Determination 745139
Dispute over cost of flood repairs for settlement, with related delay and make-safe handling
Summary
After a February 2020 flood, the insurer offered $43,006.08 for repairs while the complainant's builder quoted $103,658.56. AFCA ordered the claim settled at the builder's quote with interest, reasonable accommodation costs if the home is unliveable, and $2,000 non-financial loss.
The complainant's builder quote is the best available assessment of the flood repair cost, so the insurer must pay the policy claim in that amount.
Issues
- Claim amount dispute primary · upheld“The best available assessment of the cost of repairs is $103,658.56. The insurer must pay this amount for the cost of repairs.”
- Poor claim handling secondary · upheld“The insurer did not arrange make-safe work within a reasonable time, and the complainant and his partner had to do this work themselves.”
- Delay secondary · upheld“MK did not attend until 29 February 2020, 16 days later, and did not provide a written report or scope of works until 18 May 2020.”
Subjects and remedies
home or building damagenatural disasterpay claimpay interestpay non financial loss
Related
Text of the determination
Determination
Case number 745139
Financial firm Westpac General Insurance Limited
Determination | Case number: 745139 Page 2 of 8
Case number: 745139 15 June 2021
1 Determination overview
1.1 Complaint
The complainant holds a home insurance policy with the financial firm (the insurer). He
lodged a claim after his home was damaged by a flood in February 2020. The insurer
accepted the claim.
The parties have agreed that the insurer will settle the claim by paying the cost of repairs.
However, the parties disagree on the cost of repairs.
The complainant obtained quotes for $103,658.56 and $112,442. The insurer obtained quotes
for $31,846.42 and $43,006.08. The insurer offers to settle the claim for $43,006.08.
The complainant wants the insurer to increase its settlement offer. He also says the insurer’s
handling of the claim caused him stress and inconvenience.
1.2 Issues and key findings
Is the insurer required to increase its settlement offer?
Yes. The best available assessment of the cost of repairs is $103,658.56. The insurer must
pay this amount for the cost of repairs.
If the home is unliveable while the flood damage is being repaired, the insurer must pay the
reasonable cost of alternative accommodation, up to the policy limit.
Is the complainant entitled to any other compensation?
Yes. The insurer did not arrange make-safe work within a reasonable time, and the
complainant and his partner had to do the work themselves. This caused an unusual degree
of stress and inconvenience. The complainant is entitled to compensation for non-financial
loss in the sum of $2,000.
1.3 Determination
This determination is in favour of the complainant.
The insurer must settle the claim by paying the complainant:
$103,658.56, plus interest at the rate determined under section 57 of the Insurance
Contracts Act 1984 (Cth) from 16 March 2020 (the d ate of the complainant’s quote)
the reasonable cost of accommodation, up to the policy limit, if the home is unliveable
during repairs
$2,000 compensation for non-financial loss.
Determination | Case number: 745139 Page 3 of 8
2 Reasons for determination
2.1 Is the insurer required to increase its settlement offer?
Claim to be cash settled
On or about 9 February 2020, the complainant’s home was flooded with water from a near by
salt water lake. The complainant says the ground floor of his house was inundated with salt
water and sewage for four days. On 13 February 2020, he lodged a claim for damage caused
by the flood. The insurer accepted the claim.
The complainant wants the insurer to settle the claim by paying the cost of repairs. The
insurer has agreed to do so.
Complainant rejected insurer’s quotes
The insurer appointed a builder (MK), who inspected the property on 29 February 2020 and
15 May 2020. MK prepared a scope of works dated 18 May 2020 costed at $31,846.42. The
insurer offered to settle the claim by paying this amount to the complainant. The complainant
rejected the offer.
The insurer appointed another builder (AJ), who inspected the property on 3 September
2020. AJ prepared a scope of works dated 24 September 2020 costed at $43,006.08. The
insurer offered to settle the claim by paying this amount to the complainant. The complainant
rejected the offer.
Insurer rejected complainant ’s quotes
The complainant appointed a builder (BBB), who produced a quote dated 31 March 2020 for
$112,442.
The complainant appointed another builder (CCB), who inspected the property on 19
February 2020. CCB produced a quote dated 16 March 2020 for $109,301.50. CCB later
amended the quote; the amended quote is for $103,658.56.
The insurer says the complainant’s quotes are excessive, because they allow for the
replacement of items that were not damaged by the flood.
The most significant differences between the complainant’s quotes and the insurer’s quotes
relate to:
a detached steel shed
blueboard cladding
a treated pine deck
two custom steel doors.
Shed was damaged by flood
CCB allowed $28,142.40 (including GST) for the replacement of the shed’s roller doors and
192m 2 of wall sheets. BBB’s quote also made an allowance (not itemised) for the replacement
of these items.
AJ allowed $3,762 (including builder’s margin and GST) for the replacement of 10m 2 of wall
sheets around the roller doors. However, all sides of the shed were inundated. AJ did not
explain why only the wall sheets around the roller doors at the front of the shed needed to be
replaced.
