Home / IAG / Determination 744716

Determination 744716

Cyclone roof damage claim settlement amount

FirmIAG
Decided2021-06-07
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$33,646
Non-financial loss—
Amount claimed$92,180
SourceAFCA PDF

Summary

The complainant sought a full roof replacement for Cyclone Debbie damage after the insurer offered $19,073.15 on a cash settlement basis. The panel found the damage was only partly caused by the cyclone, increased the cash settlement to $28,806.14, and ordered reimbursement of the engineer report fee with interest.

Expert evidence did not establish the true extent of cyclone damage, so the panel apportioned the settlement at the mid-point of the two assessments.

Issues

Subjects and remedies

pay claimpay compensationpay interest

Related

All IAG determinations · Find similar determinations

Text of the determination

Determination Case number 744716 Financial firm Insurance Australia Limited Determination | Case number: 744716 Page 2 of 10 Case number: 744716 04 May 2021 1 Determination overview 1.1 Complaint The complainant is represented by (DK). For simplicity, the determination will refer to the complainant and DK as the ‘complainant’. The complainant has a home and contents insurance policy with the financial firm (the insurer). On 6 July 2017, the complainant lodged a claim with the insurer after Cyclone Debbie caused damage to his property on or about 28 March 2017. The insurer assessed and accepted the claim, undertook repairs and closed the claim in March 2018. However, the claim was re-opened in June 2019, after the complainant advised that water had entered the property causing further damage and a large section of the roof required replacement. The insurer has assessed the roof and states that while it does not believe the damage was caused by Cyclone Debbie, it was willing to accept it was possible. Therefore, it offered to resolve the claim on an ex gratia basis for $19,073.15, which assessed its liability based on the complainant ’ s scope of works. The complainant has rejected the insurer’s offer and is seeking $92,179.66 , for a total roof replacement. 1.2 Issues and key findings Is the insurer’s offer fair in all the circumstances? While the insurer has assessed the claim within the terms and conditions of the policy, in the circumstances it is appropriate for the insurer to increase its offer of cash settlement to 31.25% (or $28,806.14) of the complai nant’s Scope of Works. Is the insurer required to pay the complainant ’ s costs? The panel is not satisfied that the complainant was required to obtain professional representation from DK, nor did such representation assist their position. However, the panel is satisfied the engineer report of GG has helped. Therefore, the insurer is not required to pay DK’s professional fees however, it is required to reimburse the complaint the cost of GG’s report fee. The complainant is to provide the insurer with details and confirmation of the amount paid. 1.3 Determination The determination is substantially in favour of the insurer. Determination | Case number: 744716 Page 3 of 10 The insurer is to cash settle the claim in the amount of $28,806.14. The insurer is required to pay interest on this amount, in accordance with the Insurance Contracts Act 1984 (the Act), from 31 March 2020, until the amount is paid. The insurer is to reimburse the complainant the cost of GG’s report and to pay interest from the date the complainant paid for that report. The insurer is not required to take any further action. Determination | Case number: 744716 Page 4 of 10 2 Reasons for determination There has been a full exchange of information between the parties and each party has had the opportunity of addressing the issues in dispute. Due to the nature of the issues involved in this complaint, it has been referred to a panel for determination. The panel includes an Ombudsman, a representative with extensive industry experience and a representative with significant experience as a consumer representative. This determination follows consideration of all the information exchanged. It is based on what is fair in all the circumstances having regard to the relevant legal principles, terms of the policy, good industry practice, codes of practice and prior determinations where applicable. While both parties have made numerous submissions, for the purposes of this determination, commentary has been restricted to those issues which have a direct bearing on the outcome of the complaint. 2.1 Is the insurer’s offer fair in all the circumstances? Onus on the complainant to establish a valid claim Insurance law says the onus is on the complainant to show, on the balance of probabilities, a loss claimed falls within the cover provided by the policy. This is known as establishing a valid claim. If the complainant can establish this, the onus transfers to the insurer to establish it is entitled to decline the claim. The complainant ’s policy provides cover for accidental loss or damage. On 6 July 2017, the complainant lodged a claim with the insurer after Cyclone Debbie caused damage to his property on or about 28 March 2017. The insurer arranged for loss adjuster TB to assess the claim who noted that there was damage to downpipes, an air conditioning unit and a window. The insurer arranged to repair the assessed damage and closed the claim in March 2018. However, the claim was re-opened in June 2019, after the complainant advised