Home / Commonwealth Bank / Determination 743140

Determination 743140

Receivership, default interest and validity of guarantees on expired business facilities

FirmCommonwealth Bank
Decided2021-08-03
ProductCredit · Business lending
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

Directors and guarantors of expired business facilities complained about receivership, default interest and guarantee validity. AFCA adopted the recommendation and found in favour of the bank, which was not required to take any action.

The bank validly enforced its default and security rights under the facility terms, and the guarantees remained valid because the term extensions did not increase guarantor liability.

Issues

Subjects and remedies

small businessno remedy

Related

All Commonwealth Bank determinations · Find similar determinations

Text of the determination

Determination Case number 743140 Financial firm Bank of Western Australia Limited Determination | Case number: 743140 Page 2 of 6 Case number: 743140 3 August 2021 1 Determination overview 1.1 Complaint The complaint relates to four expired business facilities (the facilities) held with the financial firm (the bank). The borrowing entities Sp Corp, Sp Oc and A&O company (the borrower companies) are under external administration. The complainants are the directors of the borrower companies and complainants 1 and 2 have also provided guarantees as security for the facilities. The facilities are as follows: The complainants say:  The bank invalidly appointed receivers to the borrower companies and charged default interest, hindering their efforts to refinance with another lender.  The guarantees provided as security for the facilities are invalid following variations applied to the original lending term. On 29 January 2021, the case manager provided the parties with a recommendation on the issues in dispute. The recommendation was in favour of the bank. A copy of 1 Arrears as at 29 September 2020 Borr ower Guarantees Expired Arrears 1 Sp Corp c ompany Busine ss facility * 142 - 3 Comm ercial Guarantee Small business guarantee provided by complainant 1 and 2. 15 August 2018 $298,573 Sp Corp company Commercial advance *95 - 7 Comm ercial Guarantee Small business guarantee provided by complainant 1 and 2. 15 August 2018 $664,281 A&O company Busine ss facility *120 - 4 Comm ercial Guarantee Small business guarantee provided by complainant 1 and 2. 31 August 2018 $285,521 Sp Oc company Busine ss facility *131 - 9 Comm ercial Guarantee Small business guarantee provided by complainant 1 and 2. 31 August 2018 $731,535 Determination | Case number: 743140 Page 3 of 6 the recommendation is attached to this determination incorporating some typographical revisions for clarity. The complainants rejected the recommendation. 1.2 Issues and key findings Were the findings of the recommendation correct? Based on all the available information, the findings contained in the recommendation were correct and are adopted in this determination. The complainants‟ rejection of the recommendation has been considered. Does the complainants’ rejection change th e outcome? The complainants rejected the recommendation alleg ing „ serious errors of both law and fact‟ and stating they „expressly reserve their rights to proceed with their claims against the [bank] in a court of competent jurisdiction ‟. The complainants have not identified any errors of fact or law in the recommendation. After reviewing all relevant information, their rejection does not change the AFCA outcome. The complainants are free to pursue the issues disputed outside of AFCA, be it in the courts or otherwise. 1.3 Determination This determination is in favour of the bank. The bank is not required to undertake any action by this determination. Once AFCA‟s file is closed the bank may commence any recovery action necessary against the borrower companies and complainants in line with the relevant terms and conditions of the loan contracts and guarantees provided. Determination | Case number: 743140 Page 4 of 6 2 Reasons for determination 2.1 Were the findings in the recommendation correct? The recommendation was correct This complaint has been determined based on what is fair in all the circumstances, having regard to the legal principles, applicable industry codes or guidance, good industry practice and previous decisions of AFCA or its predecessor schemes (which are not binding). A full exchange of the relevant information has taken place between the respective parties. Each party has had the opportunity of addressing any iss ues raised. All of the relevant information has been reviewed and considered. The parties have raised numerous issues in their submissions to AFCA. However, commentary in this determination is restricted to those issues considered relevant to the outcome. The recommendation findings are correct I am satisfied that the recommendation contains an accurate summary of the complaint and the issues to be determined by AFCA. The recommendation correctly applied the applicable paragraphs of the AFCA Rules, Code of Banking