Determination | Case number: 745139 Page 4 of 8
MK allowed $726 (including builder’s margin and GST) for pressure -washing the outside of
the shed. However, MK said the inside of the shed was flooded. MK did not explain why the
inside of the shed did not need to be repaired or cleaned.
The insurer’s internal assessor said there was no physical damage to the shed.
Photographs show the shed was partially submerged during the flood. There is now a stain
around the perimeter of the shed at the level the water reached. CCB said the immersion of
the steel in salt water had compromised its protective coating, and it would now corrode
under ordinary environmental conditions.
According to MK, the complainant said the shed was made of ordinary Colorbond steel. MK
said it should have been made of Colorbond Ultra steel or better, because ordinary Colorbond
steel should not be used near salt water lakes. The complainant says his local council told
him the shed only needed to be clad in Colorbond Ultra if the property was close to breaking
surf, which it is not. MK’s statement indicates the steel is susceptible to damage by salt water.
This supports CCB’s assertion that the steel was damaged by the flood, w hich immersed the
bottom of the shed in salt water for four days.
The panel is satisfied that the shed was damaged by the flood, and the damaged steel needs
to be replaced.
Blueboard facade was damaged by flood
CCB allowed $10,032 for the replacement of blueboard cladding on the front facade of the
house. BBB’s quote also made an allowance (not itemised) for the replacement of blueboard.
MK said there was no visible damage to the blueboard.
AJ said there was ‘v ery minor lifting at a couple of corners ’ of the blueboard. AJ said they
could not determine whether this was because of the flood or ‘unfinished poor workmanship’.
AJ did not make any allowance for repairs to the front facade.
The panel is satisfied that the blueboard is damaged. The house is known to have been
flooded, and there is no evidence that the blueboard installation was faulty or unfinished. On
balance, it is more likely that the damage was caused by the flood.
Neither party has provided photographs showing the damage to the blueboard. AJ said the
damage was very minor. The panel has considered whether the blueboard could be repaired,
rather than replaced. However, the insurer has not provided any information to show the
blueboard could be repaired, or that it could be replaced for less than the amount quoted by
CCB.
Entire deck should be replaced
CCB allowed $21,436.80 for the replacement of a treated pine deck at the rear of the house.
BBB’s quote also made an allowance (not itemised) for the replacement of the deck.
MK allowed $9,266.40 for the replacement of the deck.
AJ allowed $10,198.32 to remove water-damaged timber, install new timber, and stain it to
match the existing timber. AJ allowed for the replacement of 43m 2 of decking; the whole deck
is 57m 2 .
AJ recommended replacement of three quarters of the timber in the deck. The other three
builders recommended replacement of the entire deck. On balance, the panel is satisfied that
replacement of the entire deck is warranted.
Determination | Case number: 745139 Page 5 of 8
Custom steel doors were damaged by flood
CCB allowed $6,718.80 for the replacement of two custom steel doors in a store room. BBB’s
quote also made an allowance (not itemised) for the replacement of the custom steel doors.
MK said there was no visible damage to the store room doors. However, MK allowed $198 to
repair and paint one of the doors. MK did not explain why they allowed this if the door had no
visible damage.
AJ allowed $672.50 to paint the doors.
Neither party has provided photographs showing the damage to the doors.
All four builders allowed for the repair or replacement of at least one of the store room doors.
They also allowed for other repairs in the store room. The panel is satisfied that the flood
water reached the store room doors.
CCB said the doors, like the steel sheets in the garage, had their protective coating
compromised by salt water, and they would now corrode. The insurer has not provided any
information to refute this.
The panel is satisfied that the custom steel doors were damaged by the flood, and need to be
replaced.
Insurer must settle claim based on complainant’s builder’s quote
CCB inspected the property about ten days after the flood. CCB’s quote covers flood -related
damage which was not covered by the scopes of work from the insurer’s builders. CCB also
provided a report supporting their quote.
MK also had the benefit of inspecting the property shortly after the flood (about three weeks).
In addition to their scope of works, MK also provided a report, emails, and comments on the
complainant’s builders’ quotes. However, the panel has found that MK overlooked some
flood-related damage to the property.
BBB inspected the property about two months after the flood. BBB quoted a similar cost of
repairs to CCB. However, BBB’s quote was less detailed, and was not itemised as the other
quotes were.
AJ inspected the property about seven months after the flood. AJ’s scope of works said:
‘ Please note accurate scoping is not possible due [to] the length of time passed since the
event ’.
For the above reasons, t he panel considers CCB’s quote to be the best available assessment
of the work needed to repair the flood damage. Therefore, the fairest outcome is for the
insurer to settle the claim in accordance with CCB’s quote.
For some work items (e.g. replacement of the deck), CCB has quoted more than the insurer’s
builders for the same work. However, the insurer has not alleged that the amounts quoted by
CCB are unreasonably high. The insurer has not provided information showing that the
complainant could appoint a builder to do the work for less. The insurer has not provided
information showing that any of the work is not required to repair damage caused by the
flood. Therefore, the fairest outcome is for the insurer to pay the full amount of CCB’s quote.
The insurer must settle the claim by paying $103,658.56. The insurer must pay interest on
this amount, at the rate determined under section 57 of the Insurance Contracts Act 1984
(Cth), from 16 March 2020.
