Dispute over scope of works and cost of repairs following sewage overflow damage; cash settlement and non-financial loss
Text of the determination
Determination
Case number 756351
Financial firm QBE Insurance (Australia) Limited
Determination | Case number: 756351 Page 1 of 17
Case number: 756351 22 March 2022
1 Determination overview
1.1 Complaint
The complainants are beneficiaries under a residential strata insurance policy with the
financial firm (insurer).
In July 2019, a claim was lodged for damage to their property, after a blockage caused the
overflow of sewerage into their property. The claim was accepted, and attempts made to
remediate the damage.
A dispute has arisen over the repairs to the property and the work required to restore the
home to its pre-event condition. The complainants also say medical treatment has been
required due to the mould and that there has been significant delay and aggravation caused
in finalising the repairs.
The insurer has made an offer of $22,600.26 to the complainants for the reasonable cost of
repairs and additional costs.
The complainants reject the insurer’s offer and are seeking compensation in the amount of
$170,653.74 to resolve the complaint.
1.2 Issues and key findings
Is the insurer required to increase its settlement offer?
The insurer has made offers to settle this matter. Based on the available information, the
insurer is required to increase its settlement offer for the cost of repairs and compensation for
non-financial loss as follows:
Pay 20% contingency on the $14,020.08
Increase the offer of compensation by $1,000 to $3,000
Refund the sum of $4,078 paid by the complainant and pay interest under section 57
of Insurance Contacts Act 1984 (Cth) (the Act)
Maintain the offer of $1,400 for one week of temporary accommodation.
Why is the outcome fair?
The outcome is fair as all the available material has been considered and the outcome is in
line with AFCA’s approach to these types of matters. The complainant and the insurer has
made submissions and all issues have been considered
1.3 Determination
This determination is substantially in favour of the financial firm.
Subject to the acceptance of the determination, the insurer is required to increase its
settlement offer for the cost of repairs by an additional $2.804.01, to a total of $16,824.82.
The insurer is to pay an additional $1,000 in compensation for non-financial loss, to a total of
$3,000.
Determination | Case number: 756351 Page 2 of 17
The insurer is to refund (if it has not already done so) the $4,078 paid by the complainants
and pay interest under section 57 of the Act, from the date of payment until settlement by the
insurer.
Pay $1,400.00 for one week of temporary accommodation
Determination | Case number: 756351 Page 3 of 17
2 Reasons for determination
2.1 Is the insurer required to increase its settlement offer?
Policy provides cover for accidental loss or damage
The product disclosure statement (PDS) outlines the circumstances under which the policy
provides cover.
The policy provides for accidental loss or damage. This policy says this means any partial or
total accidental physical loss of, or destruction of property from any sudden and accidental
cause not otherwise excluded by the policy.
Policy has discretion as to how the insurer settles claims
The PDS outlines how the insurer settles claims
Claims - how we will settle your claim
“ If Your Insured Property is Damaged, we may choose to either rebuild, replace,
repair or pay the amount it would cost to rebuild, replace or repair ” .
Offers made by the insurer to resolve the complaint
Repair works and accommodation
The insurer says following discussions with the complainants regarding rectification works, it
recommended a cash settlement for the cost of repairs to finalise the claim. Both parties have
agreed a cash settlement is an appropriate method of settlement. However, there is a dispute
as to the scope of works (SOW) and cost of repairs
Following its assessment, the insurer tasked its builder (JLG) to provide a SOW for the claim
related repairs. The Insurer requested JLG provide an estimate for the repairs while the
complainants obtained their own comparative quotes based on the same SOW.
Accordingly, the complainants provided quotations from builders (RC) for $115,469.20 and
(EB) for $109,418.51. As RC provided a higher quoted amount, RC’s SOW and quotation
were used as the basis in reviewing the information and preparing the determination.
The complainants are also seeking compensation for:
sewerage remediation (before and after repair works) totalling $ 5,876
three months temporary accommodation totalling, $19,485.60 for the duration of
repairs based upon quotation from (KA).
