Text of the determination
Determination
Case number 753603
Financial firm Allianz Australia Insurance Limited
Determination | Case number: 753603 Page 2 of 9
Case number: 753603 25 March 2021
1 Determination overview
1.1 Complaint
The complainant lodged a claim with the financial firm (insurer) for storm damage
following a severe storm and hail event on 19 January 2020.
The insurer accepted hail damage to the skylights and internal water damage. The
complainant says, following the repair of the skylights, water continued to leak though
the skylights and the downlight
The complainant wants the insurer to repair the internal and external damage to the
property and cover the cost of alternative accommodation during repairs.
1.2 Issues and key findings
Is the insurer required to attend to rectification of the skylights?
Yes. The policy requires the insurer to repair the building to the same condition as
when new. The insurer has not done this with the skylights. The insurer is required to
adequately repair the skylights, including the ventilation issues.
Is the insurer liable for any further damage to the roof?
No. The information does not establish further storm damage to the external roof.
Is the insurer entitled to cash settle the cost to repair the internal damage?
Yes. The insurer can cash settle the claim for the internal damage. The insurer is
however required to make sure the settlement is based on an actionable quote as
outlined in section 2.3. The insurer must provide an additional allowance of 10% on
the final quote to account for the transfer of risk and unforeseen contingencies.
Is the insurer liable for alternative accommodation costs?
Yes. The insurer is liable for alternative accommodation costs in accordance with the
terms of the policy.
1.3 Determination
This determination is substantially in favour of the complainant.
The insurer is required to attend to the rectification of the skylights. It must also
organise the appropriate settlement of all internal damage, as outlined in section 2.3
of this determination. The insurer is to cover the reasonable cost of alternative
accommodation in accordance with the policy terms.
Determination | Case number: 753603 Page 3 of 9
2 Reasons for determination
2.1 Is the insurer required to attend to rectification of the skylights?
The complainant says the skylights have not been adequately repaired
The complainant’s policy provides cover when one of the listed insured events cause
loss or damage to the insured home during the period of insurance. Relevant to this
complaint, the policy provides cover for ‘storm’ , including violent wind, hail and rain.
There is no dispute a severe storm event occurred on 19 January 2020. The insurer
agrees this storm event caused damage to the skylights. The insurer authorised the
replacement of the skylight domes.
The complainant says, since the skylight domes were replaced, the kitchen and
bathroom skylights build up so much condensation it drips and creates puddles of
water on the floor.
When an insurer authorises repairs, it is responsible for the quality of the repair work
and material used. However, if the complainant disputes the quality of repairs, there
must be sufficient information to show, on balance, the repairs were not completed to
the required standard.
Insurer says the condensation is caused by pre-existing issues
The insurer says the excessive condensation is caused by p re-exiting ventilation
issues. The insurer provided reports from a roof plumber (BL) dated 20 May 2020 and
another roof plumber (RC) dated 29 August 2020, to support this.
There is no dispute two of the replaced skylights show large amounts of
condensation. BL says the dome was replaced with the same material, so it is unable
to explain the additional condensation now being caused. BL later clarifies it thinks
lack of appropriate ventilation is the cause of the excessive condensation.
RC agrees the lack of ventilation is the cause of the condensation. BL provided
several recommendations to address the ventilation issues. The insurer does not
agree it is liable to rectify this issue.
Available information shows the insurer did not adequately repair the skylights
The available information shows the new skylights were not adequately repaired.
While RC says lack of condensation control was the cause of the condensation on the
new domes, RC also says the bathroom skylight dome was not fixed into place. There
is a photograph of the new skylight dome being lifted away from the skylight shaft. It is
clear this skylight requires rectification.
Determination | Case number: 753603 Page 4 of 9
Further, t he insurer’s loss adjuster (CC) provided a report dated 13 July 2020 which
refers to a reinspection by a building company (AN). This report has not been
provided to AFCA for review. However, CC says AN advised:
the cause of the condensation to the skylight domes is the result of having no
ventilation at the top of the skylight shaft
the installation of the new skylight domes have been done to a poor quality with
excessive silicone used.
CC’s report says there is ‘solid proof that the condensation is a pre-existing issue. ’ I
disagree. Just because there were ventilation holes in the original skylight assembly
does not automatically mean there were pre-existing condensation issues. Both BL’s
an d RC’s reports c learly show skylights need to be installed with adequate ventilation.
A report from the insurer’s building company (CS) says there is ‘runs of water staining
visible on internal riser’. There is nothing to support this is pre-existing damage. The
skylights were punctured by hail, therefore, resultant ‘runs of water’ would be
expected from the claimed event.
