Insurer limited heating system cover to $500 and handled the claim with unreasonable delay
Text of the determination
Determination
Case number 756988
Financial firm Commonwealth Insurance Limited
Determination | Case number: 756988 Page 2 of 8
Case number: 756988 16 April 2021
1 Determination overview
1.1 Complaint
The complainant holds a home building and contents policy (policy) with the financial firm
(insurer). On 12 November 2019, a claim was lodged for damage to the insured property
because of an escape of liquid event.
The insurer has accepted the claim, however, says its liability with respect to the hydronic
heating system replacement is $500 in line with the policy. The complainant disputes this and
is seeking a further payment of $12,595. The complainant is also seeking cover for temporary
accommodation costs and travel expenses incurred because of having to move into
temporary accommodation.
The complainant is dissatisfied with the insurer‟s management of the claim and the delays
experienced over the life of the claim.
1.2 Issues and key findings
Is the insurer’s assessment of its liability reasonable in the circumstances ?
No. The insurer is not entitled to limit its liability relating to the hydronic heating system
(heating system) to $500. The insurer is to pay the complainant the outstanding amount of
$12,595 plus interest in line with section 57 of the Insurance Contracts Act 1984 (the Act).
Is the complainant entitled to temporary accommodation expenses?
Subject to the complainant providing the insurer with relevant information, the insurer is to
cover the complainant for the claimed temporary accommodation at $495 per week in line
with this determination.
The insurer is not required to cover the complainant for the claimed travel expenses in line
with the policy provisions.
Is the complainant entitled to non-financial loss compensation?
The insurer is to pay the complainant $3,000 in non-financial loss compensation for the
reasons stated in this determination and in line with the AFCA Rules.
1.3 Determination
This Determination is substantially in favour of the complainant.
The insurer is to pay the complainant a further $12,595 towards replacement of the hydronic
heating system. The insurer is to pay interest on this amount in line with this determination.
Subject to the complainant providing evidence of the temporary accommodation expenses,
the insurer is to cover the complainant for these expenses in line with this determination.
The insurer is not required to cover the complainant for travel expenses in line with the policy.
The insurer is to pay the complainant $3,000 in non-financial loss compensation in line with
the AFCA Rules.
Determination | Case number: 756988 Page 3 of 8
2 Reasons for determination
2.1 Is the insurer’s assessment of its liability reasonable ?
The policy is an insured events contract of insurance
The policy covers the insured property against loss or damage caused by one or more the
listed insured events, including „Escape of liquids‟. Cover under the benefits is subject to the
conditions, limitations and exclusions specified in the product disclosure statement (PDS).
The insurer is entitled to rely on the policy provisions
The insurer provided the complainant with the relevant policy documentation including the
PDS and certificate of insurance (COI). Therefore, I accept the insurer is entitled to rely on
the policy provisions to assess its liability under the claim.
Policy covers failure of T join
There is no dispute a valid claim exists under the policy for the damage to the insured
property due to the failure of a T join connected to a fixed water pipe utilised by the heating
system. The dispute relates to the parties‟ interpretation of the relevant policy provisions and
the extent of cover available for the loss and damage claimed in line with their respective
policy interpretations.
The relevant policy wording states the following:
Escape of Liquid
What is covered
Your building and/or contents are covered for loss or damage caused by the sudden and
unexpected escape of liquid from any:
• …
• Fixed water pipe (but not a garden hose);
• …
• Sealed portabl e heater; or
• Fixed heating or cooling system.
… You ae only covered for up to $500 for the repair or replacement of the item from which
the liquid escaped if it formed part of your building or contents.
On reading the above policy wording, I am satisfied it says the policy:
Determination | Case number: 756988 Page 4 of 8
‒ Covers loss caused by the sudden and unexpected escape of liquid from various
items including fixed water pipes and fixed heating systems
‒ Covers damage caused by the sudden and unexpected escape of liquid from various
items including fixed water pipes and fixed heating systems
‒ Limits cover up to a maximum of $500 to repair or replace the item from which the
liquid escaped, if it formed part of the insured building.
