Text of the determination
Determination
Case number 743391
Financial firm La Trobe Financial Asset Management Limited
Determination | Case number: 743391 Page 2 of 10
Case number: 743391 10 January 2023
1 Determination overview
1.1 Complaint
In May and June 2016, the financial firm (lender) approved two commercial loans ($2,788,100
and $142,400) to the borrower, S Company (now deregistered). The loan funds were
provided to finance and develop 11 multi residential units at G situated in Queensland (the
development). The complainant provided guarantees for the facilities, along with two other
guarantors (Mr L and Mrs L). Construction was to be completed by another entity as builder
(M Company). The loans were fully drawn by way of progress payments made by the lender
to M Company which completed construction of the development.
S Company failed to repay the loans upon expiry and the lender eventually repossessed the
unsold units in the development and sold those units. The lender is pursuing the complainant
for the shortfall debt owing under the guarantees.
The complaint is about whether:
the guarantees provided by complainant for the loans are enforceable
the lender met its obligations in relation to progress payments
the lender met its obligations to the lender after the loan expired including as a mortgagee
in possession of the units.
On 4 August 2022, an AFCA case manager issued a recommendation on the issues in
dispute. The recommendation was in the lender ’s favour. A copy of the recommendation is
attached to this determination. The complainant rejected the recommendation including for
the reasons set out in section 2 below.
1.2 Issues and key findings
Were the findings in the recommendation correct?
Based on all the available information, the findings in the recommendation were correct and
are adopted in this determination. I have considered all the material submitted by the parties
including the further submissions provided after the recommendation.
Do the complainant’s further submissions change the outcome?
The complainant’s further submissions do not change the outcome for the reasons set out at
section 2.2 below. It has not been established that the lender made an error and there is no
basis to set aside the complainant’s guarantee. AFCA is only able to review the obligations as
between the lender and the complainant. AFCA is not able to review the conduct of any third
party or the question of liability as between guarantors or respective contribution rights.
Why is the outcome fair?
The outcome is fair because the lender has made no error and the complainant remains liable
in accordance with the guarantees she provided for the commercial loan agreements.
Determination | Case number: 743391 Page 3 of 10
1.3 Determination
This determination is in favour of the lender. I agree with the reasons for the recommendation
and the recommended outcome.
The complainant remains liable for the outstanding amounts owing under the guarantees.
As it appears the complainant is experiencing financial difficulty, she may wish to obtain
advice about her options. If the complainant provides the lender with a current Statement of
Financial Position (SOFP) including any assets owned, and a repayment proposal for the
outstanding debt, the lender should work with the complainant to try and agree to a
repayment arrangement that would see the debt repaid. If the complainant does not provide a
SOFP and a payment proposal or if the parties are not able to agree on a repayment
arrangement, the lender will be entitled to continue recovery action in respect of the
outstanding debt in accordance with the terms and conditions of the guarantees.
Determination | Case number: 743391 Page 4 of 10
2 Reasons for determination
2.1 Were the findings in the recommendation correct?
The recommendation was correct
I am satisfied that the recommendation contains an accurate summary of the complaint, the
issues to be determined, any applicable paragraphs of the rules and any relevant law.
I agree with the case manager’s reason and findings in the recommendation and a dopt them
as part of this determination. As I have attached the recommendation to this determination, I
have not repeated those reasons and findings.
I have considered all the available information including the further submissions made after
the recommendation, but these do not change the outcome of the complaint. I make the
following additional comments on the issues the complainant raised which I hope will assist
them further understand the outcome.
2.2 Do the complainant ’s further submissions change the
outcome?
In rejecting the recommendation, the complainant made a number of submissions that had
previously been raised and also including that:
the complainant has an equitable right to contribution from co-guarantors because the
guarantees provided ‘joint and several liabilities’ . As the guarantors have co-ordinate
liabilities, the complainant is not liable for the entire outstanding amounts owing under the
guarantees and the lender should not fix one guarantor with the obligation as it is unfair
the lender should not have released Mr L or Mrs L from liability as guarantors
if the lender has released Mrs L from liability, the complainant should be given the same
opportunity to be released to the same extent for the same consideration as Mrs L
provided. Therefore, the lender should release the complainant from liability upon payment
of the same amount as Mrs L paid to be released
the lender did not meet its obligations as a mortgagee in possession because:
> it did not give the complainant the opportunity to sell the remaining units of the
development in November 2018 and prevented the borrower from entering into
contracts of sale for the remaining units
> it failed to assist in the sale of units in a declining market
> it subsequently sold the remaining units a year later for less than the sum of the
November 2018 contracts of sale, and
> the Notice of Exercise of Power of Sale issued by the lender was misleading and the
complaint relied upon it to her detriment by deploying funds to market the remaining
units.
The complainant’s further submissions do not change the outcome for the reasons set out
below, in summary because:
the guarantees placed joint and several liabilities upon the co-guarantors for obligations
owed to the lender. The lender is entitled to enforce its contractual rights in accordance
with the provisions of the guarantees against any of the guarantors
t he complainant’s rights to co-contribution from other guarantors are not affected by this
decision and even if contribution rights exist, that is not a matter that AFCA can decide
upon. AFCA is only able to review the obligations as between the lender and the
Determination | Case number: 743391 Page 5 of 10
complainant that lodged a complaint. AFCA is not a court and is not able to review the
conduct of any third party or the question of liability as between guarantors or respective
contribution rights or make any declaration in relation to those rights
Without a valid basis, AFCA cannot direct the lender as to how to enforce it contractual
rights under the guarantees. I note that the lender has confirmed that it has not released
Mr L from liability
If the lender and a co-guarantor enter into an agreement, I do not consider that operates to
release the complainant of her obligations or require the lender to offer the same terms to
other guarantors in the circumstances
the lender met its obligations as a mortgagee in possession for the reasons set out in the
recommendation because it allowed the complainant sufficient time to sell the remaining
units after expiry of the loans in June 2017. The lender acted reasonably in progressing to
auction in December 2018. AFCA is not able to speculate on what may have occurred if
the lender had taken another course of action in November 2018. I consider that the lender
met its obligations to take reasonable care to obtain market value for the units for the
reasons set out in the recommendation
the Notice of Exercise of Power of Sale was not misleading and it has not been shown that
the complainant relied upon any misleading content to her detriment.
The guarantors are jointly and severally liable
I have reviewed the two guarantee documents the complainant signed along with the other
guarantors on 18 May 2016. The documents are identical except for the loan amounts
($2,788,100 and $142,400). The provisions in the documents relevantly state:
1. Definitions and Interpretation
…..
Debt means all money (and where the context admits any part of that money) which the
Borrower whether directly or indirectly or contingently or otherwise at any time and from
time to time is or becomes liable either alone or jointly or severally to pay the Mortgagee
on any account in without limitation:
…..
Guarantee means the guarantee and indemnity contained in this guarantee
Guarantor means each of the guarantors named as parties to this guarantee and
indemnity, jointly and severally
Guarantor’s Security means all or and securities which the Mortgagee now or at any
time whilst this guarantee is in for holds over any Guarantor’s propert y or assets and
whether given in relation to the Debt or otherwise, unless the security by its express terms
does not apply to this Guarantee or is expressly excluded;
…..
3. Continuing Guarantee
This Guarantee is continuing and irrevocable and the obligations of the Guarantor are
absolute and unconditional in all circumstances. The Mortgagee is not obliged to take any
action against any person or under any security prior to claiming from the Guarantor.
The joint and several liability provisions show the complainant and co-guarantors are jointly
liable for the whole amounts owing if the borrower fails to repay the amount owed upon
Determination | Case number: 743391 Page 6 of 10
demand or expiry, and each of them are severally liable for the whole amounts owing under
the guarantees.
The effect of the provisions above is to entitle the lender to exercise its rights under the
guarantees against one, some or all, of the guarantors and against some or all of the security
provided by the guarantors to satisfy the outstanding amounts owing under the guarantees
and indemnities. That is a commercial decision for the lender which AFCA is not able to
review.
I am satisfied the lender was entitled to exercise its contractual rights set out in the
guarantees against any or all the co-guarantors due to the joint and several provision and the
complainant remains liable for outstanding amounts owing under the guarantees.
The complainant’s right to contribution does not change the outcome
The complaint claims she is not liable for all outstanding amounts owing under the
guarantees, including because:
the lender is not entitled to exercise its rights solely against her as its unfair
the guarantors are jointly and severally liable, so have co-ordinate liabilities and a common
obligation to contribute equally
the complainant has a right to contribution from co-guarantors that cannot be defeated by
an act of the lender.
As set out above, the lender is entitled to exercises its contractual rights set out in the
guarantees to recover outstanding amounts owing under the guarantees from one, some or
all, of the guarantors.
T he complainant’s rights to co-contribution from other guarantors are not affected by this
decision and, even though the rights may exist, that is not a matter that AFCA can decide
upon as it involves parties other than the lender and complainant.
AFCA not a Court and is only able to review the obligations as between the lender and the
complainant that lodged the AFCA complaint. Therefore, AFCA is not able to review the
conduct of any third party or the question of liability as between co-guarantors or respective
contribution rights. AFCA is not able to provide any declaration or decision in relation to the
guarantors’ obligations as between themselv es.
The fact that the complainant has rights to contribution from other guarantors does not
change the lender’s right to pursue her under the guarantee. Without a valid basis, AFCA
cannot direct the lender as to how to enforce it contractual rights under the guarantees. The
issues raised by the complainant about co-contribution from the other guarantors are more
appropriately dealt with by a Court.
I accept the guarantee documents show the complainant and the co-guarantors are jointly
and severally liable for the guaranteed amounts and became liable to pay the outstanding
amounts owing under the guarantees when the lender made demands which remained
unpaid. I have reviewed the authorities the parties relied upon in their submissions and the
law regarding the right to contribution by co-guarantors, but that does not alter the conclusion
that the lender may enforce the complainant’s guarantees.
A settlement with another guarantor does not affect this outcome
The complainant says that any settlement with a co-guarantor should mean that the
complainant be given the same opportunity to be released of liability for the same
consideration and/or her liability should be likewise reduced. To support her claims, the
Determination | Case number: 743391 Page 7 of 10
complainant refers to an agreement between the lender and a co-guarantor (Mrs L) in another
AFCA complainant in January 2020. I note that the lender has confirmed that it has not
released the other guarantor, Mr L, from liability.
As stated above in relation to the issue of co-contribution, AFCA is not determining in this
decision the question of liability as between guarantors. This decision deals solely with the
issue of whether the lender can enforce the guarantee as against the complainant. I make the
following remarks to assist the complainant to understand the reasons why this does not
progress her claims at AFCA.
The provisions of the guarantees relevantly state:
4. Non-wavier
This Guarantee will not be abrogated, modified, prejudiced, affected or considered as
wholly or partially discharged by any one or more of:
…..
(b) any compounding compromise release abandonment waiver variation relinquishment
or renewal of any rights of the Mortgagee against the Borrower or any other person;
…..
(n) anything else.
5. Principal obligations
…..
5.4 The Mortgagee may release or compromise the obligations of any one or more
Guarantors, without affecting the liability of the remaining Guarantors.
The provisions reserve the lender’s rights under the guarantees against all guarantors despite
any release or compromise of obligations owing by another guarantor. I accept the provisions
have this effect and were agreed by the parties. I do not consider the provision affects a right
to co-contribution.
I also note that the settlement agreement referred to by the complainant expressly reserved
the lender’s rights against the co -guarantors (including the complainant). A clause specifically
stated the settlement agreement did not extinguish co- guarantors’ liabilities under the
guarantees. I accept the agreement includes a promise by the lender not to pursue Mrs L
under the guarantees upon certain conditions.
I consider the lender is entitled to pursue the complainant under the guarantees despite the
objections raised because:
the provisions of the guarantees reserved (as set out above) the lender ’ s rights despite
any release or compromise of obligations owing by another guarantor
the settlement agreement included a promise not to sue Mrs L but does not affect the
lender’s rights in respect to other guarantors
there is no obligation on the lender to offer the same terms to all other guarantors
the issue of co-contribution is not necessarily affected by the settlement, but it is a matter
that is more appropriately raised in a Court for the reasons set out above.
Determination | Case number: 743391 Page 8 of 10
The lender met its mortgagee in possession obligations
The complainant repeated her claim that the lender denied the borrower the opportunity to
sell the remaining units by preventing the borrower from entering the development or
finalising contracts of sale, in particular:
on 8 November 2018, unconditional contracts of sale which would have resulted in the
loans balances being paid out with a surplus remaining
on 11 December 2018, conditional contracts of sale which would have resulted in the
outstanding loan balance to less than $100,000.
The complainant also claims that on 8 November 2018, the lender issued a Notice of Power
of Sale which was misleading and caused her to believe she had another 30 days to remedy
the default under the commercial loan agreements, when the lender in fact took possession
and prevented access prior to expiry of the 30 days. As a result, she says she deployed funds
to market the development which benefitted the lender.
I have reviewed all submissions provided by parties, but the complainant has not established
that the lender made any error leading to loss. For the reasons set out in the
recommendation, I consider the lender provided plenty of time for the borrower after June
2017 in the following 12 months to sell units or refinance the debt. I make the following
remarks to assist the complainant to understand why AFCA is unable to find for her claims.