Practice (the code) and relevant legal principles regarding the binding nature of terms and conditions were there are no e xtenuating circumstances have been established. As I agree with the recommendation it is adopted into this decision and attached. I will not repeat the findings in this determination. The bank reserved its rights when negotiating with the complainants Correspondence exchanged between the parties in 2018 about the imminent and current expiry of loan facilities shows the bank expressly reserved its rights when negotiating with the borrower companies. I am satisfied this included the bank‟s rights under the credit agreements to undertake recovery action and apply default interest. There is no information to show that the bank is prevented from that action in line with the terms and conditions of the facilities. The bank was not required to stop recovery action on the promise of refinance I acknowledge the complainants say the bank‟s conduct was inappropriate when it appointed receivers and applied default interest to the facilities. Notwithstanding the com plainants taking issue with the bank‟s action , the bank acted in line with its rights under the facility agreements. The bank made it clear in negotiated agreement terms to allow complainant one more time to address the balance of the expired facilities provided they obtained an unconditional contract of sale to repay the debt and it was received within a set timeframe. As no sale contract was received, nor has any such contract been provided to date, the bank was not required to delay recovery action. It is Determination | Case number: 743140 Page 5 of 6 unreasonable to expect that the bank put any further recovery action on hold, especially where prolonging repayment of the debt owing is in neither parties‟ best interests, simply on the promise of refinance to another lender or reduction by a future sale. Variations accepted by the guarantors were to allow further time The bank met its code obligations at the time the guarantees were provided. It also complied with disclosure obligations owed to the guarantors when it obtained the consent of complainant 1 and 2 to the variations made to the facilities. It is important to note the variations were to the term of the facilities only and did not increase the guaranto rs‟ debt obligations. Rather, the variations provided the term extensions requested by the complainants. The bank acted in response to the complainants‟ pleas to allow more time to address the expired facility debt. It is unreasonable to consider that the bank‟s assistance in providing the complainants more time should be penalised by invalidating its security interests. The bank has not benefited from the extensions provided. Rather, the effect has been to prolong the bank‟s ability to recover the debt owed under the facilities. The guarantees are valid I am satisfied the guarantees remain valid based on all the relevan t information . The liability of complainant s 1 and 2 as guarantors was contingent on the borrowers failing to meet their obligations. T h is means complainant s 1 and 2 have obligations as guarantors that are dependent upon the borrower companies as debtor s failing to perform the ir obligations . The bank has not called up the guarantees to date. If the primary obligations of the borrower companies as debtors are discharged, the guarantees fall away. 2.2 Does the complainants’ rejection change the outcome? The complainants rejected the recommendation On 15 February 2021, the complainants wrote to AFCA and advised: „ My clients' view is that the initial decision maker has made serious errors of both law and fact. They expressly reserve their rights to proceed with their claims against the financial services provider in a court of competent jurisdiction. ‟ The complainants have provided no further submissions or supporting information to identify any specific alleged error. AFCA has applied the relevant industry code and legal principles Having reviewed all the relevant information, I am satisfied the relevant industry code and legal principles have been applied by AFCA. The bank is a subscriber to the code, and the correct version of the code has been applied to the complaint events. Determination | Case number: 743140 Page 6 of 6 Legal principles concerning contract law have been considered against the complainants‟ request for contractual remedies including invalidating the guarantees provided. The circumstances of the complaint do not invoke any such remedies or action by the bank. The complainants are at liberty to pursue their claims outside of AFCA AFCA is a complaint resolution service offered as a free alternative to the courts. We are not a regulator of the financial services industry. AFCA is not a court of law and has considered the complaint issues raised within the scope of our Rules. The complainants lodged their complaints to AFCA for consideration in line with our Rules and process which I am satisfied has been done. The complainants may choose to pursue their claims in another jurisdiction beyond AFCA. Recommendation