The insurer says the SOW from JLG and that of RC differ significantly. For example, the
quotation provided by RC includes removal & replacement of the entire bathroom which the
insurer says is not required.
Following review, the insurer says it is unable to accept RC ’ s SOW as the extent of repairs
are not justified. The insurer says there is insufficient evidence to establish that all works
claimed relate to the damage caused by the event. The insurer also says there is a lack of
evidence establishing the complainants ’ concerns that there may be undiscovered damage.
Determination | Case number: 756351 Page 4 of 17
Based on the advice from its experts, the insurer made an offer to compensate complainants
$17,400.08 for the reasonable cost of repairs to complete the works and temporary
accommodation.
Compensation for non-financial loss
The complainants are seeking compensation for non-financial loss in the amount of $24,900.
This includes a claim for compensation relating to twenty-six issues that were identified by the
complainants.
The insurer says AFCA cannot award an amount of $24,900 as it exceeds the $5,000 cap for
non-financial loss compensation which applies to complaints relating to General Insurance.
The insurer says it has carefully considered the issues raised by the complainants. It accepts
that a significant amount of time has elapsed since the event and it has previously provided
its apologies to the complainants for the issues experienced under the claim to date.
In recognition of the above, the insurer offered an amount of $2,000 for non-financial loss
compensation to the complainants.
Accordingly, the insurer made an offer of $22,600.26 to the complainants for the reasonable
cost of repairs and additional costs. T he insurer’s final offer to the complainants is made up of
the following:
The complainants reject the insurer’s offer and seek further compensation as outlined in the
next section of the determination (below).
Breakdown of insurer’s review / offer based on the complainants’ submissions:
List of Claims for AFCA Summary
Ite
m
Description Total [insurer]
Adjustment
GST Inclusive
[insurer] Comment
Determination | Case number: 756351 Page 5 of 17
I Reimbursements for expenses Insured $
8,876.94
$
3,150.18
Reimbursements
$
50.00
adjustment 19/01/2021 as
below
II Sewage and building rectification (3 months) $
136,876.80
$
14,020.08
JLG Quotation #
JNAC09453/1AB dated 22nd
October 2020
$
3,380.00
adjustment 19/01/2021 as
below
Temporary accommodation $
-
Furniture removalist and storage
III Non financial Compensation - 26 claims $
24,900.00
$
-
Total Cash Settlement Sought $
170,653.74
$
20,600.26
Total 19/01/2021
Description Total [Insurer]
Adjustment
[Insurer] Comment
I Total Reimbursement Sought $8,876.94
1 Medical expenses
Sunday, 11 August 2019 $
265.70
$
-
Policy 1 does not respond to
medical expenses and the
insured was referred to
policy 2 for consideration of
submitting a liability claim
against the owners
corporation for
consideration this was
never rec eived.
26th August 2019 $
56.80
$
-
4th October 2019 $
50.20
$
-
9th October 2019 $
51.80
$
-
11th October 2019 $
51.80
$
-
16th October 2019 $
692.95
$
-
Monday, 21 October 2019 $
632.15
$
-
Tuesday, 25 February 2020 $
56.80
$
-
2 Electricity, Gas and water (Policy limit) $
2,000.00
$
-
Already included in our
expenses reimbursements
$600.00
3 Cleaning 9 Aug 19 $
150.00
$
-
Already included in our
expenses reimbursements
$150.00
4 Removal and Storage Costs $
660.00
$
-
Already included in our
expenses reimbursements
$660.00
5 Levies/contributions (policy limit $2000.00) $
2,000.00
$
-
Already included in our
expenses reimbursements
$180.18
Determination | Case number: 756351 Page 6 of 17
6 Removal of Mould 18 Oct 2019 $
230.00
$
-
Already included in our
expenses reimbursements
$230.00
7 Bathroom Marble Wall Cleaning $
1,000.00
$
-
Already included in our
expenses reimbursements
$1000.00
8 Skirting board allowance for works not done by [de -
identified]
$
330.00
$
-
Already included in our
expenses reimbursements
$330.00
9 Temp Wardrobe 7 Aug 19 $
99.00
$
-
No usable wardrobe due to
presence of sewage.