I am satisfied the evidence shows the water escaped from a failed T join attached to a fixed
water pipe in the ceiling of the insured property. There is no dispute the escape of liquid has
then resulted in significant damage to the insured building, contents on lower levels and the
heating system.
I do not agree with the insurers position. The policy does not define the term „item‟ and so it is
fair to rely on the terms ordinary meaning as defined in the Macquarie Dictionary, which is “a
separate article” and an article being an “an individual piece”.
Insurer liable to cover damage to the heating system
A fair interpretation of the policy limitation is that it limits cover up to $500 to repair or replace
the item, this being the individual T join in this instance. If it was the intention of the insurer to
apply this to a complete fixed heating or cooling system, then this should have been clearly
explained/noted in its drafting of the policy provisions. Similar to how clear reference is made
to fixed heating and cooling systems just above the on the same page of the PDS.
I have not been provided with any evidence which would suggest the cost of the replacement
of the heating system incurred by the complainant is excessive. Rather, both available quotes
are consistent. Accordingly, I determine the insurer is to pay the complainant a further
$12,595, subject, to the complainant providing the insurer with evidence of payment.
The insurer is to also pay the complainant interest on this amount in line with section 57 of the
Act, from the date of payment made by the complainant to the date on which payment is
arranged by the insurer in line with this determination.
2.2 Insurer is to cover temporary accommodation till repairs
are completed
The complainant is seeking cover for the cost he has incurred and continues to incur for
temporary accommodation, which is said to be $495 per week inclusive of GST. The insurer
has accepted to cover the complainant for these expenses, subject to being provided
evidence (invoices) in support of this claim.
However, the insurer says it will limit cover to that noted in the policy provisions (52 weeks)
from 1 April 2020 to 31 March 2021. The insurer says, had it not been for delays caused by
the complainant over the life of the claim, it would have been able to repair and restore the
insured property within this timeframe.
The complainant says the delays experienced are the fault of the insurer and as such it is not
reasonable for it to seek to limit cover for temporary accommodation to the policy limit of 52
weeks. The complainant also says, under the policy he would been entitled to a like for like
temporary accommodation to the insured property, which would have cost the insurer
upwards of $2,000. However, he in good faith has attempt ed to reduce the insurer‟s expenses
under the claim.
Having considered all the available information, I accept there is clear evidence of delays
experienced over the entire life of the claim. However, it is not as simple as accepting the
insurer alone is responsible for these delays. It is clear, the insurer chose not to deal with the
Determination | Case number: 756988 Page 5 of 8
damaged heating system and partially cash settled the complainant to arrange for its repair or
replacement, before it subsequently sought to significantly reduce its liabilit y to $500 only.
The complainant made reasonable efforts to get these works done, however, given the limited
experts available, it not being his expertise, requirements for testing of the system once
installed and significant complications relating to the COVID-19 situation in Melbourne, delays
occurred. I accept both parties hold the other responsible for these delays which took the
claim to around June 2020, however, I am of the opinion it would not be fair to hold either of
the parties liable for this period of delay given the reasons above.
Following this, the evidence shows there was some delay in starting the remediation works by
the insurer‟s appointed consultants „R‟. This included delay in setting the remediation works
commencement date of 12 October 2020.
I note the complainant‟s position that he did not cause any delays as the works did
commence on 12 October 2020. However, I am not of the same view, as it is the factors that
contributed to the delay in setting this commencement date which are relevant.
The available information shows the complainant strongly insisted that he be provided with
the building repairs scope of works before he would accept the remediation scope of works.
The insurer on several occasions attempted to inform him that this was not its process and
building repairs cannot be accurately determined until such time the remediation works were
completed. These negotiations between the parties delayed the remediation works being
completed.