Case number 743140 Financial firm Bank of Western Australia Limited Recommendation | Case number: 743140 Page 1 of 15 Case number: 743140 29 January 2021 3 Overview 3.1 Complaint The complaint relates to the four business facilities (the facilities) outlined in the table below held with the financial firm (the bank). The borrower companies are currently under receivership and are listed as under external administration. The complainants are the directors of the borrower and guarantor companies (Sp Corp, Sp Oc and A&O company) and personal guarantors for the facilities. The complainants say they have been trying to refinance the facilities to a different lender, however the bank appointed receivers, changed the repayment date and charged default interest impeding their ability to refinance. The complainants also dispute the validity of the guarantees held for the facilities. 2 Arrears as at 29 September 2020 Borrower & *Facility Guarantees & indemnities Expired Arrears 2 Sp Corp c ompany Busine ss facility * 142 - 3 Commercial Guarantee and indemnities Small business and consumer guarantee and indemnities provided by complainant 1 and 2. 15 August 2018 $298,573 Sp Corp company Commercial advance *95 - 7 Commercial Guarantee and indemnities Small business and consumer guarantee and indemnities provided by complainant 1 and 2. 15 August 2018 $664,281 A&O company Busine ss facility *120 - 4 Commercial Guarantee and indemnities Small business and consumer guarantee and indemnities provided by complainant 1 and 2. 31 August 2018 $285,521 Sp Oc company Busine ss facility *131 - 9 Commercial Guarantee and indemnities Small business and consumer guarantee and indemnities provided by complainant 1 and 2. 31 August 2018 $731,535 Recommendation | Case number: 743140 Page 2 of 15 3.2 Issues and key findings Were receivers validly appointed? The receivers were validly appointed in line with the facility terms and conditions upon valid default events and notification to the complainants. The bank was entitled to exercise its contractual right to appoint receivers and managers as the primary event of default allowed it to do so. The bank is also entitled to apply default interest to the facilities. The bank had no obligation to renew the facilities when the facility terms expired. Nevertheless, the bank has provided several extensions and opportunities for the complainants to make arrangements to address the arrears and provide notice of unconditional refinance approval to refinance the balance of the expired facilities. Should the guarantees be set aside? The guarantees were obtained validly and in line with the bank‟s code obligations. Statutory declarations signed by each of the complainants show they received independent legal advice regarding the facilities and security documents at the time of providing the original guarantees. Subsequent guarantor certificates also show the complainants voluntarily chose not to obtain independent legal advice in relation to the variations and extension of the facility terms in 2016 and 2017. The guarantees remain valid until such time as the conditions to release the guarantees are met. The complainants have not met any conditions to release the guarantees and they remain valid. 3.3 Recommendation This recommendation is in favour of the bank. The bank is not required to undertake any action by this recommendation. Recommendation | Case number: 743140 Page 3 of 15 4 Reasons for recommendation 4.1 Were the receivers validly appointed? The complainants dispute the validity of the bank’s appointment of receivers The complainants request AFCA declare any receivers appointed over the companies were not validly appointed. AFCA does no t have the receiver‟s consent to the companies pursuing claims against the bank. This means as the companies are under the control of a receiver and manager, we cannot review the actions of the receivers and cannot review a complaint about financial difficulty. The director complainants (complainants 2 and 3) retain “residual rights” even after the appointment of receiver managers (receiver). These residual rights include the right to challenge the appointment of a receiver to the company. In these circumstances, the AFCA has reviewed the validity of appointment of receivers raised by complainant 2 and 3 and we don‟t need consent from the receiver s. The relationship between the companies under receivership, the facilities in dispute and the complainants is summarised below: The loan terms and conditions provide when the bank can appoint receivers We are unable to review the actions of the bank where it has acted in accordance with the terms and conditions of the agreement and without breaching any specific obligation or duty owed to the customer. In this case, the terms and conditions outline when receiver managers may be appointed following an event of default. Relevant sections of the terms and conditions are outlined in section 3.1 of this recommendation. Borrower company Director / secretary Company Facility Guarantor Sp Corp c ompany Mr And. P (Complainant 2), and Mr C