Home / Commonwealth Insurance Limited / Determination 757774
Determination 757774
claim_amount_dispute
Summary
The insurer accepted a storm claim for a home but offered a cash settlement based on a narrower repair scope than the complainant's builder quote. AFCA preferred the complainant's repair method, excluded unrelated wall and carport damage, and set a settlement of $66,142.05 or alternative options, with interest.
The insurer must repair or rebuild the damaged part so the building is restored to its pre-loss state, and any cash settlement must be fair and reasonable.
Issues
- Claim amount dispute primary · upheld
“The insurer's proposed repair has not satisfied me it either fairly addresses its policy obligations or it will avoid a manifestly inadequate result.”
- Repairs or contractors secondary · upheld
“I do not consider it is fair in the circumstances for the insurer to limit the repairs the way it intends to.”
Subjects and remedies
home or building damagenatural disasterpay claimpay interest
Text of the determination
Determination
Case number 757774
Financial firm Commonwealth Insurance Limited
Determination | Case number: 757774 Page 2 of 8
Case number: 757774 28 April 2021
1 Determination overview
1.1 Complaint
The complainant ‟s property was impacted by a garage roof blown from the
neighbouring property during a storm. He lodged a claim for the resulting damage
under his home insurance policy with the financial firm (insurer).
The insurer accepted the claim and offered to cash settle the complainant for the
value of the repair work. The dispute is about whether the settlement offered fairly
reflects the cost of the repairs.
The complainant says the insurer must cover the full cost of the quote he provided to
ensure he can complete the repair without adversely affecting the value of his
property.
The insurer disagrees and says the complainant‟s quote is excessive both in the
amounts quoted and the scope of repairs it covers. The insurer says its builder ‟ s
quote is more reflective of the true cost of the repairs.
1.2 Issue and key findings
Does the insurer’s settlement offer meet its policy obligations?
No. The complainant‟s information on the cost of repairs is preferred because the
repair he proposes more closely reflects the pre-damage state of the property.
Further, the insurer has not established its proposed repair, which is limited to the
damaged sections, is an adequate repair outcome. Therefore, the insurer cannot limit
its liability as it prefers.
1.3 Determination
This determination is in favour of the complainant.
The insurer is to settle the complainant with one of the options outlined in section 2.1
of this determination.
Determination | Case number: 757774 Page 3 of 8
2 Reasons for determination
2.1 Does the insurer’s settlement offer meet its policy obligations?
Complainant’s position on repair method is preferred
I am not satisfied the insurer has shown its position is the more reasonable for settling
the claim.
The insurer has accepted the claim and there is no dispute the insurer must settle the
complainant for his loss.
The dispute is essentially about what repairs need to be completed to meet the policy
obligations. Both parties now agree the repair needs to consider the bushfire zoning
(BAL-FZ) requirements, meaning the only issue in dispute is which repair method and
scope is more reasonable.
The insurer says replacing the undamaged sections of external wall are excessive.
The complainant says this is unfair, as the mismatched materials are likely to impact
the resale value of the property.
In this, the complainant‟s position is preferred , as his quote restores the property
more closely to the state and aesthetic in place before the claimed incident.
Conversely the insurer‟s proposed repair has not satisfied me it either fairly addresses
its policy obligations or it will avoid a manifestly inadequate result.
My reasoning is outlined below.
Settlement method cannot be manifestly inadequate
Relevant to this dispute is the provision under the heading „How we settle a claim‟.
The provision states the insurer will “repair or rebuild the lost or damaged part of your
building.”
The insurer seeks to limit the extent of its repairs on the basis it is entitled to repair
only the damaged part of the building.
In this case, the repair proposed by the insurer requires a change in material where
some material will be installed immediately next to existing material from 60 years
ago. This is in addition to the insurer‟s proposal to install a bushfire shutter over the
French door where none currently exists.
In contrast, the complainant supplied a quote from a specialist door builder (NF)
showing the bushfire shutter is not necessary to repair the French door while meeting
the BAL-FZ standard.
The complainant also obtained the opinion of a real estate sales manager (CR), who
says the proposed repair could have a drastic effect on the resale value of the
Determination | Case number: 757774 Page 4 of 8
property. CR cites the weatherboard replacement and the approach to the French
door as items of concern.
Considering all the evidence, I do not consider it is fair in the circumstances for the
insurer to limit the repairs the way it intends to. This is because its proposed method
of repair not only would likely result in a mismatch of materials but, concerningly, the
repairs themselves may reduce the value of the property.
I am satisfied such an outcome would be manifestly inadequate and would not meet
the requirement which is to restore the building to its pre-loss state.
Therefore, the complainant‟s builder quote (SS) is more persuasive, particularly in
bringing the areas up to the BAL-FZ standard with as little impact to the building
aesthetic as possible. I accept it is fair in the circumstances this quote, and its repair
method are used to form the basis of the settlement.
Insurer may settle the claim with a cash payment to complainant
I am satisfied the insurer may settle the claim with a cash payment in lieu of repairs.
The policy states the insurer decides the settlement method. As there are concerns
over appropriate licensing for repairs to BAL-FZ standard, a cash settlement is
appropriate in the circumstances. Also, both parties agree to a cash settlement.
Where an insurer exercises its discretion to cash settle a claim, AFCA expects this to
be fair and reasonable, as it may affect an entitlement to other benefits under the
policy, such as a repair guarantee.
As the complainant is assuming the risk of managing the repair process and will lose
the lifetime repair guarantee for the repair work offered by the policy, the amount of
the quote should be uplifted to reflect this. In this instance, a figure of 10% is fair.
Complainant’s quote is excessive in some parts
I have considered the insurer‟s remaining arguments about SS ‟s quote being
excessive as it:
repairs practically the whole front facing section of the property despite only part of
it being damaged in the event
replaces parts of the carport which are deteriorated rather than damaged by the
storm.