that water had entered the property causing further damage and a large section of the roof required replacement. There is no dispute that the damage which occurred during the period of insurance, was both unintended and unexpected and, the insurer acknowledges that some damage to the roof was caused by Cyclone Debbie. Therefore, a valid claim has been established. However, the issue in dispute is the percentage of damage Cyclone Debbie has caused to the roof and trusses and whether the roof requires total replacement. Determination | Case number: 744716 Page 5 of 10 The complainant’s expert s argue the cause of the damage is Cyclone Debbie In February 2019, the complainant provided the insurer with a plumbing report from BP who stated that the roof exterior and trusses of the property had been damaged during Cyclone Debbie. In addition to this report, the complainant also provided a report and quote from building consultant GS dated 22 February 2019 and engineer GG dated 1 June 2020. GG’s report will be addresse d below. GS reported that there was evidence of batten lift in more than 20% of the main house roof, as well as water staining in the lounge room wall and evidence of sagging in the ceiling near the front entry and laundry. GS concluded that due to the batten lift to more than 20% of the main roof, the roof required replacement and upgraded tie-downs. Insurer’s expert indicates not all damage was a result of Cyclone Debbie Following the request to re-open the claim, the insurer appointed assessor CP and engineer JM to report on the damage. CP reported:  the complainant advised since repairs had been carried out water had been entering the property through the ceiling near the entry  inspection of the roof above the affected area showed repairs of some sort had been done to the barge intersection and the flat section of the roof  flashing had been scribed into the steep roof sheet and sits on top of the flat roof barge with fixing that has popped, and the flashing can be lifted  gaps can be seen between the flat barge roof flashing and the flat roof sheet and this is believed to be the water entry point  finally, the roof consists of new roof sheeting which has been retro fitted to the old roof sheeting and capping. CP was of the view that the repairs to the roof may have been a cause of how the water has entered the property and that the repairs paid for by the complainant are considered temporary. Engineer JM was appointed to assess the extent of the batten lift and the extent of damage to the property relating to Cyclone Debbie. In his report, JM observed:  no damage to the timber ceiling boards in the TV room was observed however, minor moisture markings on the walls were present Determination | Case number: 744716 Page 6 of 10  a 5mm gap between a rafter and the roof baton was observed near the ridge above the eastern hall and bathroom however, the rafter was set down 55mm below the top of the ridge rafter which was only 35mm thick which resulted in a discrepancy between the rafter and the underside of the baton  two other gapes were present betwee n the baton and rafter above the kitchen. Additional timbers were also present a t this locating which indicate the framework did not neatly align at the time of construct  small gaps between a roof batten and rafter were also found at six locations above the TV room JM concludes the water entry into the TV room is likely due to the low pitch, the gaps between the baton and trust are because of wind up-lift, however, he does not consider this to be recent. In addition, JM recommended the ceiling in the laundry be removed as it is in danger of collapse. While JM was of the view the damage was not caused by Cyclone Debbie, JM advised if the benefit of doubt was given to this event causing the damage, then the affected area is limited to 46m2 (or 17.7% of the total roof area) and not the entire roof trusses. JM repeats his position with respect to the extent of the damage in two supplementary reports dated 10 March 2020 and 10 July 2020. The complaint’s engineer disputes insurer’s assessment The complainant engaged engineer (GG) who provided a report in response to JM’s findings and states that the roof has suffered damage during Cyclone Debbie. GG states the area which was damaged due to Cyclone Debbie includes the front area of the TV room, the front area of the roof over the kitchen and the front hip area over the bathroom. In his report dated 1 June 2020, GG notes:  evidence of high wind and wind blow rain entering the roof cavity as well as water staining on the timber ceiling.  roof battens have appeared to have lifted off the supporting timber members and are misalignment of original roof and prefabricated trusses  separation along the laps of the colouring roof has occurred due to high winds associated with Cyclone Debbie  the damaged area of the roof is 108m2 or 41% of the total roof area which would instigate a Council building approval for a full main roof replacement . While GG agrees with JM’s findings, the main area in dispute is the area which GG and JM consider to be damage because of Cyclone Debbie. Determination | Case number: 744716 Page 7 of 10 Expert evidence indicates apportionment is warranted to resolve the complaint Having reviewed the exchanged evidence, the panel accepts Cyclone Debbie was not entirely the cause of the damage to the roof and associated structure. However, upon review of the reports and exchanged parties, the