Home / Suncorp Group / Determination 745271
Determination 745271
Cash settlement amount for fire-damaged home building claim
Summary
After a house fire, the complainant disputed the insurer's cash settlement for rebuilding the home, saying it was insufficient. AFCA ordered a further $78,114.38 in full and final settlement of the building claim and declined non-financial loss compensation.
The policy allows cash settlement based on the insurer's rebuild cost, but a 10% contingency is fair because the quote excluded unforeseen works and likely variations.
Issues
- Claim amount dispute primary · upheld“It is fair in all the circumstances for the insurer to pay an additional 10% on top of JL's quote”
- Poor claim handling secondary · not upheld“The available evidence does not however indicate the insurer handled the claim unreasonably.”
Subjects and remedies
home or building damagepay claim
Related
All Suncorp Group determinations · Find similar determinations
Text of the determination
Determination
Case number 745271
Financial firm AAI Limited
Determination | Case number: 745271 Page 2 of 6
Case number: 745271 4 June 2021
1 Determination overview
1.1 Complaint
The complainant held a home and contents insurance policy with the financial firm
(insurer). A fire destroyed the complainant’s home requiring replacement of the home
and contents. The insurer accepted the claim and proposed to rebuild the property.
The complainant requested a cash settlement for the building repairs due to the
estimated time of completion and disruption to her family over this period. The insurer
agreed and has paid the complainant in accordance with its quoted costs for the
rebuild. The complainant says the settlement paid is insufficient for her to complete
the repairs with an independent builder. A dispute remains regarding whether the
building settlement paid is fair and reasonable.
The complainant has also raised concerns about the insurer’s claims hand ling.
1.2 Issues and key findings
Is the cash settlement paid by the insurer fair and reasonable?
It is fair in all the circumstances for the insurer to pay an additional 10% on top of JL’s
quote, as well as the $7,648.30 it has agreed to pay, in settlement of the building
claim.
Is the complainant entitled to any compensation or other costs?
The insurer has agreed to reimburse the complainant for her engineer and builder’s
fees. These assisted in determining the fair settlement of this claim. The panel does
not consider any further compensation is required.
1.3 Determination
This determination is partially in favour of the complainant.
Within fourteen days of the insurer receiving confirmation the complainant has
accepted this determination, the i nsurer should pay the complainant a further
$78,114.38 in full and final settlement of the building claim.
Determination | Case number: 745271 Page 3 of 6
2 Reasons for determination
2.1 Is the cash settlement paid by the insurer fair and reasonable?
Settlement offer based on actionable quote and fixed price comparison costs
The insurer has cash settled the complainant $704,660.79 to date for the building
works. This figure is based on an itemised quote from builder JL, which the insurer
engaged to complete the rebuild before the complainant requested a cash settlement.
The complainant is concerned she will be unable to rebuild the home for the amount
paid.
The complainant has provided a fixed price quote dated 23 February 2021 from
builder IB based on the agreed scope of works. The complainant seeks the difference
between IB’s quote of $837,559 and the settlement paid, being an additional
$132,898.21.
IB’s quote is partially itemised. However, it also includes bulk quotes for various works
(including electrical, plumbing, painting, plasterboard and solar) and is not directly
comparable to JL’s quote for these items.
The insurer notes IB’s quotation includes fixed price quotes for professional costs and
council fees, while JL included provisional sums for these items. On this basis, the
insurer offers the complainant an additional $7,648.30, being the difference between
the professional costs quoted by IB and JL (less the amounts already paid).
Policy terms on settlement clear
The insurer says it has correctly calculated and settled its liability in accordance with
the terms of the policy.
The policy provides the insurer with the choice whether to repair or rebuild the home,
or pay the complainant what it would cost the insurer to repair or rebuild the home.
The insurer notes the policy terms are clear and unambiguous in this respect.
Insurer should allow a 10% contingency
There is no dispute the insurer was prepared to rebuild the property and had
authorised this work based on JL’s actionable quote . However, the insurer agreed to
the complainant’s request fo r a cash settlement to accommodate the needs of her
family. On this basis, the insurer says it has fairly discharged its liability as it is based
on the costs it would have incurred in completing the rebuild.
