Text of the determination
Determination
Case number 740804
Financial firm AAI Limited
Determination | Case number: 740804 Page 2 of 11
Case number: 740804 21 May 2021
1 Determination overview
1.1 Complaint
In February 2017, the complainant lodged a claim with the financial firm (insurer) for
hail damage to his property. This claim was accepted. In December 2018, he noticed
rain coming through the ceilings. During the assessment of this claim, quality issues
were identified with the insurer’s previous repairs .
The insurer says the areas which need rectification are the responsibility of both its
repairer (RC) and the complainant’s builder (SC). The insurer says it will authorise RC
to complete the repairs once SC repairs its defects. The insurer says it is not liable for
the replacement of the roof or for rectification of the original building defects.
The complainant says SC assessed the damage and says it relates to the insurer’s
poor repairs and not to SC’s previous works. The complainant seeks the insurer to
completely replace his roof.
1.2 Issues and key findings
What is a fair resolution to this complaint?
There are extensive rectification issues required to the roof. It is not fair for RC to do
these works given they had the opportunity to identify and rectify this earlier and failed
to do so.
Therefore, the claim should be settled in the manner set out in section 2.1.
1.3 Determination
This determination is partially in favour of the complainant.
The claim is to be resolved as set out in section 2.1 below.
Determination | Case number: 740804 Page 2 of 11
2 Reasons for determination
2.1 What is the fair resolution to this complaint?
Parties disagree on extent of claim related repairs required
The insurer accepted liability for the hailstorm and authorised repairs. The repairs
included extensive works to the roof. These were conducted by RC. The parties also
agree there are rectification issues arising from the insurer’s repairs for the 2017
claim. This has caused further leak-related damage inside the property. However, the
parties disagree as to the extent of rectification works the insurer should be liable for.
The complainant says there are quality and workmanship issues with his roof which
he says have occurred solely as a result of the insurer’s previous repair.
The insurer has agreed to cash settle the complainant for $35,387. The insurer says
this is the extent of its liability for the roof rectification works and internal damage. The
insurer says it is not liable to replace the entire roof.
Roof is subject to further resultant damage
The complainant first contacted the insurer on 19 February 2017 to lodge the claim for
hailstorm damage to his property. Since then, the complainant has contacted the
insurer several times regarding issues with his roof. To date, the roof is still leaking.
The insurer accepts RC’s repairs were not acceptable and rectification is required.
The complainant says there was no internal (ceiling) damage from the hail storm in
2017. However, since the insurer’s repair , the ceiling has leaked during significant
rain events. The complainant disagrees the cause of the leak is the box gutters
installed by SC. This is because the roof did not leak until RC completed the repairs.
Expert material confirms quality issues with items in dispute
The parties appointed several experts to assess the quality of previous repairs and
the rectification work required. Their findings are described in detail in section 3.2. In
summary:
The insurer’s engineer, WE, identified extensive issues. This included parapet
capping flashings not being installed properly, roof flashings being inadeq uately
sealed, restrained or affixed, flashings having insufficient overlaying, poor
installation of downpipe spreaders, cladding not being properly installed, cappings
not being affixed properly. This is not a full detailed list.
RC says the leak to the window and box gutter issues are not related to its
previous work. RC notes SC completed the installation. RC says strong wind and
rain are the cause of water entry.
Determination | Case number: 740804 Page 3 of 11
The insurer’s builder, DW, says the cause of damage is RC’s poor workmanship.
DW says the main roof is made up of seven separate roofs, all requiring complete
re-roofing due to the poor workmanship in the installation of roof sheets.
The complainant’s builder TP identified several issues that include the flashing,
roof blanket/sarking, cladding, apron flashings and closing off roof sheet rib ends.
TP did not say the whole roof needs to be replaced.
The complainant’s roofing expert CR says there are issues with parapet cappings,
apron flashings, gaps between new and existing flashing, overuse of silicone, roof
sheets potentially not turned up correctly, flashings not lapping in right direction for
waterflow, sisalation not overlapping the flashing, among other issues.
The panel is satisfied there are extensive quality issues with RC’s previous repa ir.
Most of the expert evidence beyond RC’s view is consistent with this.
Insurer is required to cash settle the disputed damage
The complainant says the insurer is responsible for the repair of the entire roof. The
complainant prefers SC to complete rectification of his roof. The insurer offered to
settle the rectification issues either by:
undertaking rectification of its repairs (once SC rectifies its responsibility) or
cash settling the claim for $35,387, including the cost of internal resultant damage.
The insurer says the cash amount represents its liability for rectification works.
Further, the insurer says RC has always been willing to complete the repairs once SC
rectifies damage it is responsible for.
