Home / AIG Australia Limited / Determination 753318

Determination 753318

claim handling delay and settlement of glass damage claim

FirmAIG Australia Limited
Decided2021-11-30
ProductGeneral Insurance · Business / commercial
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The complainant sought non-financial loss compensation for stress and delay in handling a glass damage claim under its business pack policy. AFCA found the insurer handled the claim reasonably and that delays were due to factors outside its control, so no compensation was ordered.

Non-financial loss compensation requires an unusual degree of stress or inconvenience caused by the insurer's unreasonable claim handling, which was not established given Covid-19 restrictions, broker information delays and the complainant's own steps.

Issues

Subjects and remedies

business interruptionno remedy

Related

All AIG Australia Limited determinations · Find similar determinations

Text of the determination

Determination Case number 753318 Financial firm AIG Australia Limited Determination | Case number: 753318 Page 1 of 4 Case number: 753318 30 November 2021 1 Determination overview 1.1 Complaint The complainant holds business pack insurance with the financial firm (insurer). In December 2019, the complainant discovered broken glass at its commercial property during an end-of- lease inspection. The insurer accepted the claim for glass damage caused by the insured event of malicious damage under the policy. This complaint originally concerned the extent of the liability for the claim, and whether the insurer would do the repairs or cash settle the claim. During the course of this complaint, the insurer and the complainant agreed to a scope of works to repair the damage. The insurer has agreed for repairs to be done by a glass repair contractor (G), and the repair work is now being done. The complainant says it has suffered significant stress due to delays with the insurer’s handling of the claim. The complainant says the insurer insisted on cash settling the claim for a quote that was unacceptable to the complainant. The complainant says the insurer did not authorise G to do the repairs until 2021. The complainant wants the insurer to pay non-financial loss compensation for stress and inconvenience caused by the unreasonable handling of the claim. 1.2 Issues and key findings Is the complainant entitled to non-financial loss compensation? No. I am satisfied that the insurer has handled the claim in a reasonable manner. Why is the outcome fair? While there have been delays in the final settlement of the claim, I am satisfied that such delays have been due to factors outside the insurer’s control . These factors included steps taken by the complainant in relation to its consideration of the offer to settle the claim. Accordingly, it is fair that the insurer is not required to pay the complainant non-financial loss compensation. 1.3 Determination This determination is in favour of the insurer. The insurer is not required to take any further steps in relation to this complaint. Determination | Case number: 753318 Page 2 of 4 2 Reasons for determination 2.1 Is the complainant entitled to non-financial loss? AFCA may award non-financial loss compensation Under the AFCA Rules, we may award up to $5,000 compensation for non-financial loss. We will only award this compensation if you have suffered an unusual degree of stress, inconvenience or delay because the insurer was unreasonable in handling your claim. The circumstances of the complaint In December 2019, the complainant discovered broken glass at its commercial property during an end-of-lease inspection. On 26 February 2020, the insurer received a quote from G for glass repairs at the complainant’s property. The insurer notes that this quote did n ot include any relevant details for the claim. On 27 February 2020, the insurer registered the claim, acknowledged this to the complainant’s broker and requested further information from the broker. On 10 June 2020, the insurer received some information from the broker about the claim. On 17 June 2020, the insurer appointed a loss adjuster. The loss adjuster reported on 19 June 2020. On 21 July 2020, the loss adjuster provided an update and a further quote was provided by G for $34,363 for the repairs. On 2 0 August 2020, the insurer made a settlement offer based on G’s itemised quote less the applicable excesses. The complainant declined this settlement offer. On 3 September 2020, the insurer advised they could only get a quote from G, as a second glass repairer declined to assist. A final site visit was suggested. From 22 to 24 September 2020, the insurer sought further clarification from G and G provided a response. On 14 October 2020, the insurer provided G’s response to the complainant. In early 2021, the complainant provided its own quotes for the repairs. On 17 February 2021, the insurer offered to increase its settlement offer by 15% to $31,906 (from its original offer of $27,744). On 29 March 2021, G provided a new quote with itemised amounts based on each window. On 21 April 2021, the insurer confirmed its offer to cash settle the claim for $31,906 or to have G conduct the repairs. On 3 June 2021, the insurer confirmed that G would carry out the repairs. G (with a sub-contractor) is currently undertaking and completing the repairs. Determination | Case number: 753318 Page 3 of 4 The complainant says the insurer caused unnecessary delays with the claim The complainant says the insurer insisted on cash settling the claim based on G’s quotes . However, the complainant wanted G to do the repairs so there would be no trouble in the future. The complainant says it took a long time for the insurer to eventually let G do the repair work, and this caused it to suffer great stress. Insurer says delays caused by factors outside its control The insurer says it does not agree that there have been delays with the handling of the claim as they only received partial information from the broker on 10 June 2020. The insurer says it provided the complainant with a settlement offer on 20 August 2020. The insurer also says that Covid- 19 restrictions affected the ability for experts to attend the complainant’s property, and that it had difficulty with receiving information from G. The complainant is not entitled to non-financial loss compensation On considering available information, I acknowledge that a considerable period of time has passed since the date that G provided its quote to the insurer in February 2020 until the date that the insurer made its settlement offer to the complainant in August 2020. However, I accept that this was due to factors outside the insurer’s control, namely, Covid-19 restrictions, and the delay in receiving claims information from the complainant’s broker. I also note that the relevant policy terms provide the insurer with the right to pay for the cost of the repairs. Delays after the insurer’s initial settlement offer until the claim settlement was agreed have been largely due to steps taken by the complainant to seek further quotes and to consider its position about the settlement of the claim. I am satisfied that the insurer has handled the claim in a reasonable manner and that it has not caused unnecessary delays. Accordingly, I find that the complainant is not entitled to non-financial loss compensation. 2.2 Why is the outcome fair? While there have been delays in the final settlement of the claim, I am satisfied that such delays have been due to factors outside the insurer’s control . These factors include steps taken by the complainant in relation to its consideration of the offer to settle the claim. Accordingly, it is fair that the insurer is not required to pay the complainant non-financial loss compensation. Determination | Case number: 753318 Page 4 of 4 3 Supporting information 3.1 Matter relevant to the claim Complainant may raise concerns about quality of repairs The complainant has recently expressed dissatisfaction to G and the insurer about the quality of the glass repairs being done. In this regard, I note the information shows that G has advised that they warrant their works. Accordingly, if the complainant is dissatisfied with the final repairs done by G, the complainant can raise its concerns with G and the insurer. If these issues remain unresolved, the complainant can lodge a new complaint on this matter. 3.2 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.