Determination | Case number: 745139 Page 6 of 8
Insurer not required to pay for mould remediation
The complainant says mould grew at the home after the flood, and it continues to reappear.
None of the builders said there was mould damage at the property. Neither party has
provided photographs showing mould damage at the property.
The quotes from CCB and BBB did not make any allowance for mould treatment.
MK allowed $1,848 for the application of anti-microbial wash, but did not say there was any
mould at the property. At the time of their inspection, the flooding was relatively recent, and
there may have been problematic mould growth that was not yet visible. The application of
anti-microbial wash may have been recommended as a precaution.
AJ (the last builder to inspect the property, seven months after the flood) did not say there
was any mould at the property, and did not make any allowance for mould remediation.
The available information does not establish that the property requires mould remediation.
Therefore, the insurer is not required to pay for mould remediation.
Insurer must consider complainant’s entitlement to accommodation costs
If the complainant pays for alternative accommodation while his home is unliveable, the policy
covers the cost of the accommodation. This cover is limited to 12 months’ accommodation or
$39,323.70 (10% of the sum insured).
None of the builders said whether the home would be unliveable during repairs, or if so, how
long it would be unliveable for. The insurer has not offered to pay for accommodation.
If the complainant pays for accommodation while his home is unliveable due to flood damage
repairs, the insurer must reimburse him for the reasonable cost of the accommodation, up to
the policy limit.
2.2 Is the complainant entitled to any other compensation?
AFCA can award compensation for non-financial loss
Under the AFCA Rules, we can award up to $5,000 compensation for non-financial loss if a
complainant suffered an unusual degree of stress, inconvenience, or delay because an
insurer mishandled a claim.
We will only award this type of compensation if there has been an unusual degree of stress,
inconvenience, or delay. We will not award compensation for the usual amount of
inconvenience involved in making a claim. We will not award compensation for delays caused
by the complainant, or other factors outside the insurer’s control.
Complainant says insurer caused unreasonable delay
The complainant says the insurer took a long time to respond after he lodged the claim. He
says they suffered stress from having to live in the house when it was severely damaged.
The complainant lodged the claim on 13 February 2020. MK did not attend until 29 February
2020, 16 days later. MK did not provide a written report or a scope of works until 18 May
2020, three months after the claim was lodged.
In July 2020, the insurer offered to have MK perform the repairs set out in their scope of
works. However, this scope of works did not cover all of the flood damage at the
complainant’s home.
Determination | Case number: 745139 Page 7 of 8
The complainant suffered a loss in February 2020, and he has not yet been compensated.
This determination awards the complainant interest from 16 March 2020, the date of his
builder’s quote . AFCA considers that if a complainant is entitled to money, and there is a
delay in receiving payment, an award of interest will usually be sufficient to compensate for
the delay.
Complainant says insurer did not perform make-safe
The complainant says the insurer did not offer to perform make-safe work. He says he and
his partner had to remove salt water and sewage from the house with no help from the
insurer.
MK says it offered to perform make-safe work, such as installing drying fans and applying
anti-microbial treatment, but the complainant rejected the offer because he had already done
make-safe work. MK first attended the property 16 days after the claim was lodged. After the
flood, the house needed to be dried out as quickly as possible to prevent further damage. The
complainant could not reasonably have waited 16 days for the insurer to arrange make-safe
work.
The flood was part of the February 2020 East Coast Low, which resulted in thousands of
insurance claims for storm and flood damage. Because of this, the insurer may not have been
able to arrange make-safe work in less than two weeks. However, the insurer could have
offered to reimburse the complainant if he hired someone to perform make-safe work.
The policy cove rs the cost of ‘ emergency repairs and protection necessary to prevent further
loss or damage ’. Because the insurer could not arrange this within a reasonable time, the
complainant and his partner had to do this work themselves.
The complainant has not provided information showing he suffered a financial loss because
the insurer did not perform make-safe work. However, the panel considers the complainant
should be compensated for the stress and inconvenience of having to perform the work
himself.
Complainant entitled to compensation for non-financial loss
The complainant’s house was flooded. This would have been a stressful experience
regardless of how the insurer responded to the claim. However, the panel believes the
complainant suffered additional stress and inconvenience because:
the insurer’s builder did not attend the property for more than two weeks, and did not
provide a report or scope of works for three months
the insurer did not arrange make-safe work
the insurer made settlement offers that were not sufficient to fulfil its policy obligations.
The panel considers it fair for the insurer to pay the complainant compensation for non-
financial loss in the sum of $2,000.
Outcome is fair in the circumstances
The complainant suffered losses because of an event covered under the insurance policy. He
is entitled to be compensated for those losses by the insurer.
CCB’s quote is the best available assessment of the cost of repairs. Therefore, it is fair for the
claim settlement to be based on this quote.
Determination | Case number: 745139 Page 8 of 8
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
determination to the issues that are relevant to the outcome.
A panel determined this matter
Due to the nature of this complaint, we referred it to a panel for determination. The panel
includes:
an ombudsman
a member with significant experience in consumer and small business advocacy
a member with extensive experience in insurance.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information.
If there are conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.