The available material shows the complainant ha s lost trust in the insurer’s ability to
complete the necessary repairs. This is fair given the extent of rectification issues
identified in the roof and the fact RC’s initial assessment did not acknowledge these
issues. For instance, RC had the opportunity to assess, identify and rectify the issues.
However, when RC inspected the roof and leaks, RC did not acknowledge any of the
quality issues. All of the evidence provided since showed this was incorrect.
Rectification of most of the roof is required
Havi ng carefully considered all the available information, the panel finds WE’s report
compelling.
WE’s report is detailed and supported by photographs. WE identified extensive issues
with RC’s works. This included issues with apron flashings, cappings, gaps a nd
penetrations. WE also referenced this to the relevant Australian Standards.
Most of the issues identified by WE were relatively consistent with the ones identified
by the complainant’s experts.
Determination | Case number: 740804 Page 4 of 11
WE also identified issues with the roof that were part of its original construction. Most
of this was regarding box gutters. None of the complainant’s experts provided any
evidence to refute this.
The panel does not accept the insurer can be held responsible for these issues as
they relate to the original construction.
The complainant has raised several arguments saying the insurer should be liable for
all the roof issues. This includes the following:
SC does not accept there is any workmanship issues with the roof
there were no leaks before RC did the works
roo f sheets should all be deemed faulty just by RC’s association with the other
poor work
the sarking was not replaced – this means a second set of holes has compromised
the whole roof
there is no one warranty for the whole roof
RC only replaced 18 solar panels when there were 20
Except for the solar panels, the complainant’s other arguments are not persuasive for
the following reasons.
WE have provided reasons, with the relevant standards in support, showing issues
with the original construction. None of the expert evidence presented has refuted
these factors. The fact SC disputes this is not persuasive given he is not independent
and has not provided any reasoning in support.
Whilst DW is the one expert who says all of the sheets should be replaced, this is not
persuasive. WE, CR and TP do not say this. Further, WE has provided a scope of
works to rectify all the defects identified. This does not say all the sheets need to be
replaced. Given this, the panel does not accept there is sufficient basis to accept all of
the sheets should be replaced.
Regarding the sarking, none of the experts say this has been compromised to an
extent that all of the roof should be replaced.
The panel acknowledges the warranty issues are complicated given the works done
to the roof involve two different contractors. However, the evidence also shows there
is a warranty for the whole roof. This includes a lifetime warranty for the insurer’s
works.
The insurer has not refuted the complainant’s assertion there are only 18 solar pan els
replaced. It must therefore compensate the complainant for the missing two.
Determination | Case number: 740804 Page 5 of 11
Insurer should settle the roof issues in the following way
The complainant says the cost to repair the property would be estimated at $120,000.
However, he has no formal quotation to substantiate this.
The insurer has provided two quotes from RC to rectify its roof repairs and the internal
damage. Regarding the roof, the insurer says RC’s quotes are consistent with WE’s
report regarding the works required.
The insurer says it is prepared to authorise RC to complete the works. However, if the
complainant does not wish this to happen, it has offered to cash settle the works
based on RC’s quotes.
The panel does not consider it is fair for the insurer to base its cash settlement on
RC’s quote.
It is clear RC’s works were extensively poor. Further, when asked to assess its works,
it failed to recognise or acknowledge the issues. Given this, the complainant’s
concerns about allowing RC to rectify the work are legitimate.
Given this, the panel considers it is fair in all the circumstances for the roof issues to
be settled in the following way subject to the complainant accepting this
determination:
each party can obtain at least one, and no more than two, actionable quotes based
on all the works set out in WE’s report that is attributable to RC’s works – this
would mainly be under the heading ‘Works Required for Roof Sheeting & Roof
Flashings’
> the quote should also include the cost of sourcing and installing the two missing
solar panels
the quotes must be provided by an independent repairer who is suitably qualified to
do the roof works – as a minimum, this must not include SC or RC
if only one actionable quote is obtained, then the insurer is to cash settle the claim
based on that quote plus a 20% contingency. If more than one actionable quote is
obtained, then the insurer is to cash settle based on the average of those
quotations with a 20% contingency.
The internal damage is to be settled in this way
For the internal damage, it is not clear if the scope of works are accurate. This is
because leaks have continued to occur during the complaint.
Further, the panel accepts the insurer should settle all of the internal damage. There
is nothing to refute the complainant’s evidence there were no previous water entry
prior to RC’s repairs. It is also clear based on the available evidence, there are
extensive issues with RC’s roof works.
Determination | Case number: 740804 Page 6 of 11
Therefore, once the insurer has cash settled the roof in line with the above process, it
must then assess and prepare a scope of works and actionable quote for all the
internal damages. The insurer should then cash settle the complainant based on this
actionable quote and provide a reasonable allowance for any potential contingencies
that may occur.
The parties will need to work together to achieve all this.