Clearance was given by
[business] copy of Clearance
Certificate attached
10 Extension Power 9 Aug 19 $
11.99
$
8.00
No usable power point from
2nd Aug to 10 Sept. Owner
Insured was in temporary
accommodation from 24th
Aug to 3rd Sept claimable
amount has been adjusted
accordingly.
11 Laundromat 7 to 18 Sep 19 $
63.00
$
42.00
No usable plumbing for
washing machine 3rd Aug to
7 Sept. O wner Insured was
in temporary
accommodation from 24th
Aug to 3rd Sept claimable
amount as been adjusted
accordingly
12 Building Inspector Fee (limit $30,000.00) $
1,107.00
$
-
[insurer] to confirm if report
was requested. We consider
the repor t to be speculative
and hold no relevance to
the claim.
13 New bed, mattress and bedding $
1,000.00
$
-
Contents
Total sums $
50.00
Total [insurer] Adjustment
19/01/2021
II Sewage and Building Rectification Sought $136,876.80 to reinstate the apartment to before 27 July 2019
sewage incident as suggested by Building Inspector
1 Temporary Accommodation for one bedroom
apartment
$19,485.60 $
1,400.00
Allow 1 week
accommodation for
restoration to attend site to
complete full clean of built
in robe. JLG allowing to
have ozone machine within
the proper ty for maximum
of 2 days
2 Removal and Storage costs (Limit $2,500.00) $
1,562.00
$
-
JLG scope of works does not
require removal and
storage of items
3 Sewage Rectification for half the apartment after
removal of affected building Materials
$
5,876.00
$
-
[Business] cleara nce
certificate attached. J LG
amended scope of works
includes allowance for
restoration to bathroom,
Determination | Case number: 756351 Page 7 of 17
dedroom, laundry and entry
4 Hygienist to attend $
3,850.00
$
1,320.00
Provisional sum for further
clearance certificate to be
provided at completion of
JLG scope of works
5 Allowance for cleaning floor after removing gyprock $
3,300.00
$
660.00
Standard cleaning
allowance for completion of
works
6 Remove laminated flooring, clean and put back again $
5,875.10
$
-
Not required for the repair
of resultant damaged works
Entry Way (from here on, please look at J7 Revised Builder Quote for Amount)
7 Main entrance fire door to be sanded repaired and
painted
$
695.75
$
-
Included in JLG scope of
works
8 Remove and replace gyprock wall lining and metal stud
wall (approx 6.5m2)
$
885.50
Not required for the repair
of resultant damaged works
Laundry
9 Laundry Area Plasterboard $
885.50
Not required for the repair
of resultant damaged works
10 Bi - fold door to be replaced $
1,518.00
Included in JLG scope of
works
11 Laundry Cabinet door to be r eplaced $
759.00
Not required for the repair
of resultant damaged works
12 Waterproof the laundry sink $
1,265.00
Not required for the repair
of resultant damaged works
13 Drain grate to be replaced $
316.25
Included in JLG scope of
works
14 Remove wall in laundry, clean and put back new floor
and wall tiles
$
18,975.00
Not required for the repair
of resultant damaged works
The only bathroom in the one bedroom apartment
15 Replace Bathroom hinged door $
885.50
Included in JLG scope of
works
16 Replace shower Screen $
2,277.00
Included in JLG scope of
works
17 2 x drain grate to be r eplaced $
759.00
Included in JLG scope of
works
18 Door Stopper $
94.88
Not required for the repair
of resultant damaged works
19 Bathroom Ceiling to be replaced and painted $
8,855.00
JLG Scope of works includes
to complete minor scraping
and repair to ceiling set
sand and paint.