The panel considers it is fair for the insurer to rely on JL’s quote given:
the insurer was ready, willing and able to do the works, and
the policy clearly says it can cash settle based on the amount it would have cost
the insurer to rebuild the property.
Determination | Case number: 745271 Page 4 of 6
However, the panel considers an added 10% conti ngency is fair in all the
circumstances. This is a substantial job. It is likely further variances would be required
for a job of this size and nature. This is supported by the following in JL’s quote:
it specifically says the quote does not account for unforeseen damages, latent
conditions or upgrades
there is specific reference that a variation would be required when a new system is
designed for the septic tank
there was specific reference the quote does not include the possibility of additional
damage to the driveway and garden occurring during the works
Therefore, it is fair for the insurer to pay a further $70,466.08 on JL’s quote. This does
not include the further $7,648.30 the insurer has agreed to pay.
The insurer is not required to pay interest on this additional amount. This is because
the total sum paid should represent current rates.
2.2 Is the complainant entitled to any compensation or other costs?
Insurer has conducted claim reasonably
Under paragraph D.3 of the AFCA Rules, we may award compensatio n for non-
financial loss (capped at $5,000) where there has been an unusual amount of:
physical inconvenience
time taken to resolve the situation
interference with the complainant’s expectation of enjoyment or peace of mind
due to the insurer’s conduct of the claim.
We take a conservative approach to compensation and expect a complainant to bear
a normal degree of inconvenience during a claim.
The complainant expressed concerns about the management of the claim, including:
that she was required to prepare an inventory of contents items when it was
apparent she had lost everything in the fire and was trying to find somewhere to
live and deal with other stresses caused by the event
delays during the claim process, including finalising the scope of works.
The panel acknowledges losing the complainant’s home and possessions would be
extremely distressing and the claim process has been understandably difficult.
The available evidence does not however indicate the insurer handled the claim
unreasonably. The insurer is entitled to assess the contents being claimed against the
sum insured. The evidence shows the insurer issued the complainant with emergency
funds the day after the claim was lodged. Further, an initial contents payment of
$100,000 was made within 2 weeks of the event and before an inventory was
provided. The emails provided show the insurer understood it was a difficult time for
Determination | Case number: 745271 Page 5 of 6
the complainant and said she could take her time providing the inventory. The insurer
also offered the complainant and her family access to counselling sessions on several
occasions following the event.
The records provided indicate the insurer has been generally responsive to requests
from the complainant, including the request to cash settle the building claim when the
insurer had elected to rebuild the property. The insurer has also appropriately
reviewed its position on various matters based on information provided by the
complainant, and has agreed to reimburse her professional costs.
While we are sympathetic to the difficulties faced by the complainant following the
event, the panel does not consider compensation is warranted on the basis of the
insurer’s conduct of the claim.
Determination | Case number: 745271 Page 6 of 6
3 Supporting information
3.1 Process
AFCA’s approach to this complaint
This complaint has been determined based on what is fair in all the circumstances,
having regard to the legal principles, applicable industry codes or guidance, good
industry practice and previous decisions of AFCA or its predecessor schemes (which
are not binding).
A full exchange of the relevant information has taken place between the respective
parties. Each party has had the opportunity of addressing any issues raised. All of the
provided information has been reviewed and considered. The parties have raised
numerous issues in their submissions to AFCA. However, commentary in this
determination is restricted to those issues considered relevant to the outcome.
This matter was determined by a panel
Due to the nature of this dispute, it has been referred to a panel for determination.
The panel comprises the ombudsman, a member with significant experience in
consumer claims and a member with extensive experience in the insurance industry.
3.2 Relevant policy terms
How we settle your claim
We choose how we settle home claims
If we agree to pay a claim for loss, theft or damage to your home, we will decide if we will:
repair damage to your home;
rebuild your home;
pay you what it would cost us to repair or rebuild your home;
pay you the home sum insured shown on your certificate;
give you a voucher, store credit or stored value card for the amount it would cost us to
repair or rebuild an item.
If we rebuild (or pay you what it would cost us to rebuild), we wil l rebuild on a ‘new for old’
basis.