If the parties are unable to agree on the quantum for either the roof or the internal
damage, the complainant can lodge a complaint to AFCA for a decision on these
points.
Insurer is to pay the complainant the cost of TP and CR’s report
Paragraph D.5.1 of our Rules provides that AFCA may determine an insurer
contribute to legal or other professional costs incurred by a complainant in the course
of an AFCA complaint. Unless exceptional circumstances apply, AFCA will not require
an insurer to contribute more than $5,000 to these costs.
When determining whether an insurer should contribute to the payment of
professional fees incurred, AFCA will take into account the complexity of the dispute,
whether the advice was reasonably needed and whether the costs incurred were
because the expert advice was genuinely required.
In the panel’s view, the complainant needed to incur the cost of expert reports to
assist in establishing his case. The panel is satisfied the insurer should reimburse the
complainant for the costs incurred, if it has not done so already, subject to the
complainant providing the insurer with the relevant invoices for the reports.
The complainant is to provide the insurer with a copy of the paid invoice(s) for the
reports by TP and CR. Within 14 days of receipt of the invoices, the insurer is to pay
the invoiced amounts to the complainant to the extent it has not done so already.
Insurer should pay $5,000 in non-financial loss
The panel accepts the i nsurer’s handling of the claim has been poor. The available
information shows there are extensive issues with the roof repairs. This has resulted
in the claim being substantively protracted over several years. It has also resulted in
continued water entry to the property the complainant has had to deal with.
The situation has been exacerbated by RC’s failure to acknowledge and address
these issues earlier.
It is also clear this has impacted the complainant significantly.
Given this, the panel considers it fair the insurer pays $5,000 in non-financial loss.
Determination | Case number: 740804 Page 7 of 11
3 Supporting information
3.1 Process
AFCA’s approach to this complaint
This complaint has been determined based on what is fair in all the circumstances,
having regard to the legal principles, applicable industry codes or guidance, good
industry practice and previous decisions of AFCA or its predecessor schemes (which
are not binding).
A full exchange of the relevant information has taken place between the respective
parties. Each party has had the opportunity of addressing any issues raised. All the
provided information has been reviewed and considered. The parties have raised
numerous issues in their submissions. Commentary in this determination is restricted
to those issues considered relevant to the outcome.
This matter was determined by a panel
Due to the nature of this dispute, it has been referred to a panel for determination.
The panel comprises an ombudsman, a member with significant experience in
consumer and small business advocacy and a member with extensive experience in
general insurance.
How we assess complaints
AFCA is not a court of law. We do not have the power to take or test evidence on oath
or to require third parties to give evidence. When we assess complaints, we consider
available documents, the recollections of the parties and all relevant circumstances.
We give more weight to documents created at the time the events occurred . If there is
no relevant documentation, we will decide what is most likely to have occurred based
on the information provided to us. If there are conflicting recollections and these are
evenly weighted, we may find that a claim cannot be established.
3.2 Approach to non-financial loss
Compensation is awarded conservatively
Under the AFCA Rules, we may award compensation (capped at $5,000) for non-
financial loss where a complainant has suffered an unusual degree or extent of
physical inconvenience, time taken to resolve the situation or interference with their
expectation of enjoyment or peace of mind.
We take a conservative approach to compensation for non-financial loss. It is not
awarded when a person suffers the normal degree of inconvenience when a problem
occurs.
Determination | Case number: 740804 Page 8 of 11
3.3 Terms of the policy
Record Key points
Lifetime guarantee on
home repairs
When we repair or rebuild your home, we guarantee the quality of
materials and workmanship of that work for the lifetime of your home if we:
Authorise;
Arrange; and
Pay the builder or repairer directly for this work.
What we guarantee
We guarantee the material used and standard of the workmanship to be
free of defects. If a defect arises in the lifetime of your home as a result of
poor quality workmanship or use of incorrect materials, then we will rectify
the problem.
3.4 Expert material relied upon
Record Key points
Insurer ’s engineer ( WE )
Report
27 February 2020
Metal roof sheeting at the north - western corner of the rear lower roof
is distorted relative to adjacent roof sheets.
Scyon Stria wall panelling system partially deconstructed.
Multiple damage to masonry surfaces throu ghout the roofing.
S mall structure protruding from the master bedroom incorporates a
continuous steel flashing across its upper surface not affixed to
adjacent building elements.
Metal roof flashings sealed by a sealant joint without adequate
restraint by penet rating fasteners.
Longitudinal and apron flashings not fixed to masonry walls and not
provided with adequate fastener restraint.
Downpipe spreaders are discharging onto uns ealed sections of
roofing fabric.
Roof sheeting not installed square with the barge.
Building penetrations through metal clad roof not adequately sealed.
Integration of the original FC sheet wall cladding and sarking
installation with the new metal roof cladding installation not completed
in a suitable manner.