P (Complainant 3) Mr Ang. P ( Complainant 1 ) and C omplainant 2 Sp Oc company ATFT Sp Oc Unit Trust Complainant 2 Complainant 1 and 2 A&O company ATFT A$O Unit Trust Complainant 3 Complainant 1 , 2 and 3 Recommendation | Case number: 743140 Page 4 of 15 There was an event of default for each of the facilities I am satisfied the facilities were expired or in arrears at the time the bank appointed the receiver. This is taking into consideration terms and conditions definitions, facility balances, letters of variation and correspondence between the parties. In line with section 16 „Events of Default‟ under terms and conditions: An Event of Default occurs, whether or not it is in your power to prevent it, if: (a) you do not pay on time any amount payable by you under any Facility Document including under documentation relating to any [bank] Facility in the manner required under it (b) you do not comply with the terms of the Facility Documents, including the terms of the Agreement It is not disputed and clear from the loan documents, the facilities have expired. When the facilities expired, the outstanding balance of the facilities became due and payable immediately. When the outstanding balances were not repaid by the end of the term (by refinance or otherwise), the facilities were in default. The bank issued default and demand notices before it appointed receivers On 25 February 2020, the bank appointed receivers and managers to the assets of the company group following demand notices sent in October 2019 and on 23 January 2020. The bank is a subscriber to the Code of Banking Practice (the code). Chapter 21 of the code outlines the bank‟s notice requirements for small business: 75. If you are a small business and in default under your loan, we will give you 30 days‟ notice before we either require you to repay the loan in full, or take enforcement proceedings. 76. If you remedy the default during the 30 day period, and no default of the same type has arisen during that period, we will not require full repayment or take enforcement proceedings. In October 2018 the bank sent demand notices to the borrower companies and director complainants. At the same time, the bank wrote to the guarantor complainants advising them of the facilities in default. The demand notices noted the facility type, account number, outstanding balance and the 30-day demand due date for each facility in default in line with the code notice requirements for small businesses and section 16.2 of the terms and conditions. The bank was entitled to appoint receivers and acted reasonably in doing so As outlined in section 1.1 of this recommendation, the bank had security interests for each facility which was granted by the companies and guarantor complainants. The Recommendation | Case number: 743140 Page 5 of 15 companies did not remedy the defaults as required and outlined in the demand notices. Under section 16.5 of the terms and conditions the bank was entitled to appoint a receiver to manage the sale of the companies‟ assets held as security to address the balance of the facilities: If we reasonably believe that there is or may be an Event of Default, we may request a person to investigate, report to and advise us on the financial and trading condition of you and any Guarantor. I am satisfied the appointment of the receiver was reasonable in the circumstances. The sale of the company securities and equipment were likely to require specialised knowledge and it was acceptable for the bank to appoint the receiver to ensure the sale was managed by a specialist agent. Furthermore, the bank provided adequate notice and clear timeframes to address the balance of the facilities before it appointed the receivers in February 2020. The bank provided additional time to refinance after the facilities expired The bank extended the facilities by variation agreements in 2016, 2017 and 2018. In August 2018 it allowed addition time for the complainants to obtain refinance approval. Later in December 2018 the bank began to apply default interest to amounts in default. Following this, complainant 1 lodged an AFCA complaint in relation to the default interest applied and financial difficulty. In response the bank negotiated with complainant 1 allowing additional time to obtain funds to pay the facilities by reduction of debt by sale of a related business and refinance of the balance. While complainant 1 was not successful in paying down the balance as negotiated, the bank remained open to receiving confirmation of refinanced or contracts of sale beyond the negotiated due date. In default notices it reiterated its willingness to consider any reasonable proposal to deal with the defaults: Although the Bank has issued you this demand, the Bank (without prejudice to its rights under this demand) is willing to consider any further reasonable proposals you may have to deal with the defaults on your facilities or financial difficulty you may experience. In these circumstances, I am satisfied the bank provided the complainants reasonable opportunity to address the defaults before appointing