I agree with the findings made in the recommendation that the lender acted reasonably as a
mortgagee in possession, including for all the reasons set out in the recommendation. In
addition, I note that:
the borrower was required to meets it obligations to repay the amounts owing under the
commercial loan agreements within one year of settlement and the loan terms expired on
17 June 2017. The information shows the borrower was in default of its obligations under
the agreements and was obliged to repay the loans from 17 June 2017
the borrower had only sold two of the development units in the following 12 months after
expiry, prompting the lender to issue the notices of Intention to Repossess on 29 June
2018 and Power of Sale on 8 November 2018 and the lender was not obliged to provide
more time to the borrower
an independent valuation report dated 16 October 2018 shows there was a general
oversupply in the area of the type of unit offered by the development. The independent
valuation report supports the reasons why the borrower and subsequently the lender
encountered difficulties selling the remaining development units
the complainant has not provided information to support an unconditional offer of
$3,070,00 being received for the remaining units in or about September 2018
the Notice of Possession issued by the lender to the borrower on 8 November 2018 is not
misleading. It clearly stated the borrower had 30-days to remedy the default or the lender
would exercise the power of sale provided to it by section 84 of Property Law Act 1974
(Qld)
the complainant has not provided information to show what funds she deployed to market
the development in 2018 or how it represents a loss or how the lender should be held
liable for those costs. However, even accepting the complainant’s claim she deployed
funds to market the development in 2018 then I accept that was her choice to do so and it
has not been shown it was due to any misleading conduct by the lender
the complainant has not provided any information or copies of the proposed unconditional
contracts of sale for the remaining units to support any unconditional offer of $2,950,000
made by the prospective buyer on 8 November 2018. The information does not support the
lender preventing the borrower from entering into the unconditional contracts of sale for the
Determination | Case number: 743391 Page 9 of 10
remaining units. In addition, it is speculative to say that the prospective purchaser would
have avoided due diligence and signed unconditional contracts if they had inspected the
property in November 2018
conditional contracts for sale the lender received on 11 December 2018 for $2,540,000
were below the market valuation of $3,225,000 provided by the October independent
valuation report. There is no legal requirement for the lender to accept offers below the
valuer’s opinion on market value as mortgagee in possession. The lender as mortgage in
possession was legally required to take all reasonable care to secure market value for
property to discharge its obligations. An appropriate course in the circumstances was to
proceed to auction to test the market
the lender allowed the borrower sufficient time to refinance the loans and allowed the
borrower supervised access to the development to sell the remaining units despite having
taken vacant possession.
Ultimately, the available information supports the borrower ’ s attempt to refinance the loans
did not proceed and unconditional offers made by the same prospective buyer for the
remaining units either did not materialise or were made at below market value.
Based on all the available information, I am satisfied the information shows the lender met is
obligations as a mortgage in possession.
2.3 Why is the outcome fair?
The outcome is fair
The outcome is fair because in relation to the matters that AFCA can review, the lender has
not made any error or breached an obligation causing the complainant loss. Therefore, the
complainant remains bound by the guarantees she provided for the commercial loan
agreements.
Determination | Case number: 743391 Page 10 of 10
3 Supporting information
3.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has determined this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted our
determination to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information. If there are conflicting recollections and these are evenly weighted, we may find
that a claim cannot be established.
Recommendation
Case number 743391
Financial firm La Trobe Financial Asset Management Limited
Recommendation | Case number: 743391 Page 1 of 49
Case number: 743391 4 August 2022
4 Recommendation overview
4.1 Complaint
In May and June 2016, the financial firm (lender) approved two commercial loans ($2,788,100
and $142,400) to the borrower S Company (now deregistered). The loan funds were provided
to finance and develop 11 multi residential units at G situated in Queensland (the
development). The complainant along with two others provided guarantees for the facilities.
Construction was completed by another entity (M Company). The loans were fully drawn by
way of progress payments made by the lender to M Company who completed construction of
the development.
The complainant claims the guarantees she provided for the loans are not enforceable
because:
she did not receive independent legal advice and did not understand the terms of the
guarantees when she signed them
she was unduly influenced by the other guarantors when she signed the guarantees
the lender accepted progress payment requests signed by only one director of the borrower
contrary to the Corporations Act 2001.
The complainant claims the lender failed to meet its mortgagee in possession obligations
because the lender:
refused to provide a reasonable period of time to sell the remainder of the units after
completion of the development
took possession of the development and exercised the power of sale without appropriately
issuing notices
took possession of the development when negotiations were still being conducted to sell
units and refused access to the development for inspections causing additional possession
cost of $20,560.35
rejected offers for remaining units made by a prospective buyer for over $3 million and later
sold the development units for a net sum of $2,687,500
the lender acted unconscionably in selling the development, it dismissed the agents
managing the sale, it failed to instruct the new agent in a timely manner and failed to
employ sufficient and effective marketing strategies
the lender failed to comply with their duty to act in good faith or reasonably in selling the
development.
4.2 Issues and key findings
Are the guarantees enforceable?
For the reasons set out below the guarantees are enforceable.
Did the lender act appropriately by making progress payments directly to M
Company?
For the reasons set out below lender acted appropriately when it made progress payment
requests to M Company.
Recommendation | Case number: 743391 Page 2 of 49
Did the financial firm meet its mortgage in possession obligations?
For the reasons set out below the financial firm met its mortgagee in possession obligations.
Why is the outcome fair?
The outcome is fair because the complainant’s claims are not made out and the lender has
not made any error. Therefore, it is appropriate that the complainant remain liable under the
guarantee and indemnities she provided for each commercial loan facility.
4.3 Recommendation
This recommendation is in favour of the lender it is not required to compensate the
complainant or take any further action.
The complainant remains liable for the outstanding debts, $562,684.76 (account ending 3683)
and $309,199.76 (account ending 3691) as at 22 July 2022.
If the complainant is experiencing financial difficulty:
she should provide the lender with a current Statement of Financial Position (SOFP) and a
repayment proposal for the outstanding debt
the lender should work with the complainant to agree to a repayment arrangement that
would see the debt repaid over a reasonable period
if the complainant does not provide a SOFP and a payment proposal or if she is not able to
agree on a repayment arrangement, the lender will be entitled to continue recovery action
in respect of the outstanding debt in accordance with the terms and conditions of the
account.
Recommendation | Case number: 743391 Page 3 of 49
5 Reasons for recommendation
5.1 Are the guarantees enforceable?
For the reasons set out below the guarantees are enforceable.
The complainant was a director and shareholder of the borrower
The complainant claims that she has no previous business experience, and this impacted her
ability to understand documents she signed.
The lender has provided a copy of the company enquiry report it obtained on 31 March 2016
to assess the loan application by the borrower (S Company).
The report shows the complainant was appointed as secretary and director of the borrower on
27 March 2013.
At the time of the loan application (March 2016) the enquiry report confirms the complaint was
an equal share holder along with the other guarantors (who were also directors) of the
borrower.
The lender also obtained a copy of the complainant’s consumer and commercial credit report
which shows the complaint:
held the position of director for two other companies at the time of the loan application
had previously held the position of director at the M Company in 2012.
The complainant signed other documents
The complainant does not raise any issues with the signing of other documents, except to say
that she did not understand the commercial loan agreements and did not receive a benefit of
the loans.
As set out above, at the time of signing the commercial loan agreements the complainant was
director and equal shareholder of the borrower (and a current director of two other
companies) and received a benefit of loan funds.
The information provided by parties shows the complainant signed the following documents:
on 7 March 2016, the loan application on behalf of the applicant and as guarantor
on 17 May 2016, the Commercial Loan Agreement for $2,788,100 as director of the
borrower and the Guarantor’s Acknowledgement
on 8 June 2016, the General Security – All Asset Charge as director of the borrower
on 9 June 2016, the Loan Offer Letter for $142,400 as secretary of the borrower and as
guarantor
on 22 June 2016, the Financiers Development Deed as director of the borrower.
The loan application form (page 4) stated the complainant had been employed as general
manager of the M Company for four years and provided an acknowledgment to say it is true
and correct.
The commercial loan agreement and guarantor’s acknowledgement was signed by the
complainant on 17 May 2016 and was signed by the other directors and guarantors on 18
May 2016 and separately witnessed. The guarantor’s acknowledgement stated:
We acknowledge:
Recommendation | Case number: 743391 Page 4 of 49
the terms of the financial accommodation offered to the Borrower and give the
undertakings mentioned above; and
that the Lender recommended we obtain independent legal and financial
advice on our obligations.
The commercial loan agreement borr ower’s acceptance stated:
We recommend You obtain legal advice from your solicitor and financial advice from
Your finance advisor before signing this Loan Contract.
Before you sign this Loan Contract you should read and fully understand the attached
COMMERCIAL LOAN TERM which forms part of this Loan Contract.
…
The information shows the complainant signed other binding documents in varying capacities
which she does not dispute.
The complainant was advised to seek legal advice
The complainant says that she did not receive independent legal advice before signing the
guarantee.
Although it is a requirement for a lender to give a prospective guarantor time to obtain
independent legal advice, it is not a requirement that a lender insist a prospective guarantor
obtain legal advice.
The two guarantees signed by the complainant on 18 May 2016 have a warning box
immediately above the signature of the guarantor on the signing page in the guarantee which
stated:
The Certificate from the Guarantor’s solicitor relating to execution of the Guarantee and
Indemnity below the complainant’s signature stated:
I certify that I am a legal practitioner instructed and employed by the Guarantor
independently of the Mortgagee.
I certify that I explained the effect of this guarantee and indemnity to the Guarantor who
appear d to be aware of and understand the nature and effect of the obligations of the
Recommendation | Case number: 743391 Page 5 of 49
Guarantor under this guarantee and indemnity, and executed it in my presence.
The complainant also signed a Certificate and Acknowledgement from Guarantors for both
Guarantees on 18 May 2016 along with the other guarantors which stated:
The Mortgagee has drawn my/our attention to the warning printed on the cover of this
guarantee and indemnity, and in particular the recommendation that legal and financial
advice should be obtained before signing it.
I am satisfied that I am fully aware of the nature of the document and of the risks
associated with signing it. I do not regard the obtaining of legal or financial advice as
necessary and I prefer to proceed without it.
I declare that I am executing this guarantee and indemnity voluntarily.
The written warnings made it clear that there are financial risks in signing the guarantee. In
addition, the notices included that the complainant should seek legal and financial advice on
the effect of the guarantee before signing it, and they can refuse to sign the guarantee.
The information shows the complainant received independent legal advice and the lender
was entitled to accept she did based on the documentation which was certified by a solicitor.
The lender was not on notice of the undue influence
The complainant claims she was unduly influenced by the other guarantors to sign the
guarantee and indemnity document.
However, the complainant has not provided any specific details of what she says occurred or
provided any information to support this claim.
The lender was first notified of this claim on 11 March 2020. There is no information to
support the lender should have been aware that the complainant was unduly influenced when
she signed the guarantee documentation.
The information supports the complainant received legal advice about signing the guarantee
documents. Based on this, the lender was entitled to accept the guarantee documents signed
by the complaint.
The lender appropriately made progress payments directly to M Company
The complainant says the lender acted imprudently and without her authority when it directly
paid progress payments to the builder, M Company. The complainant says the progress
payment requests were not signed in accordance with section 127 (1) of the Corporations Act
2001 (the Act). The complainant’s claim is tha t two directors of S Company were required to
sign the progress payment requests when only one signed.
The lender says the progress payment requests were executed in accordance with section
127 (1) of the Act and points to section 127 (4) which does not limit the ways in which a
company may execute a document and clause 38.2 of the Commercial Loan Agreement
which stated that:
In addition any one of You can do anything in relation to this Loan Contract or any
Collateral Security even if You advise us that both or all of You must act jointly.
Recommendation | Case number: 743391 Page 6 of 49
The progress payment requests to the lender were signed by a director (and co-guarantor) of
the S Company who was also the sole director and secretary of the M Company.
I accept the lender acted appropriately because:
section 127 of the Corporations Act 2001 provides methods for execution of a deed or
agreement by a company. The progress payment requests were not intended to be
executed as a deed or an agreement and were a written request for periodic loan
drawdown to the lender and for the benefit of the lender being able to manage payments in
accordance with the Commercial Loan Agreement, Letter of Offer and Financiers
Development Deed (FDD)
the Commercial Loan Agreement was executed in accordance with section 127 of the
Corporations Act 2001. Clause 12 defined a ‘Progress Claim’ as a written request for Loan
Draw meeting the requirements provided by the lender which included direct payment to
the builder. Clause 15 stated that Progress Claims must be submitted in writing at intervals
pre-agreed and in accordance with Project Documentation and Progress Payments were
to be made directly to the building contractor and the lender reserved the right not to make
progress payment if anything happens which adversely affects the value of the mortgaged
property of if works are not proceeding satisfactorily. Key excerpts of the Agreement are
set out at section 3.2 below
the Letter of Offer was executed in accordance with section 127 of the Corporations Act
2001 . General condition 10 of the letter of offer states that, progress payments will be
determined by the lender’s valuer and may differ from the builder’s progress payment
claim. General condition 11 stated, the lender would advance the loan amount
progressively and when it sees fit to assist construction but was under no obligation to
make advances if anything happens which affects the security property or works are not
proceeding satisfactorily. Key excerpts of the Letter are set out at section 3.2 below
S Company, M Company and the lender all signed a Financiers Development Deed
executed in accordance with section 127 of the Corporations Act 2001 . The parties to deed
acknowledged that S Company was the developer and M Company was the builder and
the lender would only fund costs of construction on a cost to complete basis certified by a
Quantity Surveyor. A lender requiring regular Quantity Surveyor (QS) reports is a common
provision in development finance and is to assist the lender’s ongoing assessment of its
credit risk. Key excerpts from the Deed are set out at section 3.2 below
the Financiers Development Deed specifically stated that the lender would only pay M
Company progress payment requests after it obtained QS reports confirming construction
was proceeding. The lender adopted this process when it released progress payment
request to M Company. A summary of the QS reports is set out at section 3.3 below. I am
satisfied that S Company received the benefit from the release of the progress payments
even though the complainant did not sign the requests because the payments were made
to M Company that the S Company for services genuinely received and was contractually
bound to pay M Company for in any event
the information does not show that the complainant ever complained to the lender and the
times progress payments were made that she did not agree with the payments being made
to M Company by the lender for the services provided to S Company.
Recommendation | Case number: 743391 Page 7 of 49
5.2 Did the financial firm meet its mortgagee in possession
obligations?
The lender had obligations as mortgagee in possession
A mortgagee exercising a power of sale in Queensland is obliged by section 85 of the
Property Law Act 1974-1986 (Qld) “to take reasonable care to ensure that the property is sold
at the market value” .
In addition, a mortgagee is obliged to comply with the common law duty to act in good faith,
that is to act honestly and not fraudulently in the sale process.
The statutory and common law duties are owed to the mortgagor and owed to the guarantor.
