Home / Westpac / Determination 745139

Determination 745139

Dispute over cost of flood repairs for settlement, with related delay and make-safe handling

FirmWestpac
Decided2021-06-16
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded$103,659
Non-financial loss$2,000
Amount claimed$103,659
SourceAFCA PDF

Summary

After a February 2020 flood, the insurer offered $43,006.08 for repairs while the complainant's builder quoted $103,658.56. AFCA ordered the claim settled at the builder's quote with interest, reasonable accommodation costs if the home is unliveable, and $2,000 non-financial loss.

The complainant's builder quote is the best available assessment of the flood repair cost, so the insurer must pay the policy claim in that amount.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay interestpay non financial loss

Related

All Westpac determinations · Find similar determinations

Text of the determination

Determination Case number 745139 Financial firm Westpac General Insurance Limited Determination | Case number: 745139 Page 2 of 8 Case number: 745139 15 June 2021 1 Determination overview 1.1 Complaint The complainant holds a home insurance policy with the financial firm (the insurer). He lodged a claim after his home was damaged by a flood in February 2020. The insurer accepted the claim. The parties have agreed that the insurer will settle the claim by paying the cost of repairs. However, the parties disagree on the cost of repairs. The complainant obtained quotes for $103,658.56 and $112,442. The insurer obtained quotes for $31,846.42 and $43,006.08. The insurer offers to settle the claim for $43,006.08. The complainant wants the insurer to increase its settlement offer. He also says the insurer’s handling of the claim caused him stress and inconvenience. 1.2 Issues and key findings Is the insurer required to increase its settlement offer? Yes. The best available assessment of the cost of repairs is $103,658.56. The insurer must pay this amount for the cost of repairs. If the home is unliveable while the flood damage is being repaired, the insurer must pay the reasonable cost of alternative accommodation, up to the policy limit. Is the complainant entitled to any other compensation? Yes. The insurer did not arrange make-safe work within a reasonable time, and the complainant and his partner had to do the work themselves. This caused an unusual degree of stress and inconvenience. The complainant is entitled to compensation for non-financial loss in the sum of $2,000. 1.3 Determination This determination is in favour of the complainant. The insurer must settle the claim by paying the complainant:  $103,658.56, plus interest at the rate determined under section 57 of the Insurance Contracts Act 1984 (Cth) from 16 March 2020 (the d ate of the complainant’s quote)  the reasonable cost of accommodation, up to the policy limit, if the home is unliveable during repairs  $2,000 compensation for non-financial loss. Determination | Case number: 745139 Page 3 of 8 2 Reasons for determination 2.1 Is the insurer required to increase its settlement offer? Claim to be cash settled On or about 9 February 2020, the complainant’s home was flooded with water from a near by salt water lake. The complainant says the ground floor of his house was inundated with salt water and sewage for four days. On 13 February 2020, he lodged a claim for damage caused by the flood. The insurer accepted the claim. The complainant wants the insurer to settle the claim by paying the cost of repairs. The insurer has agreed to do so. Complainant rejected insurer’s quotes The insurer appointed a builder (MK), who inspected the property on 29 February 2020 and 15 May 2020. MK prepared a scope of works dated 18 May 2020 costed at $31,846.42. The insurer offered to settle the claim by paying this amount to the complainant. The complainant rejected the offer. The insurer appointed another builder (AJ), who inspected the property on 3 September 2020. AJ prepared a scope of works dated 24 September 2020 costed at $43,006.08. The insurer offered to settle the claim by paying this amount to the complainant. The complainant rejected the offer. Insurer rejected complainant ’s quotes The complainant appointed a builder (BBB), who produced a quote dated 31 March 2020 for $112,442. The complainant appointed another builder (CCB), who inspected the property on 19 February 2020. CCB produced a quote dated 16 March 2020 for $109,301.50. CCB later amended the quote; the amended quote is for $103,658.56. The insurer says the complainant’s quotes are excessive, because they allow for the replacement of items that were not damaged by the flood. The most significant differences between the complainant’s quotes and the insurer’s quotes relate to:  a detached steel shed  blueboard cladding  a treated pine deck  two custom steel doors. Shed was damaged by flood CCB allowed $28,142.40 (including GST) for the replacement of the shed’s roller doors and 192m 2 of wall sheets. BBB’s quote also made an allowance (not itemised) for the replacement of these items. AJ allowed $3,762 (including builder’s margin and GST) for the replacement of 10m 2 of wall sheets around the roller doors. However, all sides of the shed were inundated. AJ did not explain why only the wall sheets around the roller doors at the front of the shed needed to be replaced. Determination | Case number: 745139 Page 4 of 8 MK allowed $726 (including builder’s margin and GST) for pressure -washing the outside of the shed. However, MK said the inside of the shed was flooded. MK did not explain why the inside of the shed did not need to be repaired or cleaned. The insurer’s internal assessor said there was no physical damage to the shed. Photographs show the shed was partially submerged during the flood. There is now a stain around the perimeter of the shed at the level the water reached. CCB said the immersion of the steel in salt water had compromised its protective coating, and it would now corrode under ordinary environmental