Insurer's cash settlement for fire repairs was inadequate and it did not comply with prior recommendation
Text of the determination
Determination
Case number 733839
Financial firm Auto & General Services Pty Ltd
Determination | Case number: 733839 Page 2 of 13
Case number: 733839 11 September 2020
1 Determination overview
1.1 Complaint
The complainants have lodged a claim with the financial firm (insurer) for damage
sustained to their property following a fire event. The insurer has commenced repairs
for the damage in line with AFCA’s determination 610713. However, the complain ants
have stopped the repairs and seek cash settlement for the remainder of the repairs.
The Authority issued a subsequent recommendation 686831, addressing delays and
disagreement between the parties as to the scope of works. The parties agree to
settle the outstanding repairs by a cash payment, however, there is a dispute
regarding a fair and reasonable figure.
1.2 Issues and key findings
Has the insurer complied with the Recommendation?
I am not satisfied the insurer has fully complied with the Authority’s recommendation.
Is the insurer’s cash settlement fair and reasonable?
The insurer is required to increase its cash settlement as outlined in Section two of
this determination.
Is the insurer liable for any compensation?
The insurer is required to pay the complainants $500 compensation.
1.3 Determination
This determination is in favour of the complainants.
Within 14 days of the complainants accepting this determination, the insurer is
required to pay the complainants:
$65,000 for the repairs
$550 towards BK’s i nvoice
$515 for the disposal of rubbish
$393.04 for painting and cleaning
$5,000 for the smoke damaged books
$1,650 towards the carpet
$500 compensation awarded under recommendation 686831
$500 non-financial compensation as outlined below.
Determination | Case number: 733839 Page 3 of 13
2 Reasons for determination
This complaint has been determined based on what is fair in all the circumstances,
having regard to the relevant law, good industry practice, codes of practice and
previous decisions where applicable.
There has been a full exchange of all material information relied on for the purposes
of this determination and each party has had the opportunity to address any issues
raised by the other. All the material provided by the parties has been reviewed and
considered.
While the parties have raised numero us issues in their submissions, for the purposes
of this determination, commentary has been restricted to those issues considered
directly relevant to the outcome only.
2.1 Has the insurer complied with the Recommendation?
Circumstances of the loss
There is no dispute the complainants’ property sustained damage following a fire
event. There is no dispute the complainants have established a valid claim under the
terms and conditions of the policy. The parties disagree as to the extent of the
damage following the event.
This claim has been subject to two previous AFCA complaints. A summary of the
outcomes is outlined in Section three of this determination.
In this complaint, the complainants say:
the insurer has not complied with the recommendation issued under complaint
686831
the cash settlement offer is not adequate to cover all the required repairs
the insurer has failed to replace the split conditioning system
the insulation has been downgraded and is not compliant with the building code
they ar e not satisfied with the insurer’s handling of the claim.
It is not in dispute that the parties accepted the terms of the recommendation. As
such, the insurer was required to compile a scope of works to restore the kitchen in
line with the previous scope of works. This includes all items identified as not being
completed as per the scope of works:
remove and replace with a new unit, the reverse cycle air-conditioning register
located upon the living room wall
replace the heating unit with the duct work and the wall mounted thermostat.
the electrical power points located on the living room wall, have been removed, but
are not noted in the scope and will need to be replaced
Determination | Case number: 733839 Page 4 of 13
an electrical certificate of compliance should be provided where reinstatement or
replacement of electrical work occurs
the fire damaged ceiling joists (the ones smoke sealed with paint) will need to be
fully replaced on a like-for-like basis
the building rubble which was placed in the insured's recycling bins is to be
removed and disposed of by the builder
the insurer is to add 10 percent contingency
the insurer is to pay the complainants $500 in non-financial compensation.
The insurer only communicated its offer verbally and not in writing
Whilst the exchanged information shows the insurer was attempting to comply with
the scope of works as outlined in the recommendation and included this additional list,
this scope of works was only briefly communicated to the complainants during a
telephone conversation.