Whether or not the mortgagee complies with the section 85 duty is a question of fact. In order
to assess this question I have reviewed all available information regarding the sale and each
step in the sale process. Of particular relevance in this case are the following matters:
advertisement of the units
improvements to the development before sale
sale of the remaining units by auction or private treaty
sale of the remaining units for market value.
The lender provided reasonable time for the borrower to sell the units
The complainant says that the lender refused to provide reasonable time for the borrower to
sell the remaining nine units in the development and refused to enter into a deed of
forbearance.
The information, in summary, shows:
on 17 June 2017 the loan terms expired
on 24 August 2017, the lender informed the directors (including the complainant) of the
borrower that the property valuation was short, and the loan term could not be renewed,
and the directors agreed to be charged the late payment fees
on 29 January 2018, the lender contacted the directors (including the complainant) about a
payment of $8,013 required to meet the shortfall of the interest budget
on 12 February 2018, the lender received an email from the borrower advising that three
units had sold, and the interest payments would be brought up-to-date immediately
on 21 February 2018, the lender sent an email to a director of the borrower advising that it
would not commence recovery action provided that monthly repayments were met, and it
was provided details about any sales or refinance and updated about construction
progress and discharge
on 4 April 2018, the lender received an email from property management company on
behalf of the borrower which stated it had accepted an offer from another lender to
refinance and would settle in two to three weeks (refinance did not proceed)
on 3 May 2018, the lender says it received a request from the complainant requesting it
forbear for 90 days to allow the sale of the remaining units by auction
on 29 June 2018, t he lender’s lawyers sent the borrower a Notice of Default, Demand for
Payment and Notice of Intention to Repossess
on 11 July 2018, the borrower’s lawyer emailed the lender’s lawyer acknowledging the
default and informed the borrower was committed to selling the remaining units, had spent
$30,000 on advertising, had been let down by a number of brokers regarding refinance
and requested the lender enter into a deed of forbearance for a 6-month period
Recommendation | Case number: 743391 Page 8 of 49
on 12 July 2018, the lender says the borrower informed it that it would not be refinancing
because it did not want to incur a $100,000 brokerage fee.
The information shows the lender provided reasonable time for the borrower to sell the
remaining units or refinance. There was no obligation or requirement for the lender to enter a
deed of forbearance in the circumstances where only two of the development units had sold
(in May 2018) at the time of the request and the loan terms had expired over 12 months ago
(June 2017). The lender was entitled to mitigate its risk because the borrower had defaulted
under the loan agreements.
The lender notified the borrower prior to taking possession and exercising the
power of sale
The complainant says the lender took possession of the development without reasonable
notice because it issued the Notice of Possession and the Notice of Power of Sale at the
same time and did not provide the 30-day statutory period.
On 29 June 2018, the lender’s lawyer sent a letter to the borrower enclosing:
a Notice of Default for repayments ($208,610.30 and $8,046.40)
a Demand for Payment of loans ($2,253,542.15 and $158,481.67)
a Notice of Intention to Repossess units 2 to 10 if defaults were not rectified in 7-days.
On 09 August 2018, the lender took vacant possession of the development.
On 07 November 2018, the lender’s lawyers sent a letter to the borrower informing that as
defaults has not been rectified it had taken possession of the properties as per the notice
provided on 29 June 2018 and would no longer allow the borrower access to the properties.
On 08 November 2018, the lender’s lawyer sent a letter to the borrower enclosing a Notice of
Exercise of Power of Sale under Section 84 Property Law Act 1974-1986 (Qld) notifying the
borrower was required to remedy the default within 30 days by paying the amounts
outstanding under the loans ($2,591,917.75).
Section 84 Property Law Act 1974 -1986 (Qld) required the mortgagee to serve notice on the
mortgagor to remedy the default within 30 days prior to being able to exercise the power of
sale under the section.
The information shows the borrower did not remedy the default when the lender issued the
Notice of Exercise of Power of Sale and the lender first accepted an offer for a unit in March
2019.
The information shows the lender issued notices appropriately and in accordance with
statutory obligations.
The lender allowed the borrower access to the development to sell the units
The complainant says the lender refused to allow the access to the development and this
adversely impacted the sale of the units.
Despite the lender issuing the borrower with a Notice of Intention to Repossess and taking
vacant possession of the development as set out above it continued to allow the borrower
access to effect sale of the remaining units.
The available information shows:
on 09 August 2018, the borrower’s lawyer emailed the lender’s lawyer requesting 14 days
access to allow sale of 3 units ranging from $380,000 to $390,000
Recommendation | Case number: 743391 Page 9 of 49
on 10 August 2018, the lender’s lawyer emailed to borrower’s lawyer to advise of the
outstanding loan amounts, informing access was provided until 23 August 2018 to allow
already interested prospective purchasers to inspect and requested evidence of refinance
by 23 August 2018
on 23 August 2018, the borrower’s lawyer and property manager emailed the lender’s
lawyer about an investor purchasing the remaining units and not being able to gain access.
The lender’s lawyer advised that the property presenter was unavailable for a 6.30pm
inspection and confirmed that a viewing the prospective buyer was scheduled for 28
August 2018 at 10am
on 24 August 2018, the lender’s lawyer emailed the borrower’s lawyer to confirm the
lender would ‘co - operate regarding inspections (within reason)’.
The information shows the lender provided the borrower access to the development to try to
effect sale of the remaining units.
The offers made for the units did not materialise or were below market value
The complainant says in the period August to November 2018 the borrower received multiple
offers for the purchase of the remaining development units for over $3,000,000 which would
have discharged the outstanding debt which were rejected by the lender.
Th e lender’s legal duty, for sale of property in Queensland as mortgagee in possession, is to
show the price obtained for the property was not less than market value by reference to
expert or other relevant evidence.
The information, in summary, shows:
on 3 0 August 2018, the borrower’s lawyer emailed the lender’s lawyer to inform the
borrower was meeting with a buyer tomorrow to sign contracts for the remaining units and
requested payout figure
on 12 September 2018, the borrower’s lawyer emailed the lender’s lawyer to advise the
borrower was negotiating the sale of the remaining units for in the region $3,000,000 with
settlement in 21 days with contracts being prepared tomorrow once terms and price were
confirmed
on 17 September 2018, the borrower’s lawyer emailed the lender’s lawyer to advise the
borrower had received an offer of $3,070,000 for the remaining units subject to contract on
a 30-day settlement
on 17 September 2018, the director and co- guarantor (RL) emailed the lender’s lawyer
raising concerns about the complainant and the sale of the remaining units and asked for a
recommendation of a conveyancer so there was no conflict of interest between the co-
directors of the borrower
on 18 September 2018, the lender’s lawyer emailed RL to advise that it sho uld stay out of
issues between directors of the borrower and was reluctant to recommend another lawyer
on 20 September 2018, the director’s (RL) lawyer emailed the lender’s lawyer to advise
that it had been instructed to act and requested the payout figure
on 03 October 2018, the lender’s lawyer emailed the director’s (RL) lawyer to confirm the
indicative payout figure is $2,535,790.62 and request an update on sale of the remaining
units
on 16 October 2018, the independent valuation report valued the remaining units at
$3,225,000
on 19 October 2018, the complainant’s lawyer emailed the lender’s lawyer to request the
payout figure to be able to negotiate on the sale of the units
Recommendation | Case number: 743391 Page 10 of 49
on 24 October 2018, the lender’s lawyer emailed the complainant’s lawyer and the other
director and her lawyer to advise that if a contract of sale was entered into today or
tomorrow the payout figure was $2,582,408.55
on 24 October 2018, the complainant’s lawyer emailed the buyer’s agent to provide the
payout figure and explained that if something did not happen it would be curtains for the
development
on 28 October 2018, the buyer’s agent emailed the complainant’s lawyer to informing that
the prospective buyer was in San Francisco
on 28 October 2018, the prospective buyer emailed his agent to inform that he has request
an off-plan valuation, was concerned about it stacking up and asked the agent to request
until 29 October 2018 to review this information and submitting on an offer
on 01 November 2018, the lender’s lawyer emailed the buyer’s agent and the
complainant’s lawyer to advise that the offer made by the buyer would not allow the lender
to recover the outstanding debt in full and the offer appeared to be for an amount
significantly less than the total value of the remaining units
on 01 November 2018, the complainant’s lawyer emailed the buyer’s agent and copied in
the lender’s lawyer to ask who gave the buyer’s agent authority to enter discussion with
the mortgagee’s lawyer. The email stated:
… To date you have produced nothing but useless contracts and delay after delay.
If your client wants to negotiate a purchase it should do so via my office and not
my client’s mortgagee’s lawyer.
You and your client have had more than ample time to make an offer.
My client can sell the property under value but it cannot sell the property for less
than the payout under the mortgage and must cover rates, water, land tax and
body corporate levies and any legal or agents costs on the sale. Why don’t you
have your client formalise an offer with an amount on it rather than waste
everyone’s time asking for my time.
As you can see my client’s situation is not ideal and your prompt attention to
forming an unconditional offer with a 10% deposit is required.
In the event that you do not have a party in a position to purchase on an
unconditional basis now my client is forced to look elsewhere for a buyer.
on 08 November 2018, the complainant’s lawyer emailed the lender’s lawyer to inform the
complainant had someone to go to contract at $2,950,000 on an unconditional basis and
requested access to inspect the development tomorrow at noon
on 08 November 2018, the lender’s lawyer emailed the complainant’s lawyer attaching the
letter and Notice of Exercise of Power of Sale sent to the borrowers registered office,
advised that opportunities had been afforded to sell the remaining units and the lender had
engaged agents to sell the units which had been listed for auction on 15 December 2018
on 11 December 2018, the lender received nine conditional contracts from the same
prospective buyer for a total of $2,540,000. The lender did not accept them because they
were below the market value of $3,225,000 (as per October independent valuation report)
and below the outstanding debt of $2,633,994.65 (as per December 2018 account
statements), and an auction was scheduled on 15 December 2018
on 15 December 2018, on of each type remaining units was auctioned, the prospective
buyer did not make any bids and the two units auctioned passed in.
The information shows that:
contracts did not materialise when attempts were being made to sell the remaining units in
the period August to November 2018
Recommendation | Case number: 743391 Page 11 of 49
the lender was not required to accept the contracts it received in December 2018 due to
the total offer being under market value for the remaining units (addressed in further detail
below) and below the outstanding debt.
The lender appropriately advertised the remaining units
The complainant says the lender was unmotivated to sell the remaining units, failed to instruct
a new agent in a timely manner and failed to employ a sufficient and effective marketing
strategy.
The complainant also says in June 2018 she utilised funds ($25,972) borrowed from family
members to market the remaining units. These funds were deployed by the complainant as
director (and guarantor) of the borrower and prior to the lender taking vacant possession of
the development and when its obligations as mortgagee in possession arose. Therefore, I do
not consider that the complainant is able to recover these funds from the lender in these
circumstances.
The lender’s legal duty as set out in section 85 (1) of the Property Law Act 1974 -86 (Qld)
required it to reasonably advertise the remaining properties. That is to make reasonable
endeavours to ensure that the advertising proposed was adequate.
The lender has provided information to support the marketing campaign to sell the remaining
units. The information, in summary, shows:
on 28 August 2018, the real estate agent advised the lender’s property agent that there
was an oversupply in the local area of the type unit which remained to be sold in the
development and it was not uncommon to see a 20 to 30 percent drop in sales value.
Provided an appraisal of the properties, one-bedroom units high $200,000 to low $300,000
and two-bedroom units mid $300,000. Advised sale by auction at weekly corporate events
run in the CBD and separate marketing campaigns for each type of unit. Also provided the
condition report
on 16 October 2018, the lender received independent valuation which advised there was
an oversupply of the type of units and a buyer’s market and advised sale by private treaty
due to the low clearance rate at auctions
on 16 November 2018, having recently issued the Notice of Power of Sale the lender listed
one of each type of unit in the development on four different internet property search sites
for inspection and sale by auction
on 21 November 2018, the lender listed each type of unit in the development for sale in the
newspaper at auction
on 15 December 2018, the lender auctioned two of the units, one bedroom and two
bedrooms and they passed in
on 4 January 2019, the lender listed the units for sale on five different internet property
search sites
on 25 March 2019, the lender accepted offers for two of the remaining units
on 29 March 2019, the lender accepted an offer for one of the remaining units
on 09 April 2019, the lender listed the remaining units for sale on three different internet
property search sites
on 03 April 2019, the lender accepted offers from two of the remaining units
on 08 April 2019, the lender accepted an offer for one of the remaining units
on 09 April 2019, the lender accepted an offer for one of the remaining units
on 01 May 2019, the lender accepted an offer for one of the remaining units. The sale was
rescinded with a $15,000 deposit forfeited and applied to the account. The lender
Recommendation | Case number: 743391 Page 12 of 49
advertised the unit for auction online on 07 September 2019 and accepted an offer for the
unit on 09 September 2019
on 05 May 2019, the lender accepted an offer for the remaining unit.
The lender entered into contracts for sale with purchasers of the remaining units between 13
May and 29 May 2019 except for the sale that was rescinded, and settlements occurred
between 25 May and 08 July except for the rescinded sale.
The information shows the lender instructed its agent in a timely manner, reasonably
advertised the remaining units for sale in the period November 2018 to April 2019 and kept up
to date on the advertising campaign and the sale of the remaining units.
The lender kept informed about the sale of the remaining units
The lender received regular updates from its agent about the sale of the remaining units.