conditions. According to MK, the complainant said the shed was made of ordinary Colorbond steel. MK said it should have been made of Colorbond Ultra steel or better, because ordinary Colorbond steel should not be used near salt water lakes. The complainant says his local council told him the shed only needed to be clad in Colorbond Ultra if the property was close to breaking surf, which it is not. MK’s statement indicates the steel is susceptible to damage by salt water. This supports CCB’s assertion that the steel was damaged by the flood, w hich immersed the bottom of the shed in salt water for four days. The panel is satisfied that the shed was damaged by the flood, and the damaged steel needs to be replaced. Blueboard facade was damaged by flood CCB allowed $10,032 for the replacement of blueboard cladding on the front facade of the house. BBB’s quote also made an allowance (not itemised) for the replacement of blueboard. MK said there was no visible damage to the blueboard. AJ said there was ‘v ery minor lifting at a couple of corners ’ of the blueboard. AJ said they could not determine whether this was because of the flood or ‘unfinished poor workmanship’. AJ did not make any allowance for repairs to the front facade. The panel is satisfied that the blueboard is damaged. The house is known to have been flooded, and there is no evidence that the blueboard installation was faulty or unfinished. On balance, it is more likely that the damage was caused by the flood. Neither party has provided photographs showing the damage to the blueboard. AJ said the damage was very minor. The panel has considered whether the blueboard could be repaired, rather than replaced. However, the insurer has not provided any information to show the blueboard could be repaired, or that it could be replaced for less than the amount quoted by CCB. Entire deck should be replaced CCB allowed $21,436.80 for the replacement of a treated pine deck at the rear of the house. BBB’s quote also made an allowance (not itemised) for the replacement of the deck. MK allowed $9,266.40 for the replacement of the deck. AJ allowed $10,198.32 to remove water-damaged timber, install new timber, and stain it to match the existing timber. AJ allowed for the replacement of 43m 2 of decking; the whole deck is 57m 2 . AJ recommended replacement of three quarters of the timber in the deck. The other three builders recommended replacement of the entire deck. On balance, the panel is satisfied that replacement of the entire deck is warranted. Determination | Case number: 745139 Page 5 of 8 Custom steel doors were damaged by flood CCB allowed $6,718.80 for the replacement of two custom steel doors in a store room. BBB’s quote also made an allowance (not itemised) for the replacement of the custom steel doors. MK said there was no visible damage to the store room doors. However, MK allowed $198 to repair and paint one of the doors. MK did not explain why they allowed this if the door had no visible damage. AJ allowed $672.50 to paint the doors. Neither party has provided photographs showing the damage to the doors. All four builders allowed for the repair or replacement of at least one of the store room doors. They also allowed for other repairs in the store room. The panel is satisfied that the flood water reached the store room doors. CCB said the doors, like the steel sheets in the garage, had their protective coating compromised by salt water, and they would now corrode. The insurer has not provided any information to refute this. The panel is satisfied that the custom steel doors were damaged by the flood, and need to be replaced. Insurer must settle claim based on complainant’s builder’s quote CCB inspected the property about ten days after the flood. CCB’s quote covers flood -related damage which was not covered by the scopes of work from the insurer’s builders. CCB also provided a report supporting their quote. MK also had the benefit of inspecting the property shortly after the flood (about three weeks). In addition to their scope of works, MK also provided a report, emails, and comments on the complainant’s builders’ quotes. However, the panel has found that MK overlooked some flood-related damage to the property. BBB inspected the property about two months after the flood. BBB quoted a similar cost of repairs to CCB. However, BBB’s quote was less detailed, and was not itemised as the other quotes were. AJ inspected the property about seven months after the flood. AJ’s scope of works said: ‘ Please note accurate scoping is not possible due [to] the length of time passed since the event ’. For the above reasons, t he panel considers CCB’s quote to be the best available assessment of the work needed to repair the flood damage. Therefore, the fairest outcome is for the insurer to settle the claim in accordance with CCB’s quote. For some work items (e.g. replacement of the deck), CCB has quoted more than the insurer’s builders for the same work. However, the insurer has not alleged that the amounts quoted by CCB are unreasonably high. The insurer has not provided information showing that the complainant could appoint a builder to do the work for less. The insurer has not provided information showing that any of the work is not required to repair damage caused by the flood. Therefore, the fairest outcome is for the insurer to pay the full amount of CCB’s quote. The insurer must settle the claim by paying $103,658.56. The insurer must pay interest on this amount, at the rate determined under section 57 of the Insurance Contracts Act 1984 (Cth), from 16 March 2020. Determination | Case number: 745139 Page 6 of 8 Insurer not required to pay for mould remediation The complainant says mould grew at the home after the flood, and it continues to reappear. None of the builders said there was mould damage at the property. Neither party has provided photographs showing mould damage at the property. The quotes from CCB and BBB did not make any allowance for mould treatment. MK allowed $1,848 for the application