Replacement of ceiling not
required for the repair of
resultant damage works
20 Remove entire bathroom reuse if possible vanity
shower rail towel rail and accessories
$
31,625.00
Not required for the repair
of resultant damaged works
The only bedroom n the one bedroom apartment
21 Plasterboard to be sanded, touched up and painted $
4,427.50
Included in JLG scope of
works
Determination | Case number: 756351 Page 8 of 17
22 The cavity slider sliding door to be replaced which
involved removing
$
12,650.00
JLG Scope of works includes
for restoration to attend
site to complete full clean
of built in robe due to smell.
Removal and replacement
not required for the repair
of resultant damage works
23 Plasterboard in the bedroom cabinet $
1,897.50
Not required for the repair
of resultant damaged works
24 Reinstate wardrobe $
6,325.00
Not required for the repair
of resultant damaged works
Lounge Area
25 The cavity sliders sliding door (of at least 2.6 m tall x
1.5 m wide) to be replaced which involved removing
plasterboard
$
8,855.00
Included in JLG scope of
works
$
3,380.00
Total [insurer] Adjustment
19/01/2021
III Non Financial Compensation sought $24,900 for 26 claims for AFCA consideration
1 FF actions caused personal stress, harm and
inconvenience by not providing TA and advising it was
safe to stay in unit 22 so [complainant] to stay in
sewage infested apartment, before cleaning began. In
contract, it approved TA for both Unit 23. Both
apartments are one bedroom units
$
100.00
$
-
Our policy does not include
an additional or spe cial
benefit which responds to
the items claimed. The
insured was reimbursed for
accommodation incurred
and we followed the advice
of the appointed specialists
concerning the cleaning and
habitability.
2 Major Issue 1: FF actions caused personal stress, harm
and delayed the claim when it falsely claimed, for a
year, only one 'organic' cleaning product was used. The
actions contravened FF's good faith policy and
provided a false basis to reject [complainant’s] medical
claims
$
5,000.00
$
-
3 FF actions in not completing the works caused personal
stress, great harm and significant inconvenience with
an unusable bedroom in a one bedroom unit because
[complainant] had to stay in a sewage infested
apartment since 27 July 19. FF admitted this ( [insurer]
Para 39) and it's supported by BI's report
$
5,000.00
$
-
4 Major Issue 2: FF's actions in not advising lethality of
cleaning chemicals caused personal stress and
inconvenience to [complainant] because she had pack,
unpack and travel between Unit 22 and TA over 3
individual days from 2 to 5 Aug 2009, because the
sy mptoms wer e so strong each time she returned to
Unit 22
$
300.00
$
-
5 major Issue 3: FF actions caused delay in proceedings
when it continually refused to offer TA for futur e
rectification works in 1 bedroom unit 22 in its
settlement offers. The policy provides TA will be
provided when works covered by a claim make a home
uninhabitable
$
500.00
$
-
Determination | Case number: 756351 Page 9 of 17
6 Major Issue 4: FF's actions caused delay of more than a
year and great inconvenie nce and stress to
[complainant] when it did not provide ED's complete
scope of work, nor a complete scope of scope of works
from any contractor and refused all scopes of work
provided by [complainant] . Hence [complainant] was
unable too close the insurance matter by settling with
a cash claim, as per FF's policy, which mean she had to
endure FF's ongoing inability to get the works done and
spend nearly 18 months repeating the same
information over and over again, only to be rejected -
Th is being far beyond what's reasonably expected of a
claimant
$
5,000.00
$
-
7 FF actions caused personal stress to [complainant]
when it refused to reimburse 2019 cleaning expense of
$150 that prevented injuries caused by FF's cleaning
works. The FF r efused to do cleaning works and
[complainant] had to mitigate their refusal. Only now it
agrees to repay the fees but still has not d one so.