receivers. The complainants have not obtained any refinance approval The bank acted in accordance with good industry practice and fairly in the circumstances, by granting the complainants extensions to the facility terms, this provided them an opportunity attempt to refinance or repay the disputed loans by other means within the extended period. Notwithstanding the complainants have been unable to obtain refinance approval to date. Recommendation | Case number: 743140 Page 6 of 15 There is no information to show the companies or individual complainants obtained an unconditional offer from another lender to refinance the facilities or have any other way of repaying the loans in full. While this is unfortunate, it does not prevent the bank from enforcing its security interests and rights under the terms of the facilities. The bank’s negotiations with complainant 1 does not change valid appointment In July 2019, complainant 1 and the ba nk reached a conciliation resolution relating the A&O company debt. The conciliation was only attended by complainant 1 (not complainant 2 or 3). The resolution agreement included, after discussions between the bank and complainant 1, a strategy to repay the facility debt by sale of a related business (the related business) and the refinance of the remaining debt to another financial institution. The related business is not a security provider for the facilities. Following this, the facilities continued to accrue arrears and correspondence between the parties suggest several later assurances for repayment of the debt and sale of the related business. This and available information shows leading up to the expiry of the facilities, t he bank worked with complainant 1. However, no contract of sale or unconditional refinance offer was provided. The bank provided 30 days’ notice of default before receivers were appoint ed The bank has provided time for the company group to honour the facility and resolution agreement terms. However, the company group has not met their obligations within the required timeframes and in October 2019 the bank recommenced recover action with demand letters issued on 23 and 24 October 2019. On 29 January 2020, a further notice of continued default letter was issued to the complainants and after a further period of non-compliance, on 25 February 2020 the bank appointed receiver and managers for the company group. It is important to note, although receivers and managers were appointed in February 2020, the bank instructed them to cease recovery action when the complainants lodged a further AFCA complaint in March 2020. The bank is entitled to apply default interest Section 16.4 of the terms and conditions outlines what interest the bank can apply to the facilities in the event of default. The bank applied overdue interest to the facilities which expired in December 2018. The bank is entitled to apply default interest to the expired and overdrawn facilities. The complainants have not provided any reasonable explanation why this should not be the case in the circumstances. From a financial difficulty perspective (including prior to the appointment of receivers), it would have been at the bank‟s discretion as to whether it would apply or waiver any interest otherwise applicable to the facilities. Recommendation | Case number: 743140 Page 7 of 15 The bank is not required to allow more time for the complainants to refinance I acknowledge complainant 1 advised the bank that they were in the process of re- financing before receivers were appointed. However, the bank made it clear it would only consider withdrawing enforcement proceedings if an unconditional contract or a contract of sale to repay the debts was received with in a set timeframe. None was received nor provided to date, and the bank is not required to provide the complainants more time to attempt to secure refinance approval. 4.2 Should the guarantees be set aside? The complainants seek the guarantees be set aside as no longer valid The facilities ‟ security includes a combination of commercial guarantees, individual guarantees and residential and commercial property mortgages. The facilities have been managed by the bank‟s group credit structuring team since January 2016 with a history of loan arrears. The bank advises its main contact with the company group has been with complainant 1. The complainants in their capacities as guarantors seek any guarantees for the loans be set aside on the basis they are no longer valid due to variations to the facilities. AFCA can consider the complainants‟ claims made in their capacity as guarantors about whether the guarantees, or the amount guaranteed, should be set aside. In reviewing these matters, it is relevant to note the bank has not called upon the complainants as guarantors to remedy the defaults on the facilities to date. The guarantee obligations are outlined in the Code of Banking Practice The code outlines the bank ‟ s obligations in relation to obtaining guarantees. In line with the code, the bank must provide all individuals, irrespective of their professional acumen