Determination 754889
Dispute over scope of storm repair works and repainting
Summary
The insurer accepted a storm damage claim but revised the scope of works and declined to repaint undamaged areas. AFCA allowed the revised scope, or a cash settlement of $12,664.02 less repaired work plus 15%, and ordered $800 non-financial loss compensation for claim delays.
The policy only requires uniform-appearance repainting where needed to match damaged areas, so the insurer may rely on the revised scope of works.
Issues
- Claim amount dispute primary · not upheld“The insurer is required to repair the storm related damage in accordance with the terms of the policy. The insurer may rely on its SOW dated 7 August 2020.”
- Delay secondary · upheld“I accept the claim was originally delayed for longer than was reasonable or necessary.”
Subjects and remedies
pay non financial lossrepair or rectify
Related
All Suncorp Group determinations · Find similar determinations
Text of the determination
Determination
Case number 754889
Financial firm AAI Limited
Determination | Case number: 754889 Page 2 of 7
Case number: 754889 5 March 2021
1 Determination overview
1.1 Complaint
The complainant holds a home and contents insurance policy with the financial firm
( ‘ insurer ’ ). On 11 February 2020, she lodged a claim for storm damage to her home,
which occurred two days earlier.
The insurer accepted the claim and arranged for an inspection of the damage. The
parties agreed on a scope of works (‘SOW’ ) on 2 July 2020. The SOW included
allowance to repaint several rooms subject to internal water damage during the storm.
Repairs began soon afterwards.
The repairer was unable to complete the work and repairs ceased for a time. The
insurer later prepared a revised SOW and decided against attending to some of the
originally quoted paintwork. It says there were areas quoted which were not subject to
damage.
The complainant considers this unfair. She wants the insurer to honour the original
SOW. She also seeks compensation in addition to the $600 already paid.
1.2 Issues and key findings
Is the insurer’s proposed resolution of the claim fair ?
Yes. The insurer is required to repair the storm related damage in accordance with
the terms of the policy. The insurer may rely on its SOW dated 7 August 2020. It is
not bound by the SOW dated 2 July 2020.
Is a further award of compensation appropriate?
Yes. The insurer agreed to pay additional compensation for $800. The amount
proposed is fair.
1.3 Determination
This determination is mostly in favour of the insurer.
The insurer is entitled to repair the damage at the complainant’s property, in
accordance with the quote and SOW dated 7 August 2020. If the complainant opts to
not permit the insurer to do the work, I am satisfied the insurer may cash settle the
complainant for $12,664.02 less the cost of already repaired damage. If this is done,
the insurer must add 15% to the revised cost to allow for the possibility of additional
damage.
The insurer must pay compensation of $800 for non-financial loss.
Determination | Case number: 754889 Page 3 of 7
2 Reasons for determination
2.1 Is the insurer’s proposed resolution of the claim fair?
Parties dispute the scope of work to repair the home
There is no dispute the interior of the complainant’s home was damaged by rainwater
which entered the home during a storm. This was due to issues with the roof, which
the complainant was asked to rectify. The insurer agreed to cove r the internal
damage.
This complainant relates to the SOW for the internal damage. The complainant’s
home was inspected by builder ‘ DW ’ for the insurer. A SOW (‘original SOW’) was
prepared on 2 July 2020.
This original SOW was agreed to by the insurer and repairs started. Part way through,
the repairer became unavailable and the repairs were stopped. The insurer later
revised the original SOW in relation to the painting of rooms. It said it will only agree
to repaint whole rooms where:
this work was required to rectify water damage, and
necessary to create a uniform appearance, as detailed in the policy.
The complainant says this is unfair. This was not the scope or intent of the original
SOW. She says the insurer should not be entitled to limit its liability for the damage.
Policy details when insurer will repair/rebuild undamaged areas
The insurer’s policy outlines how it attends to certain types of repairs:
When we will repair or rebuild undamaged parts
If we cannot match the new materials with the undamaged parts, we will only pay
extra to create a uniform appearance when:
wall tiles are damaged
…
other wall coverings are damaged
(e.g. paint, wallpaper, wood panels, but not tiles) we will pay extra to paint,
wallpaper or replace undamaged wall coverings in the same room, stairs, hallway
or passageway* where the damage occurred.
The asterisk refers the reader to a diagram in the policy, which outlines how the
insurer defines a room.
Determination | Case number: 754889 Page 4 of 7
Insurer altered the scope of works after commentary by DW
Under certain circumstances, the policy pays extra to paint walls to create a uniform
appearance. The insurer confirms it agreed to do this. Based on the insurer’s file
notes, it informed the complainant on 29 June 2020 it had:
authorised painting of whole rooms … we have now authorised painting of whole
rooms the following rooms have been authorised to be painted (painting to
include, all walls, ceiling, cornice and skirting) Bedroom 1, lounge room, dining
room, ensuite and hallway
On 8 June 2020, the insurer’s file notes say it clarified with the complainant that:
we will only paint damaged surfaces however if paint does not match we could
paint [the] entire room, will not know [until] painting commences.
On 2 July 2020, the complainant emailed what she considered the original SOW
would entail. This was agreed to by the insurer, although it now says this was in error.
