A landlord's storm claim was accepted but the insurer cash settled the repair scope rather than repairing it, because of pre-existing damage. AFCA found cash settlement permitted, ordered a 20 per cent contingency uplift on the builder's scope, and rejected the claims for repair costs, loss of rent and non-financial loss.

The policy lets the insurer choose the settlement method, but a fair cash settlement must include a 20 per cent uplift for the missing lifetime guarantee and contingencies.

Issues

Subjects and remedies

home or building damagenatural disasterpay claim

Related

All Suncorp Group determinations · Find similar determinations

Text of the determination

Determination Case number 735628 Financial firm AAI Limited (AAI) Determination | Case number: 735628 Page 2 of 7 Case number: 735628 27 April 2021 1 Determination overview 1.1 Complaint The complainant lodged a claim with the financial firm (insurer) for damage sustained to his rental property following a storm. The insurer accepted the claim and engaged a builder to quote on the damage. The insurer initially agreed to carry out the repairs but informed the complainant that he would need to complete maintenance works before they commence. Shortly after the agreement to complete the repairs the insurer changed this decision due to the state of the property and therefore they offered a cash settlement. The complainant was not satisfied with this and wants the insurer to repair the property and to pay for the repairs he has undertaken. A preliminary view was provided by the case analyst in this matter which was in favour of the insurer. The complainant disputes this preliminary view and the matter has been referred for determination. 1.2 Issues and key findings Is the insurer entitled to cash settle the claim? On the information provided, on balance, the insurer is entitled cash settle the claim. It is fair that the insurer provides an uplift of 20% on the quotation for repairs, to cover contingencies. Is the insurer required to pay for the repairs carried out by the complainant? The insurer initially said that the complainant would be required to complete repairs to pre- existing damage prior the commencement of the insurer’s repairs. Within a short time, the insurer advised the complainant that it could not carry out the repairs and provided reasons. On the information provided I am satisfied that the complainant is not entitled to the cost of those repairs. Is the complainant entitled to loss of rent? I am not satisfied that the property was required to be vacated for the repairs to be carried out. The complaint is not entitled to loss of rent. Is the complainant entitled to non-economic loss? On the information provided, on balance, and considering a fair outcome I am not satisfied the complainant is entitled to non-financial loss. 1.3 Determination This determination is substantially in favour of the insurer. The insurer is to cash settle the damage based on the quotation provided by builder (AB) and is to provide uplift of 20% to cover contingencies. Determination | Case number: 735628 Page 3 of 7 2 Reasons for determination 2.1 Is the insurer entitled to cash settle the claim? The complainant lodged a claim for damage to his rental property following a storm. The insurer accepted the claim and arranged for AB to assess the damage and provide a quotation for the repairs. Initially the insurer advised the complainant that it would be necessary for repairs to pre-existing damage to be carried out prior to the commencement of the repairs by the insurer. AB also provided a scope of works totalling $2672.08. Subsequently AB advised they could not warrant the repairs due to the condition of the building. The insurer then obtained an assessment report which was carried out on 7 January 2020 in the presence of the property manager and the tenants. The property manager had advised that the maintenance had been completed and now wanted AB to complete the repairs. The assessor advised the property manager that AB would not be able to complete the repairs due to the significant cracking to the house. The assessor was advised by AB as follows: ‘… we would r ecommend a cash settlement on this claim due to the pre-existing damage that is not related to the claim in particular to the walls. This has always been our recommendation but unfortunately this wasn’t advised on the original building assessment. Due to the age of the property it would take a considerable amount of extra work to get the walls right to be able to warrant’. The assessor noted that the ‘extra work’ would not be claim related. Subsequently the insurer offered the complainant an opportunity to appoint his own builder to assess and prepare a quote. The complainant’s builder provided a quote for $5,000 plus GST. The insurer rejected the quote on the basis that it did not conform to the standard requirements of a formal quote and did not provide line items costing or necessary details for the insurer to properly compared it with AB’s quote. The insurer maintained it would cash settle AB’s quote and that it was entitled to do so under the terms of the policy. The complainant says that at his meeting with the AB and the insurer on 18 November 2020 that it came to light that the insurer had always intended to cash settled the claim. He was further advised by the representative’s Suncorp that it is rare that they would ever proceed with a claim in the s uburb because it is prone to movement which means they can’t offer a life time guarantee on the work. He then requested the following: 1. For …to refund all of the monies I have paid insurance on the property for over the years – I was never really covered … 2. A refund of the $1,500 excess fee – a bogus expense 3. The full costs of the repairs that I will need to pay another builder – (AB’S presence in the claim was entirely tokenistic from day one). 4. For the rental loss I have incurred since my tenant left in August, due to the claim not being finalised. 