertake the relevant portion of the works, I do not accept that has been shown to represent a quote that is actionable by the complainant: CC has not stated they would do the work for that amount with the complainant as their customer, rather than the insurer. That means it would not be fair for the cash settlement to be based on CC’s quoted amount. To be clear, however, I do consider a cash settlement is the appropriate resolution in this case. That is because I am satisfied the nature and extent of the necessary repair/rectification work in the bathroom means those elements which are the responsibility of the insurer, and those which are the responsibility of the complainant, are interconnected and cannot be effectively separated in the repair process. Determination | Case number: 761117 Page 3 of 4 Complainant’s quote, on balance, fairer reflection of cost to him The complainant has provided quotations from builders CJ ($38,430) and DC ($39,020) for full r epairs and believes the cash settlement should be based on those. I consider CJ’s amended quote, which separates the cost of waterproofing from the other repairs, is an appropriate point of reference; but DC’s quote is not sufficiently detailed to assist. CJ’s quote allows $4,300 (+ GST) for waterproofing/maintenance which is the complainant’s responsibility. The balance of the quote ($30,636.36 + GST) covers the remainder of the necessary repairs (including reinstatement of the bathroom area, which I consider, on balance, would need to happen in any case, simply as part of the insurer’s repairs ). I note the complainant’s quote from CJ does not provide a breakdown between labour costs and materials. However, I do not accept that means it is not still an appropriate basis for a cash settlement: that quote still separately identifies the maintenance costs (waterproofing of the flooring and walls), for which the complainant is responsible. In the particular circumstances, I am satisfied the insurer should cash settlement the claim by paying the complainant $33,699.99 (being $30,636.36 + GST), together with interest on that amount calculated from the date of the insurer’s IDR letter to the da te of settlement. 2.2 Why is the outcome fair? In situations such as this where there is an ‘overlap’ between the work for which the insurer and complainant are each separately responsible, a cash settlement is the fair and appropriate means of settling the claim. As well, it is fair that the cash settlement reflect the cost to the complainant of having his share of the work done – that is because the policy provides for repair to an ‘as new’ condition. Determination | Case number: 761117 Page 4 of 4 3 Supporting information 3.1 The AFCA process AFCA’s approa ch is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.