Home / QBE / Determination 739504

Determination 739504

Claim management delays and poor communication after house fire

FirmQBE
Decided2021-04-16
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded—
Non-financial loss$2,750
Amount claimed—
SourceAFCA PDF

Summary

The insured couple's fire claim suffered unreasonable delays, errors and poor communication before a total loss settlement. AFCA ordered $2,750 non-financial loss compensation and found the insurer entitled to the full policy premium.

The insurer's claim management fell below an acceptable standard, causing unusual stress and inconvenience under AFCA Rule D.3.3.

Issues

Subjects and remedies

home or building damagemental healthpay non financial loss

Related

All QBE determinations · Find similar determinations

Text of the determination

Determination Case number 739504 Financial firm QBE Insurance (Australia) Limited Determination | Case number: 739504 Page 2 of 5 Case number: 739504 19 March 2021 1 Determination overview 1.1 Complaint The complainant and his wife held a home building and contents insurance policy (policy) with the financial firm (insurer). On 11 May 2020, a claim was lodged for significant damage to the insured property caused by a fire. The insurer has accepted the claim. The complainant remains dissatisfied with the insurer’s management of their claim. This includes poor communication, unreasonable delays in arranging temporary accommodation and basic necessities (services), unreasonable delay in finalising the claim and charging of the total policy premium. The complainant says this has had an adverse impact on their mental health, of which the insurer was informed early in the claim as well as caused an undue extent or degree of stress, anxiety and interference with their peace of mind. The complainant is seeking non-financial loss compensation under the claim. 1.2 Issues and key findings Is the complainant entitled to non-financial loss compensation? Yes. The available information shows the insurer’s management of the claim was not to the level reasonably expected from a financial firm, especially in the circumstances relevant to this complaint. Accordingly, the insurer is to pay the complainant $2,750 in non-financial loss compensation in line with the AFCA Rules (Rules). 1.3 Determination This determination is in favour of the complainant. The insurer is to arrange payment of $2,750 to the complainant in non-financial loss compensation within 14 days of the complainant’s acceptance of this determination. Determination | Case number: 739504 Page 3 of 5 2 Reasons for determination At the time of lodging this complaint with AFCA the complainant raised various concerns including delays in the assessment of the loss, the decision regarding settlement of the claim and payment of the complainant’s entitlements under the policy. I note since lodgement of the complaint with AFCA, the insurer has determined the insured property to be a total loss and the parties have agreed to a total loss settlement amount which has recently been settled under the claim (some eight months after claim lodgement). Accordingly, in providing this determination, consideration will be limited to the matter of whether the complainant is entitled to non-financial loss compensation. This will take into consideration the insurer’s management of the claim including but not limited to the time and actions taken by the insurer in paying the total loss settlement. 2.1 Is the complainant entitled to non-financial loss compensation? Insurer is to pay the complainant $2,750 in non-financial loss compensation The Rules (Rule D 3.3) allow for an award of up to $5,000 for non-financial loss compensation, if the insurer caused the complainant to suffer an unusual degree or extent of inconvenience, delay or interference. AFCA takes a conservative approach when considering any award of compensation. Having considered the information, I am satisfied it establishes there did occur unreasonable delays and failures by the insurer at the various stages of the claim which will have caused the complainant and his wife undue stress, anxiety and inconvenience. This is especially noting the insurer was informed quite early in the life of the claim of mental health issues experienced and the impact the fire event and associated loss had already had on the complainant and his wife. I accept the information shows the level of service from the insurer was not to an acceptable level and resulted in:  delays and errors in arranging temporary accommodation for the complainants  delays and errors in arranging as well as ensuring reasonable ongoing availability of the basic necessary services of electricity, water and communications  poor communication and failures to respond to reasonable questions from the complainant within reasonable timeframes  delay and failure of appointed consultants attending to appointments or the insured property over the assessment stage of the claim  unreasonable delay in finalisi ng the claim which took approximately eight months after lodgement of the claim. Determination | Case number: 739504 Page 4 of 5 It is clear from the information that arising from the complainant’s experience and level or service received there was a lack of trust and a breakdown in the relationship between the parties. This only further complicated an already complex claim, associated assessments and interactions between the parties. I accept the complainant and his wife’s conduct and interaction with the insurer and its representatives contributed to the difficulties faced in the management of the claim. However, given the recent significant loss of their home and contents and associated stress and mental health concerns, I accept the added poor experience under the claim was significant factor for their loss or trust and confidence in the insurer. I accept the insurer has attempted to work with the complainant to resolve concerns raised and keep the claim progressing. However, I am of the opinion, these attempts and a commitment to ensure an acceptable level of service continued over the life of the claim, were not to a reasonable level under the circumstances. Given the circumstances of the claim and the complainants, I believe the insurer could and should have taken more care in the management of the various aspects of the claim. I note the insurer apologised to the complainant given the level of service provided didn’t meet expectations , as well as offered to pay him $2,000 in compensation on a without prejudice basis. The insurer says it did manage the claim in a reasonable manner and that it was not responsible for any failures or delays under the claim. I am not of the same opinion. The failures and poor level of service caused the policyholders to suffer an unusual d egree or extent of physical inconvenience, stress, anxiety and interference with the ir expectation of enjoyment or peace of mind . Accordingly, I am satisfied it is fair in all the circumstances that the insurer be required to pay the complainant $2,750 in non-financial loss compensation under the claim. The insurer is entitled to the policy premium for the relevant policy period The complainant says the insurer continued to debit the policy premium instalments over the course of the claim despite there no longer being an insured building or contents after the fire. I accept the insurer is entitled to the total agreed policy premium for the relevant policy period during which the loss occurred in line with the policy provisions. The complainant is receiving the maximum extent of benefits available under the policy, and therefore, the insurer is entitled to the full extent of the policy premium. Determination | Case number: 739504 Page 5 of 5 3 Supporting information 3.1 Process AFCA’s approach to this complaint This complaint has been determined based on what is fair in all the circumstances, having regard to the legal principles, applicable industry codes or guidance, good industry practice and previous decisions of AFCA or its predecessor schemes (which are not binding). A full exchange of the relevant information has taken place between the respective parties. Each party has had the opportunity of addressing any issues raised. All the provided information has been reviewed and considered. The parties have raised numerous issues in their submissions to AFCA. However, commentary in this determination is restricted to those issues considered relevant to the outcome. 3.2 AFCA Rules D.3.3 An AFCA Decision Maker may decide that the Financial Firm is to compensate the Complainant for non-financial loss: a) for a co mplaint relating to an individual’s privacy rights - injury has occurred to the Complainant’s feelings or humiliation has been suffered by the Complainant; or b) for other complaints – an unusual degree or extent of physical inconvenience, time taken to r esolve the situation or interference with the Complainant’s expectation of enjoyment or peace of mind has occurred.