Text of the determination
Determination
Case number 735404
Financial firm Allianz Australia Insurance Limited
Determination | Case number: 735404 Page 2 of 11
Case number: 735404 15 April 2021
1 Determination overview
1.1 Complaint
On 10 March 2020, the complainants lodged a claim for damage to their home
building caused by a burst water pipe in the upstairs bathroom.
The insurer accepted the claim, assessed the damage and offered a cash settlement.
The complainants disagree with the insurer’s scope of works and say the settlement
amount is insufficient to adequately complete all the repairs.
The complainants want to return the settlement payment and for the insurer’s builder
(TB) to complete repairs. Further, they seek kitchen appliances and their air
conditioning system to be replaced, as well as temporary accommodation.
The complainants are also dissatisfied with the delays in settling the claim as the
female complainant is severely ill and has suffered from living in a water damaged
home.
1.2 Issues and key findings
How should the claim be settled?
The claim should be settled as set out in section 2.1.
Should the insurer pay non-financial loss?
Yes. The insurer should have arranged temporary accommodation given there is
mould in the property and one of the complainants is receiving treatment for cancer.
The insurer should pay $2,000 in non-financial loss.
1.3 Determination
This determination is partially in favour of the complainants.
The insurer is to settle the claim as set out in section 2.1.
The insurer should pay $2,000 in non-financial loss.
Determination | Case number: 735404 Page 3 of 11
2 Reasons for determination
There has been a full exchange of all material information relied on for the purposes
of this determination and each party has had the opportunity to address any issues
raised by the other.
Due to the complexities involved, this dispute has been referred directly for
determination.
The determination is based on what is fair in all the circumstances, having regard to
the relevant legal principles, terms of the policy, good industry practice, codes of
practice and previous decisions where appropriate.
This determination follows consideration of all relevant information exchanged. While
the parties have raised numerous issues in their submissions, commentary has been
restricted to those issues which are considered directly relevant to the outcome only.
For the sake of brevity, in this determination the male or female complainant are
referred to as ‘the complainants’, unless otherwise specified.
2.1 How should the claim be settled?
Complainants seek cover for additional items
The insurer has mainly relied upon TB’s scope of works and quoted amount dated 9
July 2020 to support its position.
The complainants say these scope of works are incomplete. In an email dated 21
October 2020, they set out the items they say are missing and incomplete. I will
review these items.
Bamboo flooring damage stretches to the other side of the house
The complainants note the insurer agreed the bamboo flooring on the second floor’s
hall was damaged and is to be replaced. The complainants also say it stretches from
the master bedroom’s door to the other side of the house.
The insurer notes the bamboo flooring in the hall had no obvious signs of water
damage. However, after speaking to the builder, the insurer allowed this flooring
replacement on the basis that it is possible water compromised this area. The insurer
also allowed for the open plan area. The insurer does not accept the water extended
to the other side of the house.
The photos provided do not show this damage extended to the length the complainant
says. The contemporaneous inspections and scopes are consistent with the insurer’s
position. Given this, I am not satisfied the insurer is required to include this item in the
scope of works.
Determination | Case number: 735404 Page 4 of 11
Bedroom flooring next to the master bedroom
The complainants say water entered this room, causing damage to the carpet.
However, on 2 July 2020, RX inspected the area. RX reported no smell or signs of
mould in this carpet. It also saw no signs of water stains after lifting the carpet. The
insurer has offered to steam clean it for $324.50.
I am persuaded by RX’s evidence. It is supported by photos.
Given this, the insurer’s offer for this item is fair.
Wall between the master bedroom and smaller bedroom is also damaged
The insurer notes TB’s scope has provi ded an allowance for replacing water affected
skirtings and to paint walls in the master bedroom. The insurer says there is no
evidence that an increase in the scope is required.
The complainant says their builders’ quotes show an increase is required.
Th is is not apparent in the complainant’s quotes. For instance, BB’s quote dated 29
June 2020, does not include this.
Given this, I am not persuaded an additional item must be included.
Ceiling under the bamboo flooring is also damaged
Whilst the complainant believes this is likely damaged given the insurer has agreed to
replace the bamboo flooring, the available photos do not show this.
The insurer is not required to include this item.
Ceiling lights
The complainants say these should be replaced. The comp lainants say their builders
included this even though their quotes did not specifically set them out.
The insurer says the lights are reusable as there is no evidence that they were water
damaged.