The lender has provided copies of emails it received from its agent which, in summary, show:
on 28 November 2018, the agent advised - since the commencement of marketing of units
there had been three inspections. Prospective purchasers liked the size, layout and
proximity to public transport, but did not think the development was maintained well or like
the main road location. One prospective purchaser had made offers for units nine and unit
ten but recommended the offers be declined subject to approval of deposit of $15,0000
and 60-day settlement at auction
on 06 December 2018, the agent advised it had received five new enquiries and had two
groups through to inspect the units. The price indications due to oversupply of type of units
was $250,000 (two bedroom) and $200,000 (one bedroom)
on 08 January 2019, the agent advised ten enquiries were received and four inspections
had taken place over the Christmas period. Prospective purchasers liked the size, layout
and proximity to public transport but did not think the development was maintained well or
like the main road location. Price indications were $250,000 (two-bedroom units) and
$200,000 (one-bedroom unit)
on 21 January 2019, the agent advised no new enquiries and no inspections were
undertaken. The agent requested the lender provide information about list prices, NBN and
Strata fees, requiring quotes for the common areas, occupancy certificates and additional
marketing costs
on 06 February 2019, the agent advised two new inspections had taken place in the past
week. One prospective buyer was looking for a two-bedroom unit and had just started
undertaking inspections and the second prospective buyer submitted an offer for unit 10
on 11 February 2019, the agent advised two new inspections had taken place in the past
week but did not make a request to inspect the property and not knowing the asking price
was a deterrent
on 20 February 2019, the agent advised two new inspections had taken place in the past
week and both parties were showing interest but were not prepared to submit offers until
asking prices were known
on 28 February 2019, the agent advised one inspection was undertaken last week. The
price indications from interested party were $220, 000 to $240,00 (one-bedroom units) and
$280,000 to $300,000 (two-bedroom units). The agent enquired with the lender about
responding to an offer for unit ten, list prices for units, quotes to clean common areas,
additional marketing costs, response to email from unit owner and occupancy certificates
04 March 2019, the agent advised there were no new enquiries and interest party was the
prospective buyer who submitted an offer for unit ten and requested the lender provided
responses to queries about response to offer for unit ten, list process for units, quotes to
Recommendation | Case number: 743391 Page 13 of 49
clean common areas, additional marketing, response to owner of unit and occupancy
certificates
on 13 March 2019, the agent advised no new enquiries had been received, updated
valuations were due on Friday and would forward to the lender
on 25 March 2019, the lender advised the agent to proceed with additional marketing,
confirmed acceptance of the offer for units eight and ten and provided list prices for units
on 27 March 2019, the agent advised two enquiries were received and three inspections
had taken place in the past week and now that list prices had been provided those who
previously undertook inspections had commenced submitting offers. Offers for unit eight
and ten had been accepted and an offer had been submitted for unit two. Updated
advertising text had been forwarded to the lender for approval
on 2 April 2019, the agent advised three new inspections has taken place in the last week
and numerous offers had been submitted for units since list prices were provided. It was
awaiting final offers for unit six. The buyer of unit eight was expected to return contract
once received letter from lender about a grant and requested responses about contracts
and offers for development units
on 10 April 2019, the agent advised three inspections has taken place in the last week. An
offer had been received for unit two and offers had been accepted for units two, three,
four, six, eight, nine and ten. The agent was working with interested parties to secure
offers for units five and seven
on 29 April 2019, the agent advised three new inspections had taken place in the past
week but no offers. A prospective purchaser submitted a final offer of $300,000 and
request a response. Another prospective purchaser who indicated they would increase
their offer for unit seven to $310,000 had yet to formally return a contract
on 9 September 2019, the agent provided details of three offers which had been made for
unit seven. The lender advised the agent to accept the first offer
on 10 September 2019, the agent advised in the past two weeks it had received 12
enquiries and undertaken seven inspections for unit seven and that three offers had been
received with one being accepted.
I am satisfied the information shows the lender kept itself informed about the sale of the
remaining units in the development.
The lender undertook works to assist the sale of the remaining units
The lender says it undertook works at the development to assist the sale the remaining units.
There is no general obligation for a mortgagee to make improvements to the property before
sale. However, expenditure is reasonably required by the mortgagee where it is necessary
and prudent to conserve the mortgagors interest and to reasonably assist the sale of the
property or the property could not be legally sold without improvements.
The available information shows:
on 9 January 2019, the lender received an email from its agent with a condition report and
photographs about maintenance required to the car park, common areas, balconies, units
and gardens to make the development more presentable to prospective buyers
on 25 January 2019, the lender received an email its agent forwarded from an owner of
one of the units which advised there were outstanding body corporate fees and there being
no telecommunications connection to the development in breach of the development
approval. The owner provided contacted details for the body corporate and Telstra and
advised the quote for the connection was around $7,000 and required payment.
Recommendation | Case number: 743391 Page 14 of 49
The lender has provided copies of the notice and the invoice it received from the body
corporate to show that it paid outstanding fees for the amount of $2,940 which was overdue
as at 12 February 2019 and paid an invoice on 8 August 2019 for the NBN connection works
to the development totalling $4,400.
The issues of costs incurred by the lender as mortgagee in possession is addressed further
below.
The information shows the lender reasonably incurred costs for maintenance works to make
the properties more presentable and for the development units NBN connection.
The costs incurred by the lender were reasonable
The complainant says the borrower incurred additional possession costs of $20,560.35 due to
lender taking possession and only allowing supervised access to the development but has not
identified specifically which costs are in dispute.
As I accept the lender was entitled to take possession of the development, issued notices
appropriately and allowed access to effect sale of the remaining units (as set out above) I will
address whether costs incurred by the lender were reasonable.
If a mortgagee in possession incurs expenses which are regarded as excessive it may not be
entitled to recover such costs from the mortgagor.
The lender has provided it schedule of mortgagee in possession cost it incurred for the period
14 August 2018 to 23 October 2019 with the supporting invoices, notices and bills. I have
reviewed this information, it shows the costs incurred related to; legal costs, insurance,
valuation costs, body corporate fees, agent costs, tax payable, maintenance costs, council
rates, water rates and utility bills.
The lender has also provided an appendix to show the Good and Services Tax rebates it
received relating to enforcement costs and applied to the loan account of the borrower.
Based on reviewing the information above the costs incurred by the lender to fulfil its
mortgagee in possession obligations were not excessive and were reasonable in the
circumstances.
The lender appropriately sold the remaining units by private treaty
A mortgagee is generally required to sell property at auction because an appropriately
advertised auction will usually be the best way to obtain market value for the property due to
competition between prospective purchasers. However, should a mortgagee sell the property
by private treaty rather than auction it is obliged to show the reasons for effecting sale by this
method.
As set out above, the lender appropriately advertised one type of each unit for sale at auction
on 15 December 2018 but unfortunately the two units passed in. The information shows only
two units were auctioned due to the lender’s agent and the independent valuer advising that
there was an oversupply of the type of remaining units in the local area. The lender says the
intention was to attract competitive bidding, so any unsuccessful prospective purchasers
could be directed to the remaining units. It was also set against a background of borrower
only selling two of the units after the loans terms expired and construction of the development
completed.
On 15 March 2019, the lender received an independent valuation report advising on the
recommended method of sale, stating:
Recommendation | Case number: 743391 Page 15 of 49
We recommend the property be offered for sale by private treaty with an experienced
agent that is active in the local market. An appropriate advertising campaign should be
conducted during a marketing period. The sale method is recommended because this is
considered the most likely method to entice demand to achieve a sale at a reasonable
price. Public auction is not recommended as there are low clearance rates at public
auctions for this type of property in this location in the current market.
On 23 March 2019, the lender received offers for two of the units and accepted offers for the
remaining units in April and May 2019 as set out above.
The information supports there were difficulties selling the remaining units due to prevailing
market conditions and the lender appropriately sold the remaining unit by private treaty on the
advice of an independent valuer.
The lender sold the remaining units at market value
A mortgagee is bound to take reasonable steps to ascertain the value of the property before
selling it. Generally, lenders acting as mortgagee in possession are required to obtain a
sworn valuation to ascertain the value of the property. This is in line with standard industry
practice.
The certified independent valuation report the lender received dated 15 March 2019 provided
the valuation of the remaining units in the development as follows:
Market Value ‘As Is’ :
Units 2, 3, 7 & 8 $315,000
Units 5, 6 & 10 $335,000
Units 4 & 9 $240,000
Market Value Range:
Units 2, 3, 7 & 8 $300,000 to $330,000
Units 5, 6 & 10 $320,000 to $345,000
Units 4 & 9 $220,000 to $250,000
The lender has provided copies of the settlement statements and a schedule for the sale of
the remaining units. This information shows the units sold as follows:
Unit 2 $300,000
Unit 3 $305,000
Unit 4 $235,000
Unit 5 $325,000
Unit 6 $315,000
Unit 7 $329,000 (initially $310,000 – sale rescinded, and $15,000 deposit forfeited)
Unit 8 $308,500
Unit 9 $245,000
Unit 10 $325,000
All units except for unit 6 sold within the valuation range of the independent valuation. Unit 6
sold for $5,000 under the valuation range. I accept this was reasonable due the oversupply of
units in the local area, the property being on the market for a significant period (in which the
borrower had not been able to sell the unit) of time with no offers and the lender appropriately
advertising the unit for sale.
The information shows the lender took reasonable steps to value the remaining units by
obtaining a certified independent valuation of the remaining units and the units sold within the
valuation range provided by the valuer in the report.
Recommendation | Case number: 743391 Page 16 of 49
The lender sold the remaining units in timely manner
The complainant says the lender took over year to sell the remaining units and this caused
additional interest and charges to be applied.
A mortgagee is entitled to decide when to sell and, generally, how to sell. A mortgagee is not
required to wait for a time when an owner, selling in his own interest, might consider to be an
ideal time. Conversely, a mortgagee is not obliged to wait for a depressed market to rise or to
delay sale where there is a falling market.
However, if it is apparent that the market is about to rise there may be on obligation to delay
the sale. Conversely, if the market is about to fall and there is a willing buyer, then there may
be an obligation to either wait or act promptly as regard the sale of the property. Whether
such obligations exist for the mortgagee will be a question to be determined by the facts.
I accept the lender met its obligation to sell the remaining units in a timely manner because:
having taken vacant possession of the development in August 2018 it continued to allow
access to the borrower to effect sale of the remaining units
in the period August to December the borrower attempts to sell the remaining units were
unsuccessful due to the contracts not materialising or being under market value and
conditional
the lender auctioned one of each type of unit in December 2018 and the units passed in
due to there being an oversupply of the type of unit in the local area
the borrower had only been able to sell (in May 2018) two units in the development since
the loan terms expired and construction was completed
the lender obtained a certified valuation report in March 2019 and accepted offers for the
remaining units in the period March to May 2019 except for the rescinded offer. The lender
accepted an offer in September 2019
the sale of the units settled in the period 13 June and 8 July 2019 except for the rescinded
sale which settled on 23 October 2019.
The lender acted in good faith when it sold the remaining units
The complainant says the lender did not act in good faith when it sold the remaining units.
Australian courts generally state the duty as being to act in good faith and without a reckless
or wilful sacrificing of the interest of the mortgagor. That is to say there would be a clear
failure to act in good faith if there was deception, corruption, collusion or actual fraud in the
sale process.
The factors addressed above when taken together establish that the lender met is obligations
as mortgagee in possession and acted in good faith when it sold the remaining uni ts and did
not wilfully sacrifice the interest of the mortgagor.
5.3 Why is the outcome fair?
The outcome is fair
The outcome is fair because the complainant’s claims about the guarantee not being
enforceable are not made out and the lender also met its obligations as mortgage in
possession as set out above.
Recommendation | Case number: 743391 Page 17 of 49
The lender cannot be held liable for the unfortunate and prevailing market conditions which
caused difficulty for both the borrower and the lender to encountered in selling the remaining
units of the development due to an oversupply of the types of unit in the local area.
In circumstances where the complainant has not established her claims and the lender met its
met is obligations it is fair that the complaint remains liable under the guarantees for
outstanding debts as set out above.
Recommendation | Case number: 743391 Page 18 of 49
6 Supporting information
6.1 The AFCA process
AFCA’s approach is based on fairness
AFCA has assessed this complaint based on what is fair in all the circumstances, having
regard to:
the legal principles
applicable industry codes or guidance
good industry practice
previous decisions of AFCA or its predecessor schemes (which are not binding).
The respective parties have completed a full exchange of the relevant information, and each
party has had the opportunity to address any issues raised. We have reviewed and
considered all of the information the parties have provided.
While the parties have raised a number of issues in their submissions, we have restricted this
recommendation to the issues that are relevant to the outcome.
We assess complaints on available information and circumstances
AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to
require third parties to give evidence.
When we assess complaints, we consider:
available documents
the recollections of the parties
all relevant circumstances.
We give more weight to documents created at the time the events occurred. If there are no
relevant documents, we will decide what most likely occurred based on the available
information. If there are conflicting recollections and these are evenly weighted, we may find
that a claim cannot be established.
6.2 Excerpts from the Commercial Loan Agreement, Letter of
Offer and Financiers Development Deed
Clause 12 of the Commercial Facility Agreement says:
12. Definitions And Interpretations
….
Progress Claim means a written request for a Loan Draw confirming to the form
requirements We give you, signed by You and including:
…
a request by You for Us to make the Loan Draw and pay the proceeds of that
Loan Draw directly to the builder and other contractors or as otherwise agreed
by Us, along with details of the accounts to which the payments must be made
…
Recommendation | Case number: 743391 Page 19 of 49
Clause 15 of the Commercial Facility Agreement says:
15. Construction Provisions
…
15.2 Progress Claims must be submitted in writing at intervals pre-agreed and with Us
in accordance with the project documentation.
15.3 Progress Payments must be made directly to the building contractor (or
otherwise agreed by the Lender).
15.4 We fund on a cost to complete basis, You must ensure that at all times there is
sufficient Underdrawn Loan to complete the Project.
…
15.7 We reserve the right to at all times retain from the Loan an amount sufficient to
cover Our estimate of the costs to complete the construction of the Works.
…
15.10 We are under no obligation to make any progress payment, and in particular
can refuse to make any further advances if anything happens which in Our opinion,
adversely affects the value of the Mortgaged Property, or if the Works are not
proceeding satisfactorily.
…
General term and condition 10 of the Loan Offer Letter says:
The loan is to be paid in progress payments. The first advance will be made only after the
Credit Provider’s Solicitor has received and has control of your title security property and the
mortgage documents have been duly executed by all parties. The land settlement advance is
calculated by deducting the cost of construction and Lender’s mortgage insurance premium
and any other outstanding fees and insurance premiums from the loan approved, the land
settlement advance is not to exceed (90%) of the valuation of the land. You will be required to
contribute all of your funds prior to the Credit Provider making funds available at land
settlement. Further advances will be paid on the basis of the Credit Providers Valuer’s report
and may differ from your builder progress payment claim. Despite FF monitoring the building
works. FF takes no responsibility for the works. Further advances will be made payable to the
builder. Progress payments shall be drawn after the Borrower’s funds have been used so that
the Credit Provider’s funds are the final funds used in the payment of the building contract.