panel is not persuaded either party has adequately established the true amount of damage caused to the complainant’s roof by Cyclone Debbie. While both parties agree that there is damage, the amount of damage remains in dispute. The insurer has assessed the damage to be approximately 17.7% while the complainant’s engineer is of the view it is more likely to be 41%. Neither party has assessed the roof as requiring total replacement. Further, there is no evidence to establish the roof is required to be replaced because of the damage sustained during Cyclone Debbie. In the interest of bringing finality to the complaint, the panel is persuaded the insurer should increase its settlement to 31.25 % of the complainant’s scope of works. This is the mid-point of the two assessments. The panel is persuaded this is fair given the lack of persuasive evidence provided by the parties. Therefore, the cash settlement for the claim related damage is $28,806.14. The insurer is required to pay interest upon this amount, in accordance with the Act, from 31 March 2020, until the date of payment. 2.2 Is the insurer required to pay the complainants professional fees? The complainant has requested payment of his costs The complainant engaged the assistance of DK prior to lodging the complaint with AFCA. The complainant also engaged engineer GG to comment on the condition of the roof and cyclone damage. When considering whether a complainant (or its representative) should receive reimbursement for professional fees AFCA considers:  the complexity of the issues  whether the complainant reasonably needed advice or assistance  whether the complainant incurred costs because they genuinely required expert assistance and it assisted the compla inant’s position. The panel has read the submissions of DK as well as the engineer report of GG. Determination | Case number: 744716 Page 8 of 10 The panel is not satisfied the submissions of DK were reasonably required by the complainant nor do they assist with the complaint resolution or advance the complainant ’ s position. However, the panel is satisfied that GG’s report (which cost $4,840) has assisted to the extent it provides some commentary of the damage to the roof and detail around the likely requirement of Council building approval. Therefore, the insurer is not required to pay DK’s professional fees however, the insurer is required to reimburse the complainant the cost of GG ’s report. The complainant is to provide the insurer with proof of payment. The insurer is to pay interest on the amount, in accordance with the Act, from the date the complainant paid for the report, until reimbursement is made. Determination | Case number: 744716 Page 9 of 10 3 Supporting information 3.1 Process AFCA’s approach to this complaint This complaint has been determined based on what is fair in all the circumstances, having regard to the legal principles, applicable industry codes or guidance, good industry practice and previous decisions of AFCA or its predecessor schemes (which are not binding). A full exchange of the relevant information has taken place between the respective parties. Each party has had the opportunity of addressing any issues raised. All the provided information has been reviewed and considered. The parties have raised numerous issues in their submissions to AFCA. However, commentary in this determination is restricted to those issues considered relevant to the outcome. This matter was determined by a panel Due to the nature of this dispute, it has been referred to a panel for determination. The panel comprises the lead ombudsman, a member with significant experience in consumer and small business advocacy and a member with extensive experience in insurance. How we assess complaints AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider available documents, the recollections of the parties, and all relevant circumstances. We give more weight to documents created at the time the events occurred. If there is no relevant documentation, we will decide what is most likely to have occurred based on the information provided to us. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. 3.2 Relevant Policy Terms Page Product Di sclosure Statement 14 Section 1 – Your Buildings and Contents Accidental damage cover What is covered Your Buildings and/or your Cont ents as set out on your Policy Schedule are covered if they are accidentally destroyed, accidentally lost or accidentally damaged. They are covered only if you own them, or are liable for their destruction, loss or damage . Determination | Case number: 744716 Page 10 of 10 Page Product Di sclosure Statement … We will cover your Buildings and/or your Cont ents as set out on your Policy Schedule for accidental destruction, accidental loss or accidental damage 26 How we pay a claim for your Buildings When destruction, loss or damage occurs to your Buildings, we will pay the cost of rebuilding your Buildi ngs, or repairing the damage portions of your Buildings, to the same condition as when they were new. We will also pay any additional costs required for your Buildings to comply with government or loc al authority bylaws. We will not however pay these addi tional costs if you were required to comply with these bylaws, and had not done so, before the destruction, loss or damage occurred. The most that we will pay for costs required for your Buildings to comply with requirements of an authority in any one (1) period of insurance is $25,000.