$
100.00
$
-
8 FF actions caused great stress and harm to
[complainant] when its contractor failed to clean the
drainage pipes as detailed in job scope on 31 Jul 19.
[Complainant] had to live with the raw sewage and it's
smell from unclean piping for a week after FF stopped
TA.
$
700.00
$
-
9 FF's actions delayed the claim and caused great stress
to [complainant] when it agreed to r eplace Bi - fold door
on 10 Sept 19, then refused to do so multiple times
and then agreed again on 27 Aug 20. [complainant]
suffered trauma from having to repeat the same facts
over and over again in different ways for almost a year
and g etting rejected each time.
$
2,000.00
$
-
10 Major Issue 5: FF's actions in caused [complainant]
great harm when it failed to manage its contractors
and provide timely reimbursement for agreed
expenses. [Complainant] had to monitor them and
report issues and FF's contractors verbally abused her
and treated her disrespectfully to the extent that
[complainant] had to warn them to stop bullying her at
the 10 Sept 19 site inspection.
$
1,000.00
$
-
11 FF's action caused injury when it failed to order
[business] c to return and wipe down surface for
[complainant] despite the fact that FF got [business] to
do so for Unit 23. [Complainant] burnt her palm once
again
$
100.00
$
-
12 FF actions caused inconvenience for [complainant] to
move back by not allowing for TA even though the
building rectification works were incomplete. Ther e
were no tap and no silicon seal to laundry area, a
relatively simple matter than could have been resolved
with simple project planning
$
100.0 0
$
-
13 FF's action caused delay and stress to [complainant]
when it repeatedly refused to provide details for a
plumber that caused significant damage to the laundry
nor pay for the damages. [Complainant] faced rejection
and evasion each time she attempted to get FF to
redress the matter or provide information so she could
take action
$
1,000.00
$
-
Determination | Case number: 756351 Page 10 of 17
14 FF actions caused delay when it agreed to replace the
damaged bi - fold door on 10 Sep 19, then spent 11
months denying it's own agreement and
[complainant ' s ] evidence based requests until it finally
agreed to replace it on 20 Aug 20. In the process FF
made fraudulent claim, contravened FF's good faith
policy and failed to be diligent by not checking the
facts
$
3,000.00
$
-
15 FF actions caused delay of more than a year when it
agreed to replace sewage infused bathroom hing ed
door since 20 Aug 29 and refused to do so on 1 Nov 19.
FF has intentionally made fraudulent claim,
contravened FF's good faith policy and failed to be
diligent by not checking the facts
$
1,000.00
$
-
16 FF actions caused delay when it contravened it's own
response poli cy 4 times by not telling advise
[complainant ] it's contractors would not return
$
2,000.00
$
-
17 FF's actions caused delay, enlarge necessary scope of
rectification works and caused [complainant] great
harm. FF agreed to get [business] to clean the mould
when it was only on the shower screen but did nothing
for 6 weeks, despite reminders from [complai nant] . FF
compounded the issue by not advising [complainant]
that [business] wasn't going to clean up. Once
[complainant] found out she engaged a mould cleaning
specialist, but they then, it was to late. The mould had
spread to the ceiling specialists, bu t by then, it was to
late. The mould had spread to the ceiling and all over
the bathroom. It infected her eyes and ears, disabled
her vision and hearing and she had to seek urgent
medial treatment with a medial specialist in Singapore.
$
5,000.00
$
-
18 FF's actions caused a delay for more than 9 months
from 10 Sep 19 because it did not get ED to return to
work. FF stated on 10 Jul 20 that it can issue directive
for EB to return to works
$
1,000.00
$
-
19 FF actions caused delay and stress for [complainant]
when it did not reply to [complainant’s] request to get
a different builder willing to do works when she
rejected FF's first lowball cash settlement offer.