Construction must be completed within six (6) months from the date of settlement unless
otherwise varied by special conditions contained in the letter of offer.
General term and condition 11 of the Loan Offer Letter says:
The loan amount will be advanced progressively as and when FF sees fit to assist in the
construction of building works. FF is under no obligation to make nay progressive advances,
and in particular can refuse to make any further advances if anything happens which in the
opinion of FF adversely affects the value of the security property or the works are not
proceeding satisfactorily. If the insurer who has provided the mortgage insurance in respect of
this loans cancels, suspends, or limits that insurance, a default will have occurred and the
Lender can demand repayment of the whole loan.
Recommendation | Case number: 743391 Page 20 of 49
Clause 8 of the Financiers Development Deed says:
8. Cost Overruns
The Borrower is liable for and must pay any cost overruns out of their own funds and the
parties acknowledge the Lender will only provide drawdowns under the Finance Facility on a
"cost to complete" basis so the Lender will at all times withhold sufficient funds out of the
Finance Facility to meet the cost to complete the Works and those payments will not be tied
to any particular stages of construction.
The parties acknowledge the Borrower's request for a drawdown under the Finance Facility
will be processed only after receipt of an invoice from the Builder in a form acceptable to the
Lender, the Borrower's drawdown notice certified by the Quantity Surveyor on a cost to
date/cost to complete basis so that the undrawn amount under the Finance Facility is at all
times sufficient to meet the certified completion cost, the Quantity Surveyor's Confirmation
and satisfaction of other conditions precedent under the Finance Facility.
6.3 Chronology of events
Chronology
Date Key points
22 Feb 2012 S Company incorporated, and complainant’s husband appointed as director.
15 May 2012 M Company incorporated, and PL appointed as director & secretary.
27 Mar 2013 Complainant appointed as director & secretary of S Company.
26 Jul 2013 PL appointed as director of S Company.
31 Jul 2015 PL, RL & complainant listed as equal sharehold ers of S Company.
06 Mar 2015 RL appointed as director of S Company.
07 Mar 2016 Complainant signed the loan application on behalf of the borrower and as
guarantor.
18 Jan 2016 Valuation report for residential de velopment site, G QLD :
As is value $950,000
Gross realisation if complete $4,605,000 (inc GST)
Gross realisation if complete $4,186,364 (ex GST)
12 mont hs to complete project and sell units.
21 Mar 2016 Accountants letter to confirm borrower’s earnings and guarantors’ taxable
Recommendation | Case number: 743391 Page 21 of 49
Date Key points
income COM, PL & RL (complainant’s taxable income shown as $122,214).
28 Mar 2016 Broker loan submission to lender :
Borrowe r S Company
Guarant ors complainant , RL & PL
Loan purpose to build 11 units
Facility limit $2,930,400
Facility l imit 12 - month t erm .
13 Apr to 18 May 2016 Email exchan ge between R (property management company) and the
lender ’s lawyers about signing of the contracts and deeds, providing copy of
building contract and confirmation of the architect.
17 & 18 May 2016 Complainant, PL & RL sign the Commercial Loan A greement for
$2,788,1 00 at discount interest rate of 9.9% per annum on 1 - year
term:
Complainant & PL sign as directors of S Company
Complainant, PL & RL all sign the guarantor’s acknowledgement.
18 May 2016 Complainant, PL & RL signed Guarantee and Indemnities for the
facilities:
$2,788,100
$ 142,000
08 Jun 2016 Complainant, PL & RL sign Deed of General Security Agreement - All
Assets Charge:
Complainant & PL sign as directors of S Company.
09 Jun 2016 Complainant, RL & PL signs loan offer letter for $142,400 at an interest rate
of 16.5% per annum on a 1 - year term:
Complainant signs as secretary & PL signs as director of S
Company.
Complainant & RL sign as guarant ors.
17 Jun 2016 Lender’s letter to bo rrower S Company loan of $142,000 has been fully
advanced. Loan term expires on 17 June 2017. Monthly repayments of
$1,973 commence on 17 July 2016.
17Jun 2016 Lender’s letter to borrower S Company loan of $2,788,100 has been
partially advanced. Loan te rm expires on 17 June 2017. Monthly
Recommendation | Case number: 743391 Page 22 of 49
Date Key points
repayments of $1,812.53 commence on 17 July 2016.
20 Jun 2016 Email from lender to PL, RL & complainant to advise:
S ettlement of loans for G property completed on 17 June 2017
Sets out requirements for drawdown (including additional
requirements for the first and last claim):
> Progress payment request form signed and completed
> Copy of builder’s invoice
> Receipt for any monies paid to builder and confirmation of any
variations
Lender to order valuers / quantity surv eyors report and make
payment if the report is Satisfactory:
> Quantity surveyor will require Statutory Deceleration from the
builder and copy of any building inspections conducted for the
claim as required by Building Permit.
22 June 2016 Th borrower S Company, the builder Company and the lender all signed the
Financiers Development Deed.
Complainant, RL and PL signed the Financiers Development Deed as
directors of the borrower.
PL also signed the Financiers Development Deed as director and secretary
of M Company.
30 Jun 2016 Lender’s file showing emails sent to PL, RL & complainant about settlement
of loans and forms to be completed to make progress payment requests.
30 Sep 2016 PL signs a Statutory Declaration as director of M Co mpany about
agreement with S Company to complete build at G QLD to say all wages
paid to employees, monies paid to meet invoices and all insurances /
licences / approvals are in place.
[Attachment to the Quantity surveyor report below]
06 Oct 2016 Quantity Surveyor R eport (QSR) , rele vant excerpts:
1. Contract Statement:
The Value of Work for Progress Valuation No. 1 is $106, 379
(excluding GST)
The Value of Work to Complete the Project is $2,200,473 (excluding GST)
Recommendation | Case number: 743391 Page 23 of 49
Date Key points
2. Building Progress as at 30 September 2016:
The Contractor has commenced work s and have established a site
fence and temporary power on site. Earthwork s (cut to spoil) have
commenced and been substantially completed. The Contractor is
scheduled to commence the construction programme on the 10
October 2016.
4. Building Programme:
The Contractor has commenced earthwork s. Construction
commencement dat e is anticipated for 10 October 2016.
The Contractor's anticipated Completion Date is 28 August 2017.
▫ Contract Commencement Date: 10 October 2016
▫ Contract Completion Date: 28 August 2017
▫ Revised Contract Completion Date: 28 August 2017
▫ Contractor's Anticipated Completion Date: 28 August 2017
▫ GRC Forecast Completion Date: 25 Novemb er 2017
5. Variations:
No Variations have been s ubmitted to date. The Contingency cover
equates to approximately 5% of work s to complete. Please refer to
the Variation Register for further details .
06 Oct 2016 Progress Payment Request made by borrower S Company. Signed by PL
as director. Account details of M Company provided.
Amount: $106,379.
18 Nov 2016 PL signs a Statutory Declaration as director of M Company about
agreement with S Company to complete buil d at G QLD to say all wages
paid to employees, monies paid to meet invoices and all insurances /
licences / approvals are in place.
[Attachment to the Quantity surveyor report below]
22 Nov 2016 QSR , relevant excerpts:
1. Contract Statement:
The Value of Work for Progress Valuation No. 2 is $78,990
(excluding GST)
The Value of Work to Complete the Project is $2,121,483 (excluding GST)
2. Building Progress as at 21 November 2016:
The Contractor has commenced work s and have established a site
fence, temp orary toilet and temporary power on site. Earthwork s (cut
Recommendation | Case number: 743391 Page 24 of 49
Date Key points
to spoil) are complet e, strip footings and pad footings are complete,
under slab drainage w ork s are complete. The Contractor is
scheduled to commence with the ground slab and concret e columns
in the coming
weeks.
4. Building Programme:
The Contractor is progressing with the work s. There are no reported
delays at this stage. The Contractor's
anticipated revised completion date is 28 August 2017, which GRC
considers achievable at this point in time. Based
on expenditure, construction is 4% complete which is slightly behind
our indicative cashflow of 5%. Ref er to
Indicative Cashflow for furt her details.
▫ Contract Commencement Date: 10 October 2016
▫ Contract Completion Date: 28 August 2017
▫ Revised C ontract Completion Date: 28 August 2017
▫ Contractor's Anticipated Completion Date: 28 August 2017
▫ GRC Forecast Completion Date: 25 Novemb er 2017
5. Variations:
No Variations have been submitted to date. The Contingency cover
equates to approximately 5% of work s to
complete. Please refer to the Variation Register for further details.
22 Nov 2016 Progress Payment Request made by borrower S Company. Signed by PL
as director. Account details of M Company provided.
Amount: $78,990.
06 Dec 2016 Progress Payment Request made by borrower S Company. Signed by PL
as director. Account details of M Company provided.
Amount: $113,681.25.
07 Dec 2016 PL signs a Statutory Declaration as director of M Company about
agreement with S Company to complete b uild at G QLD to say all wages
paid to employees, monies paid to meet invoices and all insurances /
licences / approvals are in place.
[Attachment to the Quantity surveyor report below]
07 Dec 2016 QSR , relevant excerpts:
1. Contract Statement:
The Value of Work for Progress Valuation No. 3 is $113, 681
(excluding GST)
Recommendation | Case number: 743391 Page 25 of 49
Date Key points
The Value of Work to Complete the Project is $2,007,802 (excluding GST)
2. Building Progress as at 6 December 2016:
The Contractor has commenced work s and have established a site
fence , temporary toilet and temporary power on
site. Earthwork s (cut to spoil), strip footings, pad footings, ground
slab and ground columns are complete. Under slab
drainage including detention tank have been installed. The
Cont ractor is scheduled to commence first floor sl ab work s in the
coming week s.
4. Building Programme:
The Contractor is progressing with the work s. There are no reported
delays at this stage. The Contractor's
anticipated revised completion date is 28 August 2017, which GRC
considers achiev able at this point in time. Based
on expenditure, construction is 9% complete which is slightly behind
our indicative cashflow of 10%. Refer to
Indicative Cashflow for furt her details.
▫ Contract Commencement Date: 10 October 2016
▫ Contract Completion Dat e: 28 August 2017
▫ Revised Contract Completion Date: 28 August 2017
▫ Contractor's Anticipated Completion Date: 28 August 2017
▫ GRC Forecast Completion Date: 25 Novemb er 2017
5. Variations:
No Variations have been submitted to date. The Contingency cover
equates to approximately 5% of work s to
complete. Please refer to the Variation Register for further details.
13 Jan 2017 Progress Payment Request made by borrower S Company. Signed by PL
as director. Account details of M Company provided.
Amount: $139,360.
16 Jan 2017 PL signs a Statutory Declaration as director of M Company about
agreement with S Company to complete build at G QLD to say all wages
paid to employees, monies paid to meet invoices and all insurances /
licences / approvals are in place.
[Attachment to the Quantity surveyor report below]
18 Jan 2017 QSR , relevant excerpts:
1. Contract Statement:
The Value of Work for Progress Valuati on No. 4 is $139, 360
(excluding GST)
Recommendation | Case number: 743391 Page 26 of 49
Date Key points
The Value of Work to Complete the Project is $1,868,442 (excluding GST)
2. Building Progress as at 17 January 2017:
Structural work s inclusive of ground slab, columns and block work
are complete. The contractor is curre ntly
progressing with formwork to level 1 slab. The Contractor is
scheduled to pour the first floor concrete slab in the
coming weeks followed b y columns and b lockwork to level 1.
4. Building Programme:
The Contractor is progressing with the work s. There are no reported
delays at this stage. The Contractor's
anticipated revised completion date is 28 August 2017, which GRC
considers achievable at this point in time. Based
on expenditure, construction is 16% complete which is in line with
our indicative cash flow of 16%. Refer to Indicative
Cashflow for furt her details.
▫ Contract Commencement Date: 10 October 2016
▫ Contract Completion Date: 28 August 2017
▫ Revised Contract Completion Date: 28 August 2017
▫ Contractor's Anticipated Completion Date: 28 August 2017
▫ GRC Forecast Completion Date: 25 September 2017
5. Variations:
No Variations have been submitted to date. The Contingency cover
equates to approximately 6% of work s to
complete. Please refer to the Variation Register for further details.
02 Feb 2017 PL signs a Statutory Declaration as director of M Company about
agreement with S Company to complete build at G QLD to say all wages
paid to employees, monies paid to meet invoices and all insurances /
licences / approvals are in place.
[Attachment t o the Quantity surveyor report below]
02 Feb 2017 QSR , relevant excerpts:
1. Contract Statement:
The Value of Work for Progress Valuation No. 5 is $94,740
(excluding GST)
The Value of Work to Complete the Project is $1,773,702 (excluding GST)
2. Building Progress as at 1 February 2017:
Structural work s inclusive of ground slab, columns, block work and
Level 1 concrete slab are complete. In - slab services are complete to
Level 1. The Contractor is currently progressing with block work to
level 1 slab. The Contractor is scheduled to progress block work and
Recommendation | Case number: 743391 Page 27 of 49
Date Key points
columns to the first floor slab in the coming week s.
4. Building Programme:
The Contractor is progressing with the work s. There are no reported
delays at this stage. The Contractor's anticipat ed compl etion date is
28 August 2017, which GRC considers achievable at this point in
time. Based on expendit ure, construction is 21% complete which is
slightly behind our indicative cashflow of 25%. Refer to Indicative
Cashflow for furt her details.
▫ Contract Com mencement Date: 10 October 2016
▫ Contract Completion Date: 28 August 2017
▫ Revised Contract Completion Date: 28 August 2017
▫ Contractor's Anticipated Completion Date: 28 August 2017
▫ GRC Forecast Completion Date: 25 Sept ember 2017
5. Variations:
No Va riations have been submitted to date. The Contingency cover
equates to approximately 6% of work s to complete. Please refer to
the Variation Register for further details.