It is not apparent from the photos that the lights must be replaced. The complainant’s
builders do not specifically comment on this. I do not accept the scope of works must
include replacement.
Wall between kitchen and dining room is not included
The complainants say this needs to be included. This wall is behind the oven, which
the insurer has agreed to replace.
The insurer disputes this. The insurer notes there is no evidence of water damage to
this wall.
Determination | Case number: 735404 Page 5 of 11
There have been conflicting reports about whether the oven was damaged by the
claimed event. Further, the photos do not show this area of the kitchen was affected.
Given this, I am not persuaded this wall must be included in the scope of works.
Bedroom door
The complainant says this has been damaged in exactly the same way as the
bathroom door, which has been replaced.
The insurer disputes this.
The photos do not show this is damaged. Given this, I am not persuaded this must be
included in the scope of works.
Ground floor hallway underneath the damaged bamboo flooring
The complainants say this needs to be repainted. However, the photos do not support
this. The insurer is not required to include this in the scope of works.
Air conditioning system
The complainants raised concerns about the air conditioning (a/c) system being
damaged. The insurer has disputed this and has not included it in the scope of works.
Both parties have provided several reports, which are summarised in section 3.2
below. Having carefully reviewed the available information, I note the following.
The complainants’ second specialist NA confirms there is no a/c gas and several
parts require replacing. However, they do not mention anything about water damage.
The complainants’ other specialist (OA) says the water damaged the indoor
evaporator unit, motors printed circuit boards, zone motors and ductwork. However,
the insurer’s expert (A) made the following relevant points:
two of the three zone motors are located in the roof space and could not have been
affected by the leaking bathroom
collapsing plasterwork could not have damaged the pipework containing refrigerant
there are no printed circuit boards located within the unit, just electrical fans
Both A and the insurer’s builder TB noted the damage was limited to the lack of
refrigerant which is unrelated to the claim. Further, when testing the system shortly
after the event, the power, fans and air pressure were working.
Given this, I am not persuaded the a/c system was damaged by water. Whilst OA
refers to the zone motors and motors printed circuit boards being potentially
damaged, A makes compelling arguments against this.
Therefore, the insurer is not required to include the replacement of this system.
Determination | Case number: 735404 Page 6 of 11
Damage currently not visible
It is clear there is potential for more damage to be identified as repairs begin.
TB’s quote clearly stated it does not include hidden or concealed damage or mould
revealed during the repairs. According to the insurer, there is likely to be a lot of
mould damage.
How the claim should be settled
The insurer notes that its builder, TB, is ready, willing and able to complete the works
for the amount quoted.
Given this, the fact the insurer is relying on TB’s quote and there is likely more
damage to be identified as repairs begin, it is fair for the insurer to complete the claim
related repairs. This means that if additional damage is identified, then the insurer can
assess and, if required, include those items. Before doing so, the complainants must
return any funds received related to the building repairs.
If the complainant refuses to allow the insurer to complete the repairs, then it is fair for
the insurer to rely on TB’s quote to base a cash settlement on. However, given the
potential for variations, particularly regarding the mould where no scope of works has
been provided, then a contingency of 25% should be included.
Complainants not entitled to additional temporary accommodation
The policy pays for the additional cost of temporary accommodation in the following
circumstances:
We will reimburse the additional costs you have to pay for temporary
accommodation where:
the buildings you live in are damaged by an insured event to such an extent
that you cannot live in them, and
you temporarily take accommodation at another address.
The complainants say their home has been unliveable since the incident because the
kitchen is not functional. They also note that two of their bedrooms have mould in
them. The female complainant is quite ill.
The insurer says the premises are liveable. The only appliance in the kitchen that has
been damaged by the insured event is the dishwasher. Whilst the insurer has agreed
to replace the oven, cooktop and rangehood, it does not accept these were damaged
by the insured event.
Having carefully considered the available information, I accept the premises were not
fit to live in.
Determination | Case number: 735404 Page 7 of 11
This is due to the mould. There is clearly mould at the premises. Pictures show
evidence of some mould in the main bedroom. In its submission dated 28 October
2020, the insurer said that it expects to find a lot of mould damage once repairs begin.
There is no dispute the female complainant is unwell with stage 3 breast cancer.
Given this, I do not agree that the home can be considered liveable in context of the
mould and the female complainant’s medical condition . This situation is further
exacerbated by the fact that various kitchen appliances are not working.
Therefore, I do not accept the insurer’s position to refuse temporary accommodation
was fair in all these circumstances.
