Home / RACQ / Determination 747852

Determination 747852

Further building and rental costs after flood repairs denied; delay in repairs

FirmRACQ
Decided2021-03-15
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$500
Amount claimed$135,600
SourceAFCA PDF

Summary

The complainants claimed the cost of further building repairs after flood damage, plus rent and non-financial loss, after demolishing the property. AFCA denied the building costs but ordered 15 weeks of loss of rent and $500 for delays in repairs.

The complainants prejudiced the insurer's ability to assess alleged inadequate repairs by demolishing the property on short notice, while the insurer's delay in authorising repairs warranted compensation.

Issues

Subjects and remedies

natural disasterpay compensationpay non financial loss

Related

All RACQ determinations · Find similar determinations

Text of the determination

Determination Case number 747852 Financial firm RACQ Insurance Limited Determination | Case number: 747852 Page 2 of 6 Case number: 747852 5 March 2021 1 Determination overview 1.1 Complaint On 26 January 2019, the complainants lodged a claim under their home insurance policy held with the financial firm (insurer), following flood damage from a storm. The insurer accepted the claim and organised repairs which commenced in July 2019 and were signed off as completed in August 2019. The insurer covered loss of rent for a period of 15 weeks and the claim was finalised. On 5 January 2020, the complainants emailed the insurer advising the property was to be demolished on 7 January 2020, due to inadequate repairs by the insurer and were seeking to be settled the building sum insured of $323,000. The complainants since clarified they are seeking the costs they say were required to repair the insured damage based on their builder’s quotation for $135,600, along with additional loss of rent costs and non-financial loss due to the claim ’ s handling. The insurer says the complainants prejudiced its ability to assess the alleged inadequate repairs by demolishing the property without its consent and in an unreasonable time frame. Further, it says the act of intentionally demolishing the property is not covered under the policy and occurred after the policy had lapsed. 1.2 Issues and key findings Is the insurer entitled to deny further claimed building and rental costs? Yes, the complainants prejudiced the insurers ability to assess the complainants’ allegations of inadequate repairs by demolishing the property in an unreasonable time frame. The insurer paid the complainants 15 weeks loss of rent, the available information shows this was fair in the circumstances. Is the complainant entitled to compensation for non-financial loss? $500 compensation is warranted due to delays in organising repairs. 1.3 Determination This determination is substantially in favour of the financial firm. The insurer is not required to make any further contributions towards the claim. The insurer is to pay the complainants $500 for non-financial loss. Determination | Case number: 747852 Page 3 of 6 2 Reasons for determination This determination is based on information submitted by the parties. Each party has had an opportunity to review and respond to the other party’s submissions. This determination is based on what is fair in the circumstances, having regard to any relevant legal principles, industry codes or guidance, good industry practice, and prior determinations of AFCA or its predecessors. A panel has determined this complaint. The panel consists of the panel chair ombudsman, a representative with extensive experience in the insurance industry and a representative with extensive experience in consumer claims. 2.1 Is the insurer entitled to deny the claimed costs? Onus on the complainants to establish claimable loss When making a claim, the complainants have the onus of establishing, on the balance of probabilities (i.e. that it is more likely than not), that they suffered a loss which is covered by their insurance policy. If a claimable loss is established, the onus shifts to the insurer to establish, on the balance of probabilities, the application of any condition or exclusion it relies on to reduce its liability. Policy covers insured events subject to exclusions and conditions The cover provided by the policy is set out in the product disclosure statement (PDS) and the certificate of insurance, there is not dispute the complainants received these documents. The policy coverage details that the building is covered for insured events. The policy provides cover for flood or water run off damage to the property. The policy details the complainants’ responsibilities when claiming through the insurer. The policy says the complainants must keep damaged property, so the insurer can inspect it. Further, the complainants are not to complete any repairs or throw out damaged property unless it is a safety hazard, or the insurer agrees. The insurer says by demolishing the property with a notice period of two days and by not allowing the insurer to thoroughly assess the allegation the repairs its contractors completed were inadequate, it has prejudiced the insurers ability to verify the complainants claim. The insurer also refers to the policy excluding any intentional acts, that is, the intentional act of demolishing the insured property. Determination | Case number: 747852 Page 4 of 6 Complainants prejudiced insurer for full extent of the claim The available information shows the complainants signed off on repairs on 1 August 2019 and there is no evidence or information to show any concern with the completion of repairs was raised with the insurer prior to their email of 5 January 2020. The email of 5 January 2020, a Sunday, explains that the complainants are attempting to sell their property, only to be advised by multiple building consultants that the property has damp, rot and mould damage from the previous claim. Further, expressing their dissatisfaction with the times taken to repair the property and the methods chosen on certain repairs despite recommendations from the insurer ’ s builders. The complainants also