or prior relationship with the bank, with certain notices prior to entering into a guarantee and indemnity. Prominent and explicit notice must be given of the following issues:  the individual can refuse to enter into the guarantee and indemnity  there are financial risks involved in providing a guarantee and indemnity  the individual has a right to limit the liability under the guarantee and indemnity and the current liability under the proposed guarantee and indemnity  the individual can obtain information about the transaction or facility it is guaranteeing, and  the guarantor may obtain independent legal and financial advice in respect to the guarantee and indemnity. The bank must also allow the guarantor an appropriate amount of time to consider the finance documents and obtain independent legal and financial advice if necessary. Recommendation | Case number: 743140 Page 8 of 15 Where the guarantor does not wish to obtain independent legal and financial advice, the bank should consider obtaining a waiver of independent legal and financial advice to demonstrate that the individual has opted not to seek this advice. The bank has provided information to show the validity of the guarantees The bank has provided the following supporting documents in relation to the guarantees disputed:  signed Letters of Offer  statutory declarations by the complainants at the time of providing the guarantees outlining details of advice obtained and authorised witnesses  Guarantor Certificates showing independent advice voluntarily not obtained  guarantor correspondence including notification letters for loan variations applied  signed Privacy and Consent Forms. A summary of the disputed guarantees, documents provided to the complainants at the time of signing and advice received is set out in section 3.2 of this recommendation. Upon review of the available information and the complainants‟ arguments, t here is no evidence to suggest the bank did not fulfil its code obligations at the time of obtaining the guarantees or obtaining the complainants‟ consent to the variations of the facilit ies‟ terms. Guarantee documents show the complainants received independent legal advice and relevant disclosures. The guarantees signed by the complainants were witnessed by the lawyer who provided the independent advice. The complainants also signed waivers to say they voluntarily chose not to obtain any further advice at the time of the facilit ies‟ term variations and received relevant disclosures. An extract of the waivers signed is outlined in section 3.3 of this recommendation. The complainant’s guarantor obligations did not change due to loan variations The loan variations conducted were in the form of term extensions, for the benefit of the borrower companies, to allow further time for the complainants to reduce the debt and obtain refinance approval. The guarantor‟s obligations did not change, and each gave their consent by signing the Guarantors Acknowledgement on each Letter of Variation. Recommendation | Case number: 743140 Page 9 of 15 The guarantees should not be set aside The guarantees remain valid. The complainants have not met any conditions to release the guarantees, for example, by way of:  security property sale  refinance  repayment of debt  change in property ownership, or  variation or security swap. In the absence of any information to indicate the guarantees have been properly released, they remain valid and may be called upon in line with terms and conditions. Recommendation | Case number: 743140 Page 10 of 15 5 Supporting information 5.1 Relevant sections of General Terms and Conditions 11 Interest 11.3 Capitalisation (a) We may add amounts payable by you under clause 11.2 which are not paid when due for payment to the Outstanding Amount monthly or at such other intervals as we reasonably consider appropriat e. (b) Interest is payable on the increased Outstanding Amount at the rate and in the manner set out in clause 11.2. … 16 Events of Default 16.1 Events An Event of Default occurs, whether or not it is in your power to prevent it, if: (a) you do not pay on time any amount payable by you under any Facility Document including under documentation relating to any [bank] Facility in the manner required under it; (b) at any time the Outstanding Amount in relation to a Facility and/or [bank] Facility exceeds its Facility Limit or applicable Sublimit; (c) you do not comply with the terms of the Facility Documents, including the terms of the Agreement; … 16.2 If an Event of Default occurs If an Event of Default occurs we may choose to enforce the Agreement. If we decide to do this, we will give you notice except as set out below. The notice will tell you what the Event of Default is and ask you to fix it by a specified date. It will also cont ain any information the law requires us to give you. If you can fix the Event of Default, you have the time specified in the notice to do so after we give you the default notice. If we give you a notice, you will be given at least 30 days to fix the Event of Default. If you have not fixed it by