Further building and rental costs after flood repairs denied; delay in repairs
Summary
The complainants claimed the cost of further building repairs after flood damage, plus rent and non-financial loss, after demolishing the property. AFCA denied the building costs but ordered 15 weeks of loss of rent and $500 for delays in repairs.
The complainants prejudiced the insurer's ability to assess alleged inadequate repairs by demolishing the property on short notice, while the insurer's delay in authorising repairs warranted compensation.
Issues
- Claim denial primary · not upheld“The insurer is entitled to deny the further building costs claim as the complainants have not met their responsibilities under their policy.”
- Delay secondary · upheld“The insurer took an unusual amount of time to proceed with repairs... approximately six months to authorise repairs would have caused an unusual degree of inconvenience.”
Subjects and remedies
natural disasterpay compensationpay non financial loss
Related
Text of the determination
Determination
Case number 747852
Financial firm RACQ Insurance Limited
Determination | Case number: 747852 Page 2 of 6
Case number: 747852 5 March 2021
1 Determination overview
1.1 Complaint
On 26 January 2019, the complainants lodged a claim under their home insurance
policy held with the financial firm (insurer), following flood damage from a storm.
The insurer accepted the claim and organised repairs which commenced in July 2019
and were signed off as completed in August 2019. The insurer covered loss of rent for
a period of 15 weeks and the claim was finalised.
On 5 January 2020, the complainants emailed the insurer advising the property was
to be demolished on 7 January 2020, due to inadequate repairs by the insurer and
were seeking to be settled the building sum insured of $323,000.
The complainants since clarified they are seeking the costs they say were required to
repair the insured damage based on their builder’s quotation for $135,600, along with
additional loss of rent costs and non-financial loss due to the claim ’ s handling.
The insurer says the complainants prejudiced its ability to assess the alleged
inadequate repairs by demolishing the property without its consent and in an
unreasonable time frame. Further, it says the act of intentionally demolishing the
property is not covered under the policy and occurred after the policy had lapsed.
1.2 Issues and key findings
Is the insurer entitled to deny further claimed building and rental costs?
Yes, the complainants prejudiced the insurers ability to assess the complainants’
allegations of inadequate repairs by demolishing the property in an unreasonable time
frame.
The insurer paid the complainants 15 weeks loss of rent, the available information
shows this was fair in the circumstances.
Is the complainant entitled to compensation for non-financial loss?
$500 compensation is warranted due to delays in organising repairs.
1.3 Determination
This determination is substantially in favour of the financial firm.
The insurer is not required to make any further contributions towards the claim.
The insurer is to pay the complainants $500 for non-financial loss.
Determination | Case number: 747852 Page 3 of 6
2 Reasons for determination
This determination is based on information submitted by the parties. Each party has
had an opportunity to review and respond to the other party’s submissions.
This determination is based on what is fair in the circumstances, having regard to any
relevant legal principles, industry codes or guidance, good industry practice, and prior
determinations of AFCA or its predecessors.
A panel has determined this complaint. The panel consists of the panel chair
ombudsman, a representative with extensive experience in the insurance industry and
a representative with extensive experience in consumer claims.
2.1 Is the insurer entitled to deny the claimed costs?
Onus on the complainants to establish claimable loss
When making a claim, the complainants have the onus of establishing, on the balance
of probabilities (i.e. that it is more likely than not), that they suffered a loss which is
covered by their insurance policy.
If a claimable loss is established, the onus shifts to the insurer to establish, on the
balance of probabilities, the application of any condition or exclusion it relies on to
reduce its liability.
Policy covers insured events subject to exclusions and conditions
The cover provided by the policy is set out in the product disclosure statement (PDS)
and the certificate of insurance, there is not dispute the complainants received these
documents.
The policy coverage details that the building is covered for insured events. The policy
provides cover for flood or water run off damage to the property.
The policy details the complainants’ responsibilities when claiming through the
insurer. The policy says the complainants must keep damaged property, so the
insurer can inspect it. Further, the complainants are not to complete any repairs or
throw out damaged property unless it is a safety hazard, or the insurer agrees.
The insurer says by demolishing the property with a notice period of two days and by
not allowing the insurer to thoroughly assess the allegation the repairs its contractors
completed were inadequate, it has prejudiced the insurers ability to verify the
complainants claim.
The insurer also refers to the policy excluding any intentional acts, that is, the
intentional act of demolishing the insured property.
Determination | Case number: 747852 Page 4 of 6
Complainants prejudiced insurer for full extent of the claim
The available information shows the complainants signed off on repairs on 1 August
2019 and there is no evidence or information to show any concern with the
completion of repairs was raised with the insurer prior to their email of 5 January
2020.
The email of 5 January 2020, a Sunday, explains that the complainants are
attempting to sell their property, only to be advised by multiple building consultants
that the property has damp, rot and mould damage from the previous claim. Further,
expressing their dissatisfaction with the times taken to repair the property and the
methods chosen on certain repairs despite recommendations from the insurer ’ s
builders.
