Determination 752742

Storm damage claim for roof replacement and Bali hut rethatching; cash settlements; claim handling delay

FirmDefence Service Homes Insurance Scheme
Decided2021-11-03
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$56,925
Non-financial loss$3,000
Amount claimed$57,000
SourceAFCA PDF

Summary

The complainants sought roof replacement costs and Bali hut rethatching after 2013-2015 storm damage, and disputed cash settlements and claim delays. AFCA found the roof replacement was covered and ordered a refund on invoices plus interest, declined the Bali hut claim as deterioration, found the cash settlements correct, and awarded $3,000 for non-financial loss.

The policy insures loss caused by storm, and the evidence shows the roof was substantially damaged by the 2015 storms, while the Bali hut thatch was not shown to be storm damaged rather than deteriorated over time.

Issues

Subjects and remedies

pay claimpay interestpay non financial loss

Related

All Defence Service Homes Insurance Scheme determinations · Find similar determinations

Text of the determination

Determination Case number 752742 Financial firm Defence Service Homes Insurance Scheme Case number: 752742 26 October 2021 1 Determination overview 1.1 Complaint The complainants held a home building insurance policy with the financial firm (the insurer) when their house was damaged during storm events between 2013 and 2015. They lodged three separate claims for storm damage to the insured property. The complainants say the insurer is liable for the costs to replace their roof and to rethatch a Bali hut. The insurer denies this and says it has settled its full liability to the complainants in relation to the claims by previously paying them cash settlements for storm damage. The complainants disagree and seek approximately $57,000 from the insurer, said to be what they have paid to have the roof replaced. They have concerns about the cash settlement payments made to them in 2015. They also seek non-financial loss compensation for stress and inconvenience due to claim handling delays. 1.2 Issues and key findings Must the insurer pay for replacement of the damaged roof? Yes. The complainants have shown the policy covers the cost of replacing the damaged roof. Must the insurer pay for rethatching of the Bali hut? No. The complainants have not established the thatch was storm damaged. The panel finds that it has deteriorated over time, meaning the rethatching is not covered by the policy. Has the insurer correctly paid the cash settlements? Yes. Despite errors in the correspondence sent to the complainants and AFCA which have caused confusion, the insurer has paid the correct amounts. Are the complainants entitled to compensation? Yes. The extended delays in processing the claim caused the complainants undue inconvenience and the insurer has acted inconsistently with the General Insurance Code of Practice (the Code). The insurer is to pay the complainants $3,000 for non-financial loss. Why is the outcome fair? The outcome is fair because, on the balance of probabilities, the policy responds to the reroofing claim but not the Bali hut rethatching claim. It is fair that the insurer only covers claims where there is a policy requirement to do so. It is also fair that the insurer pay compensation given the manner in which it managed the claim. 1.3 Determination This determination is substantially in favour of the complainants. Determination | Case number: 752742 Page 2 of 11 Upon provision of invoices and receipts, the insurer is to refund to the complainants the reroofing costs they paid, less any applicable policy excess. It is also to pay interest on the net claim payment amount under section 57 of the Insurance Contacts Act from 9 August 2016 (the date the roof claim was denied) until the date it makes payment. The insurer must also pay the complainants $3,000 compensation for non-financial loss. Determination | Case number: 752742 Page 3 of 11 2 Reasons for determination 2.1 Must the insurer pay for replacement of the damaged roof? Yes. The complainants have shown the policy covers the cost of replacing the damaged roof. Policy covers insured events including damage caused by a storm The policy is an insured events policy which covers damage caused by storm, snow or hail. Relevant extracts of the policy wording are set out in section 3.2 of this determination. There is no dispute that the property sustained damage during several storm events during 2013 and 2015. The insurer has accepted the resulting claims and settled the complainants for its accepted liability. The panel notes previous coverage disputes between the parties have now been resolved, save for the e xtent of the insurer‟s liability for the roof repair and the Bali hut rethatching. The position in relation the Bali hut is set out in section 2.2 of this determination. The complainants say they have had to replace the roof at their own expense and that the insurer should pay them for the full cost of this, as the damage was the result of storm. The insurer argues its liability in relation to the roof only extended to replacing about 50 roof tiles, as the remainder of the roof was not damaged by the storm. Complainants have shown the policy responds to damage to the entire roof The complainants are required to show, on the balance of probabilities, they suffered a loss caused by a risk insured against under the policy. This is known as a valid claim. The panel is satisfied the complainants have demonstrated there is a valid claim for replacing the roof entirely. They have supplied sufficient evidence to establish that the paint coating to the