then, we can enforce the Agreement. … 16.3 Consequence s of an Event of Default If the Event of Default is not remedied within the time specified in any notice, or if we do not give you a notice, we can do any one or more of the following: (a) give you notice speci fying a new Final Repayment Date or a new Facility Expiry Date for any Facility, which may be the day we give the notice to you or any other later day; (b) decide that the Total Outstanding Amount is due and payable immediately, without further notice to you; (c) give you notice declaring the Total Outstanding Amount is immediately due and payable. (d) cancel the Agreement and any other related agreement and no longer provide any Facility or other financial accommodation to you; (e) terminat e any Risk Management Trans action and calculate the close -out amount payable in accordance with clause 7.8; (f) give you written notice requiring you to: (i) provide additional security to secure the Total Outstanding Amount, which may include depositing with us such amount that we may reasonably require; and signing our Set Off Agreement; (ii) pay us such amount to reduce the Total Outstanding Amount to the amount we reasonably require; or (iii) do bot h of (i) and (ii), within the time nominated by us. If we give you a written notice under this sub-clause 16.3(f), we will act reasonably in det ermining the additional security and/or amount we ask you to provide. In making our determination, we will consider what impact, if any, the Event of Default has on our credit risk; the value of any Secured Property; the enforceability of Security and any change in the likelihood of our being able to recover the Total Outstanding Amount from you and/or any Guarantor; Recommendation | Case number: 743140 Page 2 of 15 (g) conduct a Facility Review; (h) stop payments under any Facility; (i) exercise our rights under any Security; (j) debit any account you have authorised us to debit; (k) refuse to give you any undrawn portion of any Facility or permit any Drawing; (l) stop or suspend the provision of any product or service; (m) refuse to consent to any dealings with you or and Guarantor; (n) stop our compliance with the Agreement; (o) sue you for the Total Outstanding Amount; (p) increase the Interest Rate or Margin and remove any Int erest Rate concession or Margin on giving 10 Business Days‟ Notice; or; or (q) terminat e any or all Facilities. We may take any or all of the actions set out in clauses 16.3 and 16. 4 despite any delay or previous waiver by us, unless we have expressly agreed not to or it would be unconscionable to exercise that right later. We may also take any other action we are entitled to take under the Facility Documents following the occurrence of an Event of Default. The giving of notice under this clause gives immediat e effect to its provisions. We may take any or all of these actions in relation to both a Facility and a [BANK] Facility. 16.4 Consequence s: Interest (a) In addition to any other consequences under the Facility Documents, if: (i) an Event of Default has occurred and you fail to pay any amount (including interest) on the due date or any Facility Limit or Sublimit is exceeded on any Facility and/or [bank] Facility; (ii) any other Event of Default has occurred and: a) we have notified you of its occurrence; and b) if the Event of Default is capable of remedy, has not been remedied within the time period set out in the notice; or (iii) any other Event of Default has occurred; or (iv) we have taken action under clause 16.2, then you must pay interest on the unpaid amount calculated at the Overdue Rate from the date of the occurrence of the relevant Event of Default in the case of clause 16.4(a)(i) and claus e 16.4(a)(iv) or from the date on which the notice period expires in the case of clause 16.4(a)(ii) and claus e 16.4(a)(iii). This interest shall accrue and be capitalised in the manner specified in clause 11. 3. … 16.5 Inve stigation of financial and trading condition If we reasonably believe that there is or may be an Event of Default, we may request a person to investigat e, report to and advise us on the financial and trading condition of you and any Guarant or. You must co-operate with the person, including by providing authorisations, relevant information, rec ords and access to individuals, premises and business equipment used in the conduct of your business including, without limitation, all electronic devices (for example, computers and databases) and comply with every reasonable request they make. You must pay all Costs in connection with the investigation. Recommendation | Case number: 743140 Page 12 of 15 5.2 Disputed Guarantees Date provided Guarantor Documents received Independent Legal Advice Witness Sp Company 20 May 2011 Complainant 1 (Mr Ang. P) Letter of Offer Irrevocable Authority Small Business and Cons umer Guarantee and Indemnity Cons umer mortgage Declared – Received Registered Accountant 20 May 2011 Complainant 2 (Mr And. P) Letter of Offer Irrevocable Authority Small Business and Cons umer Guarantee and Indemnity Declared – Received