Accordingly, if the complainants can provide evidence to show they incurred
reasonable additional accommodation costs, then the insurer is liable for this. The
insurer is also to pay interest for these costs pursuant to section 57 of the Insurance
Contracts Act 1984. Interest is payable from when the costs were incurred to when
the insurer issued reimbursement.
The insurer has allowed for eight weeks of temporary accommodation while repairs
are carried out. CF recommended payment based on a weekly amount of $550 per
week, for a period of eight weeks. This amounts to $4,400. Given there is no evidence
to show this period or rate is unreasonable, I am satisfied this amount is fair if the
claim is to be cash settled.
If the insurer is to repair the damage, then the insurer must pay for reasonable
temporary accommodation costs whilst claim related repairs are being undertaken.
Insurer is to pay the following if the complainants want a cash settlement
If the complainants choose to accept a cash settlement, then the insurer is to make
the following payments to the complainants within 14 days of receiving this
confirmation minus any payment it has already made:
$40,851.17 based on TB’s revised quote
$10,212.79 for possible variances and contingencies
$230.00 for the replacement of the rangehood
$1,557.60 for window replacement
$234.50 for carpet cleaning in bedroom 2
$4,400 temporary accommodation
any temporary accommodation costs the complainants have reasonably incurred
plus interest
Determination | Case number: 735404 Page 8 of 11
2.2 Are the complainants entitled to compensation for delays?
AFCA may award compensation in certain circumstances
Under paragraph D.3 of the AFCA Rules, we may award compensation for
non-financial loss (up to $5,000) where there has been an unusual amount of physical
inconvenience, time taken to resolve the situation or interference with a comp lainant’s
expectation of enjoyment or peace of mind.
AFCA takes a conservative approach to compensation and expects a complainant to
bear a normal degree of inconvenience during a claim.
In considering an award for non-financial loss compensation, we look at what is fair in
all the circumstances. Specifically, for this case, it is appropriate to factor the overall
claims experience rather than focusing on specific individual events.
Complainants are dissatisfied with claims experience
Early in the AFCA complaint, the complainants made it clear the claim is to be marked
urgent due to the female complainant’s health concerns.
The complainants expressed discontent with their claims experience in the early
stages of the claim. Among other issues, they were dissatisfied with delays in the
settlement of the contents claim, the insurer changing its mind about its extent of
liability, having to live in a water damaged house and the insurer not willing to repair
the home.
The insurer has handled the claim in a reasonable and timely manner
I do acknowledge that the home was not liveable given the extent of potential mould
and the female complainant’s medical condition. This would have resulted in stress
and inconvenience to the complainants that should have been mitigated.
However, I accept the main delays have been due to the complainants seeking to add
items to the scope of works that mostly have not been substantiated. Therefore, I
cannot accept the insurer is responsible for this.
Further, the insurer has agreed to replace various items where there is conflicting
information about whether they were damaged by the insured event. This includes the
oven and rangehood. This was reasonable and would have mitigated the failure to
provide temporary accommodation to an exte nt.
Therefore, given this and considering our conservative approach, it is fair for the
insurer to pay $2,000 in non-financial loss.
Determination | Case number: 735404 Page 9 of 11
3 Supporting information
3.1 Relevant policy wording from Product Disclosure Statement (PDS)
Pg 10 How we will settle your buildings claim
1. At our option, we will:
a. repair or rebuild the damaged part of your building to the same condition as
when it was new; or
b. pay you the reasonable cost of repairing or rebuilding any damaged part of
your building to the same condition as when it was new; or
c. pay you up to the amount of the sum insured.
If we pay you the reasonable cost of repair or rebuilding, this means the cost of
repairing or rebuilding less any discount available to us were we to repair or
rebuild …
2. When it is not possible to use original materials during the repair or rebuilding
process, the nearest available equivalent to the original materials will be used. We
will not pay to repair or rebuild property which has not been physically damaged.
Pg 24 Additional cost of temporary accommodation
(Applicable only when you have contents cover)
‘additional costs’ mean those rental and other related costs which you have to incur at
the location of your temporary accommodation which are in addition to the costs you
would have had to incur if you continued to live at your risk address.
If you normally live in the buildings, the amount we will pay will be based on the
buildings’ rentable value.
We will reimburse the additional costs you have to pay for temporary accommodation
where:
• the buildings you live in are damaged by an insured event to such an extent that
you cannot live in them, and
• you temporarily take accommodation at another address.
