Determination 741675

Storm damage cash settlement amount disputed; fence scope of works and claims handling

FirmSuncorp Group
Decided2021-03-19
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$57,061
Non-financial loss$1,500
Amount claimed—
SourceAFCA PDF

Summary

After a storm damaged the complainant's home and front fence, the insurer offered $53,761.44 to cash settle the repairs. AFCA ordered a further $3,300 for fence footing works, the balance of the cash settlement, and $1,500 for non-financial loss.

The insurer's cash settlement was fair apart from the additional footing works likely needed if the footing is continuous, and claims handling delays caused stress and inconvenience.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay non financial loss

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination Case number 741675 Financial firm AAI Limited Determination | Case number: 741675 Page 2 of 9 Case number: 741675 26 February 2021 1 Determination overview 1.1 Complaint The complainant holds a home building and contents policy with the financial firm (insurer). The complainant’s property sustained damage from a storm in January 2020. The complainant made a claim for the damage to his property caused by the storm. The storm caused internal water damage to the kitchen ceiling and cupboards and damage to the front fence. The insurer accepted the claim for internal water damage. The insurer initially denied the claim for the front fence but later accepted liability for this. The insurer has now sought to cash settle the claim. The complainant disputes the repair costs and some of the methods of repair. He says the insurer’s allowance is insufficient to repair the property to its condition prior to the storm. 1.2 Issues and key findings What is a fair and reasonable settlement of the claim? The insurer should increase its offer by $3,300 to account for the additional work that is likely to arise in the fence’s footings. Otherwise, the insurer’s offer is fair. Should the insurer pay non-financial loss? Yes. There were issues with the insurer’s claims handling that resulted in stress and inconvenience. The insurer should pay $1,500 for non-financial loss. 1.3 Determination This determination is partially in favour of the complainant. The insurer is to pay the complainant the following:  $57,061.44 for the property repairs  $1,500 for non-financial loss. Determination | Case number: 741675 Page 3 of 9 2 Reasons for determination There has been a full exchange of material between the parties and each party has had the opportunity of addressing the issues that arise from the information exchanged. This determination follows consideration of all of the information provided and is based on what is fair in all the circumstances, having regard to the relevant legal principles, terms of the policy, good industry practice (including codes of practice) and, where applicable, prior determinations. 2.1 What is a fair and reasonable settlement of the claim? Circumstances of the loss The complainant says that a storm caused damage to his property. This included:  water damage to the kitchen, entry way, living area  front fence Later, damage was found to the bathroom, and mould was detected in the property. The insurer initially did not accept liability for the damage to the front fence. Following an engineer report (MC), the insurer later accepted the storm caused damage to about seven metres of the fence. Various scopes of works have been provided during the course of the dispute. The insurer has now offered to cash settle the repairs for $53,761.44. This is based on the following:  builder A’s scope of works dated 7 December 2020 totalling $38,437.76  restorer F’s scope of works dated 4 December 2020 totalling $9,890.82  a contingency of 10% on both quotes totalling $4,832.86  refund of $600 excess The complainant is a builder The complaint is a builder. He has questioned the reports provided by the insurer’s experts about what works need to be done to repair his property to the condition it was in before the storm. However, the complainant has not provided any alternative scope of works or quotations. He has also not provided any independent expert information to support his claim. Determination | Case number: 741675 Page 4 of 9 Insurer not required to demolish and replace the fence Following the insurer’s offer and latest scopes of works, the compla inant has provided several submissions. These were mainly to do with the scope of works for the fence. Regarding the fence, there is no dispute the damage is limited to around the central section. However, to restore this fence to its original state, the complainant believes the whole fence, including its footings, should be replaced. One of the scope of works provided by the insurer indicated this. However, the insurer has provided a report from engineer J, dated 21 December 2020, that noted the following:  the central section can be demolished without affecting the two end sections  excavations can then be made to determine if the footing is continuous or not  if the footing is not continuous, then the central footing can be replaced  if the footing is continuous, then > the footing section in the central section can be sawn/cut > details of the existing footing can be established at the time > details can be provided about fixings to the existing footings to the end section of the fence – this will likely involve drilling horizontally into the existing footing and epoxying some steel reinforcement lap bars > the new footing can then be constructed and the central fence built on top of that The complainant believes the footing is continuous. However, even if that is the case, J’s report says the damaged section of the fence can still be repaired without demolishing the whole fence and footings. There is no expert evidence to refute this. The complainant says placing a join in the footings would not be replacing the fence as is. I do not accept this means the insurer is required to do this. The footing is not part of the property’s visual aesthetic value. Its purpose is to support the fence. There is no evidence to indicate J’s proposed method would be unfit for purpo se for the fence it is supporting. Given this, I do not accept the insurer’s scope of works should include demolishing the whole fence. Insurer to increase its offer for the property repairs by $3,300 Having carefully reviewed the insurer’s current positi on, I note the following. There is no independent evidence to confirm the insurer’s scope of works, and quoted amounts, for the internal works is unfair. The insurer’s position is supported by various independent contractors. Determination | Case number: 741675 Page 5 of 9 Regarding the fence, I am not persuaded by the complainant’s position that the whole fence should be demolished and replaced. Therefore, the insurer is not required to do this. I note though that A’s scope of works does not appear to account for any additional works that may be necessary if the footing is continuous. According to J, this would likely involve drilling horizontally into existing footings to the end sections of the fence and epoxying steel reinforcement bars. Given this, and the fact the