Having reviewed the claims notes, I note:
since 20 May 2020, the insurer has been liaising with the builders to amend the
scope in line with AFCA’s recommendation
the contemporaneous notes of the discussions, reflects the sense of urgency in
finalising the scope
on 2 June 2020, the insurer apologised to the complainants for any delays
on 9 June 2020, the insurer spoke with the complainant where the complainant
expressed his dissatisfaction with the offer.
The complainants say they did not receive the scope of works and the insurer did not
communicate a formal offer in writing.
The insurer says that due to a staff member being on leave, the offer was not
communicated in writing with the complainants. Further, the complainants rejected the
offer verbally.
I consider, regardless of the complainants’ verbal rejection, it was appropriate for the
insurer to provide the complainants with a copy of the scope of works and offer, in
writing.
I will address the other findings of the recommendation in the following sections of this
determination.
Determination | Case number: 733839 Page 5 of 13
2.2 Is the insurer’s cash settlement fair and reasonable ?
Parties agree to cash settle the claim
The insurer’s policy states the insurer can decide whether it will repair damage to the
building or pay an insured what it would cost the insurer to repair the building.
When the insurer repairs the building, it guarantees the quality of materials and
workmanship of the work for the lifetime of the building.
If a defect arises in the lifetime of the building because of poor quality workmanship or
incorrect materials, then the insurer will rectify the problem. This is one of the
reasons AFCA considers it is generally preferable for an insurer to carry out repairs.
Further, a cash settlement transfers all the risk from the insurer to the complainants of
any unforeseen damage and any additional work required once repairs commence.
It is not in dispute the parties agree to cash settle the claim. I accept there is a
breakdown in communication between parties. Further, the complainants say they do
not trust the insurer. The complainants have continuously raised concerns and
expressed dissatisfaction with the quality of repairs
I consider it is appropriate in the circumstances for the insurer to cash settle the
complainants for the fair and reasonable costs of the remainder of the repairs.
For clarity, I note the insurer has commenced the repairs in line with AFCA’s
determination 610713. However, the complainants terminated the repairs. The insurer
says the builder can no longer access the site as it appears the complainants have
changed the locks. Further, I note the complainants moved back into the property due
to their concerns with the lockdown during the pandemic.
The complainants are dissatisfied with the insurer’s final scope of works
The insurer has provided a copy of its final scope of works following the acceptance
of the recommendation. Repairs total $48,327.28. Further, I note the insurer has
allowed an extra 10 percent as a buffer for any unforeseeable damage as a
contingency. The insurer made an offer of $53,160.62. The insurer is seeking to cash
settle its liability under the policy for this amount.
The complainants expressed their dissatisfaction with the offered amount. In
substantiating their positions, the complainants say:
they have provided an actionable quote from a builder totalling $121,712
the insulation has been incorrectly downgraded, and the correct insulation should
be R4
the split system is missing from the insurer’s scope of works.
Determination | Case number: 733839 Page 6 of 13
I note the complainants’ initial builder quote totalling $121,712 , has been considered
by AFCA under determination 610713, as not being an accurate reflection of the cost
of repairs resulting from the fire.
Given the complainants’ dissatisfaction with the insurer’s s cope of works and offer,
the onus shifts to them to establish the reasons for the inadequacy of the insurer’s
scope of works and offer (if any).
The complainants’ quantity surveyor’s report is not an actionable quote
The complainants engaged a quantity surveyor (BK) to review the insurer’s scope and
provide an estimate of the rectification. BK estimated the cost of repairs to be
$83,441.
T he insurer says BK’s quote is not fair and reasonable:
BK’s quote is not actionable given he is not a registered builder
the rates used are much higher than a builder’s rates
BK made extra allowance in addition to the existing scope for the bins and
miscellaneous preliminaries
the insurer can complete the repairs for the amount it has been quoted in their
scope.
I accep t BK’s estimate is not an actionable quote. BK’s estimate is mainly based on
the insurer’s scope of works , however, with higher labour and material rates. BK did
not elaborate on the reasons why his estimated rates are substantially higher than the
insurer.