03 Feb 2017 Progress Payment Request made by borrower S Company. Signed by PL
as director. Account details of M Company provided.
Amount: $ 94,740.
02 Mar 2017 PL signs a Statutory Declaration as director of M Company about
agreement with S Company to complete build at G QLD to say all wages
paid to employees, monies paid to meet invoices and all insurances /
licences / approvals are in place.
[Attachment to the Quantity surveyor report below]
02 Mar 2017 QSR , relevant excerpts:
1. Contract Statement:
The Value of Work for Progress Valuation No. 6 is $231, 443
(excluding GST)
The Value of Work to Complete the Project is $1,542,259 (excluding GST)
2. Building Progress as at 2 March 2017:
Structural work s inclusive of ground slab, columns, block work ,
concrete slab are complete up to Level 1 including Level 2 slab. In -
slab services are complete up to Level 2. The Contractor is
scheduled to progress block work to L evel 2 in the coming week s.
4. Building Programme:
The Contractor is progressing with the work s. There are no reported
delays at this stage. The Contractor's anticipat ed completion date is
28 August 2017, which GRC considers achievable at this point in
time. Based on expendit ure, construction is 32% complete which is
slightly behind our indicative cashflow of 38%. Refer to Indicative
Cashflow for furt her details.
Recommendation | Case number: 743391 Page 28 of 49
Date Key points
▫ Contract Commencement Date: 10 October 2016
▫ Contract Completion Date: 2 8 August 2017
▫ Revised Contract Completion Date: 28 August 2017
▫ Contractor's Anticipated Completion Date: 28 August 2017
▫ GRC Forecast Completion Date: 25 Sept ember 2017
5. Variations:
No Variations have been submitted to date. The Contingency cover
e quates to approximately 7% of work s to
complete. Please refer to the Variation Register for further details.
03 Mar 2017 Email from lender to M Company confirming receipt of QSR and it will
receive funds of $231,443 on Monday – need to complete claim form.
28 Mar 2017 Progress Payment Request for variation cost made by borrower S
Company. Signed by PL as director. Account details of M Company
provided.
Amount: $26,918.36.
29 Mar 2017 PL signs a Statutory Declaration as director of M Company about
agreement with S Company to complete build at G QLD to say all wages
paid to employees, monies paid to meet invoices and all insurances /
licences / approvals are in place.
[Attachment to the Quantity surveyor report below]
31 Mar 2017 QSR , relevant excerpts:
1. Contract Statement:
The Value of Work for Progress Valuation No. 7 is $109, 577
(excluding GST)
The Value of Work to Complete the Project is $1,455,010 (excluding GST)
2. Building Progress as at 29 March 2017:
Structural work s inclusive of ground slab, columns, block work ,
concrete slab are complete. In - slab services are complete with
hydraulic rough - ins complet e to blo ck walls. The Cont ractor is
scheduled to progress roof inst allation, and underslab services in the
coming week s.
4. Building Programme:
The Contractor is progressing with the work s. There are no reported
delays at this stage. The Contractor's anticipat ed c ompletion date is
28 August 2017, which GRC considers achievable at this point in
time. Based on expendit ure, construction is 36% complete which is
behind our indicative cashflow of 55%. Refer to Indicative
Recommendation | Case number: 743391 Page 29 of 49
Date Key points
Cashflow for furt her details.
▫ Contract Commence ment Date: 10 October 2016
▫ Contract Completion Date: 28 August 2017
▫ Revised Contract Completion Date: 28 August 2017
▫ Contractor's Anticipated Completion Date: 28 August 2017
▫ GRC Forecast Completion Date: 25 September 2017
5. Variations:
Variations to the value of $22,329 have been submitted and
approved. The total value of Variations included within this Progress
Valuation Report to date is $22,329. The Contingency remaining
equates to $77,671 or approximately 6% of the cost to complete.
Please ref er to the Variation Register for further details.
27 Apr 2017 QSR , relevant excerpts:
1. Contract Statement:
The Value of Work for Progress Valuation No. 8 is $158, 757
(excluding GST)
The Value of Work to Complete the Project is $1,314,225 (excluding GST)
2. Building Progress as at 24 April 2017:
Structural work s are complete inclusive of ground slab, columns,
block work , concrete s labs and roof structure. Inslab services are
complete wit h hydraulic rough - ins complete to block walls. Windows
are progre ssing to Level 1 and Level 2. Internal timber wall framing
are complete. The Contractor is scheduled to progress roof
coverings, under slab services and services rough - ins in the coming
week s.
4. Building Programme:
The Contractor is progressing with the work s. There are no reported
delays at this stage. The Contractor's anticipat ed completion date is
28 August 2017, which GRC considers achievable at this point in
time. Based on expendit ure, construction is 45% complete which is
behind our indicative cashflow of 55%. Refer to Indicative
Cashflow for furt her details.
▫ Contract Commencement Date: 10 October 2016
▫ Contract Completion Date: 28 August 2017
▫ Revised Contract Completion Date: 28 August 2017
▫ Contractor's Anticipated Completion Date: 28 August 2017
▫ GRC Forecast Completion Date: 25 September 2017
5. Variations:
Variations to the value of $40,300 have been submitted and
approved. The total valu e of Variations included within this Progress
Valuation Report to date is $33,112. The Continge ncy remaining
equa tes to $59,700 or approximately 5% of the cost to complete.
Please refer to the Variation Register for further details.
Recommendation | Case number: 743391 Page 30 of 49
Date Key points
27 Apr 2017 Progress Payment Request made by borrower S Company. Signed by PL
as director. Account details of M Comp any provided.
Amount: $158,757.
15 May 2017 PL signs a Statutory Declaration as director of M Company about
agreement with S Company to complete build at G QLD to say all wages
paid to employees, monies paid to meet invoices and all insurances /
licences / approvals are in place.
15 May 2017 Progress Payment Request made by borrower S Company. Signed by PL
as director. Account details of M Company provided.
Amount: $139,013.
16 May 2017 QSR, relevant excerpts:
1. Contract Statement:
The Value of Work for Progress Valuation No. 9 is $139, 013
(excluding GST)
The Value of Work to Complete the Project is $1,175,212 (excluding GST)
2. Building Progress as at 15 May 2017:
Roof coverings are substantially complete and rendering are
progressing to the facades. Wall and ceiling framing are
generally complete to Level 1 & 2. Electrical and mechanical
services rough - ins are progressing to Level 2. Under slung plumbing
are progressing to Level 1. Windows are generally installed to Level
1 & 2. The Co ntractor is scheduled to complete facade finishes and
drop the scaffold including commence sheeting of walls and ceilings
in the coming week s.
4. Building Programme:
There are no reported delays at this stage. The Contractor's
anticipated completion date is 28 August 2017, which GRC
considers achievable at this point in time. Based on expenditure,
construction is 52% complet e which is behind our indicative
cashflow of 74%. Refer to Indicative Cashflow for further details.
▫ Contract Commencement Date: 10 O ctober 2016
▫ Contract Completion Date: 28 August 2017
▫ Revised Contract Completion Date: 28 August 2017
▫ Contractor's Anticipated Completion Date: 28 August 2017
▫ GRC Forecast Completion Date: 25 September 2017
5. Variations:
Variations to the value o f $40,300 have been submitted and
approved. The total value of Variations included within
Recommendation | Case number: 743391 Page 31 of 49
Date Key points
this Progress Valuation Report to date is $33,112. The Contingency
remaining equates to $59,700 or approximately
6% of the cost to complete. Please refer to the Varia tion Register for further
details.
17 May 2017
Lender’s file not e, emailed borrowers & broker about the loans
expiring & the build not completing:
Includes subdivision & discharge process. We note that the above 2
loans for [G property] are due to expire on the 17 June 2017 and
work s are currently 53% completed. Construction Update: Pleas e
provide an update on; "Estimated date of completion - latest QS
report estimates September 2017. "Information on any delays in
construction "Status of subdivision (if applic able) "Status of
discharge – details of presales achieved. If the loan is to be repaid
via refinance, please advise. Loan Expiry: The loans are due to
expire on 17 June 2017, as a result the loan will be in default and
the Late Payme nt Fee under the contract will be due. As a matter of
good will FF will not commence any recovery action at this time. The
Late Payment Fee will therefore accrue on the loan and be collected
at discharge provided the following is met: "Payments are met on the
account on the due date. oIf the interest budget is extinguished then
you will need to mak e arrangement from your own resources or give
clear instructions to Progress Draws department for the payment to
come from contingency (if held) "We are to be pro vided with a
detailed list of any sales achieved, refinances to occur and the
relevant Discharge Authorit y. (attached) "We are k ept up to date
satisfactorily with respect
25 May 2017 Lender’s file notes show it was reviewing a request for a 6 - month exte nsion
subject to a valuation. The renewal would not be completed prior to the loan
terms expiring.
29 May 2017 Lender’s file notes show it requested a quote for valuation of the property.
31 May 2017 Lender’s file note showing quote of $3,700 from valuer.
30 Jun 2017 Lender’s file note shows that it received a quote from a valuer.
13 Jun 2017 QSR, relevant excerpts:
1. Contract Statement:
The Value of Work for Progress Valuation No. 10 is $173,991
(excluding GST)
The Value of Work to Complete the Project is $1,025,176 (excluding GST)
2. Building Progress as at 15 May 2017:
Recommendation | Case number: 743391 Page 32 of 49
Date Key points
Windows are installed and render to the façade are complete with paining to
commence shortly. Rough - Ins for services are generally complete to level 1
& 2 with ground car park services fit off complete. Wall and ceiling framing
are complete to Level 2with level 1 framing progressing. All balustrades are
installed with waterproof to b alconies schedule to commence shortly. The
Contractor is scheduled to commence sheeting and setting of walls and
ceilings in the coming weeks.
4. Building Programme:
There are no reported delays at this stage. The Contractor's
anticipated completion date is 28 August 2017, which GRC
considers achievable at this point in time. Based on expenditure,
construction is 59% complet e which is behind our indicative
cashflow of 74%. Refe r to Indicative Cashflow for further details.
▫ Contract Commencement Date: 10 October 2016
▫ Contract Completion Date: 28 August 2017
▫ Revised Contract Completion Date: 28 August 2017
▫ Contractor's Anticipated Completion Date: 28 August 2017
▫ GRC Forec ast Completion Date: 25 September 2017
5. Variations:
Variations to the value of $64,255 have been submitted and
approved. The total value of Variations included within
this Progress Valuation Report to date is $53,386. The Contingency
remaining equates t o $35,745 or approximately
4% of the cost to complete. Please refer to the Variation Register for further
details.
13 Jun 2017 Progress Payment Request made by borrower S Company. Signed by PL
as director. Account details of M Company provided.
Amount: $173,991.
17 Ju 2017 The loan terms expired.
05 Jul 2017 PL signs a Statutory Declaration as director of M Company about
agreement with S Company to complete build at G QLD to say all wages
paid to employees, monies paid to meet invoices and a ll insurances /
licences / approvals are in place.
05 Jul 2017 QSR, relevant excerpts:
1. Contract Statement:
The Value of Work for Progress Valuation No. 11 is $187,465
(excluding GST)
The Value of Work to Complete the Project is $864,518 (excluding GST)
Recommendation | Case number: 743391 Page 33 of 49
Date Key points
2. Building Progress as at 3 July 2017:
Facade work s are generally complete inclusive of render, paint, sun
hoods and screening. Scaffold is in the process of being removed.
Rough - ins for services are generally complete to Level 1 & Level 2.
Framing to walls and ceilings are complete to Level 1 & Level 2 with
Level 2 sheeted and set. The Contractor is scheduled to commence
work to wet areas, painting and complete sheeting of all walls and
ceilings in the coming week s.
4. Building Programme:
There are no reported delays, however the Contractor's revised
anticipated completion date is 29 September 2017. Based on
expenditure, construction is 67% complete which is behind our
indicative cashflow of 89%. Refer to Indicative Cashflow for further
details.
▫ C ontract Commencement Date: 10 October 2016
▫ Contract Completion Date: 28 August 2017
▫ Revised Contract Completion Date: 29 September 2017
▫ Contractor's Anticipated Completion Date: 29 Sept ember 2017
▫ GRC Forecast Completion Date: 29 September 2017
5. Variations:
Variations to the value of $91,061 have been submitted and
approved. The total value of Variations included to date
within this Progress Valuation Report equates to $83,873. The
Contingency remaining equates to $8,939 or approximately 1% of
the cost to complete. GRC have not verified the validit y and the
reasonableness of the variations. Payment of variations are at the
discretion of the financier. Pleas e refer to the Variation Register for
further details.
05 Jul 2017 Progress Payment Request made by borrower S Company. Signed by PL
as director. Account details of M Company provided.
Amount: Not shown.
21 Jul 2017 Progress Payment Request made by borrower S Company. Signed by PL
as director. Account details of M Com pany provided.
Amount: Not shown.
25 Jul 2017 QSR, relevant excerpts:
1. Contract Statement:
The Value of Work for Progress Valuation No. 12 is $153,367
(excluding GST)
The Value of Work to Complete the Project is $723,923 (excluding GST)
Recommendation | Case number: 743391 Page 34 of 49
Date Key points
2. Building Progress as at 24 July 2017:
Facade works are generally complete with scaffold removed. Unit finishes
are progressing to level 2 inclusive of 2 nd coat of paint and tiling to b alcony
areas. Carpentry fix unit is generally complete. Level 1 unit walls and
ceilings are sheeted with carpentry fix out progressing. Ground level wall
unit and ceiling framing is complete with rough - ins for services progres sing.
The Contractor is scheduled to continue with the finishing trades in the
coming weeks inclusive of wet area tiling and kitchen installation.
4. Building Programme:
There are no reported delays, however the Contractor's revised
anticipated completion date is 29 September 2017. Based on
expenditure, construction is 74% complete which is behind our
indicative cashflow of 90%. Refer to Indicative Cashflow for further
details.
