1 Determination overview
1.1 Complaint
In July 2018, the complainants (Mr C and Ms P) arranged to sell their home (Property R) for
$595,000 and purchase a new home (Property B) for $745,000. The complainants engaged
the financial firm (mortgage manager) to assist them with their loan applications to the lender.
A timeline of key events is set out at section 3.2 of this determination. Relevantly:
the complainants initially applied to the lender for a bridging loan of approximately
$1,108,000, so they could purchase Property B while they waited for their existing property
(Property R) to sell
before the bridging loan was approved, the complainants obtained a short-term loan of
$521,000 through a private lender (private loan), which they used to complete the
purchase of Property B
the complainants then applied to the lender for a loan to refinance the private loan.
In summary, the complainants say the mortgage manager:
contributed to the unreasonable delay in the lender approving their loan application, after
the lender‟s mortgage insurance ( LMI) was approved on 18 October 2018
unreasonably delayed the settlement of their property purchase
unreasonably delayed the refinance of the private loan, by requesting a loan for the
incorrect amount.
1.2 Issues and key findings
Did the mortgage manager cause any unreasonable delay from 18 October
2018?
The mortgage manager did not cause any unreasonable delay, as it acted in a timely manner
and reasonably assisted the complainants with their loan applications.
Why is the outcome fair?
The outcome is fair in all the circumstances because:
the delays before 18 October 2018 were caused by the complainants requesting changes
to the loan structure
the mortgage manager did not unreasonably delay the initial application for bridging
finance or the application for refinance of the private loan
the mortgage manager did not delay the settlement of the purchase of Property B
the mortgage manager is not responsible for the time taken by the lender to approve the
loan.
1.3 Determination
This determination is in favour of the mortgage manager.
The mortgage manager is not required to compensate the complainants or take any action in
relation to this determination.
Determination | Case number: 747908 Page 2 of 9
2 Reasons for determination
2.1 Did the mortgage manager cause any unreasonable delay
from 18 October 2018?
The complainants requested changes to the loan structure before 18 October
2018
The complainants signed the contract of sale for Property B on 23 July 2018. The settlement
date was originally 19 September 2018 and the contract stated that the purchase would be
funded by a loan from a different lender. The contract for sale is binding on the parties to the
contract being the vendor and the purchaser (the complainants), not the mortgage manager.
On or about 7 August 2018, the complainants submitted the first loan application to the
mortgage manager. The complainants do not dispute the events which took place from 7
August 2018 to 18 October 2018. During that time, the information shows that:
the complainants changed the loan structure on 13 August 2018, 10 September 2018, 27
September 2018 and 8 October 2018
the settlement date was extended to 17 October 2018
the vendor rejected the complainants‟ request to further extend the settlement date to 26
October 2018.
Each time the complainants changed the loan structure or amount they wanted to borrow, this
required a new lending application.
Although the complainants say they do not dispute the events which took place from 7 August
2018 to 18 October 2018, I note that given Mr C was an accredited mortgage broker, the
complainants could reasonably be expected to have been aware that:
the mortgage manager would need a reasonable time to assess their applications
their changes to the loan structure were likely to delay the assessment of their application.
The mortgage manager did not unreasonably delay the application for bridging
finance
The complainants say the mortgage manager unreasonably delayed settlement of the loan
after the Lender ‟ s Mortgage Insurance (LMI) was approved on 18 October 2018. In support
of their position, the complainants rely on an email from the mortgage manager dated 25
October 2018, which states:
Apologies for delays on this application. As of this moment, we have LMI approval and
our in- house credit has issued conditional approval subject to the funder‟s [lender‟s]
approval. This application has passed through funder‟s quality control and is wit h their
assessor. In total, the file has been with the funder since Friday the 19th and has gone
beyond their normal processing timeframe of 48 hours for assessment.
However, the mortgage manager is not responsible for any delay the lender may have
caused in assessing the loan application. I cannot consider the lender‟s conduct as part of
this complaint ; only the mortgage manager‟s conduct.