While noting the above, I also accept the insurer’s scope of works is not actionable
either and any cash settlement figure should be increased to allow for:
any volume discounts reflected in the insurer’s quote
project management or supervision costs. I note the insurer has allowed $340
which in my opinion is not a true reflection of accurate costs likely to be incurred by
the complainants in undertaking the repairs
unforeseen damage that will only be discovered once repairs commence
the additional risk assumed by the complainants in undertaking the repairs
the passage of time including any increase in costs since the insurer quote.
Given the challenges associated with the pandemic i.e. lockdown, a builder’s
availability might be a challenge for the complainants. I note the complainants were
unable to obtain a builder’s quote due to these challenges.
I do not accept the complainant’s tendered scope of works is more accurate or
actionable just because the rates are higher.
Determination | Case number: 733839 Page 7 of 13
I note there are few items which are in dispute between parties which BK has factored
in to his scope. I will address these items individually later in the determination.
The insurer is required to increase its scope to meet the R.4.0 for insulation
The complainants say the insurer’s sco pe of works has allowed for the incorrect
ceiling insulation. In BK’s scope, I note:
item 4/1A: Remove and replace ceiling insulation to entire house ceiling - glass
wool batts - R2.1 75mm thick - 136m2
item 4/1B: E/O for R4 - materials only.
Having review ed the insurer’s scope of works, I note:
item 4.10: Remove and replace ceiling insulation to entire house ceiling - glass
wool batts - R2.1 75mm thick - 136m2
item 4.20: Remove and replace ceiling insulation to entire house ceiling - glass
wool batts - R2.1 75mm thick - 136m2.
The insurer says the initial quote supplied by (TC) states that glass wool batts R2.1
was required. The insurer argues every builder attended has reflected the same rating
of the bats.
Neither parties have provided evidence to establish the current building requirement
for the insulation. Further, the insurer has not elaborated as to why the R.4 is not
acceptable. It is unclear whether the difference between the R2.1 and R.4 is a
building requirement or a sustainable option.
In the absence of any other information and for finality, I consider the complainants
costings for the ceiling insulation to be acceptable. It follows, the insurer is liable for
the R4.0 insulation as per BK’s scope of works .
Evidence shows the insurer has replaced the split system
The split system is one of the main issues in dispute regarding the final scope of
works and costings.
The insurer engaged an independent assessor (CR) to assess the quality of the
repairs and address the complainants’ concerns. Amongst other things, CR assessed
the reverse cycle air-conditioning unit and the ducted heating.
In addressing the reverse cycle air conditioner, CR says a certificate of compliance
from the contractor who undertook work on the unit was left on site. The certificate
stated the unit was reconnected using the existing supply isolator and existing
interconnection. In which case it would appear the existing unit has been refurbished
and not replaced as per the scope.
Having reviewed the certificate of compliance, I note it is dated 20 December 2019.
Determination | Case number: 733839 Page 8 of 13
In addressing the ducted heating, CR says the builder’s scope provides for ‘test and
report on ducted heating and advise if replacement is required’. However, the next
line items provides for replacement of the entire ducted heating system to the
dwelling. Further, the scope indicates the existing vents are to be removed and then
reinstalled to the ceiling.
CR says the scope indicates the existing ducted heating ceiling registers were to be
re-used which was the case during the inspection. CR concludes the reasons for
quoting of the replacement of the entire system is unclear.
The complainants say:
the insurer agreed to replace the split system following its acceptance of AFCA’s
recommendation, as per its email dated 20 May 2020
CR says the split system has not been replaced
t he old unit’s casing has been left in the front yard and the internal parts of the un it
were not disposed of as the internal parts are not evident in the photo
the casting of the split system has been left in the front yard and there are no
internal components evident in the skip bins.
In addressing CR’s findings, the insurer’s home assessor (BW) says in his email
dated 19 March 2020:
the split system has been replaced and the ‘reconnect’ noted on the compliance
certificate is a possible mistake
the ducted heating was tested and is in working order and all duct work was
replaced as per the scope
the ducted heating unit was tested, and replacement is not required as it has not
been damaged during the fire event.