of anti-microbial wash, but did not say there was any mould at the property. At the time of their inspection, the flooding was relatively recent, and there may have been problematic mould growth that was not yet visible. The application of anti-microbial wash may have been recommended as a precaution. AJ (the last builder to inspect the property, seven months after the flood) did not say there was any mould at the property, and did not make any allowance for mould remediation. The available information does not establish that the property requires mould remediation. Therefore, the insurer is not required to pay for mould remediation. Insurer must consider complainant’s entitlement to accommodation costs If the complainant pays for alternative accommodation while his home is unliveable, the policy covers the cost of the accommodation. This cover is limited to 12 months’ accommodation or $39,323.70 (10% of the sum insured). None of the builders said whether the home would be unliveable during repairs, or if so, how long it would be unliveable for. The insurer has not offered to pay for accommodation. If the complainant pays for accommodation while his home is unliveable due to flood damage repairs, the insurer must reimburse him for the reasonable cost of the accommodation, up to the policy limit. 2.2 Is the complainant entitled to any other compensation? AFCA can award compensation for non-financial loss Under the AFCA Rules, we can award up to $5,000 compensation for non-financial loss if a complainant suffered an unusual degree of stress, inconvenience, or delay because an insurer mishandled a claim. We will only award this type of compensation if there has been an unusual degree of stress, inconvenience, or delay. We will not award compensation for the usual amount of inconvenience involved in making a claim. We will not award compensation for delays caused by the complainant, or other factors outside the insurer’s control. Complainant says insurer caused unreasonable delay The complainant says the insurer took a long time to respond after he lodged the claim. He says they suffered stress from having to live in the house when it was severely damaged. The complainant lodged the claim on 13 February 2020. MK did not attend until 29 February 2020, 16 days later. MK did not provide a written report or a scope of works until 18 May 2020, three months after the claim was lodged. In July 2020, the insurer offered to have MK perform the repairs set out in their scope of works. However, this scope of works did not cover all of the flood damage at the complainant’s home. Determination | Case number: 745139 Page 7 of 8 The complainant suffered a loss in February 2020, and he has not yet been compensated. This determination awards the complainant interest from 16 March 2020, the date of his builder’s quote . AFCA considers that if a complainant is entitled to money, and there is a delay in receiving payment, an award of interest will usually be sufficient to compensate for the delay. Complainant says insurer did not perform make-safe The complainant says the insurer did not offer to perform make-safe work. He says he and his partner had to remove salt water and sewage from the house with no help from the insurer. MK says it offered to perform make-safe work, such as installing drying fans and applying anti-microbial treatment, but the complainant rejected the offer because he had already done make-safe work. MK first attended the property 16 days after the claim was lodged. After the flood, the house needed to be dried out as quickly as possible to prevent further damage. The complainant could not reasonably have waited 16 days for the insurer to arrange make-safe work. The flood was part of the February 2020 East Coast Low, which resulted in thousands of insurance claims for storm and flood damage. Because of this, the insurer may not have been able to arrange make-safe work in less than two weeks. However, the insurer could have offered to reimburse the complainant if he hired someone to perform make-safe work. The policy cove rs the cost of ‘ emergency repairs and protection necessary to prevent further loss or damage ’. Because the insurer could not arrange this within a reasonable time, the complainant and his partner had to do this work themselves. The complainant has not provided information showing he suffered a financial loss because the insurer did not perform make-safe work. However, the panel considers the complainant should be compensated for the stress and inconvenience of having to perform the work himself. Complainant entitled to compensation for non-financial loss The complainant’s house was flooded. This would have been a stressful experience regardless of how the insurer responded to the claim. However, the panel believes the complainant suffered additional stress and inconvenience because:  the insurer’s builder did not attend the property for more than two weeks, and did not provide a report or scope of works for three months  the insurer did not arrange make-safe work  the insurer made settlement offers that were not sufficient to fulfil its policy obligations. The panel considers it fair for the insurer to pay the complainant compensation for non- financial loss in the sum of $2,000. Outcome is fair in the circumstances The complainant suffered losses because of an event covered under the insurance policy. He is entitled to be compensated for those losses by the insurer. CCB’s quote is the best available assessment of the cost of repairs. Therefore, it is fair for the claim settlement to be based on this quote. Determination | Case number: 745139 Page 8 of 8 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. A panel determined this matter Due to the nature of this complaint, we referred it to a panel for determination. The panel includes:  an ombudsman  a member with significant experience in consumer and small business advocacy  a member with extensive experience in insurance. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.