roof tiles has been stripped during one or both of the storms that occurred in April then September 2015. As there is damage which has been caused by a „ storm, snow or hail‟ insured event, the policy responds to cover the associated repair cost. The panel has particularly noted that in a report dated 27 September 2016, t he complainants‟ roof tiling expert (CN) said the roof was stripped of its paint coating. CN also said it considers the roof was originally installed to meet the then applicable roofing code. CN concluded the damage to the roof „is a direct result of stor m damage‟ . The panel consider ed CN‟s report together with images of the roof as at 25 November 2013. At that point in time, the roof had some signs of aging but appeared in relatively sound condition. This is supported by the insurer‟s building exp ert (CS) who in a report dated 23 June 2014 said as much. Further, the images of the roof taken by CS on 25 November 2013 were captioned „General overview of the roof showing it in good condition‟. The images of the roof taken in 2015 show a change in colour and a speckled pattern overlaying the roof tiles which was not present in 2013. The appearance is widespread. Combined with comments by CN, this strongly suggests the roof had been substantially damaged by the 2015 storms. This is further supported by the following comments made in a report from another of the insurer‟s builders (PB ) who is quoted by the insurer in its letter dated 9 November 2015 to the complainants: Determination | Case number: 752742 Page 4 of 11 An inspection of the tiled roof covering was undertaken around the perimeter of the home. It was observed that the surface of the roof covering has scuff marks evident to the surface of the tiles, which is likely to have occurred as a result of the recent hail storm event. The scuff marks have not damaged the tile/cappings and would be considered as normal “ wear and tear ” however has given the roof a more mottled' appearance (refer to photographs 15 and 16) [sic]. The panel finds that it is inherently unlikely that a roof that was determined to be in good condition in 2013 would be materially altered by normal wear and tear within a two year period. Further, the view expressed by PB that the scuff marks were normal wear and tear misunderstands that the scuff marks happened because the tiles were hit by hail falling from the sky in major and widely reported storm events, which the policy covers. In the circumstances, the panel is satisfied the insurer‟s experts provide support for the view expressed by CS that the roof was damaged due to the 2015 storm events. I nsurer’s arguments do not assist its position The panel has considered the insurer‟s argument that there were leaks from pre -existing issues with the roof‟s barge and hip capping. However, these still need to be replaced as the images clearly show these have also had their painting coat stripped. This means they have been damaged by the storm event, meaning they too must be replaced. The panel also has concerns about the content of an email dated 26 June 2015 from a staff member of the insurer to the insure r‟s loss adjustor, which included the following: With regard to the roof, does CBS have any more photos? Do you? How about a mud map of the roof and which areas are said to be hail damaged and what areas are said to be defective construction.? What sort of tile is installed? As some pictures make it look very smooth and finished and others make them look like they have no sheen and are porous. We have a problem in that a claim made for hail damage to these tiles was made about 16 months before this one and had it been noticed by the claims officer they should have told you about this as in this claim was not accepted and we closed it after waiting 6 months for the client to send in their own roof reports which they never did. (sound familiar?) Anyway our contractor reported roof in very good order and rain must have been windblown. So it is clear to me that the client is looking for a way to have us maintain their roof for them, but I have a report from 2013 that shows and says roof is in good order and now this report which says – defect in construction and rotted roof sarking. So I am a bit stuck right now, not wanting to decline on CBS report only to risk earlier claim report being discovered and used against us. Determination | Case number: 752742 Page 5 of 11 This suggests that the insurer was aware of a material change in the condition of the roof between 2013 and 2015 and that hail damage was a relevant factor. Further commentary on this is set out in section 2.3 of this determination. Insurer to pay complainants for roof replacement costs The panel notes the complainants confirmed in earlier conversations with AFCA the roof is now repaired. The complainants used their own funds and a redraw on superannuation to pay for the cost of repair. The invoice for these repairs has not been supplied for consideration. However, the insurer has apparently seen this quote and confirmed the total came to $56,925 for replacement of the whole roof area with Colorbond roof sheeting. The insurer has not raised any objection to the quote beyond not agreeing there was a valid claim for the damage. The quote was similar to the insurer‟s previous repair cost estimate of $50,000. As the works have now been completed, upon provision of invoices and receipts, the insurer is to refund to the complainants the reroofing costs they paid, less any applicable policy excess. The insurer is not entitled to deduct any prior settlement payments as the previous payments made were for internal water damage only. Finally, the insurer must also pay the complainants interest on the net claim payment amount under section 57 of the Insurance Contacts Act from 9 August 2016 (the date the roof claim was denied) until the date it makes payment. 