In substantiating its position regarding the replacement of the split system, the insurer
has provided:
a quote dated 12 December 2019 from a heating and cooling specialist (AA)
addressed to the builder for the replacement of a 5kw split system totalling $4,400.
I note a comment ‘inspected gas heater / looks to be in good working order’.
Further, I note there is a manufacturer warranty for six years.
an invoice dated 20 December 2019 from AA for the split system totalling $4,400
a Victorian Building Authority’ s (VBA) compliance certificate dated 2 June 2020,
showing supply and installation of a new split system. Further supply and
installation of new duct and branches to existing gas heater.
Determination | Case number: 733839 Page 9 of 13
In considering the evidence, I am satisfied the insurer has replaced the split system,
the ducts and branches as per its scope of works. Further in accordance with the
recommendation, provided VBA’s compliance cert ificate for the electrical work, which
in my opinion is a compelling piece of evidence.
I accept there is confusion regarding the electrical work carried out, considering the
compliance certificate left on site and assessed by CR. Further, I accept the insurer’s
failure to clarify this issue following the recommendation acceptance has caused
confusion. I will address this point later in the following sections.
It is fair the insurer increases its cash settlement figure to $65,000
Having carefully considered the parties evidence and arguments, I accept the
insurer’s costing is a reason able starting point for considering a fair and reasonable
cash settlement for the outstanding repairs.
As outlined above, I consider it is appropriate for the insurer to increase its cash
settlement. I note the insurer has added a 10 percent contingency in addition to its
scope of works.
Further, I note the insurer has accepted:
$393.04 for the paint and cleaning costs
$5,000 for the damaged books,
As outlined above, I accept the insurer is liable for the associated costs for the
insulation. The complainants say many items of their clothing has been returned in a
damaged status following restoration. I note the complainants have not provided any
evidence to establish the extent of the loss (if any).
The complainants have expressed their concerns regarding the electrical works in the
property and say it is not working properly. The complainants are unsure if there are
any associated costs for compliance.
In addressing these concerns, the insurer says all electrical items have been isolated
to complete repairs, which were ceased because of the complainants. Further, an
allowance has been made in the scope for any outstanding work.
The insurer says the existing supply isolator has not been affected by the fire and
does not require replacement. Further a certificate of compliance by VBA is not
required. I note the complainants have not provided any evidence to re fute the
insurer’s argument.
Having considered the evidence I consider it fair that the insurer increases its cash
settlement for the outstanding repairs to $65,000. I accept there is a risk for the
complainants regarding undertaking the repairs and hidden costs which have not
been accounted for.
Determination | Case number: 733839 Page 10 of 13
I am not satisfied that BK’s scope is a real reflection of a fair and reasonable
actionable quote as it is simply not a quote but rather an estimate by a quantity
surveyor.
The complainants have tendered an invoice from BK for the cost incurred in compiling
its scope of works. Whilst I consider BK’s report has not comprehensively advanced
the complainants’ position, I consider it is fair the insurer pays 50 percent of the
invoice, being $550, as I have accepted the insulation cost as per his report.
It is fair the insurer pays the complainants $515 for the skip bin
The complainants say they have incurred $515 in ordering a skip bin to dispose all the
rubbish left behind by the insurers. The insurer says an allowance has been made for
the disposal of rubbish in the scope of works.
I do not accept this argument. The complainants have disposed the material already
left on site. Further, I consider the complainants will incur further costs in disposing
new materials during repairs which I accept is reflected in the repair costs. I consider
it is fair the insurer pays for the $515 incurred by the complainants.
It is fair the insurer pays the complainants $1,650 towards the carpet
It is not in dispute the fire has smoke damaged some of the floors which requires
sanding back and polishing. Namely, pantry, kitchen, living room and hallway.
Given the evolving situation with the pandemic, the complainants decided to move
back into the property. The complainants say the carpet was a cheap and quick
solution to enable the rooms to be safe for habitation for the complainants and their
children. The complainants provided an invoice for $3,300 for the cost incurred for the
carpet.
There is no evidence the fire has damaged the flooring in the entire property. In
saying that, I consider the complainants have mitigated their challenging situation and
I accept it is fair the insurer pays the complainants $1,650 towards the carpet.