I note the insurer, because of the compl ainant‟s insistence, did provide him with a building
scope of works before remediation works were commenced. I acknowledge the complainant‟s
insistence came from a lack of trust in the insurer because of earlier poor claim experiences,
however, I accept th e insurer‟s position that it was unhelpful and pointless to demand the
building scope of works be estimated before the remediation works were completed. So, I
accept a delay of around two months or so, was significantly contributed to by the
complainant.
In saying that, I also note that if the insurer was prepared to provide the building scope of
works before the remediation works had been completed, it could have done so much earlier
in the negotiations in the attempt to prevent the extended delays.
I note on being provided with the building scope of works in December 2020, the complainant
straight away identified several concerns with the contracts which he brought to the attention
of the insurer and its appointed consultants „J‟. The concerns raised wer e reasonable and
included matters such as repairs to items which never existed at the insured property, liability
being placed with the complainant for property he was not reasonably liable for and other
issues which were poorly explained and/or were included from standard building contracts.
It is clear for quite some time, the insurer and J, flatly refused to acknowledge the concerns
and informed the complainant that no changes would be made to the contracts. However, the
evidence shows, this is exactly what occurred once the parties communicated, some changes
were made to the contracts, some items remained the same and others were more clearly
explained to the complainant by J.
Again, I am of the opinion, had the insurer been more receptive to the compl ainant‟s
communications and there was better communication between the insurer and its
consultants, the unreasonable delay of over two months could have been avoided. So, for this
I am satisfied it is reasonable to hold the insurer significantly liable.
I accept the evidence shows there was an unreasonable delay in finalising the buildings
scope of works and contracts once the remediation works were completed. This did not occur
until 5 February 2021, when the contracts were finally signed
Determination | Case number: 756988 Page 6 of 8
Accordingly, it is fair in the circumstances the insurer continues to cover the complainant for
the cost of temporary accommodation until the repairs authorised under the claim are
completed. This based on information exchanged would most likely be a couple months after
31 March 2021.
Insurer is not obliged to cover travel expenses
The complainant is also seeking cover for travel expenses for two return trips from Rye
(temporary accommodation) to Melbourne per week at approximately $0.70 per kilometre.
The complainant says this rate is consistent with information sourced from the Australian Tax
Office website.
The complainant says he was fair and modest in choosing to live in a home owned under a
trust for $450 per week and it would be fair for the insurer to cover the claimed travel
expenses. This would still result in the insurer paying less than it otherwise would, if he were
to be provided a comparative accommodation.
The insurer does not dispute this, however, says the complainant chose to stay at their
holiday home in Rye despite the insurer‟s offer to locate a comparative prop erty closer to
home in Ivanhoe. Further, that although he was entitled to more expensive comparative
property for the temporary accommodation, this does not mean he is entitled cover equal to
the higher expenses despite electing to reside in a lower cost accommodation.
The insurer originally offered to place the complainant and his wife in a hotel until such time
they could locate a comparative property to the complainant‟s home. The complainant
declined to stay in hotel accommodation given significant concerns relating to COVID 19 and
exposure to the virus in hotels at the time (March-April 2020). I accept this was reasonable
especially the complainant‟s responsibilities for the care of his elderly mother.
The complainant strongly believes that he was given the impression in a communication from
the insurer that in accepting the temporary accommodation, it was also accepting the travel
expenses. I acknowledge the complainant‟s position and reasons for it. However, I do not
believe the evidence is sufficient to prove the insurer misled the complainant with respect to
this.
Although the complainant has been modest in his expectations regarding temporary
accommodation which has assisted in keeping the claims costs down, this does not translate
into an entitlement to the travel expenses. I am satisfied the policy does not extend to cover
the travel expenses. If they were to be paid, it would be at the insurer‟s discretion to pay on a
commercial basis, which it has advised it does not wish to do.
2.3 Is the complainant entitled to compensation?
AFCA can award non-financial loss compensation
The AFCA Rules (Rule D 3.3) allow for an award of up to $5,000 for non-financial loss
compensation, if the insurer caused the complainant to suffer an unusual degree or extent of
inconvenience, delay or interference. AFCA takes a conservative approach when considering
any award of compensation.