Another builder could have finished the works and
settled the claim, quickly. Instead FF reiterated the
same offer of $4078.00 blatantly dis regarding what
was agreed upon 10 Sep 19. FF's action caused delay
$
100.00
$
-
20 FF actions caused delay when it did not respond to
[complainant’s] email reminders for status update s
and progress within 15 business days as per FF's own
policy. This began on 7 Jan 20 happened monthly till 9
Sept 20
$
400.00
$
-
21 FF actions caused delay when it failed to escalate the
claim as required by its own policy. FF simply made
another offer which had no regards for the rectification
works agreed upon on 10 Sept 19, which bogged the
claim down as [complainant] had to prove a ll over
again what had been agreed upon
$
700.00
$
-
Determination | Case number: 756351 Page 11 of 17
Complainants say insurer should increase its settlement offer
The complainants say a cash settlement of the claim is essential for timely and sound
completion of works. The complainants say if the insurer was to complete a partial or full
restoration, they (the policy holder) have little power to influence outcomes. The complainants
say this is important because the insurer has consistently demonstrated ineptitude in
completing the required works. The complainants say the insurer has a level of accountability,
responsibility and control over the builders and works, but it has continually failed to do so
over the last year and a half.
22 FF actions caused delay and stress to [complainant]
when it continually made low cash settlement offers
that ignored the facts and relied on fraudulent
information which contravened its good faith policy. It
persistently ignored its 10 Sep 19 agreement about the
items that needed to be replaced. [Complaina nt] was
very stressed by FF's apparent intransigence which look
like it would set her back at least 50K (This was before
FF admitted to withholding critical information that
ballooned rectification costs)
$
300.00
$
-
23 Major Issue 6: FF's actions in caused long delays and
enormous stress to [complainant] when it blatantly
disregarded of General Insurance Code of Practice by
operating in bad faith and engaging in bullying tactics
to try force and [complainant] to accep t the low full
cash settlement which threatened financial loss of
more than $100,000.00 or force her to fear for her
safely when it told her on 21 July 20 that ED was the
only company it would engage to do the works
$
5,000.00
$
-
24 FF actions in failing to provide timely response on
building rectification work scope from 29 July 20 to
now delayed the whole claim process
$
400.00
$
-
25 FF's action caused delay of more than a year and
caused st ress when it failed to provide [business] 31
July final report for more than a year after
[complainant] requested a copy via SMS on 31 July 19
(she was given the ' [business] ' hygienist report instead
so she was not aware of the withheld report) I t took FF
12 months to come clean which contravenes its good
faith and high standard of service policy. It failed to
identify the egr egious errors in the report for the
entire year and when [complainant] finally pointed
them out shortly after getting the r eport, the FF finally
accepted many aspects of [complainant’s] claims.
[Complainant’s] stress over a year came about because
it was not possible to fathom why FF failed to accept
her evidence and proof.
$
5,000.00
$
-
26 FF's actions caused delay when it did not provide a
timely response of 15 business days not meet the 28
Aug 20 deadline sent by Head of Claims after escalating
the issue on 21 July 20
$
100.00
$
-
$
-
Total [insurer] Adjustment
19/01/2021
Determination | Case number: 756351 Page 12 of 17
The complainants submit the insu rer’s SOW has not included all damage requiring
rectification. Accordingly, the complainants have raised concerns regarding:
reimbursement of incurred expenses
the SOW and cost of repairs
temporary accommodation
compensation for non-financial loss
Accordingly, the complainants are seeking compensation as outlined below:
Reimbursement of incurred expenses
Having considered all the available information, the Panel is not satisfied the complainants
have provided sufficient evidence to confirm how they have suffered losses directly as a
result of the claim or their entitlement for further compensation.
On this basis the Panel believes the insurer’s offer of $3,150.18 is fair under the
circumstances. However, further consideration for non-financial loss has been given as
outlined in the latter section of the determination.
Accordingly, this part of the determination is in favour of the insurer, and it is not required to
make any further payments or take any further action.