Further, I accept by such action, the complainants mitigated further alternative
accommodation costs.
Determination | Case number: 733839 Page 11 of 13
2.3 Is the insurer liable for any further compensation?
The complainants are dissatisfied with the insurer’s handling of the claim
The complainants have expressed their dissatisfaction for the way the insurer has
handled the claim. The complainants say:
the property has been left unlocked on numerous occasions
builder has left the site unclean
debris were left on site which they had to address
the insurer has continued to show lack of empathy
the insurer has been unhelpful with the temporary accommodation
the insurer has continuously attempted to diminish the extent of the damage
the insurer has unreasonably delayed the claim.
The complainants are entitled to $500 compensation
Having reviewed the claims contemporaneous notes, I am satisfied that:
following the loss, the complainants refused to reconnect the power back to the
property, so the insurer could proceed with mitigation repairs following the event
the insurer has continuously attended to the complai nants’ requests and
dissatisfaction regarding the alternative accommodation arrangements
the ins urer continuously addressed the complainants’ concerns appointing an
engineer to assess any potential asbestos
the complainants unreasonably delayed the restora tion process for the contents
the complainants refused access to the insurer’s experts on numerous occasions
to undertake the necessary assessment, restoration or repairs
requested experts, such as the fire investigator checking rooms for smoke and soot
damage, to leave the property as they do not trust the technology used
some of the issues were outside the insurer’s control such as the water ingress at
the rental property
the insurer has paid for the alternative accommodation above the policy limit to
accommodate the complainants ’ needs.
The complainants lived in the property through winter where heating is an issue. I
accept it was the complainants’ decision to move back into the property in its
unrepaired status. Whilst I note their argument about their concerns regarding the
pandemic, I am not satisfied it was the insurer’s wrong doing or actions which led to
this situation.
Considering the evidence, I am satisfied that the insurer has handled the claim
reasonably over all. The exchanged evidence shows the insurer apologised to the
complainants on numerous occasions and has attempted to resolve the claim in a
timely manner.
Determination | Case number: 733839 Page 12 of 13
CR concluded repairs undertaken by the insurer were done to acceptable repair
method and standard, despite the complainants’ dissatisfaction with the quality of
repairs. The i nsurer continued to address the complainants’ concerns by engaging
different experts to assess the extent of the damage and address these concerns. In
saying that, I accept the complainants’ argument regarding the smoke-stained timber
was valid.
Further, the insurer agreed to cover the complainants’ books and pay them $5,000. I
note the complainants were unable to provide any proof of ownership of these books.
Further the complainants disposed these books prior to insurer inspecting the
damage.
I note the insurer has previously paid the complainants $500 compensation as per
AFCA’s determination 610713. Further, the complainants were awarded $500 under
recommendation 686831. The insurer is required to pay this amount to the
complainants if it has not already done so.
I consider an additional $500 compensation is reasonable in the circumstances. The
insurer did not clarify the split system replacement at the time of the recommendation
acceptance. Further, the insurer should have communicated its offer to the
complainants in writing regardless of the complainants’ verbal decision , given the
extent of the loss.
Determination | Case number: 733839 Page 13 of 13
3 Supporting information
3.1 Previous AFCA’s complaints
Complaint Outcome
1. 610713 Determination issued
The insurer is required to arrange repairs of the property based on its
scope of works, including the engagement of a hygienist
The insurer is required to respond to each matter raised by the complainant
regarding the contents assessme nt
The insurer is required to assess the roof gutter damage
The insurer is to pay $500 as compensation.
2. 686831 Recommendation issued
The insurer is to compile a scope of works and costing required to restore
the kitchen in line wit h the previous scope of works and the engineer’s
report. This includes all items identified as not being completed as per the
scope of works and any items yet to be repairer
The insurer is to pay the complainants the value of this scope of works plus
10% to ensure the statement of works is actionable
The insurer should also pay the complainants $500 in consideration of
stress and inconvenienc e experienc ed due to its non - compliance with the
previous scope of works.