Insurer is to pay the complainant $3,000 in non-financial loss compensation
The complainant raises several concerns with the insurer‟s ov erall claim handling,
communication and the extent of time it has taken to finalise the claim.
Determination | Case number: 756988 Page 7 of 8
The issue of delays experienced under the claim has been considered in detail within section
2 above when discussing the parties position on temporary accommodation. In short, I accept
there have occurred unreasonable delays over the life of the claim. I am of the opinion a
significant portion of the delays could have been avoided with better communication from the
insurer and applying the same degree of flexibility earlier in the claim as opposed to months
later.
The complainant has also raised concern of unreasonable delays in addressing requests for
window coverings for lower level windows at the insured property. These concerns relate to a
few attempted break-ins at the property said to be because windows were left uncovered with
lights on and doors open by repairers. Photographic evidence does show the insured property
has large windows which allow for someone from the outside to see inside the property.
The available information also supports the complainant‟s position that over several months
repeated requests were put to the insurer to ensure lights were turned off, doors closed and
for the windows to be covered, which the insurer failed to action. I accept the insurer‟s
representative dealing directly with the complainant did put forward these requests, however,
such requests were not put into action by those given instruction. This is a further example of
concerns referred to in this determination regarding communication between the insurer and
its agents.
I acknowledge the complainant ‟s opinion that he was bullied by the insurer under the claim,
especially in matters relating to acceptance and signing of contracts. The complainant
especially refers to an email sent to him from the insurer‟s representative „R‟ dated 1
February 2021. An allegation of bullying is serious matter and requires persuasive evidence
in support. Having considered the available information, I am not of the opinion it satisfies the
level of evidence required to accept the allegation.
I accept the said email could have been drafted better to communicate the insurer‟s position
and that its intention was to present the complainant with an alternative option i.e. cash
settlement for the repairs. However, equally, I do not believe it was necessary for the insurer
to then include reference to the deadline for temporary accommodation, its pending expiry
and its unwillingness to extend this benefit any further. This was a reference not necessary in
asking the complainant to sign and return the building scope of works contract as is, or as
part of presenting alternative options.
The available information also shows poor management of the insured property whilst in the
care of the i nsurer‟s appointed consultants. I accept the insurer‟s reference to the fact it would
arrange a clean-up of the property at completion of the repairs. However, this does not mean
that reasonable care should not be taken at all times over the course of the repairs, especially
with respect to furniture and use of furniture by appointed repairers.
I am satisfied the insurer‟s management of the claim has caused the complainant and his wife
to experience an undue degree or extent of physical inconvenience, stress, anxiety and time
taken to bring the claim to finality.
Accordingly, in line with AFCA‟s approach to compensation, I determine the insurer is to pay
the complainant $3,000 in non-financial loss compensation within 14 days of his acceptance
of this determination.
Why is the outcome fair?
Given the policy wording, the fact that am insured event occurred and the delays in resolving
this dispute, it is fair that:
the complainant is covered for the cost to replace the heating system
the complainant be compensated for the additional accommodation expenses till the
insured building is repaired due to delays experienced under the claim
Determination | Case number: 756988 Page 8 of 8
the complainant be compensated for the unusual degree of physical inconvenience and
time taken over the life of the claim
the insurer be allowed to decline cover for the travel expenses in line with the policy
provisions.
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
Determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
3.2 AFCA Rules
D.3.3 An AFCA Decision Maker may decide that the Financial Firm is to compensate
the Complainant for non-financial loss:
a) for a complaint relating to an individual‟s privacy rights - injury has occurred to
the Complainant‟s feelings or humiliation has been suffered by the Complainant;
or
b) for other complaints – an unusual degree or extent of physical inconvenience,
time taken to resolve the situation or interference with the Complainant‟s
expectation of enjoyment or peace of mind has occurred.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.