The original SOW included:
Paint whole rooms including doors and skirting boards:-
Living/Kitchen room
Dining room
Lounge room
Hallway
Main bedroom
Ensuite
The insurer reports DW reinspected the site on 17 July 2020 and identified there were
some areas of the interior which were not storm damaged. An annotated list of photos
from the site were provided. Amongst the observations made were:
many areas detailed for painting work were not storm affected
storm damage was present to some ceiling areas and walls
unsure if rear double doors were storm affected or not
intricate living room ceiling has some issues but these are not storm related.
DW offered commentary relating to the amount of work some areas would entail and
the costs this would incur. The wording of the commentary implies the repairer did not
want to do work it would not be appropriately compensated for. I do not consider this
appropriate. The purpose of such a report is to detail the work which needs to be
done, regardless of cost. Any commentary should be restricted to whether the work is
necessary or not.
Determination | Case number: 754889 Page 5 of 7
I accept there were significant areas of water ingress into the property. The affected
areas will require repair and/or repainting, as appropriate.
Based on DW’s further inspection and commentary , the insurer re-worked the SOW. It
considers the fair repair value for the internal damage to be $12,664.02 (‘new SOW’).
Insurer may attend to repairs in accordance with new scope of works
The insurer says the new SOW is a more accurate estimate of loss relating to the
storm incident. It notes the original SOW included the re-painting of areas which it
says were not storm damaged. The insurer does not consider the original SOW
accurately represents the incident damage.
The complainant maintains the insurer should implement the original SOW. In part,
she says this is because it began (and would likely have completed) this work before
the selected repairer had to withdraw.
Whilst I accept some repairs were undertaken pursuant to the original SOW, t here is
no evidence the complainant suffered a loss through the subsequent delay. If quoted
areas are not damaged, I see no reason the insurer should have to conduct repairs
(unless required to under the terms of the policy).
The policy only requires additional work to be done if the insurer cannot match new
materials and it is necessary to create a uniform appearance. I accept a decision on
whether this is necessary likely cannot be made until the repairs are attempted. I see
no reason why the insurer should be compelled by the original SOW to attend to
unnecessary work.
There is no independent evidence from the complainant to show all the originally
quoted walls require repainting.
The insurer agrees that should it discover additional work is required during the repair
process, it will attend to it. I am satisfied this is a fair approach and in line with the
intent of the policy wording.
Given this, I accept the insurer is only liable to repair the damage caused by the storm
event and/or in accordance with what the policy provides. I am satisfied the insurer
should attend to work as outlined in the new SOW. If additional work is required to
return the home to its pre-incident condition, the insurer may attend to this, as
necessary.
Should the complainant opt to not permit the insurer to do the work, I am satisfied it
may cash settle the complainant for the damage. This should be done for $12,664.02
less the cost of already repaired damage. If a cash settlement is arranged, the insurer
must add 15% to the revised cost to allow for the transfer of risk to the complainant
and possibility of additional damage.
Determination | Case number: 754889 Page 6 of 7
2.2 Is a further award of compensation appropriate?
Compensation may be awarded in certain circumstances
Under our Rules, the Australian Financial Complaints Authority (AFCA) may award
compensation for non-financial loss (capped at $5,000) where there has been an
unusual amount of:
physical inconvenience
time taken to resolve the situation
interference with a complainant’s expectation of enjoyment or peace of mind.
AFCA takes a conservative approach to compensation and expects a complainant to
bear a normal degree of inconvenience during the course of a claim.
Insurer’s further offer for compensation is fair
The complainant raised several issues with the insurer’s handling of her dispute.
She is dissatisfied with the delays incurred from the outset, the insurer’s decision to
alter the SOW and the refusal to implement the original SOW.
I accept the claim was originally delayed for longer than was reasonable or
necessary. I further accept there has been confusion for the complainant and
interruptions with the repair process.
The insurer acknowledges its handling of the claim has not been to a level the
complainant should reasonably expect. It previously agreed to waive the policy
excess for the claim ($400) and pay compensation ($200) in recognition of this.
Subsequent to the preliminary assessment issued by AFCA, the insurer agreed to pay
an additional $800 compensation to the complainant. I am satisfied this is fair.
Determination | Case number: 754889 Page 7 of 7
3 Supporting information
3.1 Process
AFCA’s approach to this complaint
This complaint has been determined based on what is fair in all the circumstances,
having regard to the legal principles, applicable industry codes or guidance, good
industry practice and previous decisions of AFCA or its predecessor schemes (which
are not binding).
A full exchange of the relevant information has taken place between the respective
parties. Each party has had the opportunity of addressing any issues raised. All of the
provided information has been reviewed and considered. The parties have raised
numerous issues in their submissions to AFCA. However, commentary in this
determination is restricted to those issues considered relevant to the outcome.
How we assess complaints
AFCA is not a court of law. We do not have the power to take or test evidence on
oath, or to require third parties to give evidence. When we assess complaints, we
consider available documents, the recollections of the parties, and all relevant
circumstances. We give more weight to documents created at the time the events
occurred. If there is no relevant documentation, we will decide what is most likely to
have occurred based on the information provided to us. If there are conflicting
recollections and these are evenly weighted, we may find that a claim cannot be
established.