2.2 Must the insurer pay for rethatching the Bali hut? No. The complainants have not established the thatch was storm damaged. The panel finds that it has deteriorated over time, meaning the rethatching is not covered by the policy. Insurer has not paid for rethatching In it‟s letter to AFCA dated 2 June 2021, the insurer stated: As highlighted in our initial response dated 20 October 2020, DSH Insurance has accepted all internal damage to the property as well as damage to the hut and the fence. The insurer‟s notice of response dated 20 October 2020 referred to a quotation it received totalling $15,367.00. This included only the additional damages that did not form part of the previous claims. The quotation included „ Bali Hut - PC allowance for the re-thatching of the Bali Hut Roof to best match $1,200.00 ‟. The insurer appears to have assumed the Bali Hut rethatching component was then included in the cash settlement amount it paid in November 2015. However, the contemporaneous documents suggest that $1,200 had been deducted from the cash settlement calculation on the basis the Bali hut roof damage was not covered. Further, the complainants state they have not received a payment for the Bali hut roof damage. Determination | Case number: 752742 Page 6 of 11 Accordingly, the panel has proceeded on the basis that the claim for the Bali hut rethatching cost remains a live issue. Complainants have not shown the policy responds to damage to Bali hut The complainants say they have had to rethatch the Bali hut at their own expense and that the insurer should pay them for the full cost of doing so, as the damage was the result of storm. The insurer says it has no liability in relation to the Bali hut rethatching as it was not damaged by the storm and that its condition should be attributed to gradual deterioration, which is a policy exclusion. The complainants submit that in not covering them for the rethatching the insurer has „ignored the damage from three violent „super - cell‟ events that contributed to the shredding of the thatched roof by „golf - ball‟ size hail and impact from surrounding palm trees.‟ However, they have not served any supporting reports. The insurer has provided reports dated 21 September and 1 October 2015 from builder PB who said that the „ damage to Bali Hut appears to be consistent with wear and tear based on the moss growth not being affected by the hail event‟. That view was supported by photographs taken by PB at the time. The panel acknowledges that the thatch would have been saturated in the storm events. However, there is insufficient evidence to establish that it was storm damaged; only that it has become deteriorated over time. Therefore, the complainants have not established a valid claim relating to the damage to the Bali Hut. The insurer is entitled to decline to indemnify the complainants in relation to that claim. 2.3 Has the insurer correctly paid the cash settlements? Yes. Despite errors in the correspondence sent to the complainants and AFCA which have caused confusion, the insurer has paid the correct amounts. Payments relating to April 2015 storm The insurer obtained a quote from PZ to repair the internal damage to the property relating to the April 2015 storm. The quote was in the amount of $8,470. The insurer cash settled the complainants for that amount on or about 10 September 2015. It also noted it would pay the complainants 50% of replacing the boundary fence that had been damaged, meaning a further sum of $838.75 would be paid to them Payment relating to September 2015 storm The insurer obtained a quote from UB to repair the internal damage to the property relating to the September 2015 storm (only) . UB‟s quote was for a total of $15,367, which included an allowance of $1,200 to rethatch the Bali hut. After deducting the $1,200 on the basis the Bali hut aspect of the claim was not covered, the insurer calculated a figure of $14,167. However, the insurer noted that it was yet to pay the $838.75 owing to the complainants for the boundary fence. It therefore noted that an amount of $15,005.75 was still owing to the complainants. The $14,167 was paid on or about 10 November 2015 and the $838.75 was paid on or about 11 November 2015. Determination | Case number: 752742 Page 7 of 11 Communication errors have caused confusion The complainants have expressed concern that the insurer wrongfully deducted $8,470 from the cash settlement amount paid in relation to the September 2015. The panel acknowledges that the way the insurer communicated with the complainants was confusing and contained errors that justified the complainants holding this concern. The situation was not helped by errors as to dates and amounts in a number of submissions the insurer made to AFCA. However, having carefully reviewed the information before it, the panel is satisfied the insurer has not made any wrongful deductions from the amounts paid to the complainants for the internal damage caused by the April 2015 storm ($8,470), the fence damage caused by the April 2015 storm ($838.75) and the internal damage caused by the September 2015 storm ($14,167). 