Home / Suncorp Group / Determination 758598

Determination 758598

Roof damage claim declined; cash settlement of internal water damage

FirmSuncorp Group
Decided2021-07-14
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$3,018
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The complainants claimed storm damage to their roof and laundry after the insurer accepted only internal water damage. AFCA found the roof damage was excluded wear and defects and ordered the insurer to cash settle $3,017.71 for the laundry.

Policy excludes wear, tear, gradual deterioration and defects, and the insurer may cash settle rather than repair where it cannot guarantee repairs outside its liability.

Issues

Subjects and remedies

home or building damagepay claim

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination Case number 758598 Financial firm AAI Limited Case number: 758598 14 July 2021 Determination | Case number: 758598 Page 2 of 7 1 Determination overview 1.1 Complaint The complainants hold a home and contents insurance policy with the financial firm (insurer). In April 2019, they lodged a claim for storm/hail damage, after the roof leaked and water entered the laundry, kitchen and dining rooms. On that occasion, the insurer accepted the claim and undertook repairs to the tiled area of the roof, as well as to the areas of internal damage. In late August 2019, the complainants reported further water damage in the laundry (around the downlight in the ceiling). The insurer accepted the second claim for the internal damage, but declined cover for the roof itself. That was on the basis there were maintenance issues with the various sections of different roofing (which were showing signs of pre-existing deterioration), as well as certain defects. The insurer says it is not liable for repair/rectification of defective parts of the roofing which were not damaged by an insured event. The insurer has offered to settle the claim by paying $3,017.71, the amount its builder quoted for the laundry ceiling repairs. The cash settlement is proposed because the insurer says it cannot guarantee the repairs for which it is responsible, due to the outstanding issues identified with the roofing (for which the complainant is responsible). The complainant believes the insurer should undertake at least some of the roof repairs, as well as covering the internal damage. 1.2 Issues and key findings What is the extent of the insure r’s liability ? The insurer is only liable for the internal water damage which has been identified, and for which it has already offered a cash settlement. It is not liable for any pre-existing defective or deteriorated areas of the roofing, since the evidence does not show that damage arose from a storm event; and damage arising from lack of maintenance and/or wear and tear and gradual deterioration is excluded from cover. Why is the outcome fair? It would not be fair to require the insurer to pay for repairs or rectification work for which it is not liable under the policy or otherwise. 1.3 Determination This determination is in favour of the insurer. It is required to cash settle the complainant $3,017.71 for the internal water damage (less the policy excess, if not already paid). It is not required to take any other action. Determination | Case number: 758598 Page 3 of 7 2 Reasons for determination 2.1 What is the extent of insurer’s liability? Complainant has established valid claim storm damage The policy covers loss or damage caused by specified insured events, subject to conditions and exclusions. One of the insured events is ‘storm’. There is no dispute the property was damaged by water entering during a storm event. The complainant has established a valid claim under the policy. The issue then becomes whether the insurer is entitled to decline part or all the claim, based on policy exclusions or otherwise. The policy excludes cover for defects, structural or design faults; as well as wear and tear and gradual deterioration. Expert reports show exclusions apply The complainant provided a report from roofing specialists, ICR. They identified the metal klip-lock roofing was in ‘very poor condition’, covered with rust, with some areas ‘eaten away’ so as to allow water ingress. As well, they reported various design/construction faults (in the transition flashing between the tile and metal roofing, incorrect skylight back trays, and the adjoining metal roof being severely underpitched). ICR recommended a roof replacement, but confirmed the issues they found were not from a storm event. Assessments by the insurer’s builders and roofers (K, D and BRM respectively) identified a corresponding range and type of issues. None of the ‘damage’ to the roof wa s identified as being storm-related, but instead was from lack of maintenance, and/or poor design and installation. Details of the various reports are in section 3.2 below. Lifetime guarantee not triggered by new issues in separate area of roofing The complainant has pointed out the insurer was provided with a copy of his pre-purchase inspection report when he first took out the policy. He says the insurer should therefore have been aware of the issues with the roof, but it did not raise them when the first claim was made in April 2019. On that basis, he does not accept those issues should now be used to decline the further claim. At the same time however, the complainant himself was already on notice of those issues and he should reasonably have been aware he was responsible for dealing with them. The pre- inspection report very clearly indicates further roofing specialist investigations are needed. It is also relevant to note that the previous claim involved the insurer only dealing with hail damage to the tiled areas of the roofing. Builder K’s report from April 2019 specifically addresses issues with broken tiles from the hail storm. That event did not require a detailed consideration (or any repair) of other areas of the roofing, including the metal area now in issue. Determination | Case number: 758598 Page 4 of 7 Since the insurer did