We will pay for temporary accommodation for:
• the period which we agree is reasonable necessary, or
• 12 months,
whichever period of time is the lesser.
Pg 46 When we will not pay a claim under your policy
1. Unless we state differently in your policy, we will not pay for:
…
b. any loss or damage which is not caused directly by one of the insured events;
…
Determination | Case number: 735404 Page 10 of 11
3.2 Relevant claim file notes
29 April 2020
Insd called to f/up claim and advised that he has requested CS from the LA as the
insd's wife is in hospital due to breast cancer and would like the claim to be settled as
a matter of urgency. …
12 June 2020
INS …… called to discuss how dissatisfied he is with the claim process. He advised
only part the contents has been settled and would like the claim escalated INS has
advised that the LA SR is speaking to him with disrespect and he is not happy with
this INS advised his wife is going through breast cancer and is finding the entire claim
process stressful. INS requested that assessor be changed to another company
…..INS advised that the SOW from [TB] did not include a room that was not reviewed
due to his son sleeping in it at the time of the site visit. Advised that this will need to be
assessed and included in the sow INS advised that he wants an outcome as soon as
possible as he wants to use his own trades to do the works INS advised he had sent
in a quote from his builder - advised him that this was for a full renovation of the home
not for the claimed damages and due to this a second quote was being sourced
Advised the INS l will contact the LA and request if she can finalise the contents items
that are outstanding and to confirm if she has arranged for [TB] to re attend.
3.3 Key points on expert material relied on
Record Key points
AIR CONDITIONING
Complainant’s a/c specialist
(OS )
Report
4 August 2020
Due to recent water damage , a/c system is damage d in the indoor
evaporator unit, motors printed circuit boards, zone motors and
ductwork. All require replacing but not advisable .
Full extent of damage unknown until these parts are replaced .
Complainant’s a/c specialist
(OS)
Service r eport
6 August 2020
Duc ted a/c not heating, found system damaged from water
No refrigerant in system, printed circuit boards damaged, zone motors
damaged, duct work damaged
Complainant’s a/c specialist
(OS)
Email
4 September 2020
Evaporator unit: The pipework was damaged by the collapsing structure
and caus ed a gas leak , would have contaminated the system with
moisture.
Motors printed circuit boards: the evaporator u nit’s printed circuit boards
not working with the co rrect power supplied. Replacement required to
test for any oth er faults.
Zone motors: Unsure of extent of damage until the system works again.
Ductwork: exposed to water spray, more than likely will have a bad
odour once the ducted system becomes is operational again.
Complainant’s a/c specialist
(NA)
System has no gas in it at all, due to this system is now contaminat ed
Wall controller has no display, needs replacing.
Determination | Case number: 735404 Page 11 of 11
Record Key points
Report
18 November 2020
Indoor board has failed, no longer available.
Zone motors are faulty, require replacement.
No further testing can be done until parts replaced
System needs to be replaced, cannot be repaired.
Recommend replacing ductwork as well.
Insurer’s builder (TB)
Electrical report
25 March 2020
A/c unit had power. Fans and air pressure were working.
A/c unit did not have any refrigerant gas left.
Internal and control fan in working order.
A/c system has no damage related or unrelated to the event.
There was a large amount of oil around the rota lock and on the
compressor. Not related to the event.
Insurer’s a/c specialist (AF)
Report
27 September 2020
S ystem ’ s major components working correctly. C ontrol system has a
fault - not allow complet e testing of the system.
C ollaps e of the plasterboard could not damage pipework containing
refrigerant , plaster is below the pipework.
no printed circuit board within the indoor unit
Two of three zone motors are in the roof spac e above bathroom . C ould
not have been water damaged due to location
The ductwork may have water damage . U nable to inspect until t he
t emporary ceiling has been removed.
The refrigerant leak is not claim related . Oil around the outdoor unit
service valve is consistent with the system ’ s age.
Cont rol system requires replacement. T he system was operating during
the initial assessment , the control fault would also be age , wear and tear
related .
KITCHEN APPLIANCES
Complainant’s electrician
(PE )
Report
19 April 2020
Wall oven and dishwasher have water damaged and are deemed
Beyond Economic Repair.
I nsurer’s electrician (SK)
Report
24 September 2020
Rangehood: not working, brand could not be found.
Gas cooktop (Everdure): not working.
Gas o ven (Chefs Classic Extra) : lights are up but unable to test due to
excessive grease build up (safety issue as grease could catch alight ).
Found no signs of water egress, all appliances are very dirty and greasy .
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.