Home / Suncorp Group / Determination 756981

Determination 756981

Scope of water leak damage and cash settlement for foundation repairs

FirmSuncorp Group
Decided2021-06-21
ProductGeneral Insurance · Landlord
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

A landlord accepted a leaking water pipe claim but sought demolition and rebuild costs. AFCA found the insurer's $59,761.02 cash settlement for event-related stump repairs fair and reasonable and found no obligation to rebuild.

The policy limits cover to insured-event damage, excludes pre-existing defects and ground movement, and lets the insurer choose a cash settlement that is fair in the circumstances.

Issues

Subjects and remedies

home or building damageno remedy

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination Case number 756981 Financial firm AAI Limited Determination | Case number: 756981 Page 2 of 8 Case number: 756981 21 May 2021 1 Determination overview 1.1 Complaint The complainant holds a Landlord Insurance policy with the financial firm (insurer). The complainant submitted a claim on 11 November 2018, for damage caused by a leaking water supply pipe. The insurer declined the claim on the basis the damage was caused by ground movement, which is excluded under the policy. Following further discussions between the complainant and the insurer, the claim was accepted. A dispute has arisen in relation to the scope of works and settlement for the cost of repairs. The insurer offered a cash settlement for the cost to repair the claim related damage. The complainant says the most viable option is to demolish and rebuild the property and is seeking a settlement to cover the cost of doing so. 1.2 Issues and key findings Is the insurer required to cover the cost to demolish and rebuild the property? No, the insurer is only required to indemnify the complainant for the ins ured-event related damage. 1.3 Determination This determination is in favour of the insurer. The insurer has offered a cash settlement of $59,761.02 to settle the claim. The panel confirms this settlement offer is fair and reasonable in the circumstances. Determination | Case number: 756981 Page 3 of 8 2 Reasons for determination 2.1 Is the insurer required to cover the cost to demolish and rebuild the property? No dispute an escape of liquid event caused damage to the property The complainant is required to show that, on the balance of probabilities, they suffered a loss caused by an event they are insured for under the policy. This i s known as a valid claim. The complai nant’s policy is a l andlord insurance policy that provides cover for a series of listed events including escape of liquid, subject to conditions and limitations. There is no dispute the complainant’s property suff ered damage because of a leak from a water supply pipe. The insurer has accepted the claim for damage. However, the parties dispute the extent of the insurer’s obligations under the terms and conditions of the policy. The complainant and the insurer both appointed experts to assess the cause and extent of the damage to the foundations of the house. The parties agree that several of the stumps have been damaged by the insurable event. Both the insurer’s expert s and the complainant’s expert s say the south west side of the property has suffered damage consistent with a major water leak as reported. The insurer made an offer of $59,761.02, to settle the claim. This is based on a quote and scope of works provided by the insurer’s builder to replace the stumps damaged by the escape of liquid event, including a 20% uplift for contingencies and transfer of risk. The complainant rejected this offer. The complainant says that the most economical option is to demolish the house to prevent further damage. Complainant says property to be demolished and rebuilt The complainant has provided a report from his engineer AC which says it is not good engineering practice to partially re - stump the site due to the reactive nature of the soil and the large settlements that have occurred . AC suggest s it is not financially viable to partially restump the house considering its age and condition and says consideration should be given to demolishing the house and re - building . AC does not however discuss the proximate cause of the damage, nor does AC disti nguish between the event related damage and the pre - existing damage. The complainant has also provided reports and quotations from builders A and LC. LC agrees with AC, saying the entire structure of the house has been impacted by the water damage. AC similarly recommends the house be demolished and rebuilt to be returned to a satisfactory condition. Determination | Case number: 756981 Page 4 of 8 The panel notes that LC is not a structural engineer. LC does not provide any commentary as to why he believes the entire structure of the house has been damaged by the escape of liquid event. The panel notes that neither AC nor LC provide any consideration for the insured event related damage as opposed to any pre-existing, or non-event related damage that pre-dates the damage from the escape of liquid event. Insurer ’ s experts say not all damage is related to insured event The insurer appointed a geologist (SG) shortly after the claim was submitted. SG classified the soils as highly reactive. SG says the cause of the damage is related to a combination of factors , which include the leaking water pipe, as well as non - insured eve nt related causes which include t ree drying o n the southern side of the site, drought conditions and uncapped soils. The insurer appointed an engineer, M. M found the settlement of the stumps on the south side of the property excessive and consistent with the escape of liquid event. M says the stumps on the south side therefore require replacement, estimating replacement of 20 stumps. M found no apparent settlement has occurred on the Northern side of the house. M concluded these stumps will not need replacing. The insurer later appointed engineer HC to report on the extent of the event related damage. HC says the building movement is a result of multiple causes, some of which are not insurable event related causes. HC considers the movement has been occurring due to the stumps being founded at different depths, resulting in cracking and movement of the residence. Further, HC says that to return the property to its pre- insurable event condition, the residence can be re - stumped as per the scope of works provided by the insurer, noting replacement of 34 stumps. HC does, however, note that because of pre-existing issues, ground movement will continue. HC says that demolition and reconstruction of the property would obviate the issue of further ground movement, however, this would be an upgrade. The panel also notes the report provided by the leak detection specialist, IL, which refers to evidence of previous re-stumping of the house, suggesting ground movement has been ongoing for an extended period and prior to the escape of liquid event. The panel notes the complainant’s own expert B also refers to defects in the subfloor, which it says has been altered and relevelled with substandard, non- compliant workmanship, prior to the insurable event. Insurer’s l iability limited to insurable event related damage. Having weighed all available information contained in the expert reports, the Panel accepts that there is major subsidence of stumps and foundations along the south west