▫ Contract Commencement Date: 10 October 2016
▫ Contract Completion Date: 28 Au gust 2017
▫ Revised Contract Completion Date: 29 September 2017
▫ Contractor's Anticipated Completion Date: 29 Sept ember 2017
▫ GRC Forecast Completion Date: 29 September 2017
5. Variations:
Variations to the value of $103,834 have been submitted and
appr oved. The total value of Variations included to date
within this Progress Valuation Report equates to $103,834. The remains no
contingency after consideration of all approved variations. GRC have not
verified the validity and the reasonableness of the vari ations. Payment of
variations are at the discretion of the financier. Please refer to the Variation
Register for further details.
26 Jul 2017 Lender’s letter to borrower S Company an amount of $146,628 out of your
approved loan amount of $2,788,1000 making total payment to date
$1,1,986,285.
14 Aug 2017 QSR, relevant excerpts:
1. Contract Statement:
The Value of Work for Progress Valuation No. 13 is $105,663
(excluding GST)
The Value of Work to Complete the Project is $618,260 (excluding GST)
2. Building Progress as at 24 July 2017:
Level 2 – works are progressing with carpentry fix out, tiling and painting
generally complete. Electrical fit off are progressing with downlights and
Recommendation | Case number: 743391 Page 35 of 49
Date Key points
ceiling fans installed. Plumb ing fit off is progressing with b aths and wall
mixers complete. Kitchen inst allation is scheduled to commence shortly.
Level 1 – works are progressing with carpentry fit out. Waterproofing and
painting generally complete. Electrical fit off has commenced with plumb ing
fit off b ats and wall mixers installed. The Contractor is sch eduled to
commence tiling shortly.
Ground units is progressing with services rough - ins. Enclosing of walls and
ceiling are scheduled in due course.
4. Building Programme:
There are no reported delays, however the Contractor's revised
anticipated completion date is 29 September 2017. GRC is of the
opinion this is not achievable based on current monthly expenditure.
Based on expenditure, construction is 79% complete whic h is behind
our indicative cashflow of 91%. Refer to Indicative Cashflow for
fur ther details.
▫ Contract Commencement Date: 10 October 2016
▫ Contract Completion Date: 28 August 2017
▫ Revised Contract Completion Date: 29 September 2017
▫ Contractor's Anticipated Completion Date: 29 Sept ember 2017
▫ GRC Forecast Completion Date: 31 Oc tob er 2017
5. Variations:
Variations to the value of $103,834 have been submitted and
approved. The total value of Variations included to date
within this Progress Valuation Report equates to $103,834. The remains no
contingency after consideration of all approved variations. GRC have not
verified the validity and the reasonableness of the variations. Payment of
variations are at the discretion of the financier. Please refer to the Variation
Register for further details.
14 Aug 2017 Progress Payment Request made by borrower S Company. Signed by PL
as director. Account details of M Company provided.
Amount: Not shown.
24 Aug 2017 Lender’s file note shows that the valuation of the property came up short
and that the renewal did not p roceed, and the clients have agreed to leave
the loans expired and will be charged later payment fees at settlement.
06 Sep 2017 Progress Payment Request made by borrower S Company. Signed by PL
as director. Account details of M Company provided.
Recommendation | Case number: 743391 Page 36 of 49
Date Key points
Amount : Not shown.
07 Sep 2017 QSR, relevant excerpts:
1. Contract Statement:
The Value of Work for Progress Valuation No. 14 is $101,255
(excluding GST)
The Value of Work to Complete the Project is $517,007 (excluding GST)
2. Building Progress as at 24 July 2017:
Façade works are complete with external works progressing. Finishing
trades are progressing with painting, tiling, sanitary ware and fit off electrical
to Level 1 & 2. Ground floor unit framing and rough - ins for services are
complete. The Contractor is scheduled to continue with the finishing trades
in the coming weeks inclusive of kitchen, b athroom and bedroom joinery.
4. Building Programme:
There are no reported delays, however the Contractor's revised
anticipated completion date is 23 October 2017. Based on
expenditure, construction is 84% complete which is behind our
indicative cashflow of 91%. Refer to Indicative Cashflow for further
details.
▫ Contract Commencement Date: 10 October 2016
▫ Contract Completion Date: 28 August 2017
▫ Revised Co ntract Completion Date: 29 September 2017
▫ Contractor's Anticipated Completion Date: 23 October 2017
▫ GRC Forecast Completion Date: 21 Octob er 2017
5. Variations:
Variations to the value of $103,834 have been submitted and
approved. The total value of V ariations included to date
within this Progress Valuation Report equates to $91,721. The
remains no contingency after consideration of all approved
variations. GRC have not verified the validity and the
reasonableness of the variations. Payment of variatio ns are at the
discretion of the financier. Pleas e refer to the Variation Register for
further details.
28 Sep 2017 QSR, relevant excerpts:
1. Contract Statement:
The Value of Work for Progress Valuation No. 15 is $177,059
(excluding GST)
The Value of Work to Complete the Project is $339,348 (excluding GST)
Recommendation | Case number: 743391 Page 37 of 49
Date Key points
2. Building Progress as at 24 July 2017:
Works are substantially complete with works remaining generally consisting
of ground floor windows, fit of AC units, remaining painting, kitchen stone
tops, carpets installations, sanitary fittings, appliances, gates and final clean.
The Contractor is anticipating achieving Practical Completion in the coming
weeks.
4. Building Programme:
There are no reported delays, however the Contractor's revised
anticipa ted completion date is 23 October 2017.
Based on expenditure, construction is 92% complete whic h is behind
our indicative cashflow of 96%. Refer to Indicative Cashflow for
further details.
▫ Contract Commencement Date: 10 October 2016
▫ Contract Completion Date: 28 August 2017
▫ Revised Contract Completion Date: 29 September 2017
▫ Contractor's Anticipated Completion Date: 23 October 2017
▫ GRC Forecast Completion Date: 31 Octob er 2017
5. Variations:
Variations to the value of $103,834 have been submitted and
approved. The total value of Variations included to date
within this Progress Valuation Report equates to $91,721. The remains no
contingency after consideration of all approved variations. GRC have not
verified the validity and the reasonableness of t he variations. Payment of
variations are at the discretion of the financier. Please refer to the Variation
Register for further details.
28 Sep 2017 Progress Payment Request made by borrower S Company. Signed by PL
as director. Account details of M Compa ny provided.
Amount: As per QSR #15
01 Nov 2017 PL signs a Statutory Declaration as director of M Company about
agreement with S Company to complete build at G QLD to say all wages
paid to employees, monies paid to meet invoices and all insurances /
licences / approvals are in place.
01 Nov 2017 QSR, relevant excerpts:
1. Contract Statement:
The Value of Work for Progress Valuation No. 16 is $91, 880
(excluding GST)
The Value of Work to Complete the Project is $247,468 (excluding
Recommendation | Case number: 743391 Page 38 of 49
Date Key points
GST)
2. Building Progress as at 31 October 2017:
Work s are substantially complete with work s remaining generally
consisting of fit of AC units, remaining painting, carpet installation,
remaining shower screens and mirrors, gates and final clean. The
Cont ractor is anticipat ing to achieve Practical Completion by 1
December 2017.
4. Building Programme:
The Contractor's revised anticipated completion date is 1 December
2017 which GRC considers achievable. Based on
expenditure, construction is 97% complete which is in - line wit h our
revised indicative cashflow of 96%. Refer to
Indicative Cashflow for furt her details.
▫ Contract Commencement Date: 10 October 2016
▫ Contract Completion Date: 28 August 2017
▫ Revised Contract Completion Date: 28 August 2017
▫ Contractor's Anticipated Completion Date: 1 December 2017
▫ GRC Forecast Completion Date: 1 December 2017
5. Variations:
Variations to the value of $103,834 have been submitted and
approved. The total value of Variations included to date within this
Progress Valuation Report equ ates to $91, 721. The remains no
contingency after consideration of all approved variations. GRC
have not verified the validit y and the reasonableness of the
variations. Payment of variations are at the discretion of the
financier. Please refer to the Varia tion Register for further details.
01 Nov 2017 Progress Payment Request made by borrower S Company. Signed by PL
as director. Account details of M Company provided.
Amount: $91,880.
22 Nov 2017 PL signs a Statutory Declaration as director of M Company about
agreement with S Company to complete build at G QLD to say all wages
paid to employees, monies paid to meet invoices and all insurances /
licences / approvals are in place.
22 Nov 2017 QSR, relevant excerpts:
1. Contract Statement:
The Value of Work for Progress Valuation No. 17 is $213,840
(excluding GST)
The Value of Work to Complete the Project is $33,628 (excluding GST)
2. Building Progress as at 16 November 2017:
Work s are substantially complete with work s remaining generally
consi sting of shower screens and robe doors to ground unit and
mirrors. The Contractor is anticipating to achieve Practical
Completion by 1 December 2017.
Recommendation | Case number: 743391 Page 39 of 49
Date Key points
4. Building Programme:
The Contractor's revised anticipated completion date is 1 December
2017 which GRC considers achievable. Based on
expenditure, construction is 99% complete. Refer to Indicative
Cashflow for furt her details.
▫ Contract Commencement Date: 10 October 2016
▫ Contract Completion Date: 28 August 2017
▫ Revised Contract Completion Date: 28 Augu st 2017
▫ Contractor's Anticipated Completion Date: 1 December 2017
▫ GRC Forecast Completion Date: 1 December 2017.
5. Variations:
Variations to the value of $103,834 have been submitted and
approved. The total value of Variations included to
date within this Progress Valuation Report equates to $91,721. The
remains no contingency after consideration of all
approved variations. GRC have not verified the validit y and the
reasonableness of the variations. Payment of
variations are at the discretion of the f inancier. Please refer to the Variation
Register for further details.
22 Nov 2017 Progress Payment Request made by borrower S Company. Signed by PL
as director. Account details of M Company provided.
Amount: Progress Claim No 17.
29 Jan 2018 Lender’s file note shows it emailed the borrowers, copied broker in:
Good afternoon PL & Complainant , We wish to advise that
interest in the amount of $23,066.55 is due 17/ 02/2018 based on the
current advanced to dat e, and the interest budget has insuffi cient
funds to cover the entire repayment. Currently the
balance of the loan is as follows; Construction $5,600.00
Contingency $0.00 Development $2,227.05 Interest $186.00 Total
Remaining $8,013.05 There is currently $0.83 residual from last
month's repaym ent, whic h with the remaining interest held will leave
a shortfall of $22,879.72. Please find attached a copy of the direct
debit form as well as BPay and Netbank details for direct transfer of
funds below. Please note that BPay incurs a $1.05 fee and paym ent
via EFT incurs a $2.50 fee. Please tak e this into account when
mak ing payment via these methods. BPAY : Biller Code 18309
Customer Ref No 50 213 368 3 Netbank : BSB 066
712 Account No 50 213 368 3 Please advise how you wish to mak e
the shortfall and future repayments. If you do have any questions,
please let me k now.
12 Feb 2018 Lender’s file note shows:
…Ref er below re SRB. Borrower is going to bring interest payments
up to date immediat ely. Apparently they have sold 3 properties
which I will be ob taining cont racts for. I will k eep you informed as to
my progress over the next week .
Recommendation | Case number: 743391 Page 40 of 49
Date Key points
21 Feb 2018 QSR, relevant excerpts:
1. Contract Statement:
The Value of Work for Progress Valuation No. 18 is $17, 713
(excluding GST)
The Value of Work to Complete the Project is $15,915 (excluding GST)
2. Building Progress as at 16 November 2017:
Work s are complet e and the Certificate of Classification has been
issued by the Certifier
4. Building Programme:
The Contractor's revised anticipated completion date is 1 December
2017 which GRC considers achievable. Based on
expenditure, construction is 99% complete. Refer to Indicative
Cashflow for furt her details.
▫ Contract Commencement Date: 10 October 2016
▫ Contract Completion Date: 28 August 2017
▫ Revised Contract Completion Date: 28 August 2017
▫ Contractor's Anticipated Completion Date: 1 December 2017
▫ GRC Forecast Completion Date: 1 December 2017.
5. Variations:
Variations to the value of $103,834 have been submitted and
approved. The total value of Variations included to
date within this Progress Valuation Report equates to $91,721. The
remains no contingency after consideration of all
approved variations. GRC have not verified the validit y and the
reasonableness of the variations. Payment of variations are at the
discretion of the financier. Pleas e refer to the Variation Register for
further details.
21 Feb 2018 Lender’s email to PL & property management company advising loan
expired on 17 June 2017, is in default and a late payment fee is due under
the contr act. As a gesture of goodwill will not commence recovery action.
26 Feb 2018 Progress Payment Request made by borrower S Company. Signed by PL
as director. Account details of M Company provided.
Amount: Final Claim to Draw Facility Full.
04 Apr 2018 Email from property management company advising the S Company has
accepted an offer from another lender for refinance and is to settle in the
coming 2 to 3 weeks.
Ma y 2018 Borrower sold two of the units in the development.
Recommendation | Case number: 743391 Page 41 of 49
Date Key points
3 Ma y 2018 The lender says it received a request from borrower requesting it forbear for
90 days to allow the sale of the remaining units by auction.
29 Jun 2018 Lender’s lawyers sent a letter to borrower S Company enclosing Notice of
Default, Demand for Repayment and Notice of Intention to Reposes units 2
to 10.
11 Jul 2018 Complainant’s lawyer emails the lender’s lawyers to advise:
- Acting for S Company and complainant
- Acknowledges default & was due to management of
borrower which is now restructured
- Committed to selling properties and outlaid $30,00 on
advertisement
- Client wishes to avoid debt and work with lender to sell
properties
- Requests lender enter into deed of forbearanc e to allow sale
of property.
12 Jul 2018 The lender says the borrower informed it that it would not be refinancing
because it did not want to incur a $100,00 brokerage fee.
9 Aug 2018 The lender took vacant possession of the development.
9 Aug 2018 The borrower’s lawyer emailed the lender’s lawyer requesting 14 days
access to allow sale of 3 units ranging from $380,000 to $390,000.
10 Aug 2018 The lender’s lawyer emailed to borrower’s lawyer to advise of the
outstanding loan amounts, informing acce ss was provided until 23 August
2018 to allow already interested prospective purchasers to inspect and
requested evidence of refinance by 23 August 2018.