Registered Accountant 30 October 2012 Complainant 2 Letter of Variation Declared – Received Pharmacist 31 October 2012 Complainant 1 Letter of variation Declared – Received Pharmacist 9 December 2014 Complainant 2 Letter of Variation Cons umer Mortgage Irrevocable Authority Declared received – no date or solicitor details Doctor 11 December 2014 Complainant 1 Letter of Variation Irrevocable Authority Declared received – no date or solicitor details Pharmacist 23 March 2016 Complainant 1 & 2 Offer Letter and its attachments Guarant or‟s Certificate – No legal advice received NA A & O Company 7 April 2015 Complainant 1, 2 & 3 (Mr C P) Small Business & Cons umer Guarantee & Indemnity Letter of Offer & Acceptance Irrevocable Authority Declared received on 7 April 2016 from Solicitor (BMcL Lawyers) Australian Legal Practitioner 23 March 2016 Complainant 1, 2 & 3 Offer Letter and its attachments Guarant or‟s Certificate – No legal advice received NA Recommendation | Case number: 743140 Page 13 of 15 Date provided Guarantor Documents received Independent Legal Advice Witness S p O c Company 7 April 2015 Complainant 2 Small Business & Cons umer Guarantee & Indemnity Letter of Offer & Acceptance Irrevocable Authority Declared received on 7 April 2016 from Solicitor (BMcL Lawyers) Australian Legal Practitioner 5 May 2015 Complainant 1 Small Business & Cons umer Guarantee & Indemnity Letter of Offer & Acceptance Irrevocable Authority Declared received on 7 April 2016 from Solicitor (BMcL Lawyers) Australian Legal Practitioner 23 March 2016 Complainant 1 & 2 Offer Letter and its attachments Guarant or‟s Certificate – No legal advice received NA 11 April 2017 Complainant 1 Offer Letter and its attachments Guarant or‟s Certificate – No legal advice received NA 12 April 2017 Complainant 2 Offer Letter and its attachments Guarant or‟s Certificate – No legal advice received NA 5.3 Guarantor Certificate Declaration extract “I [complainant‟s name] have voluntarily chosen not to obtain legal advice regarding the Guarantee and any security document given to me in support of [the c ompany] as trustee for [the company] (“Borrower”) obligations to the Bank (“Documents”) I certify that:  I have received a copy of the Offer Letter addressed to the Borrower and its attachments;  I have read the Offer Letter and its attachments;  I am the Guarant or named in the Offer Letter and the Guarant ee;  I have read the Documents and understand the nat ure and effect of these Documents;  I have been provided the opportunity to obtain independent legal advice;  I have voluntarily chosen not to obt ain legal advice on the nat ure and effect of the Documents; and  I have signed the Documents freely, volunt arily and without pressure from any person. Dated …. ….. [complainant signature] …. ” If you have any doubts about signing thi s certifi cate, or want more information, contact your Gove rnment consumer agency or get legal advice. Recommendation | Case number: 743140 Page 14 of 15 5.4 Timeline summary since expiry of facilities Date Action August 2018 The bank allows final extension to the complainants to secure a contract of sale or refinance. December 2018 The bank applies overdue interest rates for the expired facilities. April 2019 Complainant 1 lodges AFCA complaint regarding default interest applied. 8 July 2019 AFCA complaint resolution reached bet ween complainant 1 and the bank. 12 October 2019 Resolution promises not met by complainant 1 by 12 October 2019 due date. 23 October 2019 The bank issues demand letter for debt owed. 29 January 2020 The bank issues notice of continued default letter. 25 February 2020 Receiver and Manager appointed. 23 March 2020 The complainants lodge AFCA complaint to suspend enforcement p roceedings. 10 April 2020 Receivers appointed legal representative write to the complainants. 28 July 2020 March complaint merged with current complaint considering additional complaint issues raised in relation to valid appointment and guarantees. 5.5 Supporting information  The Code of Banking Practice  Complainants‟ submissions  Credit facilities table  Loan and security documents  Terms and conditions  Default notices  Statutory Declarations by Guarantors  Guarantor Certificates Recommendation | Case number: 743140 Page 15 of 15 5.6 Not considered in this complaint The receivers and managers conduct and financial difficulty AFCA has considered the validity of the receiver‟s appointment by considering if the bank appointed them in accordance with the loan and security terms and conditions. AFCA cannot review or intervene in any action by a validly appointed receiver and manager, including the sale of company assets or financial difficulty claims brought by on behalf of the companies. We need the receiver‟s consent to consider complain ts by the company, because upon the appointment of a receiver to manage the whole of the company‟s affairs, the directors or owners of the company are no longer capable of binding the company to any agreement reached between it and the financial firm.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.