Insurer is required to rectify the skylights, including the ventilation issues
The policy says, if the insurer agrees to cover the claim for loss or damage to the
buildings, it will cover the reasonable cost of repairing the damaged part of the
buildings to the same condition as when it was new.
I do not accept the insurer met its obligations under the policy in relation to the repair
of the skylights. The insurer’s own reports show th e skylights were not repaired to the
same condition as when new. The insurer replaced the bathroom dome
unsatisfactorily, and the repairs did not allow for adequate ventilation.
The policy says the repair of roof materials is limited to the physical area where loss
or damage occurred. It is fair, in this instance, to consider the area of damage to
include the entire skylight. This includes its assembly and ventilation if this is required
to return the skylight to the same condition as when new. To not do so, would leave
the complainant in a worse position than she was in prior to the damage.
Considering all the above, the insurer is required to rectify the skylight repairs,
including the ventilation. It is also liable for any additional internal damage that has
subsequently occurred from the initial inadequate repairs.
2.2 Is the insurer liable for any further damage to the roof?
The complainant says rain water was dripping through the downlight
The complainant says, following the storm event, water has been dripping through the
downlight. The complainant believes the storm caused damage to the external roof
which allowed this water ingress and subsequent damage.
Determination | Case number: 753603 Page 5 of 9
The insurer accepted liability for the internal water damage but says there is no storm
damage to the roof.
In this instance, the onus is on the complainant to show, on balance, there is damage
to the external roof caused by the storm event.
Storm damage is limited to the internal damage
CC’s report of 8 Sep tember 2020 confirms the storm event of 19 January 2020 was a
major contributing factor in causing the internal damage. CC says most of the
insulation was saturated and damaged the plaster board linings in the kitchen.
CC’s summary of AN’s report (which w as not provided to AFCA) shows:
a heat spray test to the area above the water ingress area in the kitchen identified
the cause is the ‘result of 2x lifted fixing screws on the air conditioning base’
a make safe was completed to this area but the ‘lifted screws would be a result of
maintenance issues, not hail damage’.
There is no information to show everyday expected rain events would usually cause
water ingress through the lifted fixing screws. Cons idering this, and CC’ s conclusion
that the storm event was a major contributing factor, the insurer’s decision to accept
liability for the internal water damage is in accordance with its policy obligations.
This does not create an obligation on the insurer to repair the fixing screws, or any
other sites of water ingress on the external roof. This is because, there is no
information to show the storm caused these issues.
The available reports identify installation issues with the external roof area
RC provides photographs and an ‘extensive list of installation faults [ … ] that all have
the potential to contribute to rainwater ingress […]’ . BL outlines much of the same
concerns with the external roof, in addition to deterioration of silicone seals. AN
outlined the same issues with the roof but says this is ‘unrelated to the cause of water
ingress’ from the claimed storm event.
Regardless of whether the identified roof issues are sites of water ingress or not, it is
clear these issues were not caused by the storm event. There is no evident hail,
rainwater or wind damage to the external roof (other than the skylights). Considering
this, I am not satisfied the complainant has established any other storm created
damage to the external sections of the roof.
2.3 Is the insurer entitled to cash settle the cost to repair the damage?
The insurer is entitled to cash settle the internal damage
When there is damage covered by the terms of the policy, the insurer has the
discretion to decide whether it will authorise the repair of the claim related damage or
pay the complainant the cost of repairing the damage. The insurer must however
Determination | Case number: 753603 Page 6 of 9
exercise this discretion fairly and reasonably considering the circumstances of the
claim and the available information.
The insurer agreed to cover the internal damage under the policy. However, it says
issues identified with the roof need to be repaired before the internal works can
proceed. It therefore offered to cash settle the complainant the cost of the internal
repairs. This was declined by the complainant.
I accept the decision to cash settle the internal damage is fair and reasonable in the
circumstances. This is because, the above non-claim related concerns with the
external roof means the insurer cannot guarantee the success of the internal repairs.
However, the available information is not sufficient to establish the amount offered is
appropriate.
Insurer is to cash settle a sufficient amount to adequately repair the damage
The insurer offered a cash settlement of $5,289.57 for the internal damage. The
insurer did not provide AFCA a copy of the quote or the relevant scope of works. It is
not clear if the cash settlement offered included all the internal damage, as outlined
above, including the:
water run marks noted on the skylight shaft
the electrical components of the kitchen ceiling (if required given the water in the
downlight)
any additional water damage caused by the inadequate repair o f the skylights.
Considering the insurer’s decision to cash settle the repair cost, it is to settle the
internal damage based on a current and actionable quote. This is to include the
expenses the complainant will reasonably incur to organise the repairs herself, such
as builder ’ s margin, administration, site supervision and insurance.