A chronology of key events is set out in section 3.2 of the determination. The available
information shows the mortgage manager acted in a timely manner and reasonably assisted
the complainants with their loan application. Specifically, the information shows that:
Determination | Case number: 747908 Page 3 of 9
the mortgage manager submitted the application to the lender on 19 October 2018, being
the day after the LMI was approved
between 22 and 30 October 2018, the mortgage manager:
> communicated with the parties
> responded to enquiries and requests for information and assistance
> followed up on progress of the application
> escalated the application with the lender.
Based on the available information, I am satisfied that the mortgage manager did not cause
any delay between 18 and 30 October 2018.
The complainants chose to finance the purchase through a private lender
On 26 October 2018, the complainants took out a loan for $521,000 through a private lender
(private loan), which had a term of 30 days. They say they were forced to do so as a result of
the lender‟s delays after 18 October 2018 , so they would not lose their deposit.
On 29 October 2018, the lender sent formal approval to the mortgage manager for a loan of
$1,108,823.90. However, neither the lender nor the mortgage manager was aware that the
complainants no longer needed this loan, as they had settled the purchase of Property B
using the private loan on the same date. On 30 October 2018, the mortgage manager was
informed about the private loan and requested further information from the complainants
about it.
On 2 November 2018, the mortgage manager informed the lender that the complainants had
chosen to obtain the private loan and they now requested a refinance of the private loan,
instead of a bridging loan.
There is no information to show the complainants informed the mortgage manager that they
were considering, or had decided to obtain, the private loan before 30 October 2018. The
mortgage manager is not responsible for the complainants‟ decision to obtain a private loan.
I am satisfied that the mortgage manager did not cause any delay to the settlement of the
purchase of Property B.
The mortgage manager did not make an error by submitting the first refinance
application
The complainants say:
they never requested a loan of $550,000
they always needed a loan of $596,000 so they could repay $550,000 to the private lender
and repay additional funds they had borrowed from family and friends to ensure settlement
took place.
The male complainant, Mr C, is an accredited broker and submitted his own application to the
mortgage manager. On 30 October 2018, the mortgage manager was told about the private
loan and emailed the complainants to request further information:
[Another broker with the mortgage manager] has advised us that you have recently
settled with a private lender for the settlement of the new property and you are seeking to
refinance that loan with us.
To enable us to see how we can consider the refinance of [Property B] we will require the
following information;
Determination | Case number: 747908 Page 4 of 9
The proposed settlement date for [Property R] being sold
The loan terms for the private funds to purchase [Property B]
Evidence of settlement of [Property B].
On 31 October 2018, the complainants responded:
confirming that the settlement date for [Property R] was 10 December 2018
providing a copy of the contract for the private loan, stating “note thousands in extra fees
due to having to arrange last minute funding to prevent legal action”
providing the settlement statement for Property B, stating “note the thousands in extra fees
due to [the lender‟s] delays”.
On 2 November 2018, the mortgage manager emailed the lender to advise that the
complainants had chosen to obtain the private loan and they now requested a refinance of
the private loan instead of a bridging loan. In relation to the loan amount, the email stated:
The loan terms for the private funds to purchase [Property B]- loan agreement Held
and can be provided
Commercial Term (short term - one month)
Loan amount of $521,000 plus additional interest at a maximum of 30 days @7.5%
Minimum interest amount $13,025
Payout approx. $534,025 …
The approved end debt was $594,506 we are seeking a loan amount of $550,000 to
refinance the private loan and to cover costs.
It appears the reference to the approved end debt refers to the initial application to the lender
for bridging finance. On 29 October 2018, the lender approved a loan of $1,108,823.90, with:
PEAK DEBT: $1,130,256 - LVR 84.98%
END DEBT: $594,506 - LVR 79.80%
In line with this approval, the complainants would have been left with an outstanding loan of
about $594,000 once both property transactions had been completed. However, this
approval was no longer relevant as the complainants now wanted to refinance the private
loan, and the lender was no longer taking security over Property R.
On 7 November 2018:
the mortgage manager informed the complainants that the lender had provided conditional
approval for a loan of $550,000
the complainants replied stating:
This loan amount is not possible as per our conversation this afternoon.