2.4 Are the complainants entitled to compensation? Yes. The extended delays in processing the claim caused the complainants undue inconvenience and the insurer has acted inconsistently with the Code. The insurer is to pay the complainants $3,000 for non-financial loss. Compensation is awarded conservatively Under the AFCA Rules, we may award compensation (capped at $5,400) for non-financial loss where a complainant has suffered an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with their expectation of enjoyment or peace of mind. We take a conservative approach to compensation for non-financial loss. It is not awarded when a person suffers the normal degree of inconvenience when a problem occurs. Claim handling Having reviewed the voluminous file available to it, the panel considers that the time taken by the insurer to investigate and determine the claims made by the complainants took longer than they should have done. Even allowing for periods where the complainants were slow to respond to the insurer, the panel is satisfied that the insurer should have been more proactive in driving the claim forward. For example, the insurer could and should have taken more initiative in obtaining focused expert commentary on the reason for the significant difference in the condition of the roof tiles from 2013 to 2015. The panel also has concerns the insurer‟s claims handling process could be characterised as being not at all times customer focused but instead was potentially directed to obtaining a particular claims outcome. The email dated 26 June 2015 from a staff member of the insurer to the insurer‟s loss adjustor quoted in section 2.1 of this determination is especially noteworthy in that context. The complainants experienced a protracted claims process, resulting in avoidable physical inconvenience and time taken to resolve the situation, beyond the norm. The panel is satisfied that the insurer has acted in a manner not consistent with the Code, relevant extracts of which are set out in section 3.3 of this determination. Determination | Case number: 752742 Page 8 of 11 For these reasons, the complainants are entitled to an award of compensation. The insurer must pay the complainants $3,000 compensation in total. 2.5 Why is the outcome fair? The outcome is fair because, on the balance of probabilities, the policy responds to the reroofing claim but not the Bali hut rethatching claim. It is fair that the insurer only covers claims where there is a policy requirement to do so. It is also fair that the insurer pay compensation given the manner in which it managed the claim. Determination | Case number: 752742 Page 9 of 11 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. A panel determined this matter Due to the nature of this complaint, we referred it to a panel for determination. The panel includes:  an ombudsman  a member with significant experience in consumer and small business advocacy  a member with extensive experience in the insurance industry. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. Determination | Case number: 752742 Page 10 of 11 3.2 Extracts from policy wording Pages 14 and 15 PART 1 LOSS OR DAMAGE TO YOUR HOME The events we insure you for We only insure you if the loss or damage to the home: • is caused by one or more of the 13 events we list below, • happens in the period of insurance, and • is not excluded either by the specific exclusions we list in this section under „What we do not insure you for‟, any of the Genera l Exclusions we list on page 32, or any exclusions listed on your certificate. … 6 Storm, snow or hail What we insure you for We insure you for loss or damage to the home caused by storm (including cyclone), snow or hail. By „storm‟ we mean a violent w ind that may occur wit h thunder or heavy rain. What we do not insure you for We do not insure you for loss or damage caus ed by wind, rain, snow or hail entering the home unless it enters because of structural damage to the home that is directly caused by the storm, snow or hail. Page 31 PART 7 GENERAL EXCLUSIONS We do not insure you for loss or damage that is not directly caused by an event that we insure you for, unless we say that we do in this policy. We do not insure you for loss or damage or legal liability that is intentionally caused by you or your family or a person acting with the consent of you or your family. We do not insure you for loss or damage or legal liability caused by: Determination | Case number: 752742 Page 11 of 11 • failing to keep the home or site in good repair and condition … • defects in structure, design, work done, or materials used on the home or at the site • wear and tear • rust, corrosion, rot, mildew, seepage, rising damp, any gr adual det erioration or process 3.3 Extracts from the Code 67. When we are assessing your claim, we will only ask for and rely on information that is relevant to our decision. If we ask you for information, then we will tell you why we need it. 76. Once we have all relevant information and have completed all enquiries, we will decide whet her to accept or deny your claim and tell you of our decision within 10 Business Days. 77. Our decision will be made within 4 months of receiving your claim, unless paragraph 78 applies. If we do not mak e a decision within that time, we will tell you in writing about our Complaints process. 78. In circumstances where: a. your claim arises from an Extraordinary Catastrophe; b. your claim is fraudulent, or we reasonably suspect it is fraudulent; c. you do not respond to our reasonable inquiries or to our requests for documents or information about your claim; d. we have difficulty communicating with you about y our claim due to circumstances beyond our control; or e. you request a delay in the claims process; then within 12 months of receiving your claim we will tell you our decision in writing. If we cannot make a decision wit hin 12 months, we will tell you in writing about our Complaints process.