For the reasons outlined previously, I consider it is fair to extend repairs to areas, to
avoiding the repairs adversely affecting the value of the property. I am satisfied SS‟s
quote for work to walls “B”, “C”, and “D” are part of the current claim.
However, I have not accepted wall “A” as the evidence shows, on balance, this
damage has not been caused by the same storm event. The report from the insurer‟s
Determination | Case number: 757774 Page 5 of 8
engineer (IT) indicates it was impacted by a tree branch sometime before the storm
and is therefore due to a separate event.
The complainant‟s information does not dispute this is the case. I also note this part of
the damage is well away from the other impact points on the property and has signs
of age and vegetation entering the hole. On balance, this is sufficient to show it is not
related to the subject storm.
I note that impact by a tree branch either by itself, or due to another storm, are
covered events. Ordinarily, the complainant would need to lodge a different claim for
this damage which will need to be assessed separately by the insurer. The
complainant‟s builder will also need to quote the repairs separately as well.
Alternatively, and for the sake of practicality the insurer may choose to accept SS‟s
quote for all walls and settle both claims as a result of this determination by applying a
second excess to the cash settlement as outlined below.
I also accept full replacement of the carport is excessive. The reports from the
insurer‟s builder AG and IT both concur there is advanced corrosion preventing them
from warranting repair work or reusing these items.
Th e complainant‟s expert also quotes to entirely replace the carport, indicating the
existing structure cannot be reused. As the damage in question is due to corrosion
and not the impact caused by the subject storm, this does not fall within the scope of
claim related repairs.
The complainant is entitled to replace the damaged carport in its entirety if he wishes,
but the insurer is only required to settle the value of its liability for the carport repairs
as outlined in AG‟s quote.
Insurer to settle the complainant with one of the following options
The complainant can be settled on the available information. However, to do so will
put the insurer in a position where it must forgo lodging a second claim and
performing an additional assessment. The information collected so far in this dispute
may be sufficient for it to make a claim decision however.
Accordingly, it is fair the insurer is given the opportunity to resolve the matter fully by
either:
paying the complainant, a settlement based on the full value of SS‟s quote
($68,496.50)
reducing the settlement by twice the policy excess ($1,000 total representing two
claims being made)
further reducing the settlement by the value SS quoted for the carport ($14,004.10
including GST)
Determination | Case number: 757774 Page 6 of 8
increasing the settlement by the value of the carport repair from AG‟s quote
($3,740.83 including builder ‟ s margin and GST)
increasing the settlement by the value of the boundary fence from AG‟s quote
($2,805 including builder‟s margin and GST)
increasing the settlement by the 10% contingency on the total cost for unforeseen
costs and the transfer of the risk to the complainant to manage the repair and the
loss of the lifetime repair guarantee ($6,103.82)
paying the complainant $66,142.05 as full and final settlement of the claim(s) and
complaint.
or:
SS resubmits the current quote less wall A, and quoting only the replacement of
the roof sheets to the carport with the insurer to accept the quote for cash
settlement so long as it remains fair and reasonable
less the policy excess
plus, the value of the boundary f ence from AG‟s quote as above
plus, a 10% contingency on the total cost as per above
the complainant may then lodge a second claim for impact or storm damage to wall
A which the insurer must assess in accordance with the policy.
In either case, the insurer must also pay the complainant interest calculated in
accordance with section 57 of the Act, payable from 11 November 2020 until the
claim(s) are settled. This is the date the insurer supplied its position on the settlement
which we did not accept as fair in the circumstances.
I note that an issue in relation to asbestos contamination has been settled by
agreement between the parties. Accordingly, that matter has not been considered as
part of this determination.
Determination | Case number: 757774 Page 7 of 8
3 Supporting information
3.1 Process
AFCA’s approach to complaints
This complaint has been determined based on what is fair in all the circumstances,
having regard to the relevant law, good industry practice, codes of practice and
previous decisions of AFCA or its predecessor schemes (which are no t binding).
A full exchange of the relevant information has taken place between the respective
parties. Each party has had the opportunity of addressing any issues raised.
All the provided information has been reviewed and considered. The parties have
raised numerous issues in their submissions to AFCA. However, commentary in this
determination is restricted to those issues considered relevant to the outcome.
How we assess complaints
AFCA is not a court of law. We do not have the power to take or test evidence on
oath, or to require third parties to give evidence. When we assess complaints, we
consider available documents, the recollections of the parties, and all relevant
circumstances.
We give more weight to documents created at the time the events occurred. If there is
no relevant documentation, we will decide what is most likely to have occurred based
on the information provided to us. If there are conflicting recollections and these are
evenly weighted, we may find that a claim cannot be established.
3.2 Policy wording
How we settle your claim
Building claims
If we agree to pay your claim, we will decide whether to:
repair or rebuild the lost or damaged part of your building
…
provide you the amount we determine to be the reasonable cost of repairing or
rebuilding the lost or damaged part of your building up to the sum insured stated
on your Certificate of Insurance .
3.3 Key points on expert evidence relied on
Record Key points
Complainant’s real estate
sales manager ( CR )
Replacing weatherboards and French door are not very attractive
and would affect the property value.
Determination | Case number: 757774 Page 8 of 8
Record Key points
Letter
Undated
Property value would be affected by the repair , perhaps by
$50,000 to $100, 000 due to the kind of buyers interested in this
type of property.
Insurer’s builder ( AG )
Report
30 J uly 2020
Guttering to the carport severely rusted.
Some missing guttering at the carport was removed prior to the
storm.
Post supports not structurally sound.
Unable to warrant repairs to the front veranda area due to wood
rot.