We still need the full amount as originally applied and approved by Lmi and [the
lender] required for the refinance which should‟ve been the purchase loan. I had to
borrow extra money from friends and family to make this happen to prevent being
sued due to [the lender‟s] excessively lengthy process.
the mortgage manager emailed the lender, stating:
Thank you for the conditional, the borrower has asked us if the loan amount can be
increased to 80% LVR $596,000 this was the amount of the end debt. I misunderstood
the applicants‟ instructions when requesting to payout the private loan as they have
Determination | Case number: 747908 Page 5 of 9
used other funds which they thought they would have back once the other property
sells.
On 8 November 2018:
the mortgage manager emailed the complainants:
As discussed yesterday, the reason why this is not straight forward is that the
transaction has changed from a purchase to a refinance, this is also the reason why
LMI may not consider re-approving (to go above 80% LVR) as the transaction has
changed - also the maximum end debt that the funder had formally was $594,506.
the complainants responded:
If there is going to be a problem with LMI then we will just have to stick with an 80%
lend.
the mortgage manager submitted a revised application to refinance the private loan for
$596,000, reflecting the maximum LVR of 80%.
The mortgage manager has been unable to provide any information to show the complainants
specifically requested a loan of $550,000. However, when the complainants replied on 31
October 2018 with the requested information, while they noted that they had had to pay
additional fees as part of the property transaction, they did not make it clear that they wanted
the add itional loan funds to repay this amount , on top of what was needed to pay out the
private loan. They did not inform the mortgage manager they had borrowed from family and
friends for settlement until 7 November 2018 .
I acknowledge that the complainants may have assumed that the mortgage manager would
apply for the amount of $594,506 that had previously been approved as the end position
under the bridging loan. However, I am not satisfied this assumption is reasonable where the
circumstances had changed because the complainants took out the private loan.
As the complainants required at least $534,025 to payout the private loan and they had not
clearly informed the mortgage manager they required additional funds, I do not consider the
mortgage manager made an error by requesting a loan amount of $550,000 on 2 November
2018, to ensure the complainants had enough funds to payout the private loan and provide an
allowance for any associated fees.
The mortgage manager did not unreasonably delay the refinance of the private
loan
On 16 November 2018, the lender issued conditional approval for $596,000. One of the
conditions was that the lender must receive “ details of account, details and solicitor details for
refinance of private loan ” .
The complainants say they provided the correct loan details and BSB for the private loan to
the mortgage manager on 30 October 2018. However, they have not provided any
information to support this.
The available information shows that:
the complainants emailed the mortgage manager the private loan account details on 19
November 2018
on the same date, the mortgage manager provided the account details to the lender
the loan offer was prepared on 23 November 2018
the loan offer was sent to the complainants on 27 November 2018 and delivered on 28
November 2018
Determination | Case number: 747908 Page 6 of 9
on 3 December 2018, the complainants emailed the mortgage manager stating the BSB
for the private loan account was incorrect on the loan offer
on 4 December 2018, the mortgage manager emailed the complainants stating, “ Loan
documents have been issued and have not been returned”.
The complainants signed the loan documents on 4 December 2018, with the BSB for the
private loan account amended by hand. The lender then finalised approval on 7 December
2018 and settlement of the refinance occurred within a week, on 13 December 2018.
The information shows the mortgage manager did not unreasonably delay the refinance of
the private loan after 8 November 2018, as:
the mortgage manager followed up with the complainants to ask them to provide
outstanding information
the mortgage manager promptly communicated with, and passed information between, the
complainants and the lender
there is no information to show the mortgage manager made an error regarding the BSB
for the private loan, as it provided the correct details to the lender on 19 November 2018.
2.2 Why is the outcome fair?
The outcome is fair in all the circumstances because:
the mortgage manager did not cause any unreasonable delay to the application for
bridging finance
the mortgage manager did not delay the settlement of Property B
it was the complainants‟ choice to finance the purchase with a private lender
the complainants did not inform the mortgage manager about the private loan until after
the bridging finance had been approved
the mortgage manager did not unreasonably delay the refinance of the private loan.
For these reasons, an award of compensation is not warranted.