23 Aug 2018 The lender’s lawyer emailed to borrower’s lawyer to advise of the
outstanding loan amount s, informing access was provided until 23 August
2018 to allow already interested prospective purchasers to inspect and
requested evidence of refinance by 23 August 2018.
24 Aug 2018 The lender’s lawyer emailed the borrower’s lawyer to confirm the lender
would ‘co - operate regarding inspections (within reason)’.
28 Aug 2018 The real estate agent advised the lender’s property agent that there was an
oversupply in the local area of the type unit which remained to be sold in the
development and it was not uncommon to see a 20 to 30 percent drop in
Recommendation | Case number: 743391 Page 42 of 49
Date Key points
sales value. Provided an apprai sal of the properties, one - bedroom units high
$200,000 to low $300,000 and two - bedroom units mid $300,000. Advised
sale by auction at weekly corporate events run in the CBD and separate
marketing campaigns for each type of unit. Also provided the condition
report.
30 Aug 2018 The borrower’s lawyer emailed the lender’s lawyer to inform the borrower
was meeting with a buyer tomorrow to sign contracts for the remaining units
and requested payout figure.
12 Sep 2018 The borrower’s lawyer emailed the lender’s lawyer to advise the borrower
was negotiating the sale of the remaining units for in the region $3,000,000
with settlement in 21 days with contracts being prepared tomorrow once
terms and price were confirmed.
17 Sep 2018 The borrower’s lawyer emailed th e lender’s lawyer to advise the borrower
had received an offer of $3,070,000 for the remaining units subject to
contract on a 30 - day settlement.
17 Sep 2018 The director and co - guarantor (RL) emailed the lender’s lawyer raising
concerns about the complainant and the sale of the remaining units and
asked the for recommendation of a conveyancer so there was no conflict of
interest between the co - directors of the borrower.
18 Sep 2018 The lender’s lawyer emailed the director (RL) to advise that it should stay
out of issues between directors of the borrower and was reluctant to
recommend another lawyer
20 Sep 2018 The director’s (RL) lawyer emailed the lender’s lawyer to advise that it had
been instructed to act and requested the payout figure
3 Oct 2018 The lender’s lawyer emailed the director’s (RL) lawyer to confirm the
indicative payout figure is $2,535,790.62 and request an update on sale of
the remaining u nits
16 Oct 2018 The independent valuation report valued the remaining units at $3,225,000.
Stated there was a surge of development approvals and there existed a risk
that off plan apartment once developed could over supply the market. There
was general o versupply of similar properties in the immediate area.
Recommended sale by private treaty due to low clearance rate at public
auction after an appropriate advertising campaign.
Recommendation | Case number: 743391 Page 43 of 49
Date Key points
19 Oct 2018 The complainant’s lawyer emailed the lender’s lawyer to request the payout
figure to be able to negotiate on the sale of the units.
24 Oct 2018 The lender’s lawyer emailed the complainant’s lawyer and the other director
and her lawyer to advise that if a contract of sale was entered into today or
tomorrow the payout f igure was $2,582,408.55.
24 Oct 2018 The complainant’s lawyer emailed the buyer’s agent to provide the payout
figure and explained that if something did not happen it would be curtains for
the development.
28 Oct 2018 The buyer’s agent emailed the compl ainant’s lawyer to informing that the
prospective buyer was in San Francisco.
28 Oct 2018 The prospective buyer emailed his agent to inform that he has request an
off - plan valuation, was concerned about it stacking up and asked the agent
to request until 29 October 2018 to review this information and submitting on
an offer.
01 Nov 2018 The lender’s lawyer emailed the buyer’s agent and the complainant’s lawyer
to advise that the offer made by the buyer would not allow the lender to
recover the outstanding debt in full and the offer appeared to be for an
amount significantly less than the total value of the remaining units
01 Nov 2018 The complainant’s lawyer emailed the buyer’s agent and copied in the
lender’s lawyer to ask who gave the buyer’s agent autho rity to enter
discussion with the mortgagee’s lawyer. The email stated,
…
To date you have produced nothing b ut useless contracts and delay after
delay.
If your client wants to negotiate a purchase it should do so via my office and
not my client’s mortgagee’s lawyer.
You and your client have had more than ample time to make an offer.
My client can sell the property under value but it cannot sell the property for
less than the payout under the mortgage and must cover rates, water, land
tax and b ody c orporate levies and any legal or agents costs on the sale.
Why don’t you have your client formalise an offer with an amount on it rather
than waste everyone’s time asking for my time.
As you can see my client’s situation is not ideal and your prompt attent ion to
Recommendation | Case number: 743391 Page 44 of 49
Date Key points
forming an unconditional offer with a 10% deposit is required.
In the event that you do not have a party in a position to purchase on an
unconditional basis now my client is forced to look elsewhere for a b uyer.
07 Nov 2018 The lender’s lawyers sen t a letter to the borrower informing that as defaults
has not been rectified it had taken possession of the properties as per the
notice provided on 29 June 2018 and would no longer allow the borrower
access to the properties.
08 Nov 2018 The complainant’ s lawyer emailed the lender’s lawyer to inform the
complainant had someone to go to contract at $2,950,000 on an
unconditional basis and requested access to inspect the development
tomorrow at noon.
08 Nov 2018 The lender’s lawyer emailed a letter to the borrower enclosing a Notice of
Exercise of Power of Sale under Section 84 Property Law Act 1974 - 1986
(Qld) notifying the borrower was required to remedy the default within 30
days by paying the amounts outstandin g under the loans ($2,591,917.75).
Ad vising that opportunities had been afforded to sell the remaining units and
the lender had engaged agents to sell the units which had been listed for
auction on 15 December 2018.
16 Nov 2018 The lender listed one of ea ch type of unit in the development on 4 different
internet property search sites for inspection and sale by auction on 15
December 2018.
21 Nov 2018 The lender listed the one of each type of unit in the development for sale in
the newspaper at auction.
28 Nov 2018 The agent advised that since the commencement of marketing of units there
had been three inspections. Prospective purchasers liked the size, layout
and proximity to public transport, but did not think the development was
maintained well or li ke the main road location. One prospective purchaser
had made offers for unit 9 and unit 10 but recommended the offers be
declined subject to approval of deposit of $15,0000 and 60 - day settlement
at auction
06 Dec 2018 The agent advised it had received five new enquiries and had two groups
through to inspect the units. The price indications due to oversupply of type
of units was $250,000 (two bedroom) and $200,000 (one bedroom).
11 Dec 2018 The lender received nine conditional contracts from the same pr ospective
Recommendation | Case number: 743391 Page 45 of 49
Date Key points
buyer for a total of $2,540,000.
15 Dec 2018 The lender auctioned one type of each unit in the development. A one
bedroom and a two bedroom.
04 Jan 2019 The lender listed the units for sale on five different internet property search
sites.
0 8 Jan 2019 The agent advised ten enquiries were received and four inspections had
taken place over the Christmas period. Prospective purchasers liked the
size, layout and proximity to public transport but did not think the
development was maintained well or like the main road location. Price
indications were $250,000 (two - bedroom units) and $200,000 (one - bedroom
unit).
09 Jan 2019 The lender received an email from its agent with a condition report and
photographs about maintenance required to the car park, common ar eas,
balconies, units and gardens to make the development more presentable to
prospective buyers.
15 Jan 2019 Lender receives an email from property agent forwarding email of owner of
unit about outstanding body corporate fees and telecommunications
conne ctions to the complex.
21 Jan 2019 The agent advised no new enquiries and no inspections were undertaken.
The agent requested the lender provide information about list prices, NBN
and Strata fees, requiring quotes for the common areas, occupancy
certifi cates and additional marketing costs.
25 Jan 2019 The lender received an email its agent forwarded from an owner of one of
the units which advised there were outstanding body corporate fees and
there being no telecommunications connection to the development in breach
of the development approval. The owner provided contacted details for the
body corporate and Telstra and advised the quote for the connection was
around $7,000 and required payment.
06 Feb 2019 The agent advised two new inspections had taken place in the past week.
One prospective buyer was looking for a two - bedroom unit and had just
started undertaking inspections and the second prospective buyer submitted
an offer for unit 10.
11 Feb 2019 Th e agent advised two new inspections had taken place in the past week
Recommendation | Case number: 743391 Page 46 of 49
Date Key points
but did not make a request to inspect the property and not knowing the
asking price was a deterrent.
12 Feb 2019 The lender paid invoice for outstanding Bode Corporate fess of $2,940.
20 Feb 2019 The agent advised two new inspections had taken place in the past week
and both parties were showing interest but were not prepared to submit
offers until asking prices were known.
28 Feb 2019 The agent advised one inspection was undertaken last week. The price
indications from interested party were $220, 000 to $240,00 (one - bedroom
units) and $280,000 to $300,000 (two - bedroom units). The agent enquired
with the lender about responding to an offer for unit ten, list prices for unit s,
quotes to clean common areas, additional marketing costs, response to
email from unit owner and occupancy certificates
04 Mar 2019 The agent advised there were no new enquiries and interest party was the
prospective buyer who submitted an offer for un it 10 and requested the
lender provided responses to queries about response to offer for unit ten, list
process for units, quotes to clean common areas, additional marketing,
response to owner of unit and occupancy certificates.
13 Mar 2019 The agent ad vised no new enquiries had been received, updated valuations
were due on Friday and would forward to the lender.
15 Mar 2019 The independent valuation report valued the remaining units as follows:
Market Value ‘As Is’:
Units 2, 3, 7 & 8 $315,000
Units 5, 6 & 10 $335,000
Units 4 & 9 $240,000
Market Value Range:
Units 2, 3, 7 & 8 $300,000 to $330,000
Units 5, 6 & 10 $320,000 to $345,000
Units 4 & 9 $220,000 to $250,000
The report recommended:
We recommend the property b e offered for sale b y private t reaty with an
experienced agent that is active in the local market. An appropriate
advertising campaign should b e conducted during a marketing period. The
Recommendation | Case number: 743391 Page 47 of 49
Date Key points
sale method is recommended because this is considered the most likely
method to entice demand to achi eve a sale at a reasonable price. Pub lic
auction is not recommended as there are low clearance rates at public
auctions for this type of property in this location in the current market .
25 Mar 2019 The lender advised the agent to proceed with additional marketing,
confirmed acceptance of the offer for unit 8 and 10 and provided list prices
for units.
25 Mar 2019 Lender accepted an offer of $308,500 for unit 8.
Lender accepted an offer of $325,000 for unit 10, contract for sale and
settlement of unit 10.
27 Mar 2019 The agent advised two enquiries were received and three inspections had
taken place in the past week and now that list prices had been provided
those who previously undertook inspectio ns had commenced submitting
offers. Offers for unit eight and ten had been accepted and an offer had
been submitted for unit two. Updated advertising text had been forwarded to
the lender for approval.
29 Mar 2019 Lender accepted an offer of $305,000 for unit 3.
02 Apr 2019 The agent advised three new inspections has taken place in the last week
and numerous offers had been submitted for units since list prices were
provided. It was awaiting final offers for unit 6. The buyer of un 8 was
expected to return contract once received letter from lender about a grant
and requested responses about contracts and offers for development units.
03 Apr 2019 Lender accepted an offer of $315,000 for unit 6.
Lender accepted an offer of $245,00 for unit 9.
08 Apr 2019 Lender accepted an offer of $235,000 for unit 4.
09 Apr 2019 Lender accepted an offer of $300,000 for unit 2.
10 Apr 2019 The agent advised three inspections has taken place in the last week. An
offer had been received for unit two and offers had been accepted for units
2, 3, 4, 6, 8, 9 and 10. The agent was working with interested parties to
secure offers for units 5 and 7.
Recommendation | Case number: 743391 Page 48 of 49
Date Key points
29 Apr 2019 The agent advised three new inspections had taken place in the past week
but no offers. A prospective purchaser submitted a final offer of $300,000
and request a response. Another prospective purchaser who indicated they
would increaser their offer for unit 7 to $310,000 had yet to formally return a
contract.
01 May 2019 Lender accepted an offer of $310,000 for un it 7 (rescinded).
13 May 2019 Lender accepted an offer of $325,000 for unit 5.
13 May 2019 Contract of sale for unit 2, 3, 4, 6, 7 (rescinded deposit of $15,000 forfeited)
& 9.
29 May 2019 Contract of sale for units 5 & 8.
13 Jun 2019 Settlement of unit 9.
19 Jun 2019 Settlement of unit 4.
24 Jun 2019 Settlement of unit 6.
27Jun 2019 Settlement of unit 2.
28 Jun 2019 Settlement of units 3 & 8.
08 Jul 2019 Settlement unit 5.
08 Aug 2019 The lender paid an invoice for $4,400 from Telstra for NBN connections to
the units.
26 Aug 2019 The independent valuation report valued the remaining unit 7 as follows:
Market Value ‘As Is’:
Unit 7 $310,000
Market Value Range:
Unit 7 $290,000 to $320,000
Recommendation | Case number: 743391 Page 49 of 49
Date Key points
The report recommended:
We recommend the property be offered for sale by private treaty
with an experienced agent that is active in the local mark et. An
appropriate advertising campa ign should be conducted during a
mark eting period. The sale method is recommended because this is
considered the most lik ely method to entice demand to achieve a
sale at a reas onable price. Public auction is not recommended as
there are low clearance rates at public auctions for this type of
property in this location in the current mark et .
09 Sep 2019 The agent provided details of three offers which had been made for unit
seven. The lender advised the agent to accept the first offer.
9 Sep 2019 Lender accepted an offer of $329,000 for unit 7.
10 Sep 2019 The agent advised in the past two weeks it had received 12 enquiries and
undertaken seven inspections for unit seven and that three offers had been
received with one being accepted.
19 Sep 2019 Contra ct of sale for unit 7.
23 Oct 2019 Settlement of unit 7.
16 Dec 2019 Lender’s Statement of Claim.
11 March 2020 Complainant’s Notice of Intention to Defend the Claim from the lender sets
out the claim induced to sign documents and that the lender ought to have
known the complainant did not know what she was signing and did benefit
from the loans.
24 Jul 2020 AFC A complaint lodged.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.