Scope of works and cost of repairs
The insurer has offered to pay the complainants $14,020.08 for the cost of the remaining
repairs, while the complainants are seeking an additional $ 115,469.20.
The Panel accepts the complainants remain dissatisfied with the insurer’s offer and are
seeking compensation as per RC’s quote. The Panel also accepts the insurer is not willing to
provide any further increase based on the recommendations from it repairer.
A SOW provides a general overview of the required works based on the available information.
However, the scope is subject to variations based on additional damages and costs that may
be incurred while repairs are undertaken.
The complainants’ property suffered damage due to an insured event and the insurer agreed
to cover the claim accordingly. The insurer proceeded with appointing various experts to
attend the property to assess and address the damage.
Having considered all the exchanged material, the Panel is satisfied the i nsurer’s proposed
SOW is adequate to address the claim related damages and required rectification work.
Determination | Case number: 756351 Page 13 of 17
For this reason, the Panel does not consider it fair to u se RC’s quote and SOW as a basis for
settlement, because the Panel is not satisfied all the noted items relate to the claimed event.
However, the Panel does believe the insurer is required to increase its settlement offer to
allow for contingencies.
The policy says in the instances where the insurer chooses to cash settle a claim, it will only
pay the policy holder what it would cost the insurer to undertake the repairs. However, when a
claim is cash settled all the associated risk is transferred onto the policy holder.
On this basis, the Panel considers it appropriate under the circumstances that the insurer
increases its offer to allow for contingencies by 20%, due to the transfer of risk which is in line
with AFCA’s approach to these types of matters.
Therefore, the insurer is to pay the complainants $14,020.08 plus $2.804.02, for
contingencies, a total of $16,824.82.
Accordingly, this part of the determination is in favour of the complainants.
Temporary accommodation
The complainants are seeking $19,485.60 for the cost of temporary accommodation, for a
period of three months.
The insurer has allowed for one week of temporary accommodation at a cost of $1,400.00. It
says this period will allow for restoration experts to attend the site, remove air pollutants and
to complete a full clean of the built-in robe.
Further, the insurer says it is unable to confirm why the complainants would need to vacate
their apartment again for the duration of these repairs as the repairs would not deem their unit
unfit for its intended purpose.
Having considered all the available information, the Panel is not satisfied the complainants
have provided sufficient evidence for the requirement or entitlement to further compensation
for the cost of temporary accommodation beyond the insurer’s offer.
On this basis the Panel believes the insurer’s offer of $1,400.00 (for seven days) is fair under
the circumstances.
Accordingly, the insurer is to pay $1,400.00 for temporary accommodation.
Compensation for non-financial loss
AFCAS takes a conservative approach to compensation for non-financial loss. It is not
awarded when a person suffers the normal degree of inconvenience expected during an
insurance claim.
Under the AFCA Rules, AFCA will award non-financial loss (up to a maximum of $5,000 per
claim) where there has been an unusual amount of:
Physical inconvenience
Time taken to resolve a situation
Interference with the complainant’s expectations of enjoyment or peace of mind
In assessing to award compensation AFCA expects complainants:
Be moderately robust
Bare the normal degree of inconvenience experience when a problem occurs, and
Determination | Case number: 756351 Page 14 of 17
Take reasonable steps to minimise inconvenience suffered.
The insurer acknowledges that there have been disagreements in relation to the appropriate
SOW. It accepts that a significant amount of time has elapsed since the event and it has
previously provided its apologies to the complainants for the issues experienced under the
claim to date.
In recognition of the above, the insurer offered an amount of $2,000 for non-financial loss
compensation to the complainants.
Based on the available information the insurer’s handling of the claim caused the
complainants a degree of stress and inconvenience.
Given this the Panel believes it is fair for the insurer ’s original settlement offer to be
increased.
Accordingly, this part of the determination is in favour of the complainants, and the insurer is
to pay the complainants $3,000 compensation for non-financial loss.