5. Compensation for the stress and time loss in disputing this claim. Determination | Case number: 735628 Page 4 of 7 Product Disclosure Statement (PDS) The PDS provides: We choose how we settle claims If we agree to pay a claim for loss, thief or damage to the building, we will decide if we will:  Repair damage to the building …  Pay you what it would cost us to repair or rebuild the building The insurer says that the policy provides sole discretion to determine how it settles a claim. I am satisfied that the insurer is entitled to settle the claim under the terms and conditions of the policy. I also note that the complainant has not provided a quote which enables the insurer to further assess the damage or provide an alternative costing in relation to the accepted damage. It appears that the complainant has not chosen to provide an itemised quotation. In the circumstances on balance, I am satisfied the insurer is entitled to cash settle the claim. However, AFCA expects the offer to be fair and reasonable in the circumstances. If the insurer had carried out the work, there would have been a lifetime guarantee. I accept that AB was unable to provide such a guarantee due to the condition of the property., On the basis that neither is there is a lifetime guarantee nor there is any allowance for contingencies that may arise in carrying out the repairs it is fair that the insurer pays an uplift of 20% on their scope of repairs, provided by AB. The damage to the property is to be settled under the terms and conditions of the policy upon the scope of works provided by AB with an uplift of 20%. 2.2 Is the complainant entitled to loss of rent? The complainant claims loss of rent on the basis that the insurer delayed in settling the claim and he says this caused the tenant to vacate the property on the basis the property was unliveable. In support of this he has provided a letter from his property manager saying that the tenants moved out because of the damage to the kitchen roof. He further says that the property cannot be let due to the potential compensation claim that might be lodged if it ’ s left in its current state. The PDS provides as follows: When you have building cover If we accept your claim for loss or damage to the building due to an insured event occurring during the period of insurance and we agree it cannot be lived in, we will pay the weekly rental amount for the reasonable amount of time it should take to repair or rebuild the building, so it can be live in again. Whilst I accept that the insurer did not deem the property unliveable, the insurer must act fairly and reasonably in making this decision. However, nothing has been provided to me that confirms that the damage for which AB provided a scope, would have required the tenants to vacate the property or would have made the property unliveable. Repairs and maintenance can be carried out without vacating Determination | Case number: 735628 Page 5 of 7 the property and nothing has been provided to show that the repairs would have impacted in relation to toilet, bathroom facilities and kitchen facilities. Whilst I accept that fairness requires that the insurer exercises its discretion in respect of this clause appropriately, I am not satisfied that the property was unavailable for rental due to the repairs that would have been undertaken under the accepted claim. The repairs required to the property which are not subject to this claim may impact on the ability of the property to be occupied but that is not the responsibility of the insurer. 2.3 Is the insurer required to pay for the repairs carried out by the complainant? The complainant has requested that the insurer pay for the repairs that he carried out which was required by the insurer prior to the work to be carry out by AB. Whilst I accept that the complainant was under the impression that the property would be repaired by AB, I note that the insurer advised the complainant that the matter would be cash settled within approximately a month after agreeing to carry out the repairs. I am not satisfied there has been any loss by the complainant on the basis that the repairs to the property, would most likely have been required in any event. I am not satisfied that the complainant has suffered a loss by carrying out repairs which would be required to the property. I note that the property is rented and that as such the complainant would be required to maintain the property in a manner that allows it to be habitable. The repairs required are certainly a benefit to the property and are not the responsibility of the insurer. This determination does not require the insurer to refund any monies paid by the complainant for the repairs to the pre-existing damage to the property. 2.4 Is the complainant entitled to non-financial compensation? AFCA can award non-financial compensation up to $5,000. AFCA will award such compensation where: there has been an unusual amount of:  physical inconvenience  time taken to resolve a situation  interference with the complainant’s expectations of enjoyment or peace of mind In assessing whether to award compensation for non-financial loss, AFCA expects complainants to:  be moderately robust  bare the normal degree of inconvenience experience when a problem occurs, and  take reasonable steps to minimise inconveniences suffered. In the current situation the complainant says that he was misled by the insurer on the basis that they never intended to undertake repairs to the property. On the information provided I do not accept this. The insurer obtained a quotation for the repairs from AB and it was only after AB was requested to carry out the repairs that the insurer was advised that the repairs could not be carried out until the pre-existing damage had be rectified. At that time AB advised it could not provide a life time guarantee in relation to the repairs due to the condition of the property. I note that the property is a terrace house built a very long time ago. The insurer arranged for its assessor to view the premises and further onsite meetings were held between the insurer, AB and the complainant. Determination | Case number: 735628 Page 6 of 7 The insurer agreed that the complainant could provide a further quotation for repairs. This was carried out but unfortunately the quotation was not sufficient for the insurer to assess whether the repairs were matters that were covered under the policy. The insurer has requested that the complainant provide a more comprehensive quotation. I note that this has not be provided. The insurer advised the complainant within approximately 1 month that they will not be able to carry out the repairs and the matter will be cash settled. I have already noted that the cash settlement requires a 20% uplift. In the circumstances I am not satisfied that the complainant is entitled to non-financial compensation including payment of refund for all premiums, payment for repairs that he undertook or for the conduct of the insurer. Determination | Case number: 735628 Page 7 of 7 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to:  the legal principles  applicable industry codes or guidance  good industry practice  previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider:  available documents  the recollections of the parties  all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.