External bedroom protr usion has not been constructed or flashed in,
so it will resist water trans fer internally.
The installed roof cladding not provided with required minimum
continuous fall.
High front eaves gutters have no effective overflow drainage.
Box gutters not provided with means of overflow drainage and joint by
mass applied sealant only .
Box gutter outlet through the western end of the north lower roof
gutter is a lesser width than the box gutter base with wat er ponding
from debris.
Cavity skin wall not constr ucted wit h moisture - resistance measures.
Insurer’s builder (RC)
Report
The window leak is un - related to any previous works.
Determination | Case number: 740804 Page 9 of 11
Record Key points
2 4 December 2018 The box gutter stop ends are not high enough. The box gutter was not
replaced by RC during previous repairs.
Ins urer’s builder (RC)
Report
4 June 2019
Client advised water entry to the front spare bedroom and the upstairs
stairwell hallway area every time it rained.
Confirm there was no water dripping in these areas during these
heavy rains.
The current roof sheeting replac ed by RC previously is a lik e for like
replacement.
C lient’s builder advised the roof sheeting does not require
replacement, it i s more of a flashing issue.
During the original h ail damage to the property there w as no
replaceme nt of fascia, guttering or box gutters.
Damage to base of upper w est wall cladding at transition flashing .
E ast upper roof – loose / displaced cladding to west wall between roof
levels .
P otential incomplete seal to apron / barge return lap junction at
southeast corner .
W est upper roof – 20 solar panels reportedly removed to allow
replacement of roof sheeting, 18 panels currently installed, support
rails expos ed at the north end.
Insurer’s builder (RC)
Report
20 June 2019
N o issues with the roof sheeting / pitch, materials / colours replaced
under the repairs b y the RC roofer.
Water damage to the downstairs spare bedroom ceiling and the
upstairs stairwell plaster ceiling from water entry.
U pper wall cladding between the mid and upper roof areas require
replacemen t and repainting .
The lower front roof area will require cladding repair work aft er the
flashings require res ealing.
Insurer’s builder (DW)
Report
2 1 March 2019
Insured advised that only 18 out of the 20 solar panels were replaced
to the main roof.
The ca use of the damage is due to poor workmanship by previous
panel builder.
Every parapet wall capping is different size - it is not 1 size fits all.
The flashings need the correct cover to prevent water ingress.
Installation of incorrect size flashing and cap ping, parapet wall
capping in sections is not secured and loose.
Complainant’s builder
( TP )
Report
5 September 2019
Entry roof – out of level northeast parapet wall capping, capping edge
undersized, top of north cladding visible where parapet capping
undersized.
Cladding loose at incomplete weat hering lap, south end of parapet
wall.
Negative gradient to apron flashing at base of balcony balustrade
wall.
Failed / fractured over flashing sealant at balcony northeast corner
and untidy flashing detail incl uding excess lap joints that rely on
sealant.
Determination | Case number: 740804 Page 10 of 11
Record Key points
Roof blanket does not discharge over/into box gutter (or by way of
hanging flashings), roof sheet rib ends not closed off.
Lower northeast roof – incomplete / fractured mass sealant seal at
west parapet wall ju nction with building south wall.
Damage/crease distortion to apron flas hing at cladded southwest
external corner.
Mass fractured sealant to southeast parapet capping junction with
building, infill style flashing fillets ineffective and failed vertically.
R oof sheeting unsupported over box gutter ret urn, parapet capping
oversized, highlight ed by gap to inner wall lining northeast.
Roof sarking not extending over fascia or drain into west gutter.
Failed / incomplete sealant at parapet junction wit h upper sout heast
bedroom, southeast corner and inc omplet e seal to parapet capping
above family room northeast corner.
Displaced fascia above upper south bedroom, exposing end of eave
lining and rim, roof cavity open at base of upper parapet wall capping.
Failed seala nt at apron flashing junction wit h cladding, at (likely)
bedroom 1.
Roof blanket /sarking does not discharge over / into box gutter (or by
way of hanging flashings ), roof sheet profile not closed off.
Misalignment of cladding boards, south end fractured ma ss sealant at
parapet wall junction with southeast corner.
Complainant’s roofing
expert ( CR )
Report
22 October 2020
Oversized parapet capping with only a 50mm turn down both sides
without fixings and relying on glue to hold them down.
Oversized apron flashings not secured down and loose.
Where weat herboards were removed on the Hi Lite roof, they have
not been refitted and are loose, exposing the sisalation.
There are gaps between the new and existing flashings with the new
overlapping and not going beh ind the existing flashing.
Overuse of silicone in some areas also is a course of concern.
Roofing sheets may not be turned up correctly.
The bottom weatherboards have not been removed and the sisalation
is not overlapping the flashing.