The insurer is required to increase its settlement offer
The complaint has been determined based on what is fair in all the circumstances, having
regard to the relevant law, good industry practice, codes of practice and previous decisions
where applicable.
There has been a full exchange of all material information relied on for the purposes of this
determination and each party has had the opportunity to address any issues raised by the
other. All the material provided by the parties has been reviewed and considered.
Based on the available information, it is evident that there has been a break down in the
relationship between the insurer and the complainants.
Accordingly, as the two parties have not been able to come to a resolution, the Panel is
satisfied a cash settlement of the claim is appropriate in this instance.
Based on its review, the Panel believes the insurer is required to increase its settlement offer
for the cost of repairs and compensation for non-financial loss. However, the insurer is not
required to make any additional payments to compensate the complainants for their expenses
or towards temporary accommodation. The Panel outlines its reasoning and
recommendations for each item in the determination below.
The i nsurer’s offer totalling $20,600.26 – based on available information nothing has been
paid to date.
Insurer’s offer for reimbursement for expenses should be $3,200.18 as per the table below
The Panel accepts that a cash settlement is the most appropriate in the circumstances.
The insurer to increase settlement for cost of repairs by 20% ($2,804.02) to cover
contingencies and loss of guarantee.
- Insurer has already allowed $14,020.08 for repairs
- By adding an additional $2,804.02 this brings the total for cost of repairs to $16,824.10
The Panel considers the offer for temp accommodation of $1,400 is fair under the
circumstances
Determination | Case number: 756351 Page 15 of 17
The insurer is also to pay $3,430.00 [insurer] adjustments(above) which includes $1,400
allowed for temporary accommodation.
The insurer is to pay $3,000 compensation for non-financial loss (increase of $1,000 from
insurer’s offer)
Insurer to increase its original offer by an additional 3,804.02 (increase in cost of repairs and
non-financial loss)
Total settlement to the complainant should be:
- $14,020.08 for repairs
- $2,804.02 uplift
- $3,150.18 reimbursement for expenses
- $3,430.00 [insurer] adjustments(above)
- $3,000.00 non-financial loss
$26,404.28 Total
The insurer is also to pay interest under section 57 of the Act, on the $3,150.18
reimbursement of expenses.
2.2 Why is the outcome fair?
This outcome is fair because both parties have had the opportunity to provide information to
support their position. Accordingly, all the available material has been considered and the
outcome is in line with AFCA’s approach to these types of matters and what is fair under the
circumstances to both parties.
Determination | Case number: 756351 Page 16 of 17
3 Supporting information
3.1 The AFCA process
AFCA’s approach is bas ed on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
A Panel determined this matter
Due to the nature of this complaint, we referred it to a Panel for determination.
3.2 Relevant policy sections
Section
Claims - how We will settle
Your claim
Replacement
If Your Insured Property is Damaged, We may choose to either
rebuild, replace, repair or pay the amount it would cost to rebuild,
replace or repair.
3.3 Supporting information
Document Key points
Insurer’s building consultant
(JL) scope of works
22 - 08 - 2020
Scope of works outlined
Cost of repairs $10,512.11
Complainants’ b uilding
consultant (RC ) quote
9 - 12 - 2020
Quote total $ 115,469.20
Determination | Case number: 756351 Page 17 of 17
Document Key points
Complainants’ email
11 - 12 - 2020
Complainants’ counter offer to the insurer, seeking compensation
of $ 170,653. 74
Complainants’ email
11 - 12 - 2020
Complainants’ list of 26 claims for non - financial loss , totalling
$24,900
Complainants’ email
11 - 12 - 2020
Complainant s ’ submissio n and supporting doc uments (various
attachments)
Complainants’ email
06 - 01 - 2021
C omplainants stating mould causing medical issues
Medical certificates attached for reference
Insurer ’ s email
20 - 01 - 2021
Insurer’s response to the complainant’s submissions and
amended offer(s )
Insurer’s builder’s comments and adjustments
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.