side of the house, consistent with a major water leak. However , the panel does not accept that demolition and rebuilding of the entire house is warranted because of the insured event.. Determination | Case number: 756981 Page 5 of 8 The available information raises other issues, unrelated to the escape of liquid event, which have caused damage (settlement) to the northern side of the house. The panel finds the engineer report provided by M compelling. M says stumps will not need replacing and that full restumping is not required. This is consistent with HC ’s views on what is required to return the house to a pre-event condition compared to upgrading the house. The policy states the insurer will not fix a fault that existed before the loss or damage occurred. It follows that the insurer is not required to upgrade the home to prevent future movement. Based on the available information, the panel is not satisfied the home requires demolition because of the escape of liquid. The insurer’s liability is limited to the escape of liquid related damage, which is the repair of the foundations to the southern side of the home. Insurer entitled to settle or repair The policy provides the insurer with the discretion to:  repair damage to the building;  rebuild the building;  pay you what it would cost us to repair or rebuild the building. AFCA expects an insurer to exercise this discretion fairly in all the circumstances. In the current circumstances, the insurer has elected to cash settle the claim. The information available shows that the house is currently structurally unsafe. It would require substantial work to address the issues of ground movement and the previous substandard workmanship to the foundations. As a result, it is understandable that there is a difficulty in a builder providing a warranty for the event related works. The panel therefore considers th e insurer’s decision to settle on a cash basis is fair and reasonable in the circumstances. The panel has considered whether the settlement fairly represents the repair costs. The quotation provided by the insurer’s builder incorporates HC’s recommendation for temporary bracing and M’s recommendations for claim related repair s. The insurer’s quote for $49,800.85, is comparable to the partial quote provided by the complainant’s builder A. The insurer has also offered a further 20% uplift to account for transfer of risk and contingencies. The panel considers this to be fair and reasonable in the circumstances. Determination | Case number: 756981 Page 6 of 8 3 Supporting information 3.1 Process AFCA’s approach to this complaint This complaint has been determined based on what is fair in all the circumstances, having regard to the legal principles, applicable industry codes or guidance, good industry practice and previous decisions of AFCA or its predecessor schemes (which are not binding). A full exchange of the relevant information has taken place between the respective parties. Each party has had the opportunity of addressing any issues raised. All the provided information has been reviewed and considered. The parties have raised numerous issues in their submissions to AFCA. However, commentary in this determination is restricted to those issues considered relevant to the outcome. This matter was determined by a panel Due to the nature of this dispute, it has been referred to a panel for determination. The panel comprises the lead ombudsman, a member with significant experience in consumer and small business advocacy and a member with extensive experience as a the insurance industry. How we assess complaints AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider available documents, the recollections of the parties, and all relevant circumstances. We give more weight to documents created at the time the events occurred. If there is no relevant documentation, we will decide what is most likely to have occurred based on the information provided to us. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. 3.2 Relevant policy wording PDS reference Wording P. 24 Escape of Liquid We cover: Loss or damage caused by liquid leaking, overflowing or bursting from any of the following: […] • water main, fire hydrant or water supply pipe; Determination | Case number: 756981 Page 7 of 8 PDS reference Wording P. 44 General Exclusions What we do not cover Defect, structural fault or design fault a defect, structural fault or design fault that you knew about (or should reasonably have known about) and did not fix before the loss or damage occurred (e.g. if there are signs that a defect previously caused damage, we will not pay a later claim for further damage from this defect). Ground move ment erosion, vibration, subsidence, landslip, landslide, mudslide, collapse, shrinkage or any other earth movement, but we will cover landslide or subsidence that is specifically covered under the following insured events: P. 52 How we settle your claim We choose how we settle building claims If we agree to pay a claim for loss, theft or damage to the building, we will decide if we will:  repair damage to the building;  rebuild the building;  pay you what it would cost us to repair or rebuild the building;  pay you the building sum insured shown on your certificate of insurance; Note: This does not apply if you have selected the Complete Replacement Cover® option.  give you a voucher, store credit or stored value card for the amount it would cost us to repair or rebuild an item. If we rebuild (or pay you what it would cost us to rebuild), we will do so on a ‘new for old’ basis. If we repair (or pay you what it would cost us to repair), we will at our option repair on a ‘new for old’ basis or repair to a similar condition to what the building was in before the loss or damage occurred. We will not:  pay more than the relevant sum insured (unless you have the Building Complete Replacement Cover® option) or policy limit;  pay extra to replace the building or landlord contents to a better standard, specification or quality than they were before the loss or damage occurred except as stated in the meaning ‘new for old’;  fix a fault that existed before the loss or damage occurred. P. 54 Building claims Dealing with defects We do not rectify structural or design faults When we accept a claim, we will not pay extra to rectify a structural or design fault at the building that you knew about (or should reasonably have known about). We will only pay you wha t it would have cost us to fix the damage from the incident covered Determination | Case number: 756981 Page 8 of 8 PDS reference Wording by your policy or, if we agree, you can pay us the extra amount it costs to rectify the structural or design fault at the building. If undamaged defective parts of the building will not s upport repairs If undamaged defective parts of the building you knew about (or should reasonably have known about) will not support repairing the damage caused by an incident covered by your policy, we will only pay what it would have cost us to repair the damage had the building not been defective. For known defects or faults Once you become aware of a defect, structural or design fault at the building, you must rectify it as soon as possible because there is no cover for loss or damage due to that defect. If you do not rectify the defect or fault, you may not be covered or we might not offer a renewal of your policy.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.