Insurer is not entitled to make deductions for discounts
The policy says, if the insurer decides to cash settle the claim, the settlement will be
based on the cost of repair, less any discounts available to the insurer if it were to
authorise the repair. I do not accept the deduction of such discounts is applicable or
fair in this instance.
This would result in the insurer providing a cash settlement that is not based on an
actionable quote. The complainant could not use the settlement to complete the claim
related repairs.
The insurer is required to make an allowance of 10% on the quote
I also consider it fair and reasonable that the insurer makes an allowance of 10% on
the final quoted amount. This is to address the risk that will be passed from the
insurer to the complainant, in organising the repairs herself, and the forfeiture of the
guarantee on the quality of repairs.
Determination | Case number: 753603 Page 7 of 9
This is also to address the potential for additional damage being discovered once
repairs commence. I consider this reasonable given the rectification issue with the
skylights and the ongoing water ingress that has occurred.
The insurer is not entitled to cash settle the cost of the adequate skylight repair
For clarity, given the insurer elected to repair the skylights, it must address the
rectification issues. It would not be fair in the circumstances for the insurer to pass its
liability for the rectification works to the complainant.
The insurer is not entitled to cash settle the rectification costs of the skylight, unless
the parties both agree to this.
2.4 Is the insurer liable for alternative accommodation costs?
The insurer is liable for alternative accommodation costs
The complainant is also seeking alternative accommodation costs while the internal
repairs are completed. The complainant says she was advised they would be required
to move out and the works would take one to two weeks.
The policy allows for alternative accommodation if the building is damaged by an
insured event and it cannot be lived in. I accept this includes when it cannot be lived
in due to the repair of the claim related damage.
Given the insurer is liable for the repair of the kitchen ceiling, I accept it is likely the
complainant and her family will require alternative accommodation during this time.
Considering this, the insurer is to confirm the estimated timeframe with the repairer
who provides the scope of works and quote for the cash settlement. The insurer is to
pay the complainant accommodation costs for this timeframe, as outlined in the terms
of the policy.
If the repairs take longer than the initial estimation, and this is from no fault of the
complainant or her nominated repairer, the insurer is to consider any further
reasonable additional costs. If this occurs, and the parties cannot agree on a
resolution, the complainant is entitled to return to AFCA for a decision on this point.
Determination | Case number: 753603 Page 8 of 9
3 Supporting information
3.1 Process
AFCA’s approach to this complaint
This complaint has been determined based on what is fair in all the circumstances,
having regard to the legal principles, applicable industry codes or guidance, good
industry practice and previous decisions of AFCA or its predecessor schemes (which
are not binding).
A full exchange of the relevant information has taken place between the respective
parties. Each party has had the opportunity of addressing any issues raised. All of the
provided information has been reviewed and considered. The parties have raised
numerous issues in their submissions to AFCA. However, commentary in this
determination is restricted to those issues considered relevant to the outcome.
How we assess complaints
AFCA is not a court of law. We do not have the power to take or test evidence on
oath, or to require third parties to give evidence. When we assess complaints, we
consider available documents, the recollections of the parties, and all relevant
circumstances. We give more weight to documents created at the time the events
occurred. If there is no relevant documentation, we will decide what is most likely to
have occurred based on the information provided to us. If there are conflicting
recollections and these are evenly weighted, we may find that a claim cannot be
established.
3.2 Relevant terms of the policy
Buildings cover – additional benefits
Alternative accommodation for you and your pets
If your home building is damaged by an insured event during the period of
insurance to such an extent that you can’t live in it, we’ll pay the rental costs for
accommodation for you and your pets for the period it reasonably takes, to repair
or rebuild your home building.
This is an extra amount, paid in addition to your buildings sum insured. No excess
applies to this benefit.
[…]
Building code compliance costs
If you need to rebuild your home buildings after loss or dam age, we’ll help pay the
costs of complying with any statutory requirements.
This is an extra amount, paid in addition to your buildings sum insured. No excess
applies to this benefit.
Determination | Case number: 753603 Page 9 of 9
How we settle your claims
Buildings claims
If we agree to cover your claim for loss of or damage to your buildings, we will pay
the reasonable cost of repairing or rebuilding the damaged part of your buildings
to the same condition as when it was new.
At our discretion, we may:
• enter into a contract with a builder to repair or rebuild your home, or
• pay you the cost of r epairing or rebuilding your home in cash or cash equivalent.
This is the cost of repairing or rebuilding, less any discounts that would be
available to us if we were to repair or rebuild.
When it is not possible to use original materials during the repair or rebuilding
process, the nearest available equivalent to the original materials will be used.