complainant maintains the footings are continuous, a further $3,300 (including the 10% contingency) should be allowed for this. I note the insurer’s cash settlement included a 10% contingency on all the other works. This is fair as it takes into consideration possible variances that may be required during the repairs. I do not accept there is sufficient basis to increase this given the lack of contradictory independent evidence. Therefore, after considering all the available information, I accept the insurer should increase its offer by $3,300 to allow for the likely additional works required to the fence footings. Otherwise, the insurer’s offer is fair. 2.2 Should the insurer pay non-financial loss? Compensation is awarded conservatively Under the AFCA Rules, we may award compensation (capped at $5,000) for non- financial loss where a complainant has suffered an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with their expectation of enjoyment or peace of mind. We take a conservative approach to compensation for non-financial loss. It is not awarded when a person suffers the normal degree of inconvenience when a problem occurs. Insurer should pay $1,500 in non-financial loss There is no dispute there were various issues with the insurer’s scope of works. This included requiring additional amounts for mould and later accepting liability for the fence. I also note the insurer did not settle on all the scope of works until around 11 months after the claim was lodged. These issues have led to stress and inconvenience for the complainant. The complainant has his father residing in the property. His father was unwell. Understandably, the complainant is frustrated at the delays in settling on a proper scope of works and how this is impacting his father. The complainant is seeking the maximum amount. I do not agree this is warranted for several reasons. Determination | Case number: 741675 Page 6 of 9 The insurer has attempted to work with the complainant in settling on these scope of works. I also accept that on the issue of the fence, the insurer’s position has been accepted to the extent it is not required to demolish and replace the whole of it. Therefore, any stresses and inconveniences a ssociated with this is not the insurer’s fault. Further, this does not appear to be the complainant’s principal place of residence. Given this, and considering our conservative approach, it is fair for the insurer to pay $1,500 in non-financial loss. Determination | Case number: 741675 Page 7 of 9 3 Supporting information 3.1 Product Disclosure Statement Establishing your loss You will need to prove that … the extent of the loss or damage you have suffered …. What we do not cover - general exclusions You are not covered under any section of your policy for damage, loss, cost … that is caused by, arises from or involves: Roots of tree s, …. the roots of trees, shrubs or plants, …. Wear, tear and gradual deterioration wear, tear, rust, fading, rising damp, mould, mildew, corrosion, rot, action of light, atmospheric or climatic conditions or gradual deterioration such as, but not limited to : ….. • gradual weathering and breakdown of bricks, mortar or concret e. To proce ss the claim, you must • allow us to inspect the damaged building; • allow us to arrange for ex perts to assess the damaged building and to quote on repair or replacement; • provide us with a quot e for repair or replacement if we ask for this. If you choos e to use our recommended repairers (when available), there is no need to obtain your own quotes; • when requested, provide us with all proofs of ownership and value, information, co -operation and assistance in relation to a claim … we may reasonably require; When the building is damaged Allowing us, a repairer or an expert appointed by us, to look at what is damaged is usually all that is needed to prove your loss. Sometimes though we might ask you to produce a copy of the most recent plans and drawings fo r the building, phot ographs of the building or other evidence that supports the extent of the loss you have suffered. If we decide that you are unable to reasonably substantiat e your claim, we might reduce or refuse your claim. Determination | Case number: 741675 Page 8 of 9 3.2 Expert Reports Record Key points financial firm’s expert HR Report Undated & 19 March 2020 financial firm’s expert AB Report 9 June 2020 financial firm’s expert FE Report 23 March 2020 financial firm’s expert MC Report 28 August 2020 financial firm’s expert JH Report 28 October 2020 & 21 December 2020 f inancial firm’s expert FN Report 6 November 2020 & 4 December 2020  Date of Cash Settlement: May 25, 2020  Repair issue Plaster/paint repairs to kitchen ceiling and ent ry/lounge ceiling due to guarantee issues (ceilings throughout the house painted 18 mont hs ago and now showing signs of paint peeling)  This is not for entire fence only for rec ently affected section where makes safe has been conducted. Approx. 8lm x 1.8m high  It was agreed in discussion with the attending assessor that no scope of works was to be provided for the front fence as this had been addressed previously. Repair Cost$ 14,335.48  The front fence cracks and leaning have been caused by tree root pressure and have been occurring over a protracted period of time.  …possible storm water …could have accumulated behind fence …caused soft soil  … the high water flow has caused water - build up and hence softening of the soils around the base of the fence with the effect of the fence rotating.  … it is necessary to demolish rotat ed section (approximat ely 7m) of fence. Replace foundation and fence to engineer’s detail and existing architectural finish. Ensure adequate redirection of water away from fence foundations.  movement of the block wall is a result of long - term movement caused by a combination of the influence of trees and vegetation and poor design/construction of the wall.  Once the central fence section is demolished, excavations can be made to determine if the footing is continuous across the fence joint  Upon inspection inside roof cavity visible moul d was detected on the undersi de of the ceiling around kitchen and open lounge/dining area. From the inside of the property it is possible to see water marks on the ceiling and in some parts the paint is peeling off.  A BUILDER IS RECOMMENCED TO ATTEND TO REMOVE ALL INSULATION TO PREVEN T CROSS CONTAMINATION AND AFFECTED GYPROCK Determination | Case number: 741675 Page 9 of 9 Record Key points financial firm’s expert AB Report 6 October 2020 & SOW’s dated 4 December 2020,6 October 2020, 15 November 2020,3 December 2020, 7 December 2020.  … recorded the damages to the ceilings throughout the open living area along with the hallway and laundry, we also noted that the cabinetry was damaged, the damage is all consistent with water ingress through the roof space as a result of a storm causing the valley to overflow, common during this particular rain event. The location where the water escaped over the cabinetry is also located in the same area as a valley that overflowed.  …t hat is approx. 7m long, has moved away from the remainder … need to remove the damage block wall and footing to allow t he installation of new adequate foo tings, …