not undertake work to the metal areas of the roof, then it is not liable, under its lifetime guarantee, for any unrelated previous or current issues with those areas. Nor is it otherwise responsible for repairs/rectification of those areas which have not been shown to be storm-damaged. Insurer is only liable for internal water damage from the latest claim Under the policy, the insurer is only liable for internal water damage caused by the insured event. In this case, that amounts to the laundry damage which has been costed at $3,017.71. The insurer has offered to cash settle the complainant that amount. I consider that is fair and appropriate in the circumstances. I appreciate the complainant wants the insurer to undertake the necessary repairs (including to the roof), but has said he would contribute to the costs. However, the insurer is not required to undertake the repairs itself. In a situation such as this, where it could not guarantee its repairs without the necessary roof maintenance/replacement (for which the complainant is responsible) being properly completed first, it is reasonable that it cash settles the claim. 2.2 Why is the outcome fair? It would not be fair to require the insurer to pay for work for which it is not liable either under the policy, or for any other reason (including previous repairs it has conducted at the property). Determination | Case number: 758598 Page 5 of 7 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. 3.2 Expert reports Reporter and date Details Complainant’s report - I CR Roofing Specialists 5 November 2020  The Klip - Lok roof is covered wit h rust and some have eaten the roof sheets away thus causing wat er ingress.  There was no proper transition flashing joining the tile and metal roof together, this is the main issue on why there are leaks.  The existing skylight back trays are not the right trays for the sheet profile,  The existing vent pipe is not flashed properl y with a back tray and dektite.  The adjoining metal corrugated roof is severely underpitched, Determination | Case number: 758598 Page 6 of 7 the lowest pitch a corrugated roof can be installed at is 5º however the existing corrugated roof is set at 2.8º  The issues we have found are not due to storm da mage or weat her events. Due to the age of the sheets they have rusted and has eaten away on the sheet turn up which is meant to keep water out of the roof cavity. A roof replac ement is required to bring the roof back up to standard. Insurer ’s report – K 21 September 2019  The transition bet ween Roof A and B has been poorly installed.  No drypans have been installed to 2x Flue penetrations.  The box gutter to Roof D is insufficient  No apron has been installed to the transition of Roof D and Roof E  Roof D is u nderpitched for the current sheet profile  The makeshift box gutter associated with Roof D is insufficient and the sheeting protrudes too far into the gutter.  No apron has been installed to the top of Roof E however Roof B overhangs Roof E by approximately 8000mm and ingress is not likely  The sheeting if Roof E is not laid square. This is evident in the gutter line and the ill fitting barge cap.  Roof E is currently underpitched for the current sheet profile  The apron flashing [to roof F] is incorrect and has been poorly installed.  The sheeting of Roof F has been incorrectly pan fixed  It is not possible to install new roof flashings to a warrantable standard. It is recommended that Roofs A, B and D be completely replaced to ensure warrant able works.  Althoug h Roof E is also under pitched this roof line does appear to be causing any ingress problems or internal damages and can likely be left installed to minimise costs. Insurer ’s report – D and BRM 12 November 2019  The rear metal corrugated roof areas are u nder pitch at 3 degrees. This is outside the manufacture’s recommendations of 5 degrees. Approx. 100m2.  The wall junction between the kliplok and corrugat ed roof area has deteriorated timber barge present..  There is no apron flashing installed along the wall junction of the klip - lok and corrugated roof areas.  Sealant on existing flashing has deteriorated and split. This is allowing for water to seep behind the flashing and over the side of the roof sheet.  Th ere is a rust hole present in the flashing and corrugated roof Determination | Case number: 758598 Page 7 of 7 sheeting.  The sealant on the flashing along the wall junction is deteriorated and split.  The sealant on the flashing at the tile and kliplok roof junction has split.  The roof tiles on the tile and kliplok roof junction area are sitting flat at 5 degrees. This is outside the manufacture’s recommendations of 22 degrees.  The timber facia bet ween the klip - lok and corrugated roof area has deteriorated and warped. This has left a gap in the join of t he timber fascia, allowing for wind driven rain to enter.  All issues outlined above are possible entry points for water ingress. Insurer’s report - K (Previous claim) 14 April 2019  Evidence of silicon applied to roof tiles as a form of make safe above th e affected area.  Approximately 13 x brok en roof tiles from hail impact 2 of these roof tiles are under the ridge capping. We could not detect any other hail damage across the roof areas.  Maintenance issues obs erved to roof – NIL  Damages are consistent with the claim and we recommend acceptance. Building report – SPP Pre Purchase Metal roof sections  Insufficient roof pitch (slope) the roofing profile installed. This is an installation defect and can cause leaks. Flat metal roof sections – Skillion roof 1  Moderate corrosion. Corrosion can lead to holes and leaks Flashings, skylights and roof penetrations  Deterioration, damage, cracks and evidence of previous leaks to the roof flashings and upgrading flashings is recommended.  repairing defects in flashings may not maintain effective waterproofing and replacement may be necessary.  A roof plumber is required to inspect roof penet rations and accessories to ensure the roof is watertight.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.