The complainants also spoke to the loss adjustor who the complainants say advised
to submit a quotation to the insurer for the full repair of the property. The email goes
on to say the property will be demolished due to the previous repairs not being
completed adequately.
The complainants then advised the demolition will be commencing 7 January 2020,
just two days after informing the insurer.
The insurer provided a statement from the loss adjustor which in summary says to
provide further information for the loss adjustor’s consideration. The panel accepts
this to be the case as the panel considers it highly unlikely the loss adjustor agreed or
advised the complainant to proceed with the demolition, given the potential costs
involved.
In their submission to AFCA, the complainants requested voice recordings, saying
they advised via telephone on 5 January 2020, of the proposed date to demolish the
property. The complainants say the insurer advised it could reopen the claim despite
the demolition and that taking photographs was a reasonable way to show the
damage to the property.
The insurer advised, it does not have any claim notes on 5 January 2020 and nor did
it receive any calls from the complainant’s phone numb er until 10 January 2020. The
panel is satisfied that a copy of this call recording is of limited value as the demolition
was already underway. The insurer also confirmed access to the system and that
there was none prior to this call. The panel accepts the insurer ’ s response to be the
case.
The insurer’s representative on the call asked the complainants to provide reports a nd
photographs of the damage. The representative did not imply cover would be afforded
and the panel agrees with the insurer ’s position that the complainants had already
commenced demolishing the property so there is little or no value in the advice.
Determination | Case number: 747852 Page 5 of 6
The complainants provided several photographs and a quotation for the building
repairs which mention water damage. This is not sufficient for the policy where the
complainant has a responsibility to maintain damaged items and contact the insurer.
The quotation and photographs alone do not confirm exactly what is required or
related to the claim and in the circumstances, the panel is satisfied that it is fair the
insurer had the opportunity to reassess the property. The complainants contacting to
advise of the demolition and providing two days’ notice was unreasonable and
prejudiced the insure to the full extent of the claim.
The complainants mention up to five builders completed inspection reports when they
were trying to sell their property, however, no building report has been provided to
confirm causation of the alleged failed or inadequate repairs.
The panel also notes the complainants ’ concerns that repairs were not completed as
recommended by the insurer ’ s builders. The panel does not consider each point
needs to be addressed as again the insurer should have had the opportunity to
assess this and the complainants have not allowed this to happen by demolishing the
property.
The property has been demolished and rebuilt and the complainants have failed to
show this was due to the insurer ’ s or its representatives’ actions.
The insurer is entitled to deny the further building costs ’ claim as the complainants
have not met their responsibilities under their policy.
Further loss of rent also not payable
The complainants advised they are seeking loss of rent for the full duration of the
complaint. The insurer provided a copy of the file notes which show at end of August
2019, it advised the complainants it was willing to settle 15 weeks loss of rent and the
complainants were to contact and confirm.
As mentioned previously, the complainants did not contact again until January 2020.
A review of the rental ledger shows the complainants continued to receive rental
income until May 2019, where the rental income ceased. The repairs were completed
approximately three months later, on 1 August 2019, which is approximately 12
weeks.
As the allegations into inadequate repairs have not been proven, the panel considers
the insurer ’ s offer was fair in the circumstances and if it has not already done so it is
to pay the 15 weeks loss of rent.
Determination | Case number: 747852 Page 6 of 6
2.2 Is the complainant entitled to compensation?
AFCA can award compensation for poor claim handling
Under the AFCA Rules, we can award up to $5,000 compensation for indirect
financial loss caused by an insurer mishandling a claim.
We can also award up to $5,000 compensation for non-financial loss if a complainant
suffered an unusual degree of stress, inconvenience, or delay because an insurer
mishandled a claim.
The complainants have the onus of establishing they suffered a loss (financial or non-
financial) due to the insurer mishandling the claim.
Insurer to pay compensation for delays in repairs
The complainants are dissatisfied with the timeliness in claims handling and ability to
contact the insurers
While the complainants have also said that the insure r mishandled the claim, the
panel is not satisfied that the complainants have established that this is the case.
However, the available information shows the insurer took an unusual amount of time
to proceed with repairs. The claim was lodged late in January 2019 and repairs
commenced in July 2019 and were completed by August 2019.
Approximately six months to authorise repairs would have caused the complainants
an unusual degree of inconvenience. Further, the complainants have shown there
were general administrative delays when trying to contact the insurer and the panel
accepts this would have affected their peace of mind.
In the circumstances the panel is satisfied that the complainants are entitled to $500
compensation for non-financial loss.
The panel recognises that this amount is only a tiny portion of the complainants’
claim, but the panel confirms that it has concluded the insurer is entitled to deny to
substantial portion of the complainants’ claim. The award for non-financial loss of
$50 0 is for claim’s handling only.