Determination | Case number: 747908 Page 7 of 9
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
AFCA assesses complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
3.2 Chronology of key events
Date Key e vent
23 Jul 2018 Cont ract of sale to purchase Property B for $745,000.
12 Sep 2018 The mortgage manager told the complainants the maximum loan amount (for the
end debt) would be $613,707 once Property R was sold.
The complainant confirmed this amount would be okay.
18 Oct 2018 LMI was approved.
19 Oct 2018 The mortgage manager sends application to the lender for a loan of $1,125,289 .
22 Oct 2018 The lender emails the mortgage manager advising the loan requires a large loan
Determination | Case number: 747908 Page 8 of 9
Date Key e vent
review.
22 Oct 2018 The mortgage manager emails the lender advising the complainant s are a bout to
lose their deposit.
23 Oct 2018 The complainants email the mortgage manager r equesting urgent attention and
advising t he y must settle on Friday 26 October 2018 .
23 Oct 2018 The mortgage manager int ernally escalates the loan application.
24 Oct 2018 The lender emails the mortgage manager advising the file will be referred to cred it
for assessment today.
26 Oct 2018 The mortgage manager emails the lender advising the complainants will lose
deposit.
The lender issues conditional approval for a loan of $1,108,823 subject to a number
of conditions including clarification and/or VEDA enquiries and receipt of an
acceptable exit strategy.
29 Oct 2018 The complainants settle the purchase of Property B with the privat e loan.
30 Oct 2018 The mortgage manager emails the complainants stating it has been told about the
private loan and requests further information from the complainants to refinance it ,
as their requested loan structure is now changing .
2 Nov 2018 The mortgage manager:
advis es the lender the complainants have settled with a private lender and no
longer require a bridging loan. The mortgage manager requests refinance of
the private loan.
submits the first application for a $550,000 loan to refinance the private loan
and requests the lender makes an exception .
7 Nov 2018 The lender issues conditional approval for the $550,000 loan subject to receiving:
copy of contract for sale of Property R
evidence of settlement of sale of Property B
copy of the private loan contract
private lender ‟s account and solicitor ‟s details to refinance the private loan.
8 Nov 2018 T he mortgage manager submits the second ( revised ) application for the $ 596,000
loan to refinance the privat e loan .
13 Nov 2018 The p rivate lender provides payout figure of $536,795 , if the loan settles by 23
November 2018.
14 Nov 2018 The mortgage manager follows up with the c om plainants concerning the outstanding
information set out in the conditional approval of 7 November 2018.
The complainants email the mortgage manager advising they provided all the
outstanding information , including the private lender‟s account details on 30 Oct ober
2018.
Determination | Case number: 747908 Page 9 of 9
Date Key e vent
16 Nov 2018 The lender issued conditional approval for $596,000, subject to receiving „ d etails of
account, details and solicitor details for refinance of private loan‟.
19 Nov 2018 The mortgage manager emails the complainants with conditional approval for the
$596,000 loan and requests the y provide the private lender ‟ s account details.
The complainants email the mortgage manager and provide the private lender‟s
bank account details.
The mortgage manager emails the lender and provides the private lender‟s bank
account details.
23 Nov 2018 The lender provides formal approval for the $596, 000 loan and issues the loan
contract .
3 Dec 2018 The complainants email the mortgage manager advising the loan contract contains
the incorrect account details for the private lender .
The mortgage manager emails the lender and provides the correct private lender‟s
account details.
4 Dec 2018 The lender emails the mortgage manager advising it consents to the complainants
amend ing the privat e lender‟s account details recorded on the loan contract and
requests they initial t he amendment .
The mortgage manager emails the complainants and requests they provide it with
the executed loan contract.
4 Dec 2018 The complainants execute the loan contract.
5 Dec 2018 The complainants return the execut e d loan contract to the le nder‟s solicitor.
7 Dec 2018 The mortgage manager emails the lender and asks if a new property valuatio n was
required .
The lender em ails the mortgage manager and advises the now expired property
valuation was acceptable at the time of the formal loan approval and advises the
parties proceed to settlement.
11 Dec 2018 The s ettlement is booked.
13 Dec 2018 S ettlement of the refinance occurs .