spoke to the loss adjustor who the complainants say advised to submit a quotation to the insurer for the full repair of the property. The email goes on to say the property will be demolished due to the previous repairs not being completed adequately. The complainants then advised the demolition will be commencing 7 January 2020, just two days after informing the insurer. The insurer provided a statement from the loss adjustor which in summary says to provide further information for the loss adjustor’s consideration. The panel accepts this to be the case as the panel considers it highly unlikely the loss adjustor agreed or advised the complainant to proceed with the demolition, given the potential costs involved. In their submission to AFCA, the complainants requested voice recordings, saying they advised via telephone on 5 January 2020, of the proposed date to demolish the property. The complainants say the insurer advised it could reopen the claim despite the demolition and that taking photographs was a reasonable way to show the damage to the property. The insurer advised, it does not have any claim notes on 5 January 2020 and nor did it receive any calls from the complainant’s phone numb er until 10 January 2020. The panel is satisfied that a copy of this call recording is of limited value as the demolition was already underway. The insurer also confirmed access to the system and that there was none prior to this call. The panel accepts the insurer ’ s response to be the case. The insurer’s representative on the call asked the complainants to provide reports a nd photographs of the damage. The representative did not imply cover would be afforded and the panel agrees with the insurer ’s position that the complainants had already commenced demolishing the property so there is little or no value in the advice. Determination | Case number: 747852 Page 5 of 6 The complainants provided several photographs and a quotation for the building repairs which mention water damage. This is not sufficient for the policy where the complainant has a responsibility to maintain damaged items and contact the insurer. The quotation and photographs alone do not confirm exactly what is required or related to the claim and in the circumstances, the panel is satisfied that it is fair the insurer had the opportunity to reassess the property. The complainants contacting to advise of the demolition and providing two days’ notice was unreasonable and prejudiced the insure to the full extent of the claim. The complainants mention up to five builders completed inspection reports when they were trying to sell their property, however, no building report has been provided to confirm causation of the alleged failed or inadequate repairs. The panel also notes the complainants ’ concerns that repairs were not completed as recommended by the insurer ’ s builders. The panel does not consider each point needs to be addressed as again the insurer should have had the opportunity to assess this and the complainants have not allowed this to happen by demolishing the property. The property has been demolished and rebuilt and the complainants have failed to show this was due to the insurer ’ s or its representatives’ actions. The insurer is entitled to deny the further building costs ’ claim as the complainants have not met their responsibilities under their policy. Further loss of rent also not payable The complainants advised they are seeking loss of rent for the full duration of the complaint. The insurer provided a copy of the file notes which show at end of August 2019, it advised the complainants it was willing to settle 15 weeks loss of rent and the complainants were to contact and confirm. As mentioned previously, the complainants did not contact again until January 2020. A review of the rental ledger shows the complainants continued to receive rental income until May 2019, where the rental income ceased. The repairs were completed approximately three months later, on 1 August 2019, which is approximately 12 weeks. As the allegations into inadequate repairs have not been proven, the panel considers the insurer ’ s offer was fair in the circumstances and if it has not already done so it is to pay the 15 weeks loss of rent. Determination | Case number: 747852 Page 6 of 6 2.2 Is the complainant entitled to compensation? AFCA can award compensation for poor claim handling Under the AFCA Rules, we can award up to $5,000 compensation for indirect financial loss caused by an insurer mishandling a claim. We can also award up to $5,000 compensation for non-financial loss if a complainant suffered an unusual degree of stress, inconvenience, or delay because an insurer mishandled a claim. The complainants have the onus of establishing they suffered a loss (financial or non- financial) due to the insurer mishandling the claim. Insurer to pay compensation for delays in repairs The complainants are dissatisfied with the timeliness in claims handling and ability to contact the insurers While the complainants have also said that the insure r mishandled the claim, the panel is not satisfied that the complainants have established that this is the case. However, the available information shows the insurer took an unusual amount of time to proceed with repairs. The claim was lodged late in January 2019 and repairs commenced in July 2019 and were completed by August 2019. Approximately six months to authorise repairs would have caused the complainants an unusual degree of inconvenience. Further, the complainants have shown there were general administrative delays when trying to contact the insurer and the panel accepts this would have affected their peace of mind. In the circumstances the panel is satisfied that the complainants are entitled to $500 compensation for non-financial loss. The panel recognises that this amount is only a tiny portion of the complainants’ claim, but the panel confirms that it has concluded the insurer is entitled to deny to substantial portion of the complainants